CN1880580A - Bridging method by cooperation of temporary bridge and bridge girder erection machine at tunnel exit - Google Patents

Bridging method by cooperation of temporary bridge and bridge girder erection machine at tunnel exit Download PDF

Info

Publication number
CN1880580A
CN1880580A CN 200610012353 CN200610012353A CN1880580A CN 1880580 A CN1880580 A CN 1880580A CN 200610012353 CN200610012353 CN 200610012353 CN 200610012353 A CN200610012353 A CN 200610012353A CN 1880580 A CN1880580 A CN 1880580A
Authority
CN
China
Prior art keywords
bridge
formation machine
bridge formation
leg
place
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN 200610012353
Other languages
Chinese (zh)
Inventor
黄耀怡
闫岢宏
魏福祥
黄树军
刘会平
耿冬梅
郭欣
姚美娜
吴岩
李坤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
QINHUANGDAO BEIDAHE TOLIAN ROAD AND BRIDGE MACHINERY CO Ltd
Original Assignee
QINHUANGDAO BEIDAHE TOLIAN ROAD AND BRIDGE MACHINERY CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by QINHUANGDAO BEIDAHE TOLIAN ROAD AND BRIDGE MACHINERY CO Ltd filed Critical QINHUANGDAO BEIDAHE TOLIAN ROAD AND BRIDGE MACHINERY CO Ltd
Priority to CN 200610012353 priority Critical patent/CN1880580A/en
Publication of CN1880580A publication Critical patent/CN1880580A/en
Pending legal-status Critical Current

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The invention relates to a method for building beam on the bridge at the outlet of tunnel, with the bridging machine, wherein it sets auxiliary bridge at the needed hole as the working platform; via longitudinal beam drawing method, sets auxiliary bridge; drawing the flexible beam into the certain position, then dropping them sheet from sheet until laying the bridge surface; the beam carrier carries the bridging machine to the appointed position at the outlet; the carrier lifts the cylinder flexible sheath to lift the bridging machine to the height of bridge beam; returning the beam at the back leg, to connect the temporary leg, detaching the bearing point of front leg, moving back the carrier, to make its cylinder and flexible sheath relative to the bridging machine; lifting the cylinder flexible sheath, detaching the temporary leg, mounting the low beam of back leg with walking platform, using the front and back cranes to crane and detach the auxiliary bridge, to be arranged on the carrier; the carrier carries the beam to the feed position; then using crane to lift the beam to right position. The invention can reduce the cost and save the time.

Description

Tunnel exit place bridge suspension bridge cooperates the beam erecting method of bridge formation machine
Technical field
The present invention relates to link to each other with the tunnel beam erecting method in highway section of special line for passenger trains bridge, relate to set up the beam erecting method that adjoining tunnel exit bridge suspension bridge cooperates the bridge formation machine specifically.
Background technology
At present, in the special line for passenger trains highway section that builds a bridge and closely link to each other with the tunnel, if adopt the bridge formation frame to come the inherent stress concrete box-beam at integral erection tunnel exit place, so far at home and abroad beyond example.This is a great problem in special line for passenger trains and the high-speed railway bridge construction, is called as " blocking the way " tiger.Its main cause be the bridge formation machine complete machine height and width big, and the size of tunnel clearance is little, can't pass through.When therefore the bridge formation machine is by the tunnel, must reequip to reduce height and to reduce width, pack reach with special vehicle again, and arrived the tunnel exit place, and then be exactly the spanning (deep valley or great river) that waits to set a roof beam in place; At this moment, because bridge formation captain degree is bigger, the bridge formation machine must put in the tunnel face and reset, erects, and could begin bridging operation.But not enough just because of headroom size in the tunnel, the bridge formation machine can't reset, and does not therefore have and uses.Usually run into this situation, can only change the design scheme of bridge tunnel, widen the distance between tunnel face and the abutment, for example the tunnel face is located massif and strengthened open cut pick length or change bridge shape etc.Obvious this way can increase investment and prolongation cycle.Thereby how to solve the difficult problem of this engineering construction, become a heat subject both domestic and external for a long time.
Summary of the invention
The objective of the invention is for addressing this problem, and provide the easy tunnel exit place bridge suspension bridge of a kind of constructing operation to cooperate the beam erecting method of bridge formation machine.
The present inventor has finished the beam erecting method of tunnel exit of the present invention through studying practice for a long period of time.
Its concrete beam erecting method step is:
A, select six or four formula suspension bridges for use, the vertical bracket beam method that hoist engine forms is set, the anterior outstanding body portion hitch frame of suspension bridge is located on the position, first hole by preceding square pier;
B, by the length of hole frame, remove the counterweight tail boom and transport, suspension bridge is laid and is finished;
Nose girder places the Beam transportation vehicle front end under C, the lifting of bridge formation machine, packs the bridge formation machine by the Beam transportation vehicle low level and goes out the tunnel and pack assigned address on the suspension bridge;
D, fall down nose girder and step up in second, between Beam transportation vehicle and bridge formation machine, original equipment oil cylinder and telescopic are set, with the bridge formation jacking to the operating mode height of setting a roof beam in place;
E, the folding rear support leg top rail that resets also connect interim leg thereon, the front leg strut that turns back, and four the oil cylinder telescopics of withdrawing withdraw from the rear portion of Beam transportation vehicle to the bridge formation machine;
F, at bridge formation machine rear portion two oil cylinder telescopics of jacking once more, remove interim leg, at the rear support leg top rail rear support leg lower transverse beam that has running truck is installed, two the oil cylinder telescopics of withdrawing, rear support leg becomes stressed fulcrum with front leg strut;
G, with forward and backward hanging beam overhead traveling crane lifting suspension bridge, place to return on the Beam transportation vehicle and get beam, prepare to set a roof beam in place;
H, Beam transportation vehicle are got beam and are run to the feeding beam position, run to the preceding hole of tunnel exit by forward and backward hanging beam overhead traveling crane lifting beam and step up beam and put in place, promptly finish preceding hole and stride and set a roof beam in place.
The good effect that beam erecting method of the present invention has is:
1, by above-mentioned beam erecting method, solves present quasi high-speed highway and can not use the bridge formation machine to put in order the difficult problem of the box-girder of integral erection adjoining tunnel exit, hole prestressed concrete, not only saved construction investment, but also shortened the cycle of construction greatly.
2, this beam erecting method has effectively utilized the function of use of bridge formation machine, only need dismounting rear support leg lower transverse beam part, folding top rail part and front leg strut, auxilliary supporting leg, can pass through the tunnel smoothly, need not increase and make any attached special equipment, promptly easy to operate, safe and reliable again.
The specific embodiment
Below in conjunction with the diagram method step of setting a roof beam in place, the present invention is described in further detail.
This bridge formation frame is established the embodiment of the tunnel exit first hole beam:
Fig. 1, adopt vertical bracket beam method, be dragged to the position with the cantilever beam form and fall within piecewise on first hole preceding stepping up six or the four formula beam suspension bridges that fixedly install small-sized electric merit hoist engine traction configuration;
Fig. 2, set up each hole suspension bridge to last slabbing beam and finish, by hole frame length, split out counterweight tail boom (each sheet cantilever beam falls repeatedly with a slice counterweight tail boom) and transport, the suspension bridge laying finishes;
Nose girder places the Beam transportation vehicle front end under Fig. 3, the lifting of bridge formation machine, packs 900t bridge formation machine by the Beam transportation vehicle low level and goes out the tunnel and park to the assigned address on the suspension bridge;
Fig. 4, the following nose girder of lifting is fallen on position, second hole, the two ends of Beam transportation vehicle be provided with four oil cylinders and flexible be placed in set up between, jacking cylinder makes telescopic lifting bridge formation machine on it to the operating mode height of setting a roof beam in place;
Fig. 5, the front leg strut of bridge formation machine set back support on the bridge pier, the rear support leg top rail resets simultaneously, and interim long column leg is set thereon, making thereafter, supporting leg forms a gate-type structure, withdrawal oil cylinder telescopic, withdraw from the rear positions of Beam transportation vehicle to the bridge formation machine, two oil cylinders of startup and telescopic act on the bridge formation machine on the Beam transportation vehicle of bridge formation drive end unit correspondence;
Fig. 6, two oil cylinders of jacking and telescopic lifting bridge formation machine, remove the interim leg of rear support leg, simultaneously, the rear support leg lower transverse beam and the rear support leg top rail integral body that have bridge formation machine running truck are installed are connected and fixed, withdrawal oil cylinder and telescopic make its rear support leg become stressed fulcrum with front leg strut;
Fig. 7, utilize forward and backward hanging beam overhead traveling crane lifting suspension bridge that it is removed, be positioned on the Beam transportation vehicle and return, vacate under-clearance, prepare to set a roof beam in place construction;
Fig. 8, Beam transportation vehicle return to be got beam and runs to end of the bridge feeding beam position, puts in place by the beam that falls to the cross-location of the preceding hole of tunnel exit of the forward and backward hanging beam overhead traveling crane lifting box-shaped concrete beam on the bridge formation machine, has promptly finished setting a roof beam in place that preceding hole strides.
When Bridge Erector erection of second hole position, can by Bridge Erector voluntarily vertical shift in position, second hole, can by Conventional program continues to set a roof beam in place, and need not to use suspension bridge auxiliary.
In the above-mentioned erection method, original when packing Bridge Erector on described oil cylinder and the telescopic beam car Special equipment.
In addition, in the above-mentioned erection method, set up the applied suspension bridge erection method in first hole and select Vertical bracket beam method also can by process conditions and the actual conditions at scene, be selected vertical incremental launching method, the pocket tail Method, scaffold method or cantilever method, or its their compound mode is set up.
In above-mentioned, described rear support leg top rail part can fold, and has so just reduced the width of bridge formation machine.The foldable structure mode of this rear support leg is that to select the inventor's the patent No. for use be technology in 200520135638.2 the utility model patent.

Claims (1)

1, a kind of tunnel exit bridge suspension bridge cooperates the beam erecting method of bridge formation machine, and its method step is:
A, the vertical bracket beam method of employing set up six or four formula suspension bridges in position, first hole;
B, piecewise six or four formula beams are fallen, finish, counterweight afterbody beam is folded down transports back, shop bridge formation face until last slabbing beam;
C, Beam transportation vehicle low level are packed out the tunnel to suspension bridge, and be in place to assigned address;
D, fall down nose girder on position, second hole, at Beam transportation vehicle front and back end jacking cylinder and telescopic lifting bridge formation machine to the operating mode height of setting a roof beam in place;
E, the rear support leg top rail that resets connect interim leg and become the gate-type structure, and the front leg strut that turns back places on the bridge pier, and withdraw simultaneously oil cylinder and telescopic, Beam transportation vehicle retreat to bridge formation machine rear portion, make oil cylinder on it and telescopic corresponding to the bridge formation machine;
F, jacking cylinder and telescopic lifting bridge formation machine are removed the interim leg of rear support leg, and back the lower transverse beam that has bridge formation machine running truck is installed, and withdrawal oil cylinder telescopic makes rear support leg become stressed fulcrum with front leg strut;
G, utilize the forward and backward hanging beam overhead traveling crane lifting of bridge formation machine to remove suspension bridge, place to return on the Beam transportation vehicle and get beam, prepare to set a roof beam in place;
H, Beam transportation vehicle are got beam and are moved to end of the bridge feeding beam position, and it is in place to set up before the tunnel exit position, first hole beam that falls by forward and backward hanging beam overhead traveling crane lifting box-shaped concrete beam.
CN 200610012353 2006-01-18 2006-01-18 Bridging method by cooperation of temporary bridge and bridge girder erection machine at tunnel exit Pending CN1880580A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 200610012353 CN1880580A (en) 2006-01-18 2006-01-18 Bridging method by cooperation of temporary bridge and bridge girder erection machine at tunnel exit

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 200610012353 CN1880580A (en) 2006-01-18 2006-01-18 Bridging method by cooperation of temporary bridge and bridge girder erection machine at tunnel exit

Publications (1)

Publication Number Publication Date
CN1880580A true CN1880580A (en) 2006-12-20

Family

ID=37518919

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 200610012353 Pending CN1880580A (en) 2006-01-18 2006-01-18 Bridging method by cooperation of temporary bridge and bridge girder erection machine at tunnel exit

Country Status (1)

Country Link
CN (1) CN1880580A (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101144260B (en) * 2007-09-21 2010-06-02 北京交通大学 Prestressing applying method for concrete genuine bridge construction
CN104594198A (en) * 2014-11-28 2015-05-06 中铁二十三局集团有限公司 Method for erecting parallel box girders in tunnel
CN105970821A (en) * 2016-06-06 2016-09-28 武汉市创先专利技术服务有限公司 Telescopic beam of bridge plate installation equipment for prefabricated assembly type viaduct
CN106555379A (en) * 2015-09-30 2017-04-05 中铁十八局集团第四工程有限公司 Pass through both wired elevated formation level Combined temporary bridge construction methods
CN113005911A (en) * 2021-03-02 2021-06-22 中交路桥华东工程有限公司 Bridge girder erection machine assembling method
CN113215994A (en) * 2021-05-11 2021-08-06 中交路桥华东工程有限公司 Method for mounting bridge girder erection machine at tunnel outlet
WO2022037112A1 (en) * 2020-08-17 2022-02-24 中铁十八局集团有限公司 Device for high-altitude push and vertical movement for 900t bridge girder erection machine

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101144260B (en) * 2007-09-21 2010-06-02 北京交通大学 Prestressing applying method for concrete genuine bridge construction
CN104594198A (en) * 2014-11-28 2015-05-06 中铁二十三局集团有限公司 Method for erecting parallel box girders in tunnel
CN106555379A (en) * 2015-09-30 2017-04-05 中铁十八局集团第四工程有限公司 Pass through both wired elevated formation level Combined temporary bridge construction methods
CN105970821A (en) * 2016-06-06 2016-09-28 武汉市创先专利技术服务有限公司 Telescopic beam of bridge plate installation equipment for prefabricated assembly type viaduct
CN105970821B (en) * 2016-06-06 2017-08-04 青岛蓝天创先科技服务有限公司 Prefabricated assembled overpass bridge plate installs the extensible canopy of equipment
WO2022037112A1 (en) * 2020-08-17 2022-02-24 中铁十八局集团有限公司 Device for high-altitude push and vertical movement for 900t bridge girder erection machine
CN113005911A (en) * 2021-03-02 2021-06-22 中交路桥华东工程有限公司 Bridge girder erection machine assembling method
CN113215994A (en) * 2021-05-11 2021-08-06 中交路桥华东工程有限公司 Method for mounting bridge girder erection machine at tunnel outlet

Similar Documents

Publication Publication Date Title
CN1880580A (en) Bridging method by cooperation of temporary bridge and bridge girder erection machine at tunnel exit
CN104631335B (en) Large-tonnage Bridge Erector and construction method thereof
CN104805773B (en) The Segmental assembling bridge-erecting machine of little curved bridge of constructing
CN101377072B (en) Construction methods of hanging beam and assembling cantilever in the bottom of steel case beam
CN201003145Y (en) Upward and self-walking type mobile die carrier
CN2853888Y (en) Guide beam type fixed point hoisting bridge girder erection machine
CN201857580U (en) Double-girder bridge girder erection machine for erecting variable span type trough girder
CN109653105B (en) Main truss system of box girder bridge cantilever construction hanging basket and use method thereof
CN1880582A (en) Bridging method of bridge girder erection machine at tunnel exit
CN109653104A (en) A kind of across the erection construction method of double line box girder change
CN110820602A (en) Single-segment box girder bridge girder erection machine and operation method thereof
CN217378620U (en) Intelligent bridge erecting system
JP5184248B2 (en) Construction method of level crossing
CN210561749U (en) Multi-frame juxtaposed double-cantilever bridge girder erection machine
CN206617175U (en) A kind of automatic liquid pressure type inverted arch trestle
CN102943443A (en) Movable mould frame bridge fabrication machine C type beam system
CN200955124Y (en) Novel railway bridging machine
CN110409311A (en) It a kind of single beam girder erecting machine and its sets a roof beam in place, via hole, the method for crossing tunnel
CN102094394A (en) Through-tunnel lower pilot girder type non-moving lifting bridge girder erection machine
CN113502743A (en) Method for mounting arch rib and main beam of steel truss arch bridge
CN112323657A (en) Integrated prefabricated bridge dismantling machine and prefabricated bridge dismantling method
CN204418034U (en) Novel large-tonnage Bridge Erector
CN210597030U (en) Double-row front supporting leg for bridge girder erection machine
CN1880581A (en) Method for erecting a last arch bridge in front of tunnel and accessing tunnel by railway bridge girder erection machine
CN210368664U (en) Wide-body bridge girder erection machine

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Open date: 20061220