CN201136735Y - 一种用于起吊铝电解槽阴极炭块组的吊具 - Google Patents

一种用于起吊铝电解槽阴极炭块组的吊具 Download PDF

Info

Publication number
CN201136735Y
CN201136735Y CNU2007200883946U CN200720088394U CN201136735Y CN 201136735 Y CN201136735 Y CN 201136735Y CN U2007200883946 U CNU2007200883946 U CN U2007200883946U CN 200720088394 U CN200720088394 U CN 200720088394U CN 201136735 Y CN201136735 Y CN 201136735Y
Authority
CN
China
Prior art keywords
steel wire
wire ring
head end
tail end
movable button
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CNU2007200883946U
Other languages
English (en)
Inventor
黄能超
倪立军
金国祥
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China First Metallurgical Group Co Ltd
Original Assignee
China First Metallurgical Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China First Metallurgical Group Co Ltd filed Critical China First Metallurgical Group Co Ltd
Priority to CNU2007200883946U priority Critical patent/CN201136735Y/zh
Application granted granted Critical
Publication of CN201136735Y publication Critical patent/CN201136735Y/zh
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Load-Engaging Elements For Cranes (AREA)

Abstract

本实用新型涉及一种吊具。一种用于起吊铝电解槽阴极炭块组的吊具,它包括有钢丝绳,其特征在于钢丝绳的首端连有活动扣,钢丝绳尾端穿过钢丝绳首端的活动扣形成封闭的首端钢丝环;钢丝绳尾端也连有一个活动扣,尾端活动扣扣合在首端钢丝环区域内部的钢丝绳上形成尾端钢丝环;行车吊钩的挂钩位置设置在首端钢丝环与尾端钢丝环公共的钢丝绳上。本实用新型的有益效果是:(1)一次可以吊装更多的炭块组,吊装速度快;(2)制作成本低,只要根据炭块组的重量进行选择一定规格与长度的钢丝绳即可。(3)吊装过程安全平稳,减少打滑现象;(4)由于钢丝绳使用活动扣,可方便安装,节省劳力。

Description

一种用于起吊铝电解槽阴极炭块组的吊具
技术领域
本实用新型涉及一种吊具,具体的说是用于起吊铝电解槽阴极炭块组的吊具。
技术背景
铝电解槽阴极内衬施工过程中,需要将铝电解槽的阴极炭块组吊装,待阴极钢棒完全穿入一侧的阴极窗口后,把阴极炭块组安装在槽底内衬上表面的特定位置。由于阴极炭块组的总长度要比阴极槽壳宽度尺寸大,要把阴极炭块组的阴极钢棒穿过阴极窗口,吊装过程中阴极炭块组必须呈倾斜方向穿入阴极窗口。传统的吊具为了能达到倾斜的目的,需要在吊索两边一边设置一电动或手拉葫芦,通过控制电动葫芦来调整倾斜的角度。传统吊具的结构较为复杂,制作成本较高;而且一次安装炭块组每班只能安装二十块左右的炭块组,吊装速度不高。
发明内容
本实用新型所要解决的技术问题是针对上述现有技术存在的不足而提供一种用于起吊铝电解槽阴极炭块组的吊具,它的结构设置简单合理,成本低廉,吊装速度快,而且吊装安全平稳。
本实用新型为解决上述提出的技术问题而提供了一种用于起吊铝电解槽阴极炭块组的吊具,它包括有钢丝绳,不同之处在于钢丝绳的首端连有活动扣,钢丝绳尾端穿过钢丝绳首端活动扣形成封闭的首端钢丝环;钢丝绳尾端也连有一个活动扣,尾端活动扣扣合在首端钢丝环区域内部的钢丝绳上形成尾端钢丝环;起吊装置挂钩位置位于首端钢丝环与尾端钢丝环之间公共的钢丝绳上。
较佳地,本实用新型一种用于起吊铝电解槽阴极炭块组的吊具还包括以下技术特征:
所述钢丝绳的长度可根据铝电解槽阴极炭块组的长度设定。
本实用新型的有益效果是:(1)因为钢丝绳的长度可设定较长,从而一次可以吊装更多的炭块组,吊装速度快;(2)制作成本低,传统方式安装阴极炭块组需要手拉葫芦及其它辅助设施,而采用该专用绳扣,只要根据炭块组的重量进行选择一定规格与长度的钢丝绳即可。(3)首端钢丝环和尾端钢丝环分别锁紧炭块组左右两个角端,吊装过程中,由于重力的作用,首端钢丝环和尾端钢丝环越锁越紧,保证吊装过程安全平稳,减少打滑现象;(4)确保炭块组的内在质量,由于在整个吊装过程中钢丝绳只与阴极炭块的侧面接触,没有与阴极钢棒接触,完全防止了因吊装不稳造成的阴极钢棒松动而导致的质量问题;(5)由于钢丝绳使用活动扣,可方便安装,节省劳力。
附图说明
图1为现有铝电解槽阴极炭块组吊装的结构示意图。
图2为本实用新型一个实施例的结构示意图。
图3为本实用新型一个实施例在使用过程中步骤一的结构示意图。
图4为本实用新型一个实施例在使用过程中步骤二的结构示意图。
图5为本实用新型一个实施例在使用过程中步骤三的结构示意图。
图6为本实用新型一个实施例在使用过程中步骤四的结构示意图。
图中,1为行车吊钩,2为钢丝绳,3为阴极碳块组,4为槽壳框架,5为槽底内衬,6为电动葫芦,7为控制按钮,8为碳块安装机,21为首端活动扣,22为尾端活动扣,23为尾端钢丝环,24为首端钢丝环。
具体实施方式
下面结合附图进一步说明本实用新型的实施例。
参考图1,传统的吊具为了能达到吊装过程中使阴极碳块组倾斜的目的,需要在吊索两边各设置一个电动葫芦6,通过拨动控制按钮7来控制电动葫芦6来调整倾斜的角度。传统吊具的结构较为复杂,制作成本较高;而且一次安装炭块组3每班只能安装二十块左右的炭块组,吊装速度不高。
如图2所示,本实用新型所采用的技术方案为:一种用于起吊铝电解槽阴极炭块组的吊具,它包括有钢丝绳2,钢丝绳2的首端连有首端活动扣21,钢丝绳2尾端穿过首端活动扣21形成封闭的首端钢丝环24。钢丝绳2尾端连有一个尾端活动扣22,尾端活动扣22扣合在首端钢丝环24区域内部的钢丝绳上形成尾端钢丝环23。吊装前只需要将钢丝绳的首端钢丝环24套住铝电解槽阴极炭块组3的一角,尾端钢丝环23套住另外一个角。再将行车吊钩1的挂在首端钢丝环24与尾端钢丝环23公共的钢丝绳上,起吊即可。因为起吊后,在铝电解槽阴极炭块组3的重力作用下使得首端钢丝环24和尾端钢丝环23的活动扣越锁越紧,从而保证吊装过程中阴极炭块组3平稳可靠。另外,还可以根据所要吊装的铝电解槽阴极炭块组3的长度设定钢丝绳2的长度,从而使钢丝绳的首端钢丝环24、尾端钢丝环23与要吊装的铝电解槽阴极炭块组3的长度合适。每班安装更多的炭块组3,加快吊装速度。
参考图3,图4,图5,图6,由于阴极炭块组3的总长度要比阴极槽壳4宽度尺寸大,要把阴极炭块组3的阴极钢棒穿过阴极窗口,吊装过程必须使阴极炭块组3呈倾斜方向穿入阴极窗口,本实用新型可以通过调整钢丝扣的位置来调整首端钢丝环24与尾端钢丝环23的长度进行吊装,起吊后如图3所示。待阴极钢棒完全穿入一侧的阴极窗口后,把阴极炭块组3缓慢落在槽底内衬5上表面,如图4所示。放松该钢丝绳2绳扣来通过调整首端钢丝环24与尾端钢丝环23的长度(调整到两侧的长度基本一样长),确保炭块组3呈水平状态,如图4所示。最后按照设计要求将炭块组3安装到位,如图5所示。
以上所揭露的仅为本实用新型的较佳实施例而已,当然不能以此来限定本实用新型之权利范围,因此依本实用新型申请专利范围所作的等同变化,仍属本实用新型所涵盖。

Claims (2)

1.一种用于起吊铝电解槽阴极炭块组的吊具,它包括有钢丝绳,其特征在于,钢丝绳的首端连有活动扣,钢丝绳尾端穿过钢丝绳首端的活动扣形成封闭的首端钢丝环;钢丝绳尾端也连有一个活动扣,尾端活动扣扣合在首端钢丝环区域的钢丝绳上形成尾端钢丝环;行车吊钩的挂钩位置设置在首端钢丝环与尾端钢丝环公共的钢丝绳上。
2.根据权利要求1所述的一种用于起吊铝电解槽阴极炭块组的吊具,其特征在于,所述钢丝绳的长度根据铝电解槽阴极炭块组的长度设定。
CNU2007200883946U 2007-11-23 2007-11-23 一种用于起吊铝电解槽阴极炭块组的吊具 Expired - Fee Related CN201136735Y (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNU2007200883946U CN201136735Y (zh) 2007-11-23 2007-11-23 一种用于起吊铝电解槽阴极炭块组的吊具

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNU2007200883946U CN201136735Y (zh) 2007-11-23 2007-11-23 一种用于起吊铝电解槽阴极炭块组的吊具

Publications (1)

Publication Number Publication Date
CN201136735Y true CN201136735Y (zh) 2008-10-22

Family

ID=40037426

Family Applications (1)

Application Number Title Priority Date Filing Date
CNU2007200883946U Expired - Fee Related CN201136735Y (zh) 2007-11-23 2007-11-23 一种用于起吊铝电解槽阴极炭块组的吊具

Country Status (1)

Country Link
CN (1) CN201136735Y (zh)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103803358A (zh) * 2014-02-28 2014-05-21 郑州发祥铝业有限公司 棒料平吊吊具及使用该吊具安装阴极钢棒的方法
CN109055989A (zh) * 2018-10-11 2018-12-21 万基控股集团检修安装有限公司 一种电解槽的修理方法
CN111960246A (zh) * 2020-08-21 2020-11-20 中国二冶集团有限公司 一种炭块组的吊装绳及吊装方法

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103803358A (zh) * 2014-02-28 2014-05-21 郑州发祥铝业有限公司 棒料平吊吊具及使用该吊具安装阴极钢棒的方法
CN103803358B (zh) * 2014-02-28 2015-12-02 郑州发祥铝业有限公司 棒料平吊吊具及使用该吊具安装阴极钢棒的方法
CN109055989A (zh) * 2018-10-11 2018-12-21 万基控股集团检修安装有限公司 一种电解槽的修理方法
CN109055989B (zh) * 2018-10-11 2020-03-31 万基控股集团检修安装有限公司 一种电解槽的修理方法
CN111960246A (zh) * 2020-08-21 2020-11-20 中国二冶集团有限公司 一种炭块组的吊装绳及吊装方法

Similar Documents

Publication Publication Date Title
CN201136735Y (zh) 一种用于起吊铝电解槽阴极炭块组的吊具
CN201582039U (zh) 水轮机转轮翻身装置
CN216512418U (zh) 一种阴极炭块加工用吊装吊具
CN211338515U (zh) 一种新型可调平预制条板吊装工具
CN209758838U (zh) 一种架桥机吊装t梁的专用吊具装置
CN207877121U (zh) 一种钢箱梁的翻身装置
CN103663144A (zh) 钢构件专用翻身器
CN218261540U (zh) 一种变压器起吊自动扶正装置
CN207973393U (zh) 一种重型板材吊装装置
CN206814313U (zh) 一种钼铁倾翻装料机构
CN203143964U (zh) 一种快速更换高炉气密箱的装置
CN206127443U (zh) 一种阳极钢爪及导杆两用吊具
CN209836818U (zh) 一种超长大倾角隧道锚大吨位散索鞍下滑及安装系统
CN209038856U (zh) 一种天车专用钢板吊具
CN203173677U (zh) 一种大型行车板钩更换用吊装工具
CN220182526U (zh) 一种电炉大料篮吊具
CN218167094U (zh) 一种具有限位锁紧功能的升降式实验炉用支架
CN214989676U (zh) 一种矿山冶金机电设备加工用起吊装置
CN221027154U (zh) 一种钢板防滑吊装装置
CN220766242U (zh) 一种防滑移和侧翻的加劲环吊具装置
CN211141295U (zh) 一种电弧炉内断电极简易起吊夹具
CN218261579U (zh) 一种机械加工板材吊装设备
CN213679442U (zh) 一种建筑混凝土预制叠合板吊具
CN215558266U (zh) 一种具有高稳定性的钢板吊运装置
CN213387385U (zh) 一种用于盾构负环管片拆除的吊装工具

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C56 Change in the name or address of the patentee

Owner name: CHINA FIRST METALLURGICAL CONSTRUCTION GROUP CORPO

Free format text: FORMER NAME: CHINA FIRST METALLURGICAL CONSTRUCTION CO., LTD.

CP01 Change in the name or title of a patent holder

Address after: 430081 Wuhan Industrial Zone, Qingshan District, Hubei, No. 3

Patentee after: China First Metallurgical Group Co., Ltd.

Address before: 430081 Wuhan Industrial Zone, Qingshan District, Hubei, No. 3

Patentee before: China First Metallurgical Construction Co., Ltd.

CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20081022

Termination date: 20151123