CN1900423A - Integrate section frame building method for steel truss - Google Patents

Integrate section frame building method for steel truss Download PDF

Info

Publication number
CN1900423A
CN1900423A CN 200610019573 CN200610019573A CN1900423A CN 1900423 A CN1900423 A CN 1900423A CN 200610019573 CN200610019573 CN 200610019573 CN 200610019573 A CN200610019573 A CN 200610019573A CN 1900423 A CN1900423 A CN 1900423A
Authority
CN
China
Prior art keywords
steel truss
girder
truss girder
whole sections
whole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN 200610019573
Other languages
Chinese (zh)
Inventor
秦顺全
潘东发
李军堂
宋伟俊
周外男
姚发海
毛伟琦
马涛
张瑞霞
王员根
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Major Bridge Engineering Co Ltd
Original Assignee
China Railway Major Bridge Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Major Bridge Engineering Co Ltd filed Critical China Railway Major Bridge Engineering Co Ltd
Priority to CN 200610019573 priority Critical patent/CN1900423A/en
Publication of CN1900423A publication Critical patent/CN1900423A/en
Pending legal-status Critical Current

Links

Images

Abstract

The present invention relatyes to whole subsection steel boom making, assembling and integrated installation. Said whole subsection steel boom pre-jointing field is arranged in factory, said boom is conveyed by barge to bridge position and installed by crane, the subsection boom is hanged and mounted on the truss, said mounted truss has large rigidity, then finely adjusting the longitudinal, transverse and tuning angle by crane.

Description

Integrate section frame building method for steel truss
Technical field the present invention relates to integrate section frame building method for steel truss
Background technology is along with China's rapid economic development, needs the project of building increasing, is the needs that adapt to the China railways great-leap-forward development, the compression duration, just requires steel truss girder to set up must to employ new technology, new technology the target that could realize shifting to an earlier date the duration.
Present steel truss girder sets up the diffusing method of piecing together of general employing to carry out, and the construction period is longer, carries out the whole sections of steel truss girder and sets up research, is intended to develop China's steel truss girder and sets up worker's method, improves modern bridge construction technical level, satisfies construction period requirement and quality requirement.
Summary of the invention the objective of the invention is to aim to provide a kind of quick construction at above-mentioned present situation, sets up reliable quality steel truss girder erection method.
The steel truss girder internode that whole sections sets up is by last lower chord, and brace, montant, railway be beam and flat connection, highway Orthotropic Steel Bridge Deck and interim rod member composition in length and breadth.
Steel truss girder becomes whole sections at producer's processing spelling, and the back water transport of going to river is set up by the direct lifting of girder erection crane to on-the-spot.
1, whole sections girder steel is pieced together the field in advance
Whole sections girder steel is pieced together the field in advance and is arranged in the producer.If the whole internode assembly unit of steel truss girder line, orthotropic plate spelling district and sections girder steel storage area.After rod member processes, be transported on the assembly unit line, be combined into whole sections, to bridge, treat frame by the harbour shipping of going to river.
2, the diffusing sections steel truss girder of piecing together of Dun Ding sets up
Four internodes in main pier top are to set up on support, adopt and hang the diffusing assembly of ship, loose and piece together rod member before appearance, must piece together in advance with whole sections girder steel rod member.The orthotropic plate of piecing together internode that looses is processed into smallclothes in producer, and assembled on site is set up after becoming big part again.
3, whole sections sets up
After four internodes in main pier top were installed, the assembly unit girder erection crane set up to bilateral symmetry from main pier respectively.Full-bridge is only at main Dun Ding, the auxiliary pier top, the abutment pier top, and in stride and close up a mouthful place and establish a spot of diffusing assembly sections, all the other internodes all adopt whole sections erection technique to finish steel truss girder and set up.
It is that sections is sling the back assembly unit on the trusses that frame is good that whole sections is installed, those frame trusses relative position fix and have very big rigidity.Treat that the beam section of frame hangs ampere-hour, if it is identical with the space geometry position of each corresponding assembly unit of frame trusses or junction, whole sections is butt joint with it very smoothly just, therefore requires whole sections to be combined into the geometrical relationship of the geometry states of back in hanging peace should be with assembly unit on pedestal the time and remains unchanged.Because the docking point position for the treatment of of the trusses end of having put up is (as amount of deflection, the corner etc.) that change, and each beam section weight, position of centre of gravity for the treatment of frame are also different, in order to realize mutual butt joint, its opposite position just must be complied with and be coordinated, thus the position of beam section should by loop wheel machine and suspender to sections vertically, laterally, corner, laterally position such as torsional angle is adjusted.
4, the precision of section assembling control
(1) precision of raising factory section assembling
Most important precision control should be placed on the splice point of 6 chord members during factory whole section assembling, must be also tighter than the deviation that standard allows to the control of basic geometric relationship such as purlin height, the purlin of bridge center line, main truss be wide.To design basic physical dimension as benchmark, its plane, elevation position all will place under the high-precision control net and measure.
(2) carry out every measurement of factory's section assembling
Adopt the short-term method to carry out steel truss girder sections spelling, untie by sections then and form independently steel truss girder internode, should carry out the plane and the height measurement at each control point of steel truss girder internode.Factory's domestic demand is put in order the installation test of sections lifting spelling lifting spelling.Also must carry out repetition measurement after the sections lifting, observe its distortion situation and change comparing with the relative position of sections each measuring point on pedestal to each measuring point.If it is too big that these numerical value differ, should analyze reason and take Corresponding Countermeasures, otherwise can not dispatch from the factory, this is operated in factory's section assembling initial stage that begins and just should solves.
(3) main points of whole section assembling on the bridge
What contact assembled beam section the earliest behind the 1. whole section assembling is brace, and brace is inserted in the gusset plate, and this moment, sections was restrained in the lateral attitude, make brace insert gusset plate difficulty does not take place, and key is to control the main truss spacing;
2. the butt joint of chord member can be docked lower chord earlier, docks upper chord again, at last brace is linked to each other with gusset plate.Can change the favourable opposition nail again into earlier with the little nail via hole that dashes during butt joint.
The interior scab of chord member should be fastened band in theoretical position, and does not clamp with rod member.Outer scab is fastened band on chord member or fasten extension thereon, and interior scab forms interior " sleeve " form, and is again that outer scab is in place after interior scab is inserted in the box-shaped rod member, beats and dashes nail and go up, twist high bolt;
3. dash nail quantity and just twist high bolt quantity and determined according to squeezing into, loop wheel machine is loose hook when;
4. in time measure the geometric position that new sections is installed the back beam-ends, after the loop wheel machine traveling, survey the displacement of beam-ends again.By the suspension centre micromatic setting of girder erection crane, adjust the distortion of whole sections steel truss girder and frame steel truss girder distortion coordination mutually.
5, construction sequence;
(1) main pier pier-side bracket is installed;
(2) utilize crane barge waterborne to install between the pier epimerite;
(3) install between the pier epimerite after, between the pier epimerite, girder erection crane is installed;
(4) bilateral symmetry lifting, the whole sections steel truss girder of installation are finished fastening of steel truss girder and are connect and weld;
(5) also stretch-draw suspension cable is installed;
(6) continue to install steel truss girder, installation and stretch-draw suspension cable;
(7) utilizing other loop wheel machines to loose at place, pier position pieces together between installation pier epimerite.
(8) steel truss girder closes up installation.
The present invention is skillfully constructed, quick construction, and its main feature is:
(1) whole sections is easy to guarantee the steel truss girder installation quality at factory's spelling;
(2) whole segment lifting spelling can effectively improve work efficiency, the quickening progress;
(3) reduce on-the-spot bridge floor welding job amount, be easy to guarantee the steel truss girder welding quality;
(4) reduce steel truss girder work high above the ground engineering amount, reduce the danger of work high above the ground.
Description of drawings
Fig. 1-Figure 10 sets up the step schematic diagram for the whole sections of steel truss girder of the present invention
The specific embodiment is set up explanation with the combined bridge steel truss girder of Wuhan Tian Xingzhou:
Construction sequence one (with reference to Fig. 1):
1, main pier pier-side bracket is installed;
2, mounting slip facility;
3, bank side assembly unit steel truss girder slippage slideway.
Construction sequence two (with reference to Fig. 2):
1, utilize crane barge waterborne to install between the pier epimerite.
Construction sequence three (with reference to Fig. 3):
1, on pier epimerite section, girder erection crane is installed.Whole segment lifting girder steel internode;
2, also stretch-draw suspension cable is installed;
3, the bank side utilizes gantry crane to be assembled into whole sections, and is to be installed.
Construction sequence four (with reference to Fig. 4):
1, continue to utilize girder erection crane that the steel truss girder internode is installed;
2, also stretch-draw suspension cable is installed;
3, the bank side utilizes gantry crane to be assembled into whole sections, and is to be installed.
Construction sequence five (with reference to Fig. 5):
1, continue to utilize girder erection crane that the steel truss girder internode is installed;
2, also stretch-draw suspension cable is installed;
3, the bank side utilizes gantry crane to be assembled into whole sections, utilizes girder erection crane that whole sections is installed.
Construction sequence six (with reference to Fig. 6):
1, continue to utilize girder erection crane that steel truss girder is installed;
2, also stretch-draw suspension cable is installed;
3, the bank side utilizes gantry crane to be assembled into whole sections, utilizes girder erection crane that whole sections is installed;
4, utilize crane barge that two internodes in auxiliary pier top, girder erection crane reach are installed.
Construction sequence seven (with reference to Fig. 7):
1, continue to utilize girder erection crane that the steel truss girder internode is installed;
2, also stretch-draw suspension cable is installed;
3, the bank side utilizes gantry crane that two internodes in auxiliary pier top are installed.
Construction sequence eight (with reference to Fig. 8):
1, continue to utilize girder erection crane that steel truss girder is installed;
2, also stretch-draw suspension cable is installed;
3, the bank side utilizes gantry crane to be assembled into whole sections, utilizes the whole sections of girder erection crane to install;
4, stride in and utilize girder erection crane to close up, stride girder erection crane in removing then.
Construction sequence nine (with reference to Fig. 9):
1, symmetry installation steel truss girder is continued in both sides;
2, also stretch-draw suspension cable is installed;
3, the bank side utilizes gantry crane to be assembled into whole sections, by the girder erection crane integral hoisting.
Construction sequence ten (with reference to Figure 10):
1, with crane barge or diffusing assembly of gantry crane rod member between abutment pier pier epimerite being installed;
2, railway deck ballast aggregate frid etc. is installed.
Beneficial effect
1) can effectively shorten the duration that steel truss girder sets up, significantly reduce the workload of field Welding and lifting.
2) the steel truss girder sections adopts batch production manufacturing, spelling, has not only guaranteed the quality of steel truss girder sections, and has significantly reduced on-the-spot workload, thereby accelerated construction speed.
3) the steel truss girder installation quality is guaranteed.

Claims (2)

1, integrate section frame building method for steel truss, its main construction sequence is:
(1) carries out the manufacturing of whole sections steel truss girder in factory, the main pier pier-side bracket of meanwhile on-the-spot installation;
(2) utilize loop wheel machine that the diffusing internode of piecing together of Dun Ding is installed;
(3) after the diffusing assembly of Dun Ding internode installs, between the pier epimerite, girder erection crane is installed;
(4) whole sections steel truss girder is transported to bridge location, utilizes the lifting of girder erection crane bilateral symmetry, first section whole sections steel truss girder is installed, after the installation contraposition, finish fastening of steel truss girder and connect and weld;
(5) girder erection crane of symmetry reach both sides, installation in position continues second section whole sections steel truss girder of lifting;
(6) repeating step (5) is finished the whole sections steel truss girder of steel truss girder and is set up;
(7) steel truss girder closes up installation.
2, integrate section frame building method for steel truss according to claim 1 is characterized in that:
(1) the whole sections of steel truss girder adopts batch production manufacturing, spelling;
(2) the field by using girder erection crane can whole segment lifting;
(3) change the job practices of traditional diffusing assembly erecting steel truss girder.
CN 200610019573 2006-07-10 2006-07-10 Integrate section frame building method for steel truss Pending CN1900423A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 200610019573 CN1900423A (en) 2006-07-10 2006-07-10 Integrate section frame building method for steel truss

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 200610019573 CN1900423A (en) 2006-07-10 2006-07-10 Integrate section frame building method for steel truss

Publications (1)

Publication Number Publication Date
CN1900423A true CN1900423A (en) 2007-01-24

Family

ID=37656391

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 200610019573 Pending CN1900423A (en) 2006-07-10 2006-07-10 Integrate section frame building method for steel truss

Country Status (1)

Country Link
CN (1) CN1900423A (en)

Cited By (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101684638B (en) * 2008-09-23 2011-06-08 中交第三航务工程局有限公司 Assembly method of section box girder
CN101713168B (en) * 2008-10-06 2011-08-10 中交第三航务工程局有限公司 Process for mounting template for manufacturing sectional box girders
CN101591888B (en) * 2008-05-28 2012-03-07 龙建路桥股份有限公司 Method for pre-pressing bracket in construction of beam of main tower of bridge
CN102535343A (en) * 2012-02-02 2012-07-04 中铁大桥局股份有限公司 Method for erecting girder on top of main tower mound of steel truss girder cable-stayed bridge
CN103911956A (en) * 2014-03-21 2014-07-09 中铁大桥局股份有限公司 Long-span cable stayed bridge steel truss girder mounting method
CN104480862A (en) * 2014-12-03 2015-04-01 中铁大桥局集团有限公司 Installation method of span steel truss girder of cable-stayed bridge side
CN104594201A (en) * 2014-12-16 2015-05-06 中铁大桥局集团有限公司 Method for erecting pier top steel beam through single-side pier-side bracket
CN104652283A (en) * 2015-01-09 2015-05-27 中铁港航局集团有限公司 Asynchronous splicing construction method for symmetrically splicing main steel girder erection cranes of cable-stayed bridge
CN104929051A (en) * 2015-06-29 2015-09-23 中建五局第三建设有限公司 Technique for processing joint where box steel beams with relatively large slenderness ratios of sections are in butt joint
CN105421239A (en) * 2015-10-30 2016-03-23 中交第二航务工程局有限公司 Hoisting method for large-span highway-railway dual-purpose steel truss girder bridge deck slab
CN105544410A (en) * 2016-01-07 2016-05-04 中铁四局集团钢结构有限公司 Joining method for rigid suspension cable stiffening chord in incremental launching method construction
TWI621752B (en) * 2015-08-06 2018-04-21 Railway steel bridge without trace renewal construction method
CN108103938A (en) * 2017-11-28 2018-06-01 江苏中铁山桥重工有限公司 A kind of double deck module solid trial assembly method of large steel girder
CN111119070A (en) * 2019-12-24 2020-05-08 江苏中铁山桥重工有限公司 Method for erecting W-shaped steel truss girder by adopting symmetrical gantry crane suspension assembly
CN111593670A (en) * 2020-06-05 2020-08-28 中国铁建大桥工程局集团有限公司 Construction method of channel-crossing large-span trestle
CN115305835A (en) * 2022-08-15 2022-11-08 中铁九桥工程有限公司 Construction method for erecting double-section whole-section steel truss girder by using girder erection crane

Cited By (20)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101591888B (en) * 2008-05-28 2012-03-07 龙建路桥股份有限公司 Method for pre-pressing bracket in construction of beam of main tower of bridge
CN101684638B (en) * 2008-09-23 2011-06-08 中交第三航务工程局有限公司 Assembly method of section box girder
CN101713168B (en) * 2008-10-06 2011-08-10 中交第三航务工程局有限公司 Process for mounting template for manufacturing sectional box girders
CN102535343A (en) * 2012-02-02 2012-07-04 中铁大桥局股份有限公司 Method for erecting girder on top of main tower mound of steel truss girder cable-stayed bridge
CN103911956A (en) * 2014-03-21 2014-07-09 中铁大桥局股份有限公司 Long-span cable stayed bridge steel truss girder mounting method
CN103911956B (en) * 2014-03-21 2015-11-18 中铁大桥局集团有限公司 A kind of large span stayed-cable bridge steel truss girder mounting method
CN104480862A (en) * 2014-12-03 2015-04-01 中铁大桥局集团有限公司 Installation method of span steel truss girder of cable-stayed bridge side
CN104594201A (en) * 2014-12-16 2015-05-06 中铁大桥局集团有限公司 Method for erecting pier top steel beam through single-side pier-side bracket
CN104594201B (en) * 2014-12-16 2016-04-20 中铁大桥局集团有限公司 A kind of method utilizing one-sided pier-side bracket to set up pier top girder steel
CN104652283A (en) * 2015-01-09 2015-05-27 中铁港航局集团有限公司 Asynchronous splicing construction method for symmetrically splicing main steel girder erection cranes of cable-stayed bridge
CN104929051A (en) * 2015-06-29 2015-09-23 中建五局第三建设有限公司 Technique for processing joint where box steel beams with relatively large slenderness ratios of sections are in butt joint
TWI621752B (en) * 2015-08-06 2018-04-21 Railway steel bridge without trace renewal construction method
CN105421239A (en) * 2015-10-30 2016-03-23 中交第二航务工程局有限公司 Hoisting method for large-span highway-railway dual-purpose steel truss girder bridge deck slab
CN105544410A (en) * 2016-01-07 2016-05-04 中铁四局集团钢结构有限公司 Joining method for rigid suspension cable stiffening chord in incremental launching method construction
CN108103938A (en) * 2017-11-28 2018-06-01 江苏中铁山桥重工有限公司 A kind of double deck module solid trial assembly method of large steel girder
CN108103938B (en) * 2017-11-28 2019-08-06 江苏中铁山桥重工有限公司 A kind of double deck module solid trial assembly method of large steel girder
CN111119070A (en) * 2019-12-24 2020-05-08 江苏中铁山桥重工有限公司 Method for erecting W-shaped steel truss girder by adopting symmetrical gantry crane suspension assembly
CN111119070B (en) * 2019-12-24 2022-02-11 江苏中铁山桥重工有限公司 Method for erecting W-shaped steel truss girder by adopting symmetrical gantry crane suspension assembly
CN111593670A (en) * 2020-06-05 2020-08-28 中国铁建大桥工程局集团有限公司 Construction method of channel-crossing large-span trestle
CN115305835A (en) * 2022-08-15 2022-11-08 中铁九桥工程有限公司 Construction method for erecting double-section whole-section steel truss girder by using girder erection crane

Similar Documents

Publication Publication Date Title
CN1900423A (en) Integrate section frame building method for steel truss
CN100549348C (en) Construction method for hanging wide span arcuated open-web beam
CN102070071B (en) Steel reinforcement cage hoisting method
CN101041974A (en) Structure conversion layer type steel concrete girder mould suspension construction method
CN206053285U (en) A kind of modular assembly of high-altitude overlength is encorbelmented steel platform
CN104712143A (en) Reversed mould construction method for circular reinforced concrete chimney wall
CN206352391U (en) Socket joint type key slot type Quick Release support system
CN104153495B (en) A kind of attachment structure of Multi-function light concrete curtain wall
CN103216103A (en) Pre-deformation construction method for mounting oblique-arc-shaped combined steel-structured column of annular roof
CN1908335A (en) Suspension holder construction method
CN209455933U (en) A kind of superimposed sheet lifting appliance for hoisting
CN106836255B (en) The integral prefabricated structure of basement bottom board catch pit steel mesh and method of construction
CN109823964B (en) Prefabricated stair hoisting connection structure and hoisting method
CN106121221B (en) Building template bracing means
CN106150105A (en) A kind of stiffened column installation method
CN102444275A (en) Silo flexible slip form torsion resistance construction device
CN1048065C (en) Method and equipment for construction of concrete cylinder
CN210032554U (en) Hanging basket suitable for special-shaped structure
CN100560918C (en) Large steel girder member bar turning device and member bar turning method thereof
CN205348731U (en) Core section of thick bamboo reinforcing bar post is from promoting formula operation platform
CN109914694A (en) A kind of steel-structure factory building load-bearing pillar and its manufacturing method
CN102817376B (en) Settlement joint construction method for big-volume slabstone concrete
CN1720374A (en) Innovative prestressed scaffolding system
CN205114897U (en) That climbs formula braced system in tower built -in is put has bad luck device certainly
CN108425634A (en) A kind of anchor cable of adjustable-angle pulls out light rig job platform

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication