CN1880581A - Method for erecting a last arch bridge in front of tunnel and accessing tunnel by railway bridge girder erection machine - Google Patents

Method for erecting a last arch bridge in front of tunnel and accessing tunnel by railway bridge girder erection machine Download PDF

Info

Publication number
CN1880581A
CN1880581A CN200610012354.3A CN200610012354A CN1880581A CN 1880581 A CN1880581 A CN 1880581A CN 200610012354 A CN200610012354 A CN 200610012354A CN 1880581 A CN1880581 A CN 1880581A
Authority
CN
China
Prior art keywords
tunnel
overhead traveling
traveling crane
bridge
girder
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN200610012354.3A
Other languages
Chinese (zh)
Other versions
CN1880581B (en
Inventor
张红卫
江创华
黄树军
魏福祥
杨翠红
李坤
周春江
邢立成
乔伟立
耿冬梅
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Qinhuangdao Tianye Tolian Heavy Industry Co Ltd
Original Assignee
QINHUANGDAO BEIDAHE TOLIAN ROAD AND BRIDGE MACHINERY CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by QINHUANGDAO BEIDAHE TOLIAN ROAD AND BRIDGE MACHINERY CO Ltd filed Critical QINHUANGDAO BEIDAHE TOLIAN ROAD AND BRIDGE MACHINERY CO Ltd
Priority to CN2006100123543A priority Critical patent/CN1880581B/en
Publication of CN1880581A publication Critical patent/CN1880581A/en
Application granted granted Critical
Publication of CN1880581B publication Critical patent/CN1880581B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The invention relates to a method for setting the last hole bridge of tunnel by railway bridging machine, wherein the suspend beam can be folded and rotate, without interfering the tunnel outlet, to mount the front hole bridge beam at the front hole position; and it folds the back leg, front leg, and the auxiliary leg, to meet the size of tunnel, to arrange the whole bridging machine on the beam carrier, to pass the tunnel. The invention can reduce the time and the cost.

Description

Railway bridge erecting machine sets up last bridge before the tunnel and advances the method in tunnel
Technical field
The present invention relates to the method that a kind of 900t special line for passenger trains bridge formation frame is established last bridge before the tunnel and entered the tunnel.
At present, when setting up last position, hole before setting up the tunnel of machine, there are a lot of difficulty, often adopt the method for bridging to solve,, cause the construction cost height as cast-in-situ concrete beam for passenger dedicated railway line, and problem such as long construction period.And when the tunnel, often dismantle the bridge formation machine on a large scale, transportation is reinstalled again then.When dismounting, must use crane gear, and often because near the restriction in place, the job site tunnel entrance, the problem that can cause crane gear to use, must be by manpower or supporting facility, thereby cause great amount of manpower, the waste of material resources and financial resources has had a strong impact on the normal use of bridge formation machine.
Summary of the invention
The objective of the invention is for addressing the above problem, and provide a kind of railway bridge erecting machine to set up last bridge before the tunnel and advance the method in tunnel.
Method step of the present invention:
A, set up before the tunnel the second last bridge and set up and finish, will descend the nose girder overhead traveling crane to retreat to the semi girder rear portion, folding semi girder control device is installed;
B, start folding semi girder control device, anterior semi girder is returned back to and the hands-off vertical cantilever in tunnel on behind the pin joint;
C, bridge formation machine run to position, last hole, tunnel, and preceding hanging beam overhead traveling crane and auxilliary supporting leg are prepared lifting nose girder down;
The anti-change gear lifting of D, preceding hanging beam overhead traveling crane and auxilliary supporting leg nose girder down is transported in the tunnel, and dismounting is nose girder front and back supporting leg down, and anchoring temporarily;
E, preceding hanging beam overhead traveling crane retreat under the handling supporting leg before and after the nose girder, and Beam transportation vehicle runs to the feeding beam position, the forward and backward hanging beam overhead traveling crane lifting concrete beam beam that puts in place to last hole;
The anti-change gear lifting of F, preceding hanging beam overhead traveling crane and auxilliary supporting leg nose girder down retreats on the last Kong Liang;
G, bridge formation machine retreat to position, second hole, by folding control device semi girder are resetted, and following nose girder overhead traveling crane moves to the semi girder front end;
H, oil cylinder and telescopic are installed on Beam transportation vehicle, jacking bridge formation machine rear portion, the rear support leg lower transverse beam that dismounting has running truck sets up interim leg, makes the rear support leg position become the gate-type structure, withdrawal oil cylinder telescopic;
I, Beam transportation vehicle move forward to bridge formation machine bottom, and oil cylinder and telescopic jacking bridge formation machine are installed thereon, simultaneously, and folding forwards, backwards auxilliary supporting leg and front leg strut;
J, withdrawal jacking cylinder telescopic place on the Beam transportation vehicle bridge formation machine integral body, pack by the Beam transportation vehicle low level and pass through tunnel.
The good effect that method of the present invention had is: when having solved present bridge formation frame and establishing the tunnel, the rear support leg and the semi girder that need integral demounting bridge formation machine, and be difficult to dispose the practical problem of crane facility, the massif that perhaps changes the tunnel entrance place strengthens open cut length, widen that the tunnel face is advanced and abutment between distance; Or cast-in-place beam method.So not only increased the investment of engineering, and increased construction period, the present invention has had simple and efficient realization setting up of last bridge only limits under the situation of partial disassembly, utilizes the special equipment of original bridge formation promptly to finish.Made full use of the function of use of bridge formation machine, in order to reduce construction cost and construction period.
The specific embodiment
Be one to show method of the present invention better, be described in further detail below in conjunction with diagram.
Its method step is:
Fig. 1 after the second last bridge sets up and finishes before tunnel entrance, with descending the nose girder overhead traveling crane to retreat to the root of cantilever, installs bridge formation machine semi girder control device;
Fig. 2 starts the oil cylinder that folds the semi girder control device, and withdrawal oil cylinder pulling support makes leading portion semi girder partly upwards slowly return back to the upright position along the pin joint at this place;
Fig. 3, the complete machine via hole of bridge formation machine puts in place, outstanding straight on the head beam and tunnel are not interfered till;
Fig. 4, by nose girder under preceding hanging beam overhead traveling crane and the anti-change gear lifting of auxilliary supporting leg, and the forward and backward supporting leg of nose girder under the anchoring temporarily, will descend nose girder to be transported in the tunnel, preceding hanging beam overhead traveling crane is return nose girder front and back supporting leg under the handling, prepares to set a roof beam in place;
Fig. 5, the bridge formation machine moves to last position, hole beam that falls by forward and backward hanging beam overhead traveling crane lifting concrete beam and puts in place;
Fig. 6 is worked to cooperate moving to last Kong Liang under the handling behind the nose girder by preceding hanging beam overhead traveling crane and the anti-change gear of auxilliary supporting leg;
Fig. 7, bridge formation machine complete machine retreat to position, second hole, start the revolution of oil cylinder control cantilever and reset, and following nose girder overhead traveling crane moves forward to the semi girder end;
Fig. 8 installs oil cylinder and telescopic, jacking bridge formation machine rear portion on the fortune beam, dismounting has the rear support leg lower transverse beam of running truck, makes the rear support leg top rail folding, and interim leg is installed at its rear support leg top rail position, make rear support leg become the gate-type structure, withdrawal oil cylinder telescopic;
Fig. 9 makes the Beam transportation vehicle reach, and integral body places under the bridge formation machine, and oil cylinder and telescopic jacking bridge formation machine are installed, and removes interim supporting leg, simultaneously, and folding forwards, backwards front leg strut and auxilliary supporting leg;
Figure 10, withdrawal oil cylinder and telescopic place on the Beam transportation vehicle bridge formation machine, pack the bridge formation machine by the Beam transportation vehicle low level and pass through tunnel more conveniently.
In above-mentioned, described folding rear support leg structure is the utility model patent technology that adopts the inventor's the patent No. 200520135638.2.And folding semi girder is that to adopt the patent No. of the present invention be 200520135637.8 utility model patent technology.

Claims (1)

1, a kind of railway bridge erecting machine sets up last bridge before the tunnel and advances the method in tunnel, and its method step is:
A, set up before the tunnel the second last bridge and set up and finish, will descend the nose girder overhead traveling crane to retreat to the semi girder rear portion, folding semi girder control device is installed;
B, start folding semi girder control device, anterior semi girder is returned back to and the hands-off vertical cantilever of tunnel on behind the pin joint;
C, bridge formation machine run to position, last hole, tunnel, and preceding hanging beam overhead traveling crane and auxilliary supporting leg are prepared lifting nose girder down;
The anti-change gear lifting of D, preceding hanging beam overhead traveling crane and auxilliary supporting leg nose girder down is transported in the tunnel, and dismounting is nose girder front and back supporting leg down, and anchoring temporarily;
E, preceding hanging beam overhead traveling crane retreat under the handling supporting leg before and after the nose girder, and Beam transportation vehicle runs to the feeding beam position, the forward and backward hanging beam overhead traveling crane lifting concrete beam beam that puts in place to last hole;
The anti-change gear lifting of F, preceding hanging beam overhead traveling crane and auxilliary supporting leg nose girder down retreats on the last Kong Liang;
G, bridge formation machine retreat to position, second hole, by folding control device semi girder are resetted, and following nose girder overhead traveling crane moves to the semi girder front end;
H, oil cylinder and telescopic are installed on Beam transportation vehicle, jacking bridge formation machine rear portion, the rear support leg lower transverse beam that dismounting has running truck sets up interim leg, makes the rear support leg position become the gate-type structure, withdrawal oil cylinder telescopic;
I, Beam transportation vehicle move forward to bridge formation machine bottom, and oil cylinder and telescopic jacking bridge formation machine are installed thereon, simultaneously, and folding forwards, backwards auxilliary supporting leg and front leg strut;
J, withdrawal jacking cylinder telescopic place on the Beam transportation vehicle bridge formation machine integral body, pack by the Beam transportation vehicle low level and pass through tunnel.
CN2006100123543A 2006-01-18 2006-01-18 Method for erecting a last arch bridge in front of tunnel and accessing tunnel by railway bridge girder erection machine Active CN1880581B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2006100123543A CN1880581B (en) 2006-01-18 2006-01-18 Method for erecting a last arch bridge in front of tunnel and accessing tunnel by railway bridge girder erection machine

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2006100123543A CN1880581B (en) 2006-01-18 2006-01-18 Method for erecting a last arch bridge in front of tunnel and accessing tunnel by railway bridge girder erection machine

Publications (2)

Publication Number Publication Date
CN1880581A true CN1880581A (en) 2006-12-20
CN1880581B CN1880581B (en) 2010-10-13

Family

ID=37518920

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2006100123543A Active CN1880581B (en) 2006-01-18 2006-01-18 Method for erecting a last arch bridge in front of tunnel and accessing tunnel by railway bridge girder erection machine

Country Status (1)

Country Link
CN (1) CN1880581B (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101476296B (en) * 2009-01-14 2011-04-06 中铁六局集团有限公司 Anchoring device and method for auxiliary lower nose girder rear support leg of bridging machine
CN102312410A (en) * 2011-07-18 2012-01-11 中铁三局集团有限公司 Construction method for tunnel portal short-distance erection by 900t bridge girder erection machine
CN102720133A (en) * 2011-03-31 2012-10-10 江苏恩纳斯重工机械有限公司 Ultralow segment lifting bridge girder erection machine with one anchored end
CN103422439A (en) * 2013-07-25 2013-12-04 河北工业大学 Lower guide beam bridge girder erection machine and method for complete machine passing through tunnel
CN114293474A (en) * 2021-12-31 2022-04-08 中铁十四局集团青岛工程有限公司 Carrying support and high-speed rail bridge girder erection machine transferring method

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2418156Y (en) * 2000-04-28 2001-02-07 秦皇岛市北戴河机械厂 Double guiding-beam bridge-laying machine
DE10046681A1 (en) * 2000-09-21 2002-04-25 Bilfinger Berger Ag Construction method for bridge superstructure with bridge plates constructed off-site moved over installed plates and suspended from crane trolley to be lowered into place
CN1225589C (en) * 2003-05-13 2005-11-02 中铁工程机械研究设计院 Light rail communication PC rail beam conveying and mounting equipment and construction method
CN2635727Y (en) * 2003-09-17 2004-08-25 郑州大方桥梁机械有限公司 Single span type bridge erecting machine
DE102004002102A1 (en) * 2004-01-14 2005-08-04 Scheuerle Fahrzeugfabrik Gmbh Method for laying bridge sections onto vertical supports using a movable gantry crane supported on the uprights and lifting the sections off a trackless transporter

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101476296B (en) * 2009-01-14 2011-04-06 中铁六局集团有限公司 Anchoring device and method for auxiliary lower nose girder rear support leg of bridging machine
CN102720133A (en) * 2011-03-31 2012-10-10 江苏恩纳斯重工机械有限公司 Ultralow segment lifting bridge girder erection machine with one anchored end
CN102720133B (en) * 2011-03-31 2014-03-05 江苏恩纳斯重工机械有限公司 Ultralow segment lifting bridge girder erection machine with one anchored end
CN102312410A (en) * 2011-07-18 2012-01-11 中铁三局集团有限公司 Construction method for tunnel portal short-distance erection by 900t bridge girder erection machine
CN103422439A (en) * 2013-07-25 2013-12-04 河北工业大学 Lower guide beam bridge girder erection machine and method for complete machine passing through tunnel
CN103422439B (en) * 2013-07-25 2015-11-11 河北工业大学 Tunnel approach crossed by a kind of lower nose girder bridge-erecting machine and complete machine thereof
CN114293474A (en) * 2021-12-31 2022-04-08 中铁十四局集团青岛工程有限公司 Carrying support and high-speed rail bridge girder erection machine transferring method
CN114293474B (en) * 2021-12-31 2024-01-23 中铁十四局集团青岛工程有限公司 Method for transferring carrying support and viaduct machine

Also Published As

Publication number Publication date
CN1880581B (en) 2010-10-13

Similar Documents

Publication Publication Date Title
CN101343861B (en) Construction method for replacing old frame bridge by new frame bridge in existing railway lines
CN107165192A (en) A kind of pipe gallery segmentation brake type shaped steel door frame and its construction
CN1880581A (en) Method for erecting a last arch bridge in front of tunnel and accessing tunnel by railway bridge girder erection machine
CN105155423A (en) Upward moving type movable formwork for continuous box girder construction
CN102373670B (en) Mobile platform carrying and erecting integrated machine and bridge erecting method
CN203049466U (en) Downward bracket self-moving formwork bridge fabrication machine
CN102953343A (en) Descending bracket self-mobile model framework bridge fabrication machine
CN102410017A (en) Supporting type integrated tunneling-anchoring machine
CN202544854U (en) Lining trolley for subway station
CN103485282A (en) Method for gantry machine to go into and out of tunnels to erect box girders
CN107558378A (en) A kind of Bridge Erector and its bridging method for being used to set up full precast beam
CN1880582A (en) Bridging method of bridge girder erection machine at tunnel exit
CN212247900U (en) A artifical beam device that traverses that is used for bridge and tunnel zero distance to erect T roof beam
CN205529914U (en) Tunnel case roof beam structure bridge crane is crossed to HZQD900 type
CN103147406A (en) Small-curve cross-mountain tunnel box girder transporting and erecting integrated machine and head and tail hole box girder erection method thereof
CN103132463A (en) Movable hanger operating platform and manufacturing, installing, using and removing methods thereof
CN106087768A (en) A kind of method of assembled mobile formwork in bridge tunnel narrow short transition time section
CN201943004U (en) Double-girder transporting and erecting integrated bridge girder erecting machine capable of realizing girder erecting at zero distance from tunnel portal
CN1880580A (en) Bridging method by cooperation of temporary bridge and bridge girder erection machine at tunnel exit
CN203248170U (en) Lining trolley for secondary lining construction of pedestrian crosswalk
CN205857044U (en) A kind of novel construction beam
CN106013783A (en) Formwork support and erecting method thereof
CN204343172U (en) A kind of Bridge Erector
CN205259074U (en) Basket traveling system is hung to triangle
CN102268858A (en) Cradle for suspension pouring of arch-type bridge

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of invention: Method for erecting a last arch bridge in front of tunnel and accessing tunnel by railway bridge girder erection machine

Effective date of registration: 20121121

Granted publication date: 20101013

Pledgee: China Co. truction Bank Corp Qinhuangdao port professional branch

Pledgor: QINHUANGDAO TIANYE TOLIAN HEAVY INDUSTRY Co.,Ltd.

Registration number: 2012990000708

PLDC Enforcement, change and cancellation of contracts on pledge of patent right or utility model
C41 Transfer of patent application or patent right or utility model
TR01 Transfer of patent right

Effective date of registration: 20160622

Address after: 066004 No. 3 Tianshan Road, Qinhuangdao economic and Technological Development Zone, Hebei, China

Patentee after: QINHUANGDAO TIANYE TOLIAN HEAVY INDUSTRY Co.,Ltd.

Address before: 066100 Jincheng Road 48, Beidaihe District, Hebei, Qinhuangdao

Patentee before: QINHUANGDAO TIANYE TOLIAN HEAVY INDUSTRY Co.,Ltd.

PC01 Cancellation of the registration of the contract for pledge of patent right

Date of cancellation: 20220907

Granted publication date: 20101013

Pledgee: China Co. truction Bank Corp Qinhuangdao port professional branch