CN1851137A - Gate-type crane semiarch integral-hoisting steel-pipe arch process - Google Patents

Gate-type crane semiarch integral-hoisting steel-pipe arch process Download PDF

Info

Publication number
CN1851137A
CN1851137A CN 200610042740 CN200610042740A CN1851137A CN 1851137 A CN1851137 A CN 1851137A CN 200610042740 CN200610042740 CN 200610042740 CN 200610042740 A CN200610042740 A CN 200610042740A CN 1851137 A CN1851137 A CN 1851137A
Authority
CN
China
Prior art keywords
arch
gantry crane
steel tube
steel
tube arch
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN 200610042740
Other languages
Chinese (zh)
Inventor
孙永刚
李世清
张金灵
郝良秋
李宏涛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway First Engineering Group Co Ltd
Original Assignee
China Railway First Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway First Engineering Group Co Ltd filed Critical China Railway First Engineering Group Co Ltd
Priority to CN 200610042740 priority Critical patent/CN1851137A/en
Publication of CN1851137A publication Critical patent/CN1851137A/en
Pending legal-status Critical Current

Links

Images

Abstract

The invention relates to erecting construction of a steel pipe concrete arch bridge, especially a door crane-used half-arch integral steel pipe arch hoisting process, dividing each arch rib into two hoisted units, where each 1/2 arch is hoisted by two door cranes, where a fixed door crane serves as an arch span hoister and an active door crane serves as an arch foot hoister. And the invention is applied to bottom, middle and top bearing arch bridges constructed by bracket-free process. And the span of the steel pipe arch installed by the invention can reach above 300 meters, and the weight of the installed steel pipe can reach above 2000 tons. And it does not influence navigation, able to applied to single- or multiple- span construction; the hoisting safety is higher; and the shape of the arch axis is good; it needs no huge anchoring system and applied to various arch bridges.

Description

Gate-type crane semiarch integral-hoisting steel-pipe arch process
Technical field
The invention belongs to technical field of bridge construction, relate to the erection construction of concrete-filled steel tubes arch bridge, particularly gate-type crane semiarch integral-hoisting steel-pipe arch process.
Background technology
One of topmost operation is exactly that arch rib is installed in the concrete-filled steel tubes arch bridge construction, and the method for installation has: no support cable lifting; The lifting of limited bracket cable; Full wafer arch rib or limited bracket crane barge are installed; The lifting of suspension bridge type cable; Rotator construction; Assemble on the support; Jack tiltedly draws button to hang cantilever etc.
Tiltedly draw button extension cantilever method and rotation swivel construction method to do simple the introduction with jack comparatively commonly used.It is exactly to utilize the Suo Li that is used to detain the suspension cable of hanging steel pipe when lifting to adjust arch rib axis deformation when controlling the lifting absolute altitude and adjusting the cast of pipe inner concrete that jack tiltedly draws button to hang that cantilever installs.Need handling, button to hang two cover systems, equipment has high input; Long construction period; Working security is poor; Lift limited in one's ability; Huge anchor ingot system need be set; Become line of apsides shape error big; Remove difficulty.
Construction by swing generally is applicable to the construction of all kinds of single hole arch bridges, its basic principle is: arch ring or whole superstructure are divided into two and half stride, utilize landform or simple beam to be assembled into semiarch in the two sides, river respectively, utilize dynamical system that its two halves are striden donor then and turn to bridge axial location (or design elevation) and join the two sections of a bridge, etc into arch.The Construction of Swivel of Arch Bridge method according to the difference of its rotational orientation be divided into turning in the plane, two kinds of vertical turns.Turning to be divided in the plane has two kinds of balance weight rotator construction and no balance weight rotator constructions.There is the balance weight rotator construction of turning only to be applicable to the single hole bridge; Balance weight is excessive uneconomical; Construction span less (span is not more than 160m), no balance weight rotator construction only is applicable to the single hole bridge; Only be applicable to geological conditions V-arrangement riverbed construction preferably; The anchoring system complexity; The cable lifting construction is long in time limit; Construction equipment has high input; Huge anchor ingot system need be set; Working security is poor; Lift limited in one's ability; Become line of apsides shape error bigger, the arch internal stress is bigger; Remove difficulty.
Summary of the invention
The present invention proposes a kind of gate-type crane semiarch integral-hoisting steel-pipe arch process, and this is a kind of brand-new arch rib Installation Modes, and its span that steel tube arch is installed can reach more than 300 meters, and its installed steel pipe arch weight can reach more than 2000 tons.
Technical scheme of the present invention is: gate-type crane semiarch integral-hoisting steel-pipe arch process comprises the steps:
1.1 gantry crane setting and steel tube arch transportation by driving are in place
Whenever stride down stride the footpath 1/3 and 2/3 place be provided with a fixedly gantry crane, stride steel tube arch front end lifting appliance as 1/2, two arch springing places respectively establish a movable gantry crane, stride steel tube arch rear end lifting appliance as 1/2, the whole steel tube arch of striding is divided into four sections and processes in factory, after assembly unit welding and the passed examination, with the iron barge ship on the water transportation by driving to bridge location handle affairs establish earlier two fixedly under the gantry crane;
1.2 1/4 vault rises and butt joint
Two 1/4 arch closure end next doors are set up support and are used two table oils top jacking simultaneously steel tube arch on the iron barge ship, and successively increase to prop up and fill up to design height, after 1/4 steel tube arch jacking puts in place two ship tractions are docked, adjust the hull position, two 1/4 arch axis lines are adhered to specification, fixedly truss on two ships is connected, make two ship shape become whole;
1.3 1/4 arch closure is 1/2 arch
By oil top fine setting steel tube arch facade line style, make the accurate contraposition of steel tube arch, its axis and close up an absolute altitude and satisfy code requirement, with the arch abutment outward flange by the aligned in position during pre-assembly the in the factory, junction plate is installed, is carried out repetition measurement once more, after meeting the requirements fully it is welded on request, form 1/2 arch ring, the moulding of half range main arch rib was waited to hang after butt welded seam carried out 100% ultrasonic testing/ ultrasonic examination passed examination after having welded;
1.4 1/2 arch section promotes
After the hull translation puts in place, on steel tube arch, install forward and backward suspender, at first fixedly promote the oil top on gantry crane and the movable gantry crane continuously by 1/2 good steel tube arch of 2 level liftings simultaneously of steel strand welding, after treating that steel tube arch has just broken away from support, only start the fixedly oily continuously top of the preceding suspension centre of gantry crane, slowly promote steel tube arch by steel strand; Treat that 1/2 arches upward and hangs axis when substantially parallel with theoretical axis, suspension centre oil top continuously behind the startup activity gantry crane, the front and back suspension centre promotes steel tube arch synchronously;
1.5 arch springing pin joint
The steel tube arch arch springing cuts with scissors when arriving design height temporarily, adjusts the arch springing position, penetrates interim hinge pin axle, slowly promotes preceding suspension centre and measures absolute altitude at any time, and the arch axis line is overlapped with theoretical axis, finishes semiarch and installs;
1.6 in like manner finish 1/2 arch installation in addition;
1.7 vault closes up
Promote the oil top by fixing gantry crane and accurately adjust vault absolute altitude and linear, survey temperature at that time, add the temperature correction value, according to the vault size, steel pipe is reserved in cutting and installation in position welds, and finishes arch ring and closes up;
1.8 cable wind rope is laid
After arch ring closes up,, 4 road cable wind ropes are set in the every side of arch ring in order to prevent bridge location place wind effect;
1.9 gantry crane and arch ring cable wind rope are removed
In like manner finish other one side steel tube arch and install, and the beam wind support is installed, after the two sides steel tube arch is stable, remove gantry crane and arch ring cable wind rope.
Described gantry crane adopts fixedly gantry crane and movable gantry crane, the gantry crane overall height is meter lifting spaces, spring of arch+10, the gantry crane width be bridge wide+4~6 meters, a gantry crane hoisting weight can reach 600~800 tons, promptly adopts four gantry crane integral lifting of half arch that the steel tube arch that weighs about 2000~3000 tons can be installed; 300~400 tons of movable gantry crane hoisting weights; The gantry crane lifting means uses and promotes jack continuously, and its maximum lift weight can reach more than 1000 tons, during work, moves back and forth drive moveable anchor clamping steel strand by two table oil top oil cylinders and promotes steel tube arch continuously.
The present invention is applicable to lower support type, half-through, the Deck Arch Bridges construction of no rack technique construction.For the bigger arch bridge of span, its superiority is more obvious, and is applicable to highway, municipal bridge construction that the duration is short.Adopt the present invention's construction not influence navigation; Can be used for the construction of single span or multispan; The lifting safety is higher; Lifting is subjected to wind effect little; Field welding is few, and the arch axis line is linear good; Crane capacity hangs much larger than cable; The construction equipment input is hung much smaller than cable; Construction period is short; Huge anchor ingot system need be set; Be applicable to all kinds of arch bridges.
Description of drawings
Accompanying drawing is an installation steps schematic diagram of the present invention.
The specific embodiment
Construction general arrangement and hanging device
1 construction general arrangement
Gate-type crane semiarch integral-hoisting steel-pipe arch is that every arch rib is divided into two lifting elements, and per 1/2 arch adopts two gantry cranes to lift by crane.Fixedly gantry crane is as lifting appliance in 1/2 span of arch, and movable gantry crane is as 1/2 arch arch springing lifting appliance.
2 hanging devices
2.1 fixing gantry crane
Fixedly gantry crane is made up of gantry crane, pile foundation support table basis and cable wind rope three parts.
1., gantry crane
The gantry crane overall height is determined according to steel tube arch spring of arch and lifting space, is generally meter lifting space (comprising spreader height), spring of arch+10.The gantry crane width determines according to bridge width, be generally bridge wide+4~6 meters.
Gantry crane is made up of column, crossbeam two parts.Gantry crane column and crossbeam can be assembled by universal rod body, also can adopt the formingspace trussed construction.Its form of fracture calculates according to hoisting weight to be determined.
A gantry crane hoisting weight can reach 600~800 tons.Promptly adopt four gantry crane integral lifting of half arch that the steel tube arch that weighs about 2000 tons can be installed.
2., gantry crane basis
Open cut foundation or pile foundation support table form of structure can be adopted according to lifting weight and geological condition in the gantry crane basis.For hoisting weight less can adopt open cut foundation, for the bigger then employing pile foundation support table form of structure of hoisting weight.
3., gantry crane cable wind rope
Cable wind rope is arranged on the gantry crane both sides, be divided into along bridge to two kinds of directions of direction across bridge.Be anchored in main pier cushion cap along bridge to cable wind rope.The direction across bridge cable wind rope is anchored in the suitable distance water of door frame both sides on the anchor.
According to the stressed size in the hoisting process, determine the quantity of cable wind rope.
2.2 movable gantry crane
Movable gantry crane except when the lifting steel tube arch arch rib as the back suspension centre, go back double as trigonum goods and materials lifting appliance.
Movable gantry crane hoisting weight is by fixedly gantry crane hoisting weight 1/2 design, and promptly its hoisting weight is by 300~400 tons of designs.
2.3 promote jack continuously
The gantry crane lifting means uses and promotes jack continuously, and its maximum lift weight can reach more than 1000 tons.During work, move back and forth drive moveable anchor clamping steel strand by two table oil top oil cylinders and promote steel tube arch continuously.
The gate-type crane semiarch integral-hoisting steel-pipe arch construction technology process is as follows:
Make in the factory 1/4 steel tube arch arch sections-→ construction arching interim gantry crane-→ 1/4 arch sections transportation-→ 1/4 steel tube arch sections jacking-→ two in place 1/4 an arch sections butt joint form 1/2 arch-→ 1/2 an arch sections promote the interim hinge pin of-→ 1/2 arch sections arch springing connect-→ two 1/2 arch closures-→ half range arch ring closure in addition-→ install wind brace-→ arch springing builds
Steel tube arch is set up concrete construction sequence
1.1 gantry crane setting and steel tube arch transportation by driving are in place
Whenever stride down stride the footpath 1/3 and 2/3 place be provided with a fixedly gantry crane, stride steel tube arch front end lifting appliance as 1/2, two arch springing places respectively establish a movable gantry crane, stride steel tube arch rear end lifting appliance as 1/2, the whole steel tube arch of striding is divided into four sections and processes in factory, after assembly unit welding and the passed examination, with the iron barge ship on the water transportation by driving to bridge location handle affairs establish earlier two fixedly under the gantry crane;
1.2 1/4 vault rises and butt joint
Two 1/4 arch closure end next doors are set up support and are used two table oils top jacking simultaneously steel tube arch on the iron barge ship, and successively increase to prop up and fill up to design height, after 1/4 steel tube arch jacking puts in place two ship tractions are docked, adjust the hull position, two 1/4 arch axis lines are adhered to specification, fixedly truss on two ships is connected, make two ship shape become whole;
1.3 1/4 arch closure is 1/2 arch
By oil top fine setting steel tube arch facade line style, make the accurate contraposition of steel tube arch, its axis and close up an absolute altitude and satisfy code requirement, with the arch abutment outward flange by the aligned in position during pre-assembly the in the factory, junction plate is installed, is carried out repetition measurement once more, after meeting the requirements fully it is welded on request, form 1/2 arch ring, welding comprises web member intersection, main chord tube butt joint circumferential weld, the welding of batten plate embedding benefit section.The moulding of half range main arch rib was waited to hang after butt welded seam carried out 100% ultrasonic testing/ ultrasonic examination passed examination after having welded.
1.4 1/2 arch section promotes
After the hull translation puts in place, on steel tube arch, install forward and backward suspender, at first fixedly promote the oil top on gantry crane and the movable gantry crane continuously by 1/2 good steel tube arch of 2 level liftings simultaneously of steel strand welding, after treating that steel tube arch has just broken away from support, only start the fixedly oily continuously top of the preceding suspension centre of gantry crane, slowly promote steel tube arch by steel strand; Treat that 1/2 arches upward and hangs axis when substantially parallel with theoretical axis, suspension centre oil top continuously behind the startup activity gantry crane, the front and back suspension centre promotes steel tube arch synchronously;
1.5 arch springing pin joint
The steel tube arch arch springing cuts with scissors when arriving design height temporarily, adjusts the arch springing position, penetrates interim hinge pin axle, slowly promotes preceding suspension centre and measures absolute altitude at any time, and the arch axis line is overlapped with theoretical axis, finishes semiarch and installs;
1.6 in like manner finish 1/2 arch installation in addition;
1.7 vault closes up
Promote the oil top by fixing gantry crane and accurately adjust vault absolute altitude and linear, survey temperature at that time, add the temperature correction value, according to the vault size, steel pipe is reserved in cutting and installation in position welds, and finishes arch ring and closes up;
1.8 cable wind rope is laid
After arch ring closes up,, 4 road cable wind ropes are set in the every side of arch ring in order to prevent bridge location place wind effect;
1.9 gantry crane and arch ring cable wind rope are removed
In like manner finish other one side steel tube arch and install, and the beam wind support is installed, after the two sides steel tube arch is stable, remove gantry crane and arch ring cable wind rope.

Claims (2)

1, gate-type crane semiarch integral-hoisting steel-pipe arch process is characterized in that: described technology comprises the steps:
1.1 gantry crane setting and steel tube arch transportation by driving are in place
Whenever stride down stride the footpath 1/3 and 2/3 place be provided with a fixedly gantry crane, stride steel tube arch front end lifting appliance as 1/2, two arch springing places respectively establish a movable gantry crane, stride steel tube arch rear end lifting appliance as 1/2, the whole steel tube arch of striding is divided into four sections and processes in factory, after assembly unit welding and the passed examination, with the iron barge ship on the water transportation by driving to bridge location handle affairs establish earlier two fixedly under the gantry crane;
1.2 1/4 vault rises and butt joint
Two 1/4 arch closure end next doors are set up support and are used two table oils top jacking simultaneously steel tube arch on the iron barge ship, and successively increase to prop up and fill up to design height, after 1/4 steel tube arch jacking puts in place two ship tractions are docked, adjust the hull position, two 1/4 arch axis lines are adhered to specification, fixedly truss on two ships is connected, make two ship shape become whole;
1.3 1/4 arch closure is 1/2 arch
By oil top fine setting steel tube arch facade line style, make the accurate contraposition of steel tube arch, its axis and close up an absolute altitude and satisfy code requirement, with the arch abutment outward flange by the aligned in position during pre-assembly the in the factory, junction plate is installed, is carried out repetition measurement once more, after meeting the requirements fully it is welded on request, form 1/2 arch ring, the moulding of half range main arch rib was waited to hang after butt welded seam carried out 100% ultrasonic testing/ ultrasonic examination passed examination after having welded;
1.4 1/2 arch section promotes
After the hull translation puts in place, on steel tube arch, install forward and backward suspender, at first fixedly promote the oil top on gantry crane and the movable gantry crane continuously by 1/2 good steel tube arch of 2 level liftings simultaneously of steel strand welding, after treating that steel tube arch has just broken away from support, only start the fixedly oily continuously top of the preceding suspension centre of gantry crane, slowly promote steel tube arch by steel strand; Treat that 1/2 arches upward and hangs axis when substantially parallel with theoretical axis, suspension centre oil top continuously behind the startup activity gantry crane, the front and back suspension centre promotes steel tube arch synchronously;
1.5 arch springing pin joint
The steel tube arch arch springing cuts with scissors when arriving design height temporarily, adjusts the arch springing position, penetrates interim hinge pin axle, slowly promotes preceding suspension centre and measures absolute altitude at any time, and the arch axis line is overlapped with theoretical axis, finishes semiarch and installs;
1.6 in like manner finish 1/2 arch installation in addition;
1.7 vault closes up
Promote the oil top by fixing gantry crane and accurately adjust vault absolute altitude and linear, survey temperature at that time, add the temperature correction value, according to the vault size, steel pipe is reserved in cutting and installation in position welds, and finishes arch ring and closes up;
1.8 cable wind rope is laid
After arch ring closes up,, 4 road cable wind ropes are set in the every side of arch ring in order to prevent bridge location place wind effect;
1.9 gantry crane and arch ring cable wind rope are removed
In like manner finish other one side steel tube arch and install, and the beam wind support is installed, after the two sides steel tube arch is stable, remove gantry crane and arch ring cable wind rope.
2, gate-type crane semiarch integral-hoisting steel-pipe arch process as claimed in claim 1, it is characterized in that: described gantry crane adopts fixedly gantry crane and movable gantry crane, the gantry crane overall height is meter lifting spaces, spring of arch+10, the gantry crane width be bridge wide+4~6 meters, a gantry crane hoisting weight can reach 600~800 tons, promptly adopts four gantry crane integral lifting of half arch that the steel tube arch that weighs about 2000~3000 tons can be installed; 300~400 tons of movable gantry crane hoisting weights; The gantry crane lifting means uses and promotes jack continuously, and its maximum lift weight can reach more than 1000 tons, during work, moves back and forth drive moveable anchor clamping steel strand by two table oil top oil cylinders and promotes steel tube arch continuously.
CN 200610042740 2006-04-27 2006-04-27 Gate-type crane semiarch integral-hoisting steel-pipe arch process Pending CN1851137A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 200610042740 CN1851137A (en) 2006-04-27 2006-04-27 Gate-type crane semiarch integral-hoisting steel-pipe arch process

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 200610042740 CN1851137A (en) 2006-04-27 2006-04-27 Gate-type crane semiarch integral-hoisting steel-pipe arch process

Publications (1)

Publication Number Publication Date
CN1851137A true CN1851137A (en) 2006-10-25

Family

ID=37132638

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 200610042740 Pending CN1851137A (en) 2006-04-27 2006-04-27 Gate-type crane semiarch integral-hoisting steel-pipe arch process

Country Status (1)

Country Link
CN (1) CN1851137A (en)

Cited By (19)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101852017A (en) * 2010-06-03 2010-10-06 重庆交通大学 Pouring method of tailrace tube bifurcation concrete for hydraulic power station without bracket
CN101871198A (en) * 2010-07-16 2010-10-27 上海同济宝冶建设机器人有限公司 Vertical turning lifting installation method for steel bridge arch ribs
CN101725179B (en) * 2009-11-06 2011-04-06 清华大学 Construction method of integrally rotating, drawing up and slipping large steel arch structure
CN102561207A (en) * 2010-12-31 2012-07-11 中铁工程设计咨询集团有限公司 Construction method for vertically rotating arch rib
CN102733312A (en) * 2012-07-03 2012-10-17 宁波二十冶建设有限公司 Arch rib manufacturing process
CN103147401A (en) * 2013-03-06 2013-06-12 中交一公局第一工程有限公司 Construction method and structure of self-climbing portal frame
CN103711081A (en) * 2013-12-26 2014-04-09 中国一冶集团有限公司 Method for locating position of flange on upper end opening of skewback through coordinate correction method
CN104328740A (en) * 2014-11-10 2015-02-04 中铁武桥重工(珠海)有限公司 Large-span steel tubular arched bridge vertical rotation construction and linear control method
CN104404887A (en) * 2014-12-01 2015-03-11 中铁二十局集团第一工程有限公司 Large span steel tube arch bridge stents-free hoisting process
CN104594197A (en) * 2014-12-01 2015-05-06 中铁二十局集团第一工程有限公司 Construction process of large-span steel tube arch bridge without supports
CN105274940A (en) * 2015-10-15 2016-01-27 辽宁金建工业安装工程有限公司 Integrated mounting method for bridge arch rib
CN105803952A (en) * 2014-12-29 2016-07-27 杨光华 Assembly process equipment for overhauling of bridge girder with three-hinged arch mechanism
CN105839546A (en) * 2016-06-01 2016-08-10 中交四公局第五工程有限公司 Arch rib buckling and hanging installing structure of steel pipe arch bridge
CN106012864A (en) * 2016-07-27 2016-10-12 中铁上海工程局集团有限公司 Method for lifting and installing whole bridge arch rib
CN109680619A (en) * 2019-01-18 2019-04-26 中铁三局集团有限公司 A kind of steel truss beam sling Arch Bridge Construction method big suitable for environmental restrictions
CN110104548A (en) * 2018-12-18 2019-08-09 南通振华重型装备制造有限公司 A kind of gantry crane main beam structure method of construction
CN110565527A (en) * 2019-08-06 2019-12-13 中交第一航务工程局有限公司 Method for installing prestressed T-beam on non-rotating synchronous double-lifting-hoisting sea
CN111636306A (en) * 2020-06-03 2020-09-08 中铁上海工程局集团有限公司 Construction method for sectional assembly and integral lifting of large-span steel box arch rib
WO2022099548A1 (en) * 2020-11-12 2022-05-19 China Railway No.3 Engineering Group Co.Ltd Method for installing steel tube arches

Cited By (27)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101725179B (en) * 2009-11-06 2011-04-06 清华大学 Construction method of integrally rotating, drawing up and slipping large steel arch structure
CN101852017A (en) * 2010-06-03 2010-10-06 重庆交通大学 Pouring method of tailrace tube bifurcation concrete for hydraulic power station without bracket
CN101871198A (en) * 2010-07-16 2010-10-27 上海同济宝冶建设机器人有限公司 Vertical turning lifting installation method for steel bridge arch ribs
CN102561207A (en) * 2010-12-31 2012-07-11 中铁工程设计咨询集团有限公司 Construction method for vertically rotating arch rib
CN102733312A (en) * 2012-07-03 2012-10-17 宁波二十冶建设有限公司 Arch rib manufacturing process
CN103147401B (en) * 2013-03-06 2015-03-25 中交一公局第一工程有限公司 Construction method of self-climbing portal frame
CN103147401A (en) * 2013-03-06 2013-06-12 中交一公局第一工程有限公司 Construction method and structure of self-climbing portal frame
CN103711081A (en) * 2013-12-26 2014-04-09 中国一冶集团有限公司 Method for locating position of flange on upper end opening of skewback through coordinate correction method
CN104328740A (en) * 2014-11-10 2015-02-04 中铁武桥重工(珠海)有限公司 Large-span steel tubular arched bridge vertical rotation construction and linear control method
CN104594197B (en) * 2014-12-01 2016-03-23 中铁二十局集团第一工程有限公司 A kind of long-span steel pipe arch bridge non-support construction process
CN104404887A (en) * 2014-12-01 2015-03-11 中铁二十局集团第一工程有限公司 Large span steel tube arch bridge stents-free hoisting process
CN104594197A (en) * 2014-12-01 2015-05-06 中铁二十局集团第一工程有限公司 Construction process of large-span steel tube arch bridge without supports
CN105803952A (en) * 2014-12-29 2016-07-27 杨光华 Assembly process equipment for overhauling of bridge girder with three-hinged arch mechanism
CN105274940A (en) * 2015-10-15 2016-01-27 辽宁金建工业安装工程有限公司 Integrated mounting method for bridge arch rib
CN105274940B (en) * 2015-10-15 2016-08-24 辽宁金建工业安装工程有限公司 A kind of bridge arch rib integral installation method
CN105839546A (en) * 2016-06-01 2016-08-10 中交四公局第五工程有限公司 Arch rib buckling and hanging installing structure of steel pipe arch bridge
CN106012864A (en) * 2016-07-27 2016-10-12 中铁上海工程局集团有限公司 Method for lifting and installing whole bridge arch rib
CN106012864B (en) * 2016-07-27 2017-10-13 中铁上海工程局集团有限公司 A kind of method of the overall erection & lift of bridge arch rib
CN110104548B (en) * 2018-12-18 2020-06-05 南通振华重型装备制造有限公司 Construction method of gantry crane main beam structure
CN110104548A (en) * 2018-12-18 2019-08-09 南通振华重型装备制造有限公司 A kind of gantry crane main beam structure method of construction
CN109680619A (en) * 2019-01-18 2019-04-26 中铁三局集团有限公司 A kind of steel truss beam sling Arch Bridge Construction method big suitable for environmental restrictions
CN110565527A (en) * 2019-08-06 2019-12-13 中交第一航务工程局有限公司 Method for installing prestressed T-beam on non-rotating synchronous double-lifting-hoisting sea
CN110565527B (en) * 2019-08-06 2021-03-19 中交第一航务工程局有限公司 Method for installing prestressed T-beam on non-rotating synchronous double-lifting-hoisting sea
CN111636306A (en) * 2020-06-03 2020-09-08 中铁上海工程局集团有限公司 Construction method for sectional assembly and integral lifting of large-span steel box arch rib
CN111636306B (en) * 2020-06-03 2022-06-03 中铁上海工程局集团有限公司 Construction method for sectional assembly and integral lifting of large-span steel box arch rib
WO2022099548A1 (en) * 2020-11-12 2022-05-19 China Railway No.3 Engineering Group Co.Ltd Method for installing steel tube arches
US11655600B2 (en) 2020-11-12 2023-05-23 China Railway No.3 Engineering Group Co.Ltd Method for installing steel tube arches

Similar Documents

Publication Publication Date Title
CN1851137A (en) Gate-type crane semiarch integral-hoisting steel-pipe arch process
CN110952550B (en) Suspended self-supporting pile driving method and pile driver
CN103669211B (en) Hydraulic multi-function cantilever lifting beam machine and steel box girder assembling method
CN103290784B (en) Arched girder conjugative bridge construction method for hanging
CN102561191A (en) Integral lifting system and construction method for arch bridge ribs
CN101078198A (en) Steel box beam erection method for self-anchored suspension bridge
CN110258293A (en) Cable-stayed bridge steel truss girder main pylon pier top erection construction method
CN2719998Y (en) Climbing device of hydraulic automatic climbing imitation system
CN111501584A (en) Bridge dismantling construction method for prestressed concrete continuous beam
CN103216103A (en) Pre-deformation construction method for mounting oblique-arc-shaped combined steel-structured column of annular roof
CN206204766U (en) Single column pier bridge antidumping diagonal brace bracing means
CN103132702A (en) Longspan pipe truss pulling bar lifting and overhead rotating emplacing construction method
CN206538687U (en) Cable-stayed bridge end bay beam section construction system
CN106193284B (en) The installation method and mounting structure of large span space drop level continuous truss frame
CN206800215U (en) Bridge incremental launching Bridge Erector
CN211113627U (en) Unsettled self-supporting formula pile driver
CN105484166A (en) Ladder-shaped mast type cantilever assembling crane
CN210855047U (en) Be suitable for transmission material between reverse construction method floor with small-size swing arm formula electric hoist
CN101041948A (en) Construction equipment for integral roof-holding highway bridge top superstructure
CN210177371U (en) Cable-stayed cantilever type integrated bridge girder erection machine capable of piling
CN205171343U (en) Combination beam self anchored suspension bridge
CN209797311U (en) Combined lifting tower crane on self-climbing heavy hoister
CN1793521A (en) Optimizing frictional resistance bored concrete pile construction equipment and its bored concrete pule and construction method thereof
CN112695607A (en) Construction method and system for asymmetric cantilever beam of cable-stayed bridge
CN106120880A (en) A kind of offshore wind farm single-pile foundation Compressive Bearing Capacity assay device

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication