CN205857044U - A kind of novel construction beam - Google Patents

A kind of novel construction beam Download PDF

Info

Publication number
CN205857044U
CN205857044U CN201620824219.8U CN201620824219U CN205857044U CN 205857044 U CN205857044 U CN 205857044U CN 201620824219 U CN201620824219 U CN 201620824219U CN 205857044 U CN205857044 U CN 205857044U
Authority
CN
China
Prior art keywords
plate
construction
girder
crossbeam
novel construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201620824219.8U
Other languages
Chinese (zh)
Inventor
孙立伟
李秀文
苏义春
武智慧
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Qinhuangdao Zhongke Railway Steel Structure Co Ltd
Original Assignee
Qinhuangdao Zhongke Railway Steel Structure Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Qinhuangdao Zhongke Railway Steel Structure Co Ltd filed Critical Qinhuangdao Zhongke Railway Steel Structure Co Ltd
Priority to CN201620824219.8U priority Critical patent/CN205857044U/en
Application granted granted Critical
Publication of CN205857044U publication Critical patent/CN205857044U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

This utility model provides a kind of novel construction beam;This length of 32.6m of girder that just beam is arranged, deck-molding 1.7m, deck-siding 0.48m, girder uses Q345qD steel with crossbeam material, not only reducing the weight of construction beam, greatly reduce the difficulty of construction middle girder lifting, the frame bridge for two-wire, multi-thread circuit is constructed and the frame bridge construction of the less circuit of sweep also has the preferable suitability, it is also applied for the single undercrossing tunnel frame bridge that case span is bigger or oblique angles is bigger construction, and the construction of the undercrossing tunnel frame bridge of many casees;This crossbeam that just beam is arranged may be provided in highest order, a secondary high position, middle position, secondary low level, five kinds of positions of lowest order, goes for the construction basis of multiple different depth;The increasing of this just girder construction span, promotes to eliminate the construction procedure of temporary support and system transform in Framed underpass bridge, decreases the construction period of Framed underpass bridge, saved construction cost, is suitable to railway and makes somebody a mere figurehead the construction of hardened link and promote the use of.

Description

A kind of novel construction beam
Technical field
This utility model relates to a kind of novel construction beam, belongs to railway technical field of construction equipment.
Background technology
At present, when existing railway carries out culvert jacking, in order to ensure the normal operation of existing line above culvert, prevent Railway station track subsides, and needs erection construction just beam that existing line carries out built on stilts reinforcing.
During erection construction just beam, need existing line is carried out the of short duration block of 1-2 hour, at present, construction beam Set up and mainly lift up into row by the rescue of autocrane or railway interests.Due to working depth during crane lifting, during lifting Also need to grid power blackout coordinate, had a strong impact on the operation of other equipment, meanwhile, hindered the operation of other parallel circuits, exist Certain security risk.And use railway breakdown to hang, due to rescue hang be the rail vehicles in railway accident or its Its barrier carries out the special purpose vehicle of lifting cleaning, is mainly used in urgent railway breakdown, it is desirable to stand ready, rescues Helping to hang and once come into operation, it sets up needs flower long time so that complete the lifting of just beam in of short duration blocking time Bringing difficulty, it addition, rescue is after suspension bracket sets, its dismounting is also required to the long period, once railway generation emergency, will be unable to and Time arrive in, bring security risk.
The built on stilts reinforcing present stage of existing railway in operation has mainly used three kinds of technology, horizontal lifts vertical builder's jack sky method for strengthening: i.e. Using rail beam to do longeron, 40H shaped steel does crossbeam and lifts the built on stilts hardened link method on take-up road, the parts that this method needs More, structure is complicated and unstable, and safety coefficient is little, it is desirable to train speed limit 25km/h, it is impossible to meet movement requirement, does not builds View uses;D type construction beam makes somebody a mere figurehead method for strengthening: i.e. use the D type construction beam of sizing to make somebody a mere figurehead hardened link, existing have D12, Tetra-kinds of spans of D16, D20, D24, the method simple in construction, safety and stability, but, maximum span is only 24 meters, can not meet big Span structure passes through needs, and bigger to span or that oblique angles the is bigger frame bridge construction suitability is poor, even phase There is also weight with the construction beam of span the heaviest, girder is higher is unfavorable for the problems such as construction;Construction beam is built on stilts continuously adds Gu method, the method that the large-scale steel I-beam of fixing modulus uses equal strength connect forms the continuous beam of long span, and centre sets One or more fulcrums define redundant structure, but, with curve half in the case of double track railway section distance between centers of tracks is less Also cannot use when footpath is less, large-scale steel I-beam lateral stiffness is not enough, and less stable is unfavorable to traffic safety, and cost is high, Particularly cannot use Large-scale Hoisting equipment in electrified sections, use and there is beam body when manually setting a roof beam in place and topple the peaces such as unstability Full blast danger.
Utility model content
The purpose of this utility model is to provide a kind of novel construction beam to solve the problems referred to above;Due to this just beam The a length of 32.6m of girder arranged, deck-molding 1.7m, deck-siding 0.48m, girder uses Q345qD steel with crossbeam material, not only subtracts The weight of few construction beam, greatly reduces the difficulty of construction middle girder lifting, and width of main beam is less, for two-wire, multi-thread line The frame bridge construction on road and the frame bridge construction of the less circuit of sweep also have the preferable suitability, are also applied for single case span The undercrossing tunnel frame bridge construction that bigger or oblique angles is bigger, and the construction of the undercrossing tunnel frame bridge of many casees;Meanwhile, This crossbeam that just beam is arranged may be provided in highest order, a secondary high position, middle position, secondary low level, five kinds of positions of lowest order, thus can be suitable for Construction basis in multiple different depth;It addition, the increasing of this just girder construction span, promote to cancel during Framed underpass bridge The construction procedure of temporary support and system transform, thus decrease the construction period of Framed underpass bridge, largely save Construction cost, is suitable to railway and makes somebody a mere figurehead the construction of hardened link and promote the use of.
In order to achieve the above object, this utility model is realized by following technological means.
A kind of novel construction beam, it is by girder, splice plate, crossbeam, bracket, connecting plate, dividing plate, slag trap, strength plate, gear Foot, hand hole part combine, and it is characterized in that: the upper and lower two ends of girder are provided with the first cover plate, and the first cover plate upper end is provided with and adds Strong plate, is provided with multiple dividing plate in girder, dividing plate both sides arrange energetically plate, and girder lower end is provided with rubber support, support plate, rubber Glue bearing is fixed with support plate by gear foot;Girder is fixedly connected by bracket, connecting plate and 49 crossbeams, and crossbeam is upper and lower Both sides are provided with the second cover plate, and the second cover plate lower end is provided with slag trap, is provided with the first web, on the first web in the middle part of crossbeam It is provided with fixed plate, gripper shoe, is fixedly connected by first segment plate, brace, second section plate, Section of three plate between crossbeam.
The a length of 32.6m of described girder, deck-molding 1.7m, deck-siding 0.48m, girder is spliced by 3 sections, sections it Between be fixedly connected by splice plate, splice plate both sides and the second web are provided with hand hole, splicing form is bolt splicing.
Described crossbeam riding position is divided into highest order, a secondary high position, middle position, secondary low level, lowest order, 49 crossbeam adjacent row Row, the spacing between crossbeam is 670mm.
Described girder uses Q345qD steel with crossbeam material.
The three of girder sections are first used splice plate splicing by operation principle: before undercrossing tunnel frame bridge holds out against construction After complete, a girder is fallen within side supports plate, then crossbeam is connected with girder through use bracket, connecting plate from rail Connecing, crossbeam top is connected with rail by rail fastening, then, is connected with another root girder by crossbeam by bracket, connecting plate, Then, first segment plate, second section plate, Section of three plate, brace are connected with crossbeam, Framed underpass bridge after installing, can be started The excavation of construction.
This utility model mainly has the advantages that
1, this length of 32.6m of girder that just beam is arranged, deck-molding 1.7m, deck-siding 0.48m, girder uses with crossbeam material Q345qD steel, not only reduce the weight of construction beam, greatly reduce the difficulty of construction middle girder lifting, and width of main beam is relatively Little, the frame bridge for two-wire, multi-thread circuit is constructed and the frame bridge construction of the less circuit of sweep also has the most applicable Property, it is also applied for the single undercrossing tunnel frame bridge that case span is bigger or oblique angles is bigger construction, and wears ferrum under many casees The construction of road frame bridge.
2, this crossbeam that just beam is arranged may be provided in highest order, a secondary high position, middle position, secondary low level, five kinds of positions of lowest order, so Just go for the construction basis of multiple different depth.
3, the increasing of this just girder construction span, promotes to eliminate temporary support and system transform during Framed underpass bridge Construction procedure, thus decrease the construction period of Framed underpass bridge, largely saved construction cost, be suitable to railway frame The construction of empty hardened link is promoted the use of.
Accompanying drawing explanation
Accompanying drawing 1 is the plan structure schematic diagram of a kind of novel construction beam of this utility model.
Accompanying drawing 2 is that the A-A of a kind of novel construction beam of this utility model is to structural representation.
Accompanying drawing 3 is the girder splicing construction schematic diagram of a kind of novel construction beam of this utility model.
As shown in Figure 1-Figure 3, each ingredient of above-mentioned a kind of novel construction beam is represented by following Arabic numerals:
Girder-1, splice plate-2, first segment plate-3, brace-4, second section plate-5, crossbeam-6, Section of three plate-7, reinforcement Plate-8, the first cover plate-9, bracket-10, fixed plate-11, gripper shoe-12, connecting plate-13, dividing plate-4, the first web-15, second Cover plate-16, slag trap-17, strength plate-18, rubber support-19, support plate-20, gear foot-21, the second web-22, hand hole-23.
Detailed description of the invention
Embodiment
As shown in Figure 1-Figure 3, a kind of novel construction beam, it is by girder 1, splice plate 2, crossbeam 6, bracket 10, connecting plate 13, dividing plate 14, slag trap 17, strength plate 18, gear foot 21, hand hole 23 part combine.
As shown in Figure 1-Figure 3, girder about 1 two ends are provided with the first cover plate 9, and the first cover plate 9 upper end is provided with reinforcing plate 8, it is provided with multiple dividing plate 14 in girder 1, dividing plate 14 both sides arrange energetically plate 18, and girder 1 lower end is provided with rubber support 19, props up Seat board 20, rubber support 19 is fixed with support plate 20 by gear foot 21;Girder 1 is by bracket 10, connecting plate 13 and 49 horizontal strokes Beam 6 is fixedly connected, and crossbeam about 6 both sides are provided with the second cover plate 16, and the second cover plate 16 lower end is provided with slag trap 17, crossbeam It is provided with the first web 15 in the middle part of in the of 6, the first web 15 is provided with fixed plate 11, gripper shoe 12, between crossbeam 6, passes through first segment Plate 3, brace 4, second section plate 5, Section of three plate 7 are fixedly connected.
The described a length of 32.6m of girder 1, deck-molding 1.7m, deck-siding 0.48m, girder 1 is spliced by 3 sections, sections Between be fixedly connected by splice plate 2, splice plate 2 both sides and the second web 22 are provided with hand hole 23, splicing form is spiral shell Bolt splices.
Described crossbeam 6 riding position is divided into highest order, a secondary high position, middle position, secondary low level, lowest order, and 49 crossbeams 6 are adjacent Arrangement, the spacing between crossbeam 6 is 670mm.
Described girder 1 uses Q345qD steel with crossbeam 6 material.
This construction beam (D32 type just beam) arranges size and is shown in Table 1.
Table 1

Claims (4)

1. a novel construction beam, it is by girder (1), splice plate (2), crossbeam (6), bracket (10), connecting plate (13), dividing plate (14), slag trap (17), strength plate (18), gear foot (21), hand hole (23) part combine, it is characterized in that: girder (1) upper and lower two End is provided with the first cover plate (9), and the first cover plate (9) upper end is provided with reinforcing plate (8), and girder is provided with multiple dividing plate in (1) (14), dividing plate (14) both sides arrange energetically plate (18), and girder (1) lower end is provided with rubber support (19), support plate (20), rubber Bearing (19) is fixed with support plate (20) by gear foot (21);Girder (1) is by bracket (10), connecting plate (13) and 49 horizontal strokes Beam (6) is fixedly connected, and crossbeam (6) is provided with the second cover plate (16) in both sides up and down, and the second cover plate (16) lower end is provided with pushing off the slag Plate (17), crossbeam (6) middle part is provided with the first web (15), the first web (15) is provided with fixed plate (11), gripper shoe (12), it is fixedly connected by first segment plate (3), brace (4), second section plate (5), Section of three plate (7) between crossbeam (6).
The novel construction beam of one the most according to claim 1, is characterized in that: girder (1) a length of 32.6m, deck-molding 1.7m, deck-siding 0.48m, girder (1) is spliced by 3 sections, is fixedly connected by splice plate (2) between sections, splicing Being provided with hand hole (23) on plate (2) both sides and the second web (22), splicing form is bolt splicing.
The novel construction beam of one the most according to claim 1, is characterized in that: crossbeam (6) riding position be divided into highest order, A secondary high position, middle position, secondary low level, lowest order, 49 crossbeam (6) arranged adjacent, the spacing between crossbeam (6) is 670mm.
The novel construction beam of one the most according to claim 1, is characterized in that: girder (1) uses with crossbeam (6) material Q345qD steel.
CN201620824219.8U 2016-07-28 2016-07-28 A kind of novel construction beam Active CN205857044U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620824219.8U CN205857044U (en) 2016-07-28 2016-07-28 A kind of novel construction beam

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620824219.8U CN205857044U (en) 2016-07-28 2016-07-28 A kind of novel construction beam

Publications (1)

Publication Number Publication Date
CN205857044U true CN205857044U (en) 2017-01-04

Family

ID=57653407

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620824219.8U Active CN205857044U (en) 2016-07-28 2016-07-28 A kind of novel construction beam

Country Status (1)

Country Link
CN (1) CN205857044U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109098102A (en) * 2018-10-11 2018-12-28 中铁第五勘察设计院集团有限公司 Just beam ruggedized construction for switch section
CN111021415A (en) * 2020-01-06 2020-04-17 山东济铁工程建设集团有限公司 Construction structure and method for transition beam of railway underpass type frame bridge
CN114182583A (en) * 2021-11-30 2022-03-15 上海同济工程咨询有限公司 Supporting structure of temporary beam
CN114318979A (en) * 2021-12-31 2022-04-12 中铁六局集团石家庄铁路建设有限公司 Automatic pulling-through system and method for reinforcing I-steel of jacking line of frame-structured bridge

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109098102A (en) * 2018-10-11 2018-12-28 中铁第五勘察设计院集团有限公司 Just beam ruggedized construction for switch section
CN109098102B (en) * 2018-10-11 2024-04-30 中铁第五勘察设计院集团有限公司 A just roof beam reinforced structure for switch district section
CN111021415A (en) * 2020-01-06 2020-04-17 山东济铁工程建设集团有限公司 Construction structure and method for transition beam of railway underpass type frame bridge
CN114182583A (en) * 2021-11-30 2022-03-15 上海同济工程咨询有限公司 Supporting structure of temporary beam
CN114182583B (en) * 2021-11-30 2024-05-10 上海同济工程咨询有限公司 Support structure of toilet beam
CN114318979A (en) * 2021-12-31 2022-04-12 中铁六局集团石家庄铁路建设有限公司 Automatic pulling-through system and method for reinforcing I-steel of jacking line of frame-structured bridge
CN114318979B (en) * 2021-12-31 2023-08-18 中铁六局集团石家庄铁路建设有限公司 Automatic penetrating and pulling system and method for frame bridge jacking line reinforcement I-steel

Similar Documents

Publication Publication Date Title
CN205857044U (en) A kind of novel construction beam
CN111945580B (en) Bridge deck erection method for large-radian curve type steel box girder
CN202064293U (en) Traction system used for steel trussed beam cantilever hauling construction
CN101380954A (en) Suspension train traffic system with hanging rail
CN105155414A (en) Floor-type slant-legged steel truss bracket of lower transverse beam of large-span cable tower
CN102134832B (en) Movable support and movable support assisted method for erecting steel box beams through non-variable amplitude frame beam crane
CN104532749A (en) Support used for construction of upper beam of main tower of suspension bridge
CN102817329A (en) Process for erecting construction auxiliary girder on existing railway
CN201102544Y (en) Hanging train traffic system of hanging rail
CN109208471A (en) A kind of bridge maintenance nacelle construction platform
CN205205685U (en) Span wire pier is function portal device at most
CN205046477U (en) Large -span cable support tower bottom end rail console mode battered leg steel purlin support
CN204385629U (en) A kind of support for the construction of suspension bridge king-tower top rail
CN112144401B (en) Bridge girder erection machine over-span method based on curve track and large longitudinal slope environment
CN205857004U (en) A kind of construction beam
CN203716044U (en) Low bearing or middle bearing cable arch combined structural bridge
CN207175246U (en) A kind of gantry crane work anti-dumping bracing means
CN113832863B (en) Method for double-frame bridge
CN202865707U (en) Equipment for erecting and constructing beam and vertical beam on existing line
CN102535351B (en) Web plate type bridge fabrication machine for constructing bridge under strong wind and high altitude conditions and construction process
CN204919348U (en) Supplementary head tower of using of self anchored suspension bridge installation
CN111945572B (en) Multi-connected arch bridge erecting machine and multi-connected arch bridge erecting method
CN201943006U (en) Main tower zone movable bracket for assisting non-variable amplitude girder erecting crane to erect steel box girders
CN201647844U (en) Beam lifting station without abutments
CN205804178U (en) Scalable without holder device for the liftable of bridge coping construction

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant