TWI621752B - Railway steel bridge without trace renewal construction method - Google Patents

Railway steel bridge without trace renewal construction method Download PDF

Info

Publication number
TWI621752B
TWI621752B TW104125588A TW104125588A TWI621752B TW I621752 B TWI621752 B TW I621752B TW 104125588 A TW104125588 A TW 104125588A TW 104125588 A TW104125588 A TW 104125588A TW I621752 B TWI621752 B TW I621752B
Authority
TW
Taiwan
Prior art keywords
steel bridge
construction
bridge
railway
main beam
Prior art date
Application number
TW104125588A
Other languages
Chinese (zh)
Other versions
TW201706477A (en
Inventor
Hong-Shan Chen
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed filed Critical
Priority to TW104125588A priority Critical patent/TWI621752B/en
Publication of TW201706477A publication Critical patent/TW201706477A/en
Application granted granted Critical
Publication of TWI621752B publication Critical patent/TWI621752B/en

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

鐵路鋼橋無痕更新施工方法,主要係設有門型架構,以及可連結於該門型架構之搬運車。藉由搬運車將門型架構拖運至需更新之鋼橋段,將舊鋼橋吊起並搬運至工地存放,以及由工地搬運新鋼橋至施工段,將新鋼橋放置於原舊鋼橋段,並完成鋪軌及鋪設人行步道橫樑及縱板之作業,從而使鐵路鋼橋的更新施工更具效率,施工過程無需架設施工便橋、開闢施工便道,利用既有鐵道,免除傳統工法需佔據廣大施工用地或租借用地之困擾,即可進行舊鋼橋或損壞鋼橋更新,因要抽換時本創新設備移動到現場可快速完成安裝、吊掛作業及拆離作業,所以利用夜間短暫封鎖施工且不會影響日間鐵路運輸。其中該門型架構係設有一主樑,於主樑設有支撐橫樑、油壓柱腳及懸吊結構,俾於施工時使支撐橫樑橫置於油壓柱腳下方,藉由油壓柱腳使主樑升起,再藉由懸吊結構將舊鋼橋吊起,以反向作法將新鋼橋放置於原舊鋼橋段。 The railway steel bridge has no trace renewal construction method, which mainly has a door structure and a truck that can be connected to the door structure. By hauling the door structure to the steel bridge section to be renewed, the old steel bridge was lifted and transported to the construction site, and the new steel bridge was moved from the construction site to the construction section, and the new steel bridge was placed on the old steel bridge. Section, and complete the work of laying rails and laying pedestrian beams and vertical plates, so that the renewal of railway steel bridges is more efficient. There is no need to build bridges and bridges for construction during construction, and use existing railways to eliminate the need for traditional construction methods. If the construction land or the leased land is troubled, the old steel bridge or the damaged steel bridge can be renewed. Since the innovative equipment is moved to the site to be quickly installed, suspended and detached, the short-term blockade construction at night is used. It will not affect daytime rail transport. The door type structure is provided with a main beam, and the main beam is provided with a supporting beam, a hydraulic column foot and a suspension structure, and the supporting beam is placed under the foot of the hydraulic column during the construction, by the hydraulic column foot The main beam is raised, and the old steel bridge is lifted by the suspension structure, and the new steel bridge is placed in the original old steel bridge section in a reverse manner.

Description

鐵路鋼橋無痕更新施工方法 Railway steel bridge without trace renewal construction method

本發明係有關一種鐵路鋼橋無痕更新施工方法,尤指一種具高強度之輕型結構使鐵路鋼橋的更新施工更具效率,施工過程無需架設施工便橋、開闢施工便道,利用既有鐵道,免除傳統工法需佔據廣大施工用地或租借用地之困擾,即可進行舊鋼橋或損壞鋼橋更新,利用極短暫夜間列車停駛封鎖施工時間,恢復原橋樑日間鐵路運輸功能之鐵路鋼橋無痕更新施工方法。 The invention relates to a railway steel bridge seamless updating construction method, in particular to a light structure with high strength, which makes the railway steel bridge update construction more efficient, and the construction process does not require a facility to bridge, open a construction access road, and utilize existing railways. Exempting traditional construction methods from occupying a large amount of construction land or renting land, the old steel bridge or damaged steel bridge can be renewed, and the construction time of the train is blocked by the extremely short night train, and the railway steel bridge that restores the original bridge daytime railway transportation function has no trace. Update the construction method.

按;一般之鐵路橋樑於使用相當之時間後,由於老舊鋼橋腐蝕會影響行車安全性,因此其鋼橋需更新。惟有些鐵路橋樑係位於具觀光價值的風景區,其施工現場大多地勢險峻,傳統吊裝工法無法克服吊裝困難,機具、鋼橋運輸均操作不便,無法以移動式起重機直接開車到現場進行鋼樑吊裝作業,且在施工期間需徵租大面積施工用地、開闢施工便道、架設施工便橋或是事前架設固定式天車等傳統工法除且增加作業困擾、增加施工成本、增加施工工期,也肯定破壞美麗環境,以及中斷鐵路的運輸,影響甚至完全阻礙了居民與觀光客的交通便利性,實也為鐵路橋樑於鋼橋更新的困擾。申請人有鑑於此,經不斷研究、實驗,遂萌生設計一種鐵路鋼橋更新施工方法,使鐵路鋼橋的更新施工得以更具效率,且不會影響正常車輛通行。 According to the general railway bridge after the use of the time, the corrosion of the old steel bridge will affect the safety of the train, so its steel bridge needs to be updated. However, some railway bridges are located in scenic spots with sightseeing value. Most of the construction sites are steep. The traditional lifting method can't overcome the difficulty of lifting. The equipment and steel bridge transportation are inconvenient to operate. It is impossible to drive directly to the site with mobile cranes to carry out steel beam lifting. In the course of construction, it is necessary to rent a large area of construction land, open a construction road, build a facility bridge or install a fixed crane beforehand, and increase the operation troubles, increase the construction cost, increase the construction period, and certainly destroy the beautiful The environment, as well as the disruption of railway transportation, have even completely impeded the convenience of transportation between residents and tourists, and it has also plagued the renewal of railway bridges in steel bridges. In view of this, the applicant has continuously researched and experimented, and Meng Mengsheng designed a railway steel bridge renewal construction method to make the railway steel bridge renewal construction more efficient and will not affect the normal vehicle traffic.

本發明之主要目的,即在提供一種能快速移動的鐵路鋼橋無痕更新施工方法,使鐵路鋼橋的更新施工更具效率,無需架設施工便橋、開闢施工便道,利用既有鐵道,免除傳統工法需佔據廣大施工用地或租借用地之困擾,即可進行舊鋼橋或損壞鋼橋更新且不會破壞美麗環境,利用極短暫施工時間恢復原橋樑日間鐵路運輸作業。 The main object of the present invention is to provide a non-marking renewal construction method for a railway steel bridge capable of rapid movement, so that the renewal construction of the railway steel bridge is more efficient, no need to build a facility bridge, open a construction road, and utilize the existing railway to eliminate the tradition. The construction method needs to occupy the trouble of the construction land or the leased land, and the old steel bridge or the damaged steel bridge can be updated without damaging the beautiful environment, and the daytime railway transportation operation of the original bridge can be restored by using a very short construction time.

前述之鐵路鋼橋無痕更新施工方法,係設有門型架構,以及可連結於該門型架構之搬運車(是鐵路局的電搖車)。藉由搬運車將門型架構拖運至需更新之鋼橋段,將舊鋼橋吊起並搬運至工地暫置,以及由工地搬運新鋼橋至施工段,將新鋼橋放置於原舊鋼橋段,最後並完成鐵路鋪軌及鋪設人行步道橫樑及縱板之作業,從而使鐵路鋼橋的更新施工更具效率,且不會影響原橋樑日間鐵路運輸作業。 The aforementioned railway steel bridge seamless construction method has a door type structure and a transport vehicle (which is an electric wagon of the railway bureau) that can be connected to the door type structure. By hauling the door structure to the steel bridge section to be renewed, the old steel bridge was lifted and transported to the construction site for temporary placement, and the new steel bridge was moved from the construction site to the construction section, and the new steel bridge was placed on the old steel. At the end of the bridge section, the railroad track laying and the pavement beam and vertical plate are completed, so that the renewal of the railway steel bridge is more efficient and will not affect the daytime railway transportation of the original bridge.

前述之鐵路鋼橋無痕更新施工裝置,其中該門型架構係設有一主樑,於主樑設有支撐橫樑、油壓柱腳及懸吊結構,俾於施工時使支撐橫樑橫置於油壓柱腳下方,藉由油壓柱腳使主樑升起,再藉由懸吊結構將舊鋼橋吊起,以反向做法將新鋼橋放置於原舊鋼橋段。 The aforementioned railway steel bridge has no trace renewal construction device, wherein the door structure is provided with a main beam, and the main beam is provided with a supporting beam, a hydraulic column foot and a suspension structure, and the supporting beam is horizontally placed on the oil during construction. Below the foot of the column, the main beam is raised by the hydraulic column foot, and the old steel bridge is lifted by the suspension structure, and the new steel bridge is placed in the original steel bridge section in reverse.

前述之鐵路鋼橋無痕更新施工裝置,其中之懸吊結構係設於主樑上方,且可沿主樑位移,以利於新、舊鋼橋之懸吊及搬運。 The aforementioned railway steel bridge has no trace renewal construction device, wherein the suspension structure is arranged above the main beam and can be displaced along the main beam to facilitate the suspension and transportation of the new and old steel bridge.

前述之鐵路鋼橋無痕更新施工裝置,其中支撐橫樑係連結設於主樑上方之吊車,藉由吊車控制支撐橫樑的上、下並定位於鋼軌間。 The aforementioned railway steel bridge has no trace renewal construction device, wherein the support beam is connected to the crane disposed above the main beam, and the support beam is controlled by the crane to be up and down and positioned between the rails.

前述之鐵路鋼橋無痕更新施工裝置,其中之懸吊結構係為天車。 The aforementioned railway steel bridge has no trace renewal construction device, wherein the suspension structure is a crane.

1‧‧‧門型架構 1‧‧‧door architecture

11‧‧‧主樑 11‧‧‧ main beam

12‧‧‧支撐橫樑 12‧‧‧Support beam

121‧‧‧吊車 121‧‧‧ Crane

13‧‧‧油壓柱腳 13‧‧‧Hydraulic column foot

14‧‧‧懸吊結構 14‧‧‧suspension structure

15‧‧‧控制室 15‧‧‧Control room

2‧‧‧搬運車 2‧‧‧Truck

21‧‧‧載具 21‧‧‧ Vehicles

3‧‧‧工地 3‧‧‧Worksite

4‧‧‧舊鋼橋 4‧‧‧Old Steel Bridge

5‧‧‧新鋼橋 5‧‧‧New Steel Bridge

6‧‧‧吊車 6‧‧‧ Crane

7‧‧‧軌道 7‧‧‧ Track

8‧‧‧人行步道橫樑 8‧‧‧Pedestrian walking beam

9‧‧‧縱板 9‧‧‧ vertical board

A‧‧‧鐵路橋樑 A‧‧‧ Railway Bridge

第1圖係本發明之立體圖。 Figure 1 is a perspective view of the present invention.

第2圖係本發明之施工現場圖。 Figure 2 is a construction site diagram of the present invention.

第3圖至第12圖係本發明之施工狀態圖。 3 to 12 are views showing the construction state of the present invention.

第13圖係本發明之軌道及人行步道橫樑鋪設狀態圖。 Figure 13 is a diagram showing the state of the rails and pedestrian walkway beams of the present invention.

請參閱第1圖,係為本發明之立體圖。如圖所示,本創發明包含門型架構1,以及可連結於該門型架構1之搬運車2。其中,該門型架構1係設有一主樑11,於主樑11下方兩端適當位置分別設有可上、下移動之支撐橫樑12,使支撐橫樑12連結設於主樑11上方之吊車121,主樑11的兩端側方係分別設有油壓柱腳13,主樑11的上方則設有懸吊結構14,該懸吊結構14係可沿該主樑11移動,主樑11的端部係分別設有控制室15,藉由控制室15控制前述支撐橫樑12、油壓柱腳13及懸吊結構14之動作。於本實施例中,該懸吊結構14係為天車,該門型架構1係由載具21(鐵擔車)所承載,使載具21連接於搬運車2,藉由搬運車2拉動該門型架構1。 Please refer to Fig. 1 for a perspective view of the present invention. As shown, the present invention includes a portal structure 1 and a truck 2 that can be coupled to the portal architecture 1. The door structure 1 is provided with a main beam 11 , and the support beam 12 which can be moved up and down is respectively disposed at appropriate positions on both ends of the main beam 11 , and the support beam 12 is connected to the crane 121 disposed above the main beam 11 . The two ends of the main beam 11 are respectively provided with a hydraulic column leg 13 , and above the main beam 11 , a suspension structure 14 is provided, and the suspension structure 14 is movable along the main beam 11 , and the main beam 11 is The end portions are respectively provided with control chambers 15, and the operation of the support beam 12, the hydraulic column legs 13 and the suspension structure 14 is controlled by the control chamber 15. In the present embodiment, the suspension structure 14 is a crane, and the portal structure 1 is carried by the carrier 21 (iron-car), and the carrier 21 is connected to the truck 2, and is pulled by the truck 2. The gate type architecture 1.

請參閱第2圖,係為本發明之施工現場圖。如圖所示,本發明於實際作業時,係於施工現場(鐵路橋樑A)附近設置一工地3,以供 存放新鋼橋4及舊鋼橋5,並於工地3設有吊車6,以供吊起舊鋼橋4及新鋼橋5。 Please refer to Fig. 2, which is a construction site diagram of the present invention. As shown in the figure, in the actual operation, the present invention is provided with a construction site 3 near the construction site (railway bridge A) for The new steel bridge 4 and the old steel bridge 5 are stored, and a crane 6 is provided at the construction site 3 for lifting the old steel bridge 4 and the new steel bridge 5.

藉由前述構件的組合,構成鐵路鋼橋無痕更新施工裝置。俾 於施工時,藉由搬運車2將門型架構1拖運至鐵路橋樑A需更新之鋼橋段,驅動支撐橫樑12使其橫置於油壓柱腳13下方,俾使油壓柱腳13以支撐橫樑12為定位伸展,再藉由懸吊結構14與油壓柱腳13進而使主樑11向上升起將舊鋼橋4吊起透過懸吊結構14將舊鋼橋4移動至一端吊放在載具21(鐵擔車)之上,並由搬運車2運至工地3暫放,以及由工地3搬運新鋼橋5至施工段,藉由懸吊結構14將新鋼橋5放置於原舊鋼橋4段,並完成鋪軌及鋪設人行步道橫樑及縱板之作業,從而使鐵路橋樑A之鋼橋的更新施工更具效率,且不會影響原橋樑日間鐵路運輸作業。 Through the combination of the foregoing members, a railway steel bridge seamless construction device is constructed.俾 During construction, the door structure 1 is hauled by the truck 2 to the steel bridge section of the railway bridge A, and the support beam 12 is driven to be placed under the hydraulic column leg 13 so that the hydraulic column foot 13 is The support beam 12 is positioned and stretched, and then the old steel bridge 4 is lifted by the suspension structure 14 and the hydraulic column leg 13 to lift the old steel bridge 4 through the suspension structure 14 to move the old steel bridge 4 to one end. Above the vehicle 21 (iron car), transported by the truck 2 to the work site 3 for temporary release, and the new steel bridge 5 is transported by the work site 3 to the construction section, and the new steel bridge 5 is placed by the suspension structure 14 The original old steel bridge 4 sections, and completed the work of laying rails and laying pedestrian walkway beams and vertical plates, so that the renewal of the steel bridge of the railway bridge A is more efficient, and will not affect the daytime railway transportation of the original bridge.

請同時參閱第3圖至第12圖,係為本發明之施工狀態圖。如圖所示,本發明於施工作業時,係包含以下之步驟: Please refer to FIG. 3 to FIG. 12 at the same time, which is a construction state diagram of the present invention. As shown in the figure, the present invention includes the following steps during construction work:

1、藉由搬運車2將門型架構1拖運至鐵路橋樑A需更新之鋼橋段(請參閱第3圖,並配合第2圖,搬運車2係行駛於原有之鐵路軌道)。 1. The door structure 1 is hauled by the truck 2 to the steel bridge section of the railway bridge A (see Figure 3, and with the second figure, the truck 2 is driven on the original railway track).

2、於搬運車2將門型架構1運至鐵路橋樑A需更新之鋼橋段後,藉由吊車121將支撐橫樑12由主樑11向下垂放(請參閱第4圖)。 2. After the truck 2 transports the portal structure 1 to the steel bridge section of the railway bridge A to be renewed, the support beam 12 is suspended downward from the main beam 11 by the crane 121 (see Fig. 4).

3、於支撐橫樑12垂放後,使其定位於油壓柱腳13的下方,於本實施例,係改用鍊條吊車將支撐橫樑12定位,亦可藉由其他方式操作(請 參閱第5圖)。 3. After the supporting beam 12 is placed down, it is positioned below the hydraulic column leg 13. In this embodiment, the chain crane 12 is used to position the supporting beam 12, and can be operated by other means (please See Figure 5).

4、操控油壓柱腳13伸展至定位升起,同時由搬運車2拉出載具21,完成門型架構1之定位,使門型架構1位於需更新之舊鋼橋4的上方,施工人員將舊鋼橋4由鐵路橋樑A切斷鋼軌(請參閱第6圖)。 4. The hydraulic pin 13 is extended to the position and raised, and the carrier 21 is pulled out by the truck 2 to complete the positioning of the door structure 1 so that the door structure 1 is located above the old steel bridge 4 to be renovated. Personnel cut the steel rails from the old steel bridge 4 by railroad bridge A (see Figure 6).

5、操控懸吊結構14至適當位置,藉由懸吊結構14與油壓柱腳13將舊鋼橋4吊起(請參閱第7圖)。 5. Operate the suspension structure 14 to the appropriate position, and lift the old steel bridge 4 by the suspension structure 14 and the hydraulic column leg 13 (see Figure 7).

6、搬運車2及載具21回到施工位置,已吊掛有舊鋼橋4之懸吊結構14向載具21方向移動,將舊鋼橋4垂放於載具21,由搬運車2拖回工地3,藉由吊車6將舊鋼橋4吊起存放於工地3(請參閱第8圖,並配合第2圖)。 6. The transport vehicle 2 and the carrier 21 are returned to the construction position, and the suspension structure 14 in which the old steel bridge 4 has been hung is moved in the direction of the carrier 21, and the old steel bridge 4 is placed on the carrier 21 by the transport vehicle 2 Dragged back to the site 3, the old steel bridge 4 is lifted and stored on the construction site 3 by the crane 6 (please refer to Figure 8 and cooperate with Figure 2).

7、吊車6於吊放舊鋼橋4後,再吊起新的鋼橋5及原有軌道7以及新的人行步道橫樑8(容後敘述),將新鋼橋5及新的人行步道橫樑8置於搬運車2之載具21,由搬運車2拖運至施工位置,再藉由懸吊結構14將新鋼橋5及原有之軌道7以及新的人行步道橫樑8吊起,並移動至主樑11之適當位置(請參閱第9圖,並配合第2圖)。 7. After lifting the old steel bridge 4, the crane 6 hoisted the new steel bridge 5 and the original track 7 and the new pedestrian walkway beam 8 (described later), the new steel bridge 5 and the new pedestrian walkway beam. 8 The carrier 21 placed on the truck 2 is hauled by the truck 2 to the construction site, and the new steel bridge 5 and the original rail 7 and the new pedestrian walkway beam 8 are lifted by the suspension structure 14 and Move to the appropriate position of the main beam 11 (see Figure 9 and match Figure 2).

8、藉由懸吊結構14與油壓柱腳13將新鋼橋5及原有之軌道7以及新的人行步道橫樑8放置於原舊鋼橋4之位置,將新鋼橋5予以固定,完成新鋼橋5與舊鋼橋4的更換(請參閱第10圖)。 8. The new steel bridge 5 and the original rail 7 and the new pedestrian walkway beam 8 are placed at the position of the old steel bridge 4 by the suspension structure 14 and the hydraulic column leg 13, and the new steel bridge 5 is fixed. Replace the new steel bridge 5 with the old steel bridge 4 (see Figure 10).

9、搬運車2更換載具21後回到施工位置,使載具21位於主樑11兩端下方,準備載離門型架構1(請參閱第11圖)。 9. After the carrier 2 replaces the carrier 21, it returns to the construction position, so that the carrier 21 is located below both ends of the main beam 11, and is ready to be loaded away from the door structure 1 (refer to Fig. 11).

10、門型架構1之油壓柱腳13回縮,使支撐橫樑12回收於主樑11下方,從而使主樑11兩端定位放置於搬運車2載具21,俾由搬運車2將門型架構1運離(請參閱第12圖)。 10. The hydraulic column leg 13 of the door frame structure 1 is retracted, so that the support beam 12 is recovered under the main beam 11, so that both ends of the main beam 11 are positioned and placed on the carrier 2 carrier 21, and the door type is set by the truck 2 Architecture 1 is shipped away (see Figure 12).

11、前述於完成第一個需更新之鋼橋段後,係於步驟10之動作後,由搬運車2將門型架構1拖運至次一需更新之鋼橋段,並重複第2至第10之作業步驟,從而逐步完成整條鐵路橋樑A之新鋼橋5與舊鋼橋4的更換的施工作業。 11. After completing the first steel bridge section to be updated, after the action of step 10, the door structure 1 is hauled by the truck 2 to the next steel bridge section to be updated, and the second to the second The operation steps of 10, thereby gradually completing the replacement work of the replacement of the new steel bridge 5 and the old steel bridge 4 of the entire railway bridge A.

請參閱第13圖,係為本發明之軌道及人行步道橫樑鋪設狀態 圖。如圖所示,本發明於完成新鋼橋5與舊鋼橋4的更換後,利用吊車121將人行步道橫樑8佈放於新鋼橋5之上並以人工鎖固螺栓完成,隔日清晨後利用列車空檔以人工鎖固縱板9,完成整個鐵路橋樑A之更新作業。 Please refer to Fig. 13 for the laying status of the rails and pedestrian walkways of the present invention. Figure. As shown in the figure, after the replacement of the new steel bridge 5 and the old steel bridge 4 is completed, the pedestrian walkway beam 8 is placed on the new steel bridge 5 by the crane 121 and completed by manual locking bolts, after the next morning. The vertical movement of the railway bridge A is completed by manually locking the vertical plate 9 by using the train neutral.

本發明之施工作業,至少存在有以下之優點: The construction work of the present invention has at least the following advantages:

1、整個施工期間完全不會破壞美麗環境,改變以往橋樑抽換施工需開闢施工便道及架設施工便橋或事前架設固定式天車之傳統工法,更可節省大量施工經費且不會中斷鐵路運輸(可於夜間非運輸時段施工),維持居民與觀光客的交通便利性。 1. During the whole construction period, the beautiful environment will not be destroyed at all. It is necessary to open the traditional method of constructing the construction access road and the shelf facility bridge or the fixed crane beforehand. It can save a lot of construction funds and will not interrupt the railway transportation ( It can be used during non-transportation hours at night to maintain the convenience of residents and tourists.

2、位於地勢險峻,機具、鋼橋運輸不易及操作不便之施工現場,可完全克服作業障礙。 2. It is located on the construction site where the terrain is steep, the equipment and steel bridge are not easy to transport and the operation is inconvenient, and the obstacles can be completely overcome.

3、克服傳統吊裝工法無法以移動式起重機直接開車到現場之缺失。 3. Overcome the lack of traditional hoisting methods that cannot be driven directly to the site by mobile cranes.

4、利用既有鐵道運輸鋼橋與機具安全迅速。 4. Safe and rapid use of existing railways to transport steel bridges and implements.

5、為綠建築無痕工法,於施工期間完全不需破壞自然環境,達到友善環境、永續經營之目的。 5. There is no trace method for green buildings. During the construction period, there is no need to destroy the natural environment and achieve the purpose of friendly environment and sustainable operation.

前述實施例,僅為說明本發明之較佳實施方式,而非限制本 發明之範圍,凡經由些微修飾、變更,仍不失本發明之要義所在,亦不脫本發明之精神範疇。 The foregoing embodiments are merely illustrative of preferred embodiments of the invention, and are not intended to The scope of the invention is not limited to the spirit and scope of the invention.

綜上所述,本創作以設有主樑、支撐橫樑、油壓柱腳及懸 吊結構之門型架構,配合帶動門型架構之搬運車可快速移動、架設、吊裝、拆離步驟,構成鐵路鋼橋更新施工裝置,使鐵路鋼橋的更新施工更具效率,改變以往橋樑抽換施工需開闢施工便道及架設施工便橋或架設固定式天車之傳統工法,更可節省大量施工經費且不會破壞美麗環境,以及不會中斷鐵路的正常運輸通行。為一實用之設計,誠屬一俱新穎性之發明,爰依法提出專利之申請,祈 鈞局予以審查,早日賜准專利,至感德便。 In summary, the creation is provided with a main beam, a supporting beam, a hydraulic column foot and a suspension. The door structure of the hoisting structure can be quickly moved, erected, hoisted and detached with the truck with the door type structure to form a railway steel bridge renewal construction device, which makes the railway steel bridge update construction more efficient and changes the previous bridge pumping For the construction of the construction, it is necessary to open up the traditional construction method of the construction access road and the shelf facility or the fixed crane. It can save a lot of construction funds and will not damage the beautiful environment and will not interrupt the normal transportation of the railway. For a practical design, it is an invention of novelty. If you apply for a patent in accordance with the law, you will be punished by the Bureau of Prosecution, and you will be granted a patent as soon as possible.

Claims (5)

一種鐵路鋼橋無痕更新施工方法,包含:於需抽換之鐵路橋樑施工現場附近設置一工地,以供存放新製鋼橋及抽換後之舊鋼橋,並於工地設有吊車,以供吊起舊鋼橋及新鋼橋;設置一門型架構,係設有一主樑,於該主樑下方兩端適當位置分別設有可上、下移動之支撐橫樑,主樑的兩端側方係分別設有油壓柱腳,上方則設有可沿該主樑移動之懸吊結構,該門型架構係置於一連接於搬運車之載具;藉由搬運車及載具將門型架構拖運至鐵路橋樑需更新之鋼橋段,置放支撐橫樑使其橫置於油壓柱腳下方,俾使油壓柱腳以支撐橫樑為定位伸展,進而使主樑向上升起;將舊鋼橋由鐵路橋樑切斷,藉由門型架構之懸吊結構將舊鋼橋吊起,並由搬運車運至工地存放;由搬運車將新鋼橋搬運至施工現場,藉由門型架構之懸吊結構將新鋼橋放置於原舊鋼橋之位置;於新鋼橋鋪設軌道及人行步道橫樑以及縱板,完成整個鐵路橋樑之鋼橋的更新作業。 A construction method for railway steel bridge without traces, comprising: setting a construction site near the construction site of the railway bridge to be exchanged for storing the new steel bridge and the old steel bridge after the replacement, and providing a crane at the construction site for Lifting the old steel bridge and the new steel bridge; setting a door structure with a main beam, and supporting beams at the two ends below the main beam, which can be moved up and down, and the two ends of the main beam are laterally There are hydraulic column legs respectively, and a suspension structure movable along the main beam is arranged at the top. The door structure is placed on a carrier connected to the truck; the door structure is dragged by the truck and the carrier. Shipped to the steel bridge section of the railway bridge, the supporting beam is placed so as to be placed under the foot of the hydraulic column, so that the hydraulic column foot is extended by the supporting beam, so that the main beam rises upward; The bridge is cut off by the railway bridge. The old steel bridge is lifted by the suspension structure of the door structure and transported by the truck to the construction site. The new steel bridge is transported by the van to the construction site, with the door structure. Suspension structure places the new steel bridge in the position of the old steel bridge; Yu Xin Bridge laying track and pedestrian trails beams and vertical panels, complete the update operation of the entire steel bridge railway bridge. 如申請專利範圍第1項所述之鐵路鋼橋更新施工方法,其中,主樑上方係設有吊車,支撐橫樑為可快速臨時連結於吊車,藉由吊車移動支撐橫樑之上、下動作。 For example, the railway steel bridge renewal construction method described in claim 1 is characterized in that a crane is arranged above the main beam, and the support beam is fast and temporarily connected to the crane, and the crane supports the upper and lower movements of the beam. 如申請專利範圍第1項所述之鐵路鋼橋更新施工方法,其中,主樑的端部係分別設有控制室,藉由控制室控制支撐橫樑、油壓柱腳及懸吊結構之 動作。 For example, the railway steel bridge renewal construction method described in claim 1 is characterized in that the end portions of the main beam are respectively provided with a control room, and the control beam controls the support beam, the hydraulic column foot and the suspension structure. action. 如申請專利範圍第1項所述之鐵路鋼橋更新施工方法,其中,懸吊結構係為天車。 For example, the railway steel bridge renewal construction method described in claim 1 is characterized in that the suspension structure is a crane. 如申請專利範圍第1項所述之鐵路鋼橋更新施工方法,其中,搬運車所連接之載具係為鐵担車。 For example, the railway steel bridge renewal construction method described in claim 1 is characterized in that the carrier connected to the truck is an iron-powered vehicle.
TW104125588A 2015-08-06 2015-08-06 Railway steel bridge without trace renewal construction method TWI621752B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
TW104125588A TWI621752B (en) 2015-08-06 2015-08-06 Railway steel bridge without trace renewal construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
TW104125588A TWI621752B (en) 2015-08-06 2015-08-06 Railway steel bridge without trace renewal construction method

Publications (2)

Publication Number Publication Date
TW201706477A TW201706477A (en) 2017-02-16
TWI621752B true TWI621752B (en) 2018-04-21

Family

ID=58608930

Family Applications (1)

Application Number Title Priority Date Filing Date
TW104125588A TWI621752B (en) 2015-08-06 2015-08-06 Railway steel bridge without trace renewal construction method

Country Status (1)

Country Link
TW (1) TWI621752B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108423031B (en) * 2018-03-27 2020-05-26 株洲时代电子技术有限公司 Seamless line micro-displacement measuring method

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1900423A (en) * 2006-07-10 2007-01-24 中铁大桥局股份有限公司 Integrate section frame building method for steel truss

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1900423A (en) * 2006-07-10 2007-01-24 中铁大桥局股份有限公司 Integrate section frame building method for steel truss

Also Published As

Publication number Publication date
TW201706477A (en) 2017-02-16

Similar Documents

Publication Publication Date Title
CA2812335C (en) Bridge span replacement system
JP6476426B2 (en) Member renewal method using lifting device
JP5318538B2 (en) Steel structure construction method
WO2019080824A1 (en) Novel track laying machine for urban rail transport project and construction method therefor
JP7193172B2 (en) Floor slab erection machine
CA2812336A1 (en) Bridge span replacement method
JP2021070978A (en) Heavy object movement device and heavy object movement method using the heavy object movement device
JP5507383B2 (en) Heavy load erection machine and heavy load erection method
WO2022001169A1 (en) Highway-railway dual-purpose track-laying machine for urban rail transit engineering
CN111038940A (en) Rail mounted is used for hoist and mount traction system of transportation
CN207498754U (en) A kind of novel track-laying machine of city track traffic engineering
JP5184248B2 (en) Construction method of level crossing
TWM516060U (en) Railway steel beam bridge seamless update construction device
JP2006028881A (en) Self-propelled pc floor slab erecting machine and pc floor slab erecting method
TWI621752B (en) Railway steel bridge without trace renewal construction method
CN204151699U (en) A kind of frame plate machine for changing steel truss girder bridge bridge deck
CN102225580B (en) Method for longitudinally moving box girder internal mold
KR101024784B1 (en) Rotation bridge deck establishment method and equipment by means of move-car and rotation plate
CN111719358A (en) Highway-railway dual-purpose track laying machine for urban rail transit engineering and use method thereof
CN106192761A (en) A kind of method disassembling mobile formwork in bridge tunnel narrow short transition time section
JP6672545B2 (en) Removal member removal method and member replacement method
JP4330141B2 (en) Precast concrete floor laying equipment
CN107285209A (en) A kind of Novel U-shaped erection equipment and its operating method
CN104164838A (en) Light combined type beam moving trolley
CN207108292U (en) Novel U-shaped erection equipment