CN200999346Y - 一种全钢制通用加固式杆塔桩基 - Google Patents

一种全钢制通用加固式杆塔桩基 Download PDF

Info

Publication number
CN200999346Y
CN200999346Y CNU2006201385680U CN200620138568U CN200999346Y CN 200999346 Y CN200999346 Y CN 200999346Y CN U2006201385680 U CNU2006201385680 U CN U2006201385680U CN 200620138568 U CN200620138568 U CN 200620138568U CN 200999346 Y CN200999346 Y CN 200999346Y
Authority
CN
China
Prior art keywords
pile foundation
reinforcing rib
positioning balance
balance dish
pile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CNU2006201385680U
Other languages
English (en)
Inventor
刘海峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CNU2006201385680U priority Critical patent/CN200999346Y/zh
Application granted granted Critical
Publication of CN200999346Y publication Critical patent/CN200999346Y/zh
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

一种全钢制通用加固式杆塔桩基,由地脚螺杆、上定位平衡盘、下定位平衡盘、加强筋、上连接板、下连接板和桩基中心钢管等部件组成,其特征在于:该桩基采用全钢材料,经加工、加固、防腐制成,使用时由专用打桩机直接将桩基夯入地层中、上端与杆或塔相接。由桩基的上下定位平衡盘与环形排列的地脚螺杆组成一个引重心向下装置,可将桩基所承受的重力的重心下移,增强桩基的稳固性。桩基中心钢管的外围设有加强筋和加强筋连接板,大大增加了桩基与土层的接触面积,进一步增强桩基的稳固性。桩基的外表经喷砂工艺后,采用桥梁级防腐处理,确保桩基的使用寿命。

Description

一种全钢制通用加固式杆塔桩基
技术领域
本实用新型涉及适用于交通信号灯杆、电力杆塔、通信线杆等杆塔的桩基,即一种全钢制通用加固式杆塔桩基。
背景技术
杆塔桩基是一个重要的受力部位,是所有立杆竖塔工程施工中的重要环节。目前通常使用的杆塔桩基多为钢筋水泥浇筑,存在着施工工期长,占地面积大、冬季不能施工,不易避开赔损等缺陷。
发明内容
本实用新型的目的是提供一种施工工期短、占地面积小,施工不受季节限制,施工方便快捷的杆塔桩基,即一种全钢制通用加固式杆塔桩基。
本实用新型由地脚螺杆、上定位平衡盘、下定位平衡盘、加强筋、上连接板、下连接板和柱基中心钢管等部件组成。
地脚螺杆位于杆塔桩基上部呈环形排列,其下端与下定位平衡盘相穿接,上部与上定位平衡盘相穿接,上定位平衡盘、下定位平衡盘与杆塔桩基中心钢管相穿接,这样由上定位平衡盘、下定位平衡盘与环形排列的地脚螺杆组成一个引重心向下装置。这种装置可将桩基所承受的重力的重心下移,以增强杆塔桩基的稳固性能。地脚螺杆的上端与杆或塔下端法兰盘用螺母固定相连接。地脚螺杆的粗细与杆塔桩基的大小和所承受的压力相匹配,地脚螺杆的长短与杆塔桩基长度成正比,其长度应占杆塔桩基长度的3%至5%;地脚螺杆的数量与法兰盘上的穿孔数量相对应。
桩基中心钢管为桩基的主体部件,是一个空心钢管。其上部外围设有上定位平衡盘和下定位平衡盘,地脚螺杆与上定位平衡盘、下定位平衡盘相穿接。为增大塔杆桩基与土层的接触面积,以提高杆塔桩基的稳固性能,在桩基中心钢管的外围设有加强筋,为确保加强筋的强度设置了加强筋连接板。这样塔杆桩基与土层的接触面积大大增加,其抗外力、抗旋转的性能大大增强。有关数字表明:加强筋的长度占杆塔桩基长度的30%时,其稳固性能可提高2倍以上。需要说明的是加强筋设置的长度与杆塔桩基所承受的外力大小有关,一般说来,角杆、边杆由于所受外力不均衡,其杆塔桩基的加强筋应适当加长。加强筋的连接板可按需要设置两个或两个以上。
本实用新型的一种全钢制通用加固式杆塔桩基,其特征在于,该桩基采用全钢材料制成,由地脚螺杆、上定位平衡盘、下定位平衡盘、加强筋、加强筋上连接板、加强筋下连接板和桩基中心钢管组成,各部件之间经焊接构成一体。
所述桩基上部外围设有环形排列的地脚螺杆,其下端与下定位平衡盘相穿接,上部与上定位平衡盘相穿接,上定位平衡盘、下定位平衡盘与桩基中心钢管相穿接,由上定位平衡盘、下定位平衡盘与环形排列的地脚螺杆组成一个引重心向下装置。
所述桩基中心钢管的外围设有加强筋,加强筋外缘设有加强筋上连接板和加强筋下连接板,由加强筋与加强筋上连接板、下连接板构成了一个桩基稳固架。
所述桩基外表设有防腐涂层,防腐涂层由底面涂层和表面涂层组成。
有益效果:本实用新型采用全钢制成,应用时由专业打桩机将桩基直接夯入地层中。首先该桩基最大的优势为:施工方便快捷,可大大提高工作效率,缩短施工工期。一般情况下,用夯桩机夯一个桩基仅用5-10分钟即可完成。这样用原浇筑方法需15天的工期,使用钢桩仅用30-60分钟就能完成。其次是该桩基占地面积小,无施工污染。三是施工不受季节限制,施工时可有效避开赔损。四是桩基应用范围广泛,可用于电力杆塔、通信杆塔、交通信号杆塔的桩基。同时该桩基按需可灵活使用,即可以一个杆配一个桩基,也可多个桩基进行组合,呈分桩同塔使用结构。
附图说明
图1是本实用实用新型结构示意图;
图2是本实用新型定位平衡盘结构示意图。
图中:1杆塔固定螺母、2地脚螺杆、3上定位平衡盘、4加强筋、5上连接板、6下定位平衡盘、7下连接板、8桩基中心钢管。
具体实施方式
下面结合附图和实施例对本实用新型作进一步描述。
本实用新型通过以下方法可以实现:
1、选材:本实用新型以使用Q235圆钢和Q345钢板为主要原料。
2、所需设备:火焰切割机、直流电焊机、喷砂机、等离子切割机、剪板机、车床、折弯机、埋弧焊机、合缝机和校直机等。
3、下料成型:(略)。
4、组装:桩基的各零部件加工完成后,进行焊接组装。
5、防腐处理:焊接组装完成后,进行喷砂,最后进行防腐处理,先涂环氧高锌底漆,再涂环氧煤沥清面漆。

Claims (4)

1.一种全钢制通用加固式杆塔桩基,其特征在于,该桩基采用全钢材料制成,由地脚螺杆、上定位平衡盘、下定位平衡盘、加强筋、加强筋上连接板,加强筋下连接板和桩基中心钢管组成,各部件间经焊接构成一体。
2.根据权利要求1所述的一种全钢制通用加固式杆塔桩基,其特征在于,桩基上部外围设有呈环形排列的地脚螺杆,地脚螺杆的下端与下定位平衡盘相穿接,上端与上定位平衡盘相穿接,上定位平衡盘、下定位平衡盘与杆塔桩基中心钢管相穿接,由上定位平衡盘、下定位平衡盘与呈环形排列的地脚螺杆组成一个引重心向下装置。
3.根据权利要求1所述的一种全钢制通用加固式杆塔桩基,其特征在于,桩基中心钢管的外围设有加强筋,加强筋外缘设有加强筋上连接板和强加筋下连接板,由加强筋与加强筋上连接板、下连接板构成了一个桩基稳固架。
4.根据权利要求1所述的一种全钢制通用加固式杆塔桩基,其特征在于,桩基外表设有防腐涂层,防腐涂层由底面涂层和表面涂层组成。
CNU2006201385680U 2006-09-15 2006-09-15 一种全钢制通用加固式杆塔桩基 Expired - Lifetime CN200999346Y (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNU2006201385680U CN200999346Y (zh) 2006-09-15 2006-09-15 一种全钢制通用加固式杆塔桩基

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNU2006201385680U CN200999346Y (zh) 2006-09-15 2006-09-15 一种全钢制通用加固式杆塔桩基

Publications (1)

Publication Number Publication Date
CN200999346Y true CN200999346Y (zh) 2008-01-02

Family

ID=39013751

Family Applications (1)

Application Number Title Priority Date Filing Date
CNU2006201385680U Expired - Lifetime CN200999346Y (zh) 2006-09-15 2006-09-15 一种全钢制通用加固式杆塔桩基

Country Status (1)

Country Link
CN (1) CN200999346Y (zh)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102720223A (zh) * 2011-03-31 2012-10-10 上海宝冶集团有限公司 输电线路杆塔基础加固方法
CN103147459A (zh) * 2013-03-13 2013-06-12 江苏省电力公司宜兴市供电公司 快速成型10kV钢管杆金属基础
CN103597142A (zh) * 2011-03-08 2014-02-19 阿文戈亚太阳能新技术有限公司 用于将太阳能收集器支承结构的基础放置在地面中的装置和方法
CN104265053A (zh) * 2014-10-21 2015-01-07 温州电力设计有限公司 一种高压输电线路江中塔
CN104314096A (zh) * 2014-11-01 2015-01-28 山东力源铁塔制造有限公司 采用环氧煤化沥青面漆防腐的钢管杆桩式基础的施工方法

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103597142A (zh) * 2011-03-08 2014-02-19 阿文戈亚太阳能新技术有限公司 用于将太阳能收集器支承结构的基础放置在地面中的装置和方法
CN102720223A (zh) * 2011-03-31 2012-10-10 上海宝冶集团有限公司 输电线路杆塔基础加固方法
CN103147459A (zh) * 2013-03-13 2013-06-12 江苏省电力公司宜兴市供电公司 快速成型10kV钢管杆金属基础
CN104265053A (zh) * 2014-10-21 2015-01-07 温州电力设计有限公司 一种高压输电线路江中塔
CN104265053B (zh) * 2014-10-21 2016-04-06 温州电力设计有限公司 一种高压输电线路江中塔
CN104314096A (zh) * 2014-11-01 2015-01-28 山东力源铁塔制造有限公司 采用环氧煤化沥青面漆防腐的钢管杆桩式基础的施工方法

Similar Documents

Publication Publication Date Title
US10851537B2 (en) Assemblable structural column joint connection using fiber-reinforced concrete filled round double steel tubes and mounting method thereof
CN200999346Y (zh) 一种全钢制通用加固式杆塔桩基
CN202031369U (zh) 钢砼结构通信杆塔
CN103114604A (zh) 预应力混凝土圆筒型风力发电机组基础
CN112412707A (zh) 一种装配式风电机组圆截面混凝土支撑结构
CN108824475A (zh) 一种输电线路等边三角形承台桩装配式基础
CN204849806U (zh) 一种输电线路用钢管杆
CN110593301A (zh) 一种预制基础组件及其拼装方法
CN214741846U (zh) 一种装配式风电机组圆截面混凝土支撑结构
CN210086651U (zh) 一种装配式结构柱
CN209243755U (zh) 一种定日镜支撑装置
CN112627221A (zh) 一种预应力中空夹层钢管混凝土格构式混合导管架
CN208430522U (zh) 钢桁架结构的风机基础
CN207160052U (zh) 一种连接拱形波纹钢结构的拱座
CN111155548A (zh) 一种预应力锚栓基础
CN207597718U (zh) 内置环绕式螺旋箍筋的防屈曲钢管混凝土组合柱
CN209323559U (zh) 通信塔压入式地桩结构
CN206204985U (zh) 一种环保型装配式后注浆钢筒桩基础
CN218117149U (zh) 一种钢结构安装施工钢管柱混凝土灌芯用操作平台
CN215252985U (zh) 一种预应力中空夹层钢管混凝土格构式混合导管架
CN217781937U (zh) 一种用于冲坑修补的锚固结构
CN206903349U (zh) 一种路灯杆型微站钢模装配式快装配重装置
CN209779668U (zh) 一种定日镜立柱和基础二合一桩基
CN210563690U (zh) 一种电力铁塔安装底座
CN218623612U (zh) 混凝土电线杆的连接结构

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term

Granted publication date: 20080102

EXPY Termination of patent right or utility model