CN1884724A - 复合式堆载静载荷试验方法 - Google Patents
复合式堆载静载荷试验方法 Download PDFInfo
- Publication number
- CN1884724A CN1884724A CN 200610012888 CN200610012888A CN1884724A CN 1884724 A CN1884724 A CN 1884724A CN 200610012888 CN200610012888 CN 200610012888 CN 200610012888 A CN200610012888 A CN 200610012888A CN 1884724 A CN1884724 A CN 1884724A
- Authority
- CN
- China
- Prior art keywords
- preloading
- pouring weight
- platform
- weight
- ballast
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Landscapes
- Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)
Abstract
一种复合式堆载静载荷试验方法,包括以下步骤:(1)制作堆载重块;(2)制作压重平台;(3)堆砌压重平台支座;(4)连接支座与压重平台;(5)根据载荷试验要求堆载荷重。本发明采用堆载重块做压重平台支座,并与压重平台机械地连成一个整体,扩大了整体试验荷载底面与地基的接触面积,提高了堆重的稳定性和安全性;支座的堆载重块也成为静载试验的荷重,充分利用了支座的重量,提高了静载试验的荷载能力;减少了压重平台上部的荷重,降低了整体荷重的重心高度,增加了工程的安全性,较传统堆载静载试验,提高了工程的安全性和试验荷载能力及工作效率,同时可减缩试验工期,降低工程成本,易于生产操作。
Description
技术领域
本发明涉及一种静载荷试验方法,特别是一种复合式堆载静载荷试验方法,属于建筑工程地基与基础试验及检测技术领域。
背景技术
堆载法是竖向抗压静载荷试验的方法之一,常用于为确定建筑工程地基与基础竖向抗压承载力的试验与检测中。传统堆载方法,常采用方木、沙石(土)包或专制的支架作为压重平台的下支座,反力荷载重量只利用压重平台以上的堆载重量,在做大吨位静载试验时,堆载荷重越大,整个反力装置的安全性就越难保证,试验荷载能力也受到相对局限,工作效率降低,致使工程成本相对提高。
发明内容
本发明的目的在于提供一种复合式堆载静载荷试验方法,以提高静载试验,尤其是大吨位静载试验的安全性、荷载能力和工作效率,降低工程成本。
本发明的构思是这样的。本发明的方法是对传统堆载方式静载荷试验方法的改进,主要改进点是:压重平台支座采用堆载重块堆砌而成,在堆载重块和压重平台上设置连接点,将压重平台下堆载重块堆砌成的支座与压重平台连接,使其不但起支撑压重平台的作用,同时也成为堆载荷重的组成部分。
具体地,本发明的方法包括如下步骤:
(1)制作堆载重块
堆载重块用混凝土制作,形状为规则的长方体或正方体形,在每块堆载重块上设两个隐藏式吊点;
(2)制作压重平台
压重平台由多根纵横排列的工字钢焊接而成,顶面由钢板铺垫,整体平台等分为几块,平台底部工字钢上焊接挂接环;
(3)堆砌压重平台支座
压重平台下用堆载重块作平台支座,作支座的堆载重块按照静载试验要求进行设计堆砌,并标记出支座重块边缘位置,底层的堆载重块两个吊点的方向与压重平台工字钢长轴方向一致。
(4)连接支座与压重平台
使压重平台工字钢下的挂接环与作支座的堆载重块吊点上下对齐,用挂钩将压重平台与作支座的堆载重块连接在一起。
(5)堆载荷重
根据载荷试验要求的荷重,将堆载重块整齐吊放于压重平台上,每一层堆载重块的外边缘都小于其下层堆载重块的外边缘。
本发明取得的积极效果是:
本发明的方法中,采用堆载重块做压重平台支座,并将堆载重块堆砌的支座与压重平台机械地连成一个整体,扩大了整体试验荷载底面与地基的接触面积,提高了堆重的稳定性和安全性;支座的堆载重块也成为静载试验的荷重,充分利用了支座的重量,提高了静载试验的荷载能力;充分利用了压重平台下部支座的重量,减少了压重平台上部的荷重,比传统堆载方法提高了工作效率,降低了整体荷重的重心高度。另外,堆载重块堆砌的支座与压重平台紧密连接,与平台上的堆载荷重形成一整体,更增加了工程的安全性。比传统静载试验堆载法提高了工程的安全性和试验荷载能力及工作效率,同时可减缩试验工期,降低工程成本,且易于生产操作。
具体实施方式
以下实施例用于说明本发明。
某电厂工程采用桩基础,需进行13组基桩竖向静载试验,由于基岩埋深较浅,无法采用锚桩提供反力,确定采用堆载法,工程设计要求试验加载量约500吨,按1.2的安全系数,反力装置堆载重量不应小于600吨。
(1)制做堆载重块
在工地现场浇制长方体形混凝土重块120块,每块长、宽、高为2米、1米、1米,重5吨,内部上下设两层钢筋网片,重块的两个吊点采用隐藏式,有利于重块的堆码,吊点钢筋与上下两层钢筋网片焊接在一起,相距1.2米。
(2)制做压重平台
压重平台长9米、宽8米,由4块拚接成,压重平台由多根30型工字钢焊接而成,顶面由厚3mm花纹钢板铺垫,压重平台工字钢下部用厚30mm的钢板割制焊有挂接环,试验安装放置时工字钢下挂接环与支座的第一层堆载重块吊点上下对齐,保证压重平台与支座便于连接;
(3)堆砌平台支座
采用堆载重块作为压重平台下支座,堆砌前先丈量好尺寸,并标记出支座重块边缘位置,堆砌时严格按照标记位置进行施工,支座分为两层,第一层堆载重块长轴方向与压重平台下工字钢长轴同向,第二层堆载重块垂直于第一层堆载重块,并放于第一层堆载重块两个吊点中间,支座共用30块堆载重块作成;
(4)连接支座与压重平台
放置压重平台时注意工字钢下挂接环与支座堆载重块吊点的上下对齐,保证压重平台与支座便于连接,采用5吨抗拉能力的紧绳器、U型环,将压重平台与支座的第一层堆载重块紧密连接在一起;
(5)堆载荷重
根据载荷试验要求的荷重,使用吊车将堆载重块整齐吊放于压重平台上,每层堆载重块的外边缘都小于下层堆载重块的外边缘,有利于荷重的稳定和安全,压重平台上共堆放三层重块。
本实施例效果评价:
(1)本工程支座底层共采用了堆载重块20块,每块与地面接触面积2m2,整个堆载体底层与地面的接触面积是40m2,大大增加了堆载试验地基的稳定性和安全性。
(2)由于将支座与压重平台紧密连接为一体,用于支座的30块堆载重块也成为堆载试验的荷重,每块堆载重块重5吨,支座堆载重块共重150吨,可使压重平台上少堆荷重150吨,相当比传统堆载法提高了150吨的荷载能力,同时压重平台上减少两层荷载,整体堆载荷重的重心高度降低,使工程更加安全。
(3)由于压重平台上减少了两层荷载,因此加快了工程进度,提高了工作效率,整个工程较计划工期提前10多天完成,提前工期约40%,节约成本约30%。
Claims (1)
1、一种复合式堆载静载荷试验方法,其特征是该方法包括以下步骤:
(1)制作堆载重块
堆载重块用混凝土制作,形状为规则的长方体或正方体形,在每块堆载重块上设两个隐藏式吊点;
(2)制作压重平台
压重平台由多根纵横排列的工字钢焊接而成,顶面由钢板铺垫,整体平台等分为几块,平台底部工字钢上焊接挂接环;
(3)堆砌压重平台支座
压重平台下用堆载重块作平台支座,作支座的堆载重块按照静载试验要求进行设计堆砌,并标记出支座重块边缘位置,底层的堆载重块两个吊点的方向与压重平台工字钢长轴方向一致。
(4)连接支座与压重平台
使压重平台工字钢下的挂接环与作支座的堆载重块吊点上下对齐,用挂钩将压重平台与作支座的堆载重块连接在一起。
(5)堆载荷重
根据载荷试验要求的荷重,将堆载重块整齐吊放于压重平台上,每一层堆载重块的外边缘都小于其下层堆载重块的外边缘。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CNB2006100128886A CN100402761C (zh) | 2006-06-28 | 2006-06-28 | 复合式堆载静载荷试验方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CNB2006100128886A CN100402761C (zh) | 2006-06-28 | 2006-06-28 | 复合式堆载静载荷试验方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN1884724A true CN1884724A (zh) | 2006-12-27 |
CN100402761C CN100402761C (zh) | 2008-07-16 |
Family
ID=37583024
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CNB2006100128886A Expired - Fee Related CN100402761C (zh) | 2006-06-28 | 2006-06-28 | 复合式堆载静载荷试验方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN100402761C (zh) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN100453999C (zh) * | 2007-07-31 | 2009-01-21 | 中铁二局股份有限公司 | 32m/900t预应力混凝土先张箱梁静载试验方法 |
CN104074208A (zh) * | 2014-06-30 | 2014-10-01 | 徐州市建科技术有限公司 | 一种复合地基静载荷试验专用离合式承压箱 |
CN104631416A (zh) * | 2013-11-07 | 2015-05-20 | 贵州中建建筑科研设计院有限公司 | 地基承载力载荷试验的方法及组合式堆载反力标准块 |
CN107190785A (zh) * | 2017-06-08 | 2017-09-22 | 攀枝花天誉工程检测有限公司 | 基桩静载试验方法 |
Family Cites Families (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN2221210Y (zh) * | 1994-11-09 | 1996-02-28 | 乔墩华 | 一种试桩装置 |
GB2323174B (en) * | 1997-03-14 | 2000-08-09 | Kvaerner Cementation Found Ltd | Automatic static load testing for piles |
-
2006
- 2006-06-28 CN CNB2006100128886A patent/CN100402761C/zh not_active Expired - Fee Related
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN100453999C (zh) * | 2007-07-31 | 2009-01-21 | 中铁二局股份有限公司 | 32m/900t预应力混凝土先张箱梁静载试验方法 |
CN104631416A (zh) * | 2013-11-07 | 2015-05-20 | 贵州中建建筑科研设计院有限公司 | 地基承载力载荷试验的方法及组合式堆载反力标准块 |
CN104631416B (zh) * | 2013-11-07 | 2017-02-22 | 贵州中建建筑科研设计院有限公司 | 地基承载力载荷试验的方法及组合式堆载反力标准块 |
CN104074208A (zh) * | 2014-06-30 | 2014-10-01 | 徐州市建科技术有限公司 | 一种复合地基静载荷试验专用离合式承压箱 |
CN104074208B (zh) * | 2014-06-30 | 2015-11-11 | 徐州市建科技术有限公司 | 一种复合地基静载荷试验专用离合式承压箱 |
CN107190785A (zh) * | 2017-06-08 | 2017-09-22 | 攀枝花天誉工程检测有限公司 | 基桩静载试验方法 |
CN107190785B (zh) * | 2017-06-08 | 2019-03-05 | 攀枝花天誉工程检测有限公司 | 基桩静载试验方法 |
Also Published As
Publication number | Publication date |
---|---|
CN100402761C (zh) | 2008-07-16 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN201581656U (zh) | 大型复杂建筑工地用钢栈桥 | |
CN111650047B (zh) | 一种大吨位土料载荷试验竖向反力加载装置及其加载方法 | |
CN103061360A (zh) | 一种大吨位静载试验加力系统 | |
CN102031756A (zh) | 现浇箱梁的支撑组件及现浇箱梁的施工方法 | |
CN101718097A (zh) | 螺栓连接箱形预制装配式混凝土塔吊基础 | |
CN1884724A (zh) | 复合式堆载静载荷试验方法 | |
CN205421365U (zh) | 一种复合地基载荷试验装置 | |
CN201534977U (zh) | 螺栓连接环向箱形预制装配式混凝土塔吊基础 | |
CN212336080U (zh) | 一种装配化压重式塔吊基础结构 | |
CN105971033B (zh) | 地基基础管桩试压检测配重的组合水箱和试压检测方法 | |
CN208792381U (zh) | 一种建筑专用二维平滑滑动抗震减震阻尼装置 | |
CN110644380A (zh) | 一种大跨径跨线桥加宽工程狭窄空间梁板安装方法 | |
CN206844181U (zh) | 整体式散体吨袋堆载装置 | |
CN201512809U (zh) | 螺栓连接箱形预制装配式混凝土塔吊基础 | |
CN110905009A (zh) | 设副支墩的8500吨级基桩静载试验压重平台及搭建方法 | |
CN210369074U (zh) | 一种整体式钢结构框架压重堆载体 | |
CN2813711Y (zh) | 可防止煤气柜基土沉降的基础结构 | |
CN107217693B (zh) | 土木工程用竖向抗压静载试验大型基桩地面压重堆载方法 | |
CN202672177U (zh) | 一种风力发电机的塔架基础 | |
CN220284900U (zh) | 基桩大吨位堆载延展式压重平台 | |
CN205875233U (zh) | 地基基础管桩试压检测配重的组合水箱 | |
CN212001316U (zh) | 钢板桩组合式静载平台 | |
CN213267983U (zh) | 一种装配组合式塔机基础 | |
CN212742608U (zh) | 一种软土地基群桩半支盘桩基础结构 | |
CN218342069U (zh) | 一种应用放梁台座的存梁结构 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
C17 | Cessation of patent right | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20080716 Termination date: 20120628 |