CN110820602A - A single-segment box girder bridge erecting machine and its operation method - Google Patents

A single-segment box girder bridge erecting machine and its operation method Download PDF

Info

Publication number
CN110820602A
CN110820602A CN201911265906.5A CN201911265906A CN110820602A CN 110820602 A CN110820602 A CN 110820602A CN 201911265906 A CN201911265906 A CN 201911265906A CN 110820602 A CN110820602 A CN 110820602A
Authority
CN
China
Prior art keywords
support
fixedly connected
box girder
bridge
machine
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201911265906.5A
Other languages
Chinese (zh)
Inventor
张昶
叶业
魏民
王浩
罗璐
高果
穆帮桥
黄�俊
王洪
刘前林
曾好
朱可
唐毅
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chongqing Communications Construction Group Co ltd
Chongqing Construction Engineering Group Co Ltd
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201911265906.5A priority Critical patent/CN110820602A/en
Publication of CN110820602A publication Critical patent/CN110820602A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • E01D21/10Cantilevered erection
    • E01D21/105Balanced cantilevered erection
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • E01D21/06Methods or apparatus specially adapted for erecting or assembling bridges by translational movement of the bridge or bridge sections

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

本发明公开了一种单台节段箱梁架桥机及其操作方法,解决了架桥过程中单台节段箱梁的架设问题,而且架桥机前支腿墩前附墩支承架轻便且安全可靠、能快速拆装及转场,解决了目前的操作平台不方便进行湿接缝施工及梁底修饰问题。包括盖梁和底座,所述盖梁的外侧固定安装有架桥机主梁,所述架桥机主梁的上端固定连接有支撑梁,所述支撑梁的上端固定连接有导梁,所述导梁的上端固定安装有起重天车,所述导梁的下端固定连接有前辅助支腿,所述导梁的下端固定连接有中支腿,所述导梁的下端固定连接有后辅助支腿,所述中支腿的下端固定安装有连接梁,所述连接梁的下端安装有单台节段箱梁。

Figure 201911265906

The invention discloses a single-segment box girder bridge erection machine and an operation method thereof, which solves the erection problem of a single-segment box girder during the bridge erection process, and the support frame attached to the pier in front of the front leg pier of the bridge erector is lightweight And it is safe and reliable, and can be disassembled and assembled quickly and transferred, which solves the problem that the current operating platform is inconvenient for wet joint construction and beam bottom decoration. It includes a cover beam and a base, the outer side of the cover beam is fixedly installed with the main beam of the bridge erection machine, the upper end of the main beam of the bridge erection machine is fixedly connected with a support beam, and the upper end of the support beam is fixedly connected with a guide beam, the The upper end of the guide beam is fixedly installed with the crane crane, the lower end of the guide beam is fixedly connected with the front auxiliary leg, the lower end of the guide beam is fixedly connected with the middle support leg, and the lower end of the guide beam is fixedly connected with the rear auxiliary leg A connecting beam is fixedly installed at the lower end of the middle support leg, and a single segment box beam is installed at the lower end of the connecting beam.

Figure 201911265906

Description

一种单台节段箱梁架桥机及其操作方法A single-segment box girder bridge erecting machine and its operation method

技术领域technical field

本发明涉及一种单台节段箱梁架桥机,具体涉及一种单台节段箱梁架桥机及其操作方法。The invention relates to a single-section box girder bridge erecting machine, in particular to a single-segment box girder bridge erecting machine and an operation method thereof.

背景技术Background technique

架桥机就是将预制好的梁片放置到预制好的桥墩上去的设备。架桥机属于起重机范畴,因为其主要功能是将梁片提起,然后运送到位置后放下。架桥机与一般意义上的起重机有很大的不同。其要求的条件苛刻,并且存在梁片上走行,或者叫纵移。The bridge erection machine is a device that places the prefabricated beams on the prefabricated piers. The bridge erection machine belongs to the category of cranes, because its main function is to lift the beam pieces, then transport them to the position and put them down. A bridge erecting machine is very different from a crane in the general sense. The required conditions are harsh, and there is running on the beam, or longitudinal movement.

在公路、铁路轨道上行驶、用于整跨架设小跨梁的桥梁施工机械。因其架桥工效高,在中国铁路桥梁标准设计中,多考虑以它架设为设计原则。其机身庞大,超出铁路运输限界,须解体运送,到达工地后,再组装使用。中国常备的架桥机有三种,多用来分片架设钢筋或预应力混凝土梁。架桥机纵向运行轨道两侧规定高度要求对应水平,保持平稳。前、中、后支腿各横向运行轨道要求水平,并严格控制间距,三条轨道必须平行。架桥机还设置有液压系统、电气系统、柴油发电机组以及安全保护监控系统等部分。Bridge construction machinery that runs on roads and railway tracks and is used to erect small-span beams across the entire span. Because of its high efficiency of bridging, in the standard design of railway bridges in China, it is often considered as the design principle. Its fuselage is huge and exceeds the limit of railway transportation. It must be disassembled and transported. After arriving at the construction site, it will be assembled and used. There are three kinds of bridge erection machines in China, which are mostly used to erect steel bars or prestressed concrete beams in pieces. The specified height on both sides of the longitudinal running track of the bridge erecting machine is required to correspond to the level and keep it stable. The horizontal running rails of the front, middle and rear outriggers are required to be level, and the spacing is strictly controlled, and the three rails must be parallel. The bridge erecting machine is also equipped with hydraulic system, electrical system, diesel generator set and safety protection monitoring system.

架桥机分为架设公路桥,常规铁路桥,客专铁路桥等几种。架桥机在架设单台节段箱梁时,目前的方式比较笨重,设备支撑架自重较大,不方便进行快速拆装及转场。而且操作平台不方便进行湿接缝施工及梁底修饰。因此,需要对现有技术进行改进。Bridge erection machine is divided into erecting highway bridges, conventional railway bridges, passenger railway bridges and so on. When the bridge erecting machine erects a single segment box girder, the current method is relatively cumbersome, and the equipment support frame has a large self-weight, which is inconvenient for quick disassembly and transition. Moreover, the operation platform is inconvenient for wet joint construction and beam bottom decoration. Therefore, there is a need for improvements to the prior art.

发明内容SUMMARY OF THE INVENTION

本发明的目的在于提供一种单台节段箱梁架桥机及其操作方法,解决了架桥过程中单台节段箱梁的架设问题,而且架桥机前支腿墩前附墩支承架轻便且安全可靠、能快速拆装及转场,解决了目前的操作平台不方便进行湿接缝施工及梁底修饰问题。The purpose of the present invention is to provide a single-segment box girder bridge erection machine and an operation method thereof, which solves the erection problem of a single-segment box girder during the bridge erection process, and the front outrigger pier is supported by the front pier. The frame is light, safe and reliable, and can be quickly disassembled and transferred, which solves the problems that the current operating platform is inconvenient for wet joint construction and beam bottom decoration.

本发明的目的可以通过以下技术方案实现:The object of the present invention can be realized through the following technical solutions:

一种单台节段箱梁架桥机,包括盖梁和底座,所述盖梁的外侧固定安装有架桥机主梁,所述架桥机主梁的上端固定连接有支撑梁,所述支撑梁的上端固定连接有导梁,所述导梁的上端固定安装有起重天车,所述导梁的下端固定连接有前辅助支腿,所述导梁的下端固定连接有中支腿,所述导梁的下端固定连接有后辅助支腿,所述中支腿的下端固定安装有连接梁,所述连接梁的下端安装有单台节段箱梁;A single-segment box girder bridge erection machine comprises a cover beam and a base, a main beam of the bridge erection machine is fixedly installed on the outer side of the cover beam, and a support beam is fixedly connected to the upper end of the main beam of the bridge erection machine. The upper end of the support beam is fixedly connected with a guide beam, the upper end of the guide beam is fixedly installed with a crane, the lower end of the guide beam is fixedly connected with a front auxiliary leg, and the lower end of the guide beam is fixedly connected with a middle leg , the lower end of the guide beam is fixedly connected with a rear auxiliary leg, the lower end of the middle leg is fixedly installed with a connecting beam, and the lower end of the connecting beam is installed with a single segment box beam;

所述底座与地面固定连接,所述底座的上端固定连接有支撑座,所述支撑座的上端固定连接有钢支撑柱,所述支撑柱的上端固定连接有工字钢支撑,所述工字钢支撑的上端固定连接有调节沙筒,所述调节沙筒的上端固定连接有调节楔块,所述调节楔块与盖梁的悬臂底部接触。The base is fixedly connected to the ground, the upper end of the base is fixedly connected with a support seat, the upper end of the support base is fixedly connected with a steel support column, the upper end of the support column is fixedly connected with an I-beam support, and the I-shaped steel support is fixedly connected to the upper end of the support column. The upper end of the steel support is fixedly connected with an adjusting sand barrel, and the upper end of the adjusting sand barrel is fixedly connected with an adjusting wedge, and the adjusting wedge is in contact with the bottom of the cantilever of the cover beam.

优选的,所述钢支撑柱的中部通过螺栓安装有支撑拉杆,所述支撑拉杆与盖梁通过螺栓紧固连接。Preferably, a support tie rod is installed in the middle of the steel support column through bolts, and the support tie rod and the cover beam are fastened with bolts.

优选的,所述调节楔块由两个楔块和一个拉杆构成,且拉杆的两侧安装螺母。Preferably, the adjusting wedge is composed of two wedges and a pull rod, and nuts are installed on both sides of the pull rod.

优选的,所述支撑座、支撑柱和工字钢支撑为焊接结构。Preferably, the support seat, the support column and the I-beam support are of welded structures.

优选的,所述导梁为矩形桁架结构形式,弦杆是由钢板拼焊而成的工字梁,腹杆为槽钢对扣而成的箱形杆件。Preferably, the guide beam is in the form of a rectangular truss structure, the chord is an I-beam formed by tailor-welding steel plates, and the web is a box-shaped member formed by double-buckling channel steel.

优选的,所述中支腿上设有顶升和横移、纵移油缸。Preferably, the middle outriggers are provided with oil cylinders for lifting, lateral movement and longitudinal movement.

一种单台节段箱梁架桥机的操作方法,具体步骤包括:A method for operating a single-segment box girder bridge erecting machine, the specific steps comprising:

步骤一:施工下部结构,下部结构完成后通过架桥机吊装中支点墩顶块并进行临时固定;Step 1: Construction of the lower structure, after the completion of the lower structure, the top block of the middle fulcrum pier is hoisted by the bridge erection machine and temporarily fixed;

步骤二:吊装首跨箱梁,调整箱梁节段位置,并进行预拼装;Step 2: Hoist the first span box girder, adjust the position of the box girder segment, and carry out pre-assembly;

步骤三:将前两个箱梁匹配面进行涂摸胶粘结剂,且两个箱梁匹配定位,并施加临时预应力挤紧固化,重复以上步骤拼装至十一号块;Step 3: Apply adhesive on the matching surfaces of the first two box girders, match and position the two box girders, apply temporary prestress to squeeze and tighten, and repeat the above steps to assemble to No. 11 block;

步骤四:安装湿接缝模板,浇筑湿接缝并养生,利用起重天车吊装超前墩墩顶块,并锚固好;Step 4: Install the wet joint formwork, pour the wet joint and maintain it, use the crane to hoist the top block of the advanced pier, and anchor it well;

步骤五:待湿接缝浇筑混凝土达到%,分批对称张拉体外预应力,完成张拉后,整机卸载,拆除吊挂,并倒运吊挂到地面;Step 5: When the wet joints are poured concrete reaches %, the external prestress is symmetrically tensioned in batches. After the tension is completed, the whole machine is unloaded, the hanging is removed, and it is transported and hung to the ground;

步骤六:利用天车进行跨越式倒运后,墩中支腿到超前墩,并锚固好;Step 6: After the overhead crane is used to carry out the reverse transportation by leaps and bounds, the outriggers in the pier are moved to the leading pier and anchored well;

步骤七:架桥机向前纵移,天车位于主框架前方作为配重,纵移到位并调整好架桥机的姿势;Step 7: The bridge erection machine moves forward longitudinally, the crane is located in front of the main frame as a counterweight, and the bridge erection machine is moved longitudinally in place and the posture of the bridge erection machine is adjusted;

步骤八:按首跨顺序拼装中跨主梁,并浇筑湿接缝;Step 8: Assemble the mid-span main beams in the order of the first span, and pour the wet joints;

步骤九:待混凝土强度达到%,分批对称张拉中跨预应力;Step 9: When the concrete strength reaches %, the mid-span prestress is symmetrically tensioned in batches;

步骤十:施工尾跨主梁,完成后张拉负弯矩预应力钢束;Step 10: construct the main beam of the tail span, and tension the prestressed steel bundle with negative bending moment after completion;

步骤十一:桥面铺装及附属设施安装。Step 11: Bridge deck paving and installation of ancillary facilities.

本发明的有益效果:本方案采用节段拼装架桥机单幅整孔悬挂拼装架设,然后横移完成另一幅整孔悬挂拼装架设,双幅整孔完成后纵移到新的一跨逐跨完成架设。The beneficial effects of the present invention are as follows: this scheme adopts the segmental assembly bridge erection machine for single-width whole-hole suspension assembly and erection, and then traverses to complete another whole-hole suspension, assembly and erection, and longitudinally moves to a new span-by-span after the completion of double-width whole-hole construction Complete erection.

架桥机采用步履式行走,能自行移位过孔,支腿倒运采用自动跨越式倒腿方式,横移轨道也可自行倒运;架桥机喂梁方式满足桥下喂梁,兼顾前部、尾部喂梁;架桥机能够满足湿接缝施工,自带可移动梁底操作平台,梁底操作平台即可进行湿接缝施工又可进行梁底修饰;架桥机具备自架墩顶(或梁端块)块功能;架桥机前支腿墩前附墩支承架轻便且安全可靠、能快速拆装及转场。The bridge erecting machine adopts the walking type, which can move through the holes by itself. The outriggers are reversed by the automatic leaping type, and the traverse track can also be reversed by themselves; Feed the beam at the tail; the bridge erection machine can meet the construction of wet joints, and it comes with a movable beam bottom operating platform, which can carry out wet joint construction and beam bottom decoration; or beam end block) block function; the pier support frame attached to the front of the front leg pier of the bridge erecting machine is light, safe and reliable, and can be quickly disassembled and transferred.

附图说明Description of drawings

为了便于本领域技术人员理解,下面结合附图对本发明作进一步的说明。In order to facilitate the understanding of those skilled in the art, the present invention will be further described below with reference to the accompanying drawings.

图1为本发明整体结构示意图;Fig. 1 is the overall structure schematic diagram of the present invention;

图2为本发明盖梁支撑结构示意图;2 is a schematic diagram of the support structure of the cover beam of the present invention;

图3为本发明图2中A区域细节放大图;Fig. 3 is the enlarged view of detail of A area in Fig. 2 of the present invention;

图4为本发明的拼装流程图;Fig. 4 is the assembly flow chart of the present invention;

图5为本发明步骤一拼装示意图;Fig. 5 is a schematic diagram of step 1 assembling of the present invention;

图6为本发明步骤二拼装示意图;Fig. 6 is the assembly schematic diagram of step 2 of the present invention;

图7为本发明步骤三拼装示意图;7 is a schematic diagram of step 3 assembling of the present invention;

图8为本发明步骤四拼装示意图;8 is a schematic diagram of step 4 assembling of the present invention;

图9为本发明步骤五拼装示意图;Fig. 9 is the assembly schematic diagram of step 5 of the present invention;

图10为本发明步骤六拼装示意图;Figure 10 is a schematic diagram of step 6 assembling of the present invention;

图11为本发明步骤七拼装示意图;Figure 11 is a schematic diagram of the seventh step of assembling of the present invention;

图12为本发明步骤八拼装示意图;Figure 12 is a schematic diagram of the eighth step of assembling of the present invention;

图13为本发明步骤九拼装示意图;Figure 13 is a schematic diagram of step nine assembling of the present invention;

图14为本发明步骤十拼装示意图;Figure 14 is a schematic diagram of step ten assembling of the present invention;

图15为本发明步骤十一拼装示意图。FIG. 15 is a schematic diagram of the eleventh step of the present invention assembling.

图中:1、盖梁;2、架桥机主梁;3、支撑梁;4、导梁;5、起重天车;6、前辅助支腿;7、中支腿;8、后辅助支腿;9、连接梁;10、单台节段箱梁;11、底座;12、支撑座;13、钢支撑柱;14、支撑拉杆;15、工字钢支撑;16、调节沙筒;17、调节楔块。In the picture: 1. Cover beam; 2. Main beam of bridge erection machine; 3. Support beam; 4. Guide beam; 5. Crane crane; 6. Front auxiliary outrigger; 7. Middle outrigger; 8. Rear auxiliary Outrigger; 9. Connecting beam; 10. Single segment box beam; 11. Base; 12. Support seat; 13. Steel support column; 14. Support rod; 15. I-beam support; 16. Adjusting sand barrel; 17. Adjust the wedge.

具体实施方式Detailed ways

下面将结合实施例对本发明的技术方案进行清楚、完整地描述,显然,所描述的实施例仅仅是本发明一部分实施例,而不是全部的实施例。基于本发明中的实施例,本领域普通技术人员在没有作出创造性劳动前提下所获得的所有其它实施例,都属于本发明保护的范围。The technical solutions of the present invention will be clearly and completely described below with reference to the embodiments. Obviously, the described embodiments are only a part of the embodiments of the present invention, rather than all the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those of ordinary skill in the art without creative efforts shall fall within the protection scope of the present invention.

请参阅图1-15所示,一种单台节段箱梁架桥机,包括盖梁1和底座11,盖梁1的外侧固定安装有架桥机主梁2,架桥机主梁2为架桥机主体支撑结构,为整个架桥机提供了稳定的支撑,架桥机主梁2的翼缘板宽1.4m,梁高2.8m,全长33m(分为3个节段,节段长度11m),节段间采用高强螺栓联接,节段解体后可由公路或铁路运输,下翼缘板上和下盖板底部设有供前辅助支腿托、挂轮走行的轨道,机臂与中支腿7和后辅助支腿8通过高强螺栓固定联接,前辅助支腿6纵移时可与机臂相对运动,架梁时通过托挂轮组、定位装置与机臂铰接架桥机主梁2的上端固定连接有支撑梁3,支撑梁3为构造梁,具有支撑作用,支撑梁3的上端固定连接有导梁4,导梁4的高度为2.8m,单根导梁长46m(前导梁33.5:11+11+11+1.5、后导梁:12.5:11+1.5),导梁4的上端固定安装有起重天车5,起重天车5是架桥机的主要工作单元,设有80t起升机构卷扬机及控制和操作系统,天车总重40t,起升小车加回转吊耳重量9.4t,金属结构加大车走行机构等重17.5t,起重天车5的外形尺寸(天车高度×轨距×跨度)为8.8×3.6×6m,起重天车5采用凹式结构架,走行机构采用链传动牵引,重物移运器承重走行的方式,起重小车起升机构为电机驱动,行星齿轮减速机内藏式卷扬机传动,起升机构的高速轴和卷筒上均设有制动装置,高速轴采用液压推杆制动器作为常规运行制动,电机与减速机之间通过带制动轮的齿轮联轴器连接;低速级采用液压盘式制动器作为紧急制动,确保吊梁作业安全可靠,起升机构包括起升卷扬机、动滑轮组、定滑轮组和均衡滑轮等,滑轮组倍率为2×16,其中均衡滑轮架上安装有荷重传感器,可以实时反映起升载荷,起升卷扬机为电机驱动行星齿轮减速机内藏式卷扬机,电机自带制动装置,起重天车5卷扬机构采用主动排绳器排绳,排绳器由变频电机、链轮、链条、丝杆、螺母、导向杆、支座和导向滚轮等组成传动机构,是一个随动系统,与卷扬机形成闭环控制。卷扬机转一圈,排绳器的导向滚轮横向移动一个钢丝绳直径距离,导向滚轮走到一端,钢丝绳在卷筒上缠绕完一层,通过接近开关使导向滚轮反向运动,开始第二层钢丝绳的缠绕,导梁4的下端固定连接有前辅助支腿6,前辅助支腿6支撑在超前墩承台的立柱上,主要用于过跨时倒运后辅助支腿8和中支腿7,前辅助支腿6拼装后总体尺寸为6.5×5.12×0.8m,辅助前支腿6主要由托挂轮机构、折叠柱、伸缩柱等组成,架梁作业时与机臂纵向固定成铰接结构,成为柔性支腿,与机臂、中支腿7组成龙门架结构,满足架梁作业支撑要求,纵移作业时辅助前支腿6与机臂之间可相对运动,实现架桥机步履纵移,辅助前支腿6设有折叠机构,可以满足正常架梁和最后一孔箱梁架设时辅助前支腿上桥台支撑的需要,导梁4的下端固定连接有中支腿7,中支腿7用于支承和顶升整个架桥机,尤其是架桥机满载施工时的支撑,其上设有顶升和横移、纵移油缸,驱动架桥机动作,单个中支腿7拼装后总体尺寸为8.2×3.13×2.02m,单个中支腿7总重为30t,中支腿7通过液压油缸实现支撑枕木的支垫和拆除,满足纵移时换步和架梁作业时稳定支撑要求,两支腿下设有横移机构,通过横移油缸推动二号柱带动机臂摆头,从而横向调整架桥机位置,适应曲线架梁需要,由于运梁车驮运架桥机工况的需要,下横梁设计成可拆卸式,导梁4的下端固定连接有后辅助支腿8,后辅助支腿8支承在梁面上,用于倒运后中支腿7,并代替中支腿7起支撑作用(三点支撑),直至架桥机处于最大后悬臂状态,后辅助支腿8可以挂在后导梁上,随主框架一起纵移前行,单个后辅助支腿8拼装后总体尺寸为7.64×3.85×1.76m,单个后辅助支腿8总重为12t,中支腿7的下端固定安装有连接梁9,连接梁9的下端安装有单台节段箱梁10,单台节段箱梁10由钢筋混凝土预制而成;Please refer to Fig. 1-15, a single-segment box girder bridge erection machine, including a cover beam 1 and a base 11, the outer side of the cover beam 1 is fixedly installed with the main beam 2 of the bridge erection machine, and the main beam of the bridge erection machine 2 It is the main support structure of the bridge erecting machine and provides stable support for the entire bridge erecting machine. The flange plate width of the main girder 2 of the bridge erecting machine is 1.4m, the beam height is 2.8m, and the total length is 33m (divided into 3 sections, section 2). The segment length is 11m), and the segments are connected by high-strength bolts. The segments can be transported by road or rail after disintegration. The lower flange plate and the bottom of the lower cover plate are provided with tracks for front auxiliary outriggers and hanging wheels. It is fixedly connected with the middle outrigger 7 and the rear auxiliary outrigger 8 through high-strength bolts. When the front auxiliary outrigger 6 moves longitudinally, it can move relative to the machine arm. When the beam is erected, the bridge erection machine is hinged with the arm through the supporting and hanging wheel set and the positioning device. The upper end of the main beam 2 is fixedly connected with a support beam 3. The support beam 3 is a structural beam and has a supporting function. The upper end of the support beam 3 is fixedly connected with a guide beam 4. The height of the guide beam 4 is 2.8m, and the length of a single guide beam is 46m. (Front guide beam 33.5: 11+11+11+1.5, rear guide beam: 12.5: 11+1.5), the upper end of the guide beam 4 is fixedly installed with a crane 5, which is the main work of the bridge erection machine The unit is equipped with an 80t hoisting mechanism hoist, control and operating system, the total weight of the crane is 40t, the weight of the hoisting trolley plus the slewing lug is 9.4t, the metal structure increases the weight of the traveling mechanism of the vehicle, and the equal weight is 17.5t. The overall dimensions (height of the crane x gauge x span) are 8.8 x 3.6 x 6m, the crane crane 5 adopts a concave structure frame, the running mechanism adopts chain drive traction, the heavy object mover runs under load, and the lifting trolley The hoisting mechanism is driven by a motor, driven by a built-in hoist in a planetary gear reducer. The high-speed shaft and drum of the hoisting mechanism are equipped with braking devices. The machine is connected by a gear coupling with a brake wheel; the low-speed stage adopts a hydraulic disc brake as an emergency brake to ensure the safe and reliable operation of the hoisting beam. Etc., the pulley set magnification is 2×16, and the load sensor is installed on the balance pulley frame, which can reflect the lifting load in real time. The hoisting mechanism of the crane 5 adopts an active rope arranging device for arranging the rope. The rope arranging device is composed of a frequency conversion motor, a sprocket, a chain, a screw, a nut, a guide rod, a support and a guide roller. It is a follow-up system. The winch forms a closed-loop control. The hoist rotates once, the guide roller of the rope arranger moves laterally a distance of the diameter of the wire rope, the guide roller goes to one end, the wire rope is wound on the reel one layer, and the guide roller moves in the opposite direction through the proximity switch to start the second layer of wire rope. Winding, the lower end of the guide beam 4 is fixedly connected with the front auxiliary outrigger 6, and the front auxiliary outrigger 6 is supported on the upright column of the advanced pier cap, which is mainly used for the rear auxiliary outrigger 8 and the middle outrigger 7 to be transported backwards when crossing the span. The overall size of the auxiliary outriggers 6 after assembling is 6.5×5.12×0.8m. The auxiliary front outriggers 6 are mainly composed of a supporting wheel mechanism, a folding column, a telescopic column, etc. When the beam is erected, it is fixed longitudinally with the machine arm into a hinged structure, forming a hinged structure. The flexible outriggers, together with the arm and the middle outrigger 7, form a gantry structure to meet the support requirements of the beam erection operation. The auxiliary front outrigger 6 and the arm can move relative to each other during the longitudinal movement operation, so as to realize the longitudinal movement of the bridge erecting machine. The auxiliary front outrigger 6 is provided with a folding mechanism, which can meet the needs of supporting the upper abutment of the auxiliary front outrigger when the normal frame beam and the last hole box girder are erected. The lower end of the guide beam 4 is fixedly connected with a middle outrigger 7, which 7. It is used to support and lift the whole bridge erecting machine, especially the support when the bridge erecting machine is fully loaded. There are jacking, transverse and longitudinal oil cylinders on it to drive the action of the bridge erecting machine. After the single middle outrigger 7 is assembled The overall size is 8.2×3.13×2.02m, and the total weight of a single middle outrigger 7 is 30t. The middle outrigger 7 realizes the support and removal of the support sleeper through the hydraulic cylinder to meet the requirements for stable support during step change during longitudinal movement and beam erection operation. , There is a traverse mechanism under the two legs, and the second column is driven by the traverse cylinder to drive the arm to swing its head, so as to adjust the position of the bridge erection machine horizontally to meet the needs of the curved beam erection. The lower cross beam is designed to be detachable, the lower end of the guide beam 4 is fixedly connected with a rear auxiliary leg 8, and the rear auxiliary leg 8 is supported on the beam surface, which is used to transport the rear middle leg 7 and replace the middle leg. 7 plays a supporting role (three-point support) until the bridge erecting machine is in the state of the maximum rear cantilever, the rear auxiliary leg 8 can be hung on the rear guide beam, and moves longitudinally along with the main frame. After the single rear auxiliary leg 8 is assembled The overall size is 7.64×3.85×1.76m, the total weight of a single rear auxiliary leg 8 is 12t, the lower end of the middle leg 7 is fixedly installed with a connecting beam 9, and the lower end of the connecting beam 9 is installed with a single segment box girder 10. The platform segment box girder 10 is prefabricated by reinforced concrete;

底座11与地面固定连接,底座11为现浇混凝土墩座,底座11的上端固定连接有支撑座12,底座11为支撑座12提供了支撑结构,支撑座12的上端固定连接有钢支撑柱13,支撑柱13的上端固定连接有工字钢支撑15,底座11、支撑座12和钢支撑柱13为焊接结构,构成盖梁1的悬臂的主体支撑结构,工字钢支撑15的上端固定连接有调节沙筒16,调节沙筒16的上端固定连接有调节楔块17,调节楔块17与盖梁1的悬臂底部接触。The base 11 is fixedly connected to the ground, the base 11 is a cast-in-place concrete pier, the upper end of the base 11 is fixedly connected with a support base 12, the base 11 provides a support structure for the support base 12, and the upper end of the support base 12 is fixedly connected with a steel support column 13 , the upper end of the support column 13 is fixedly connected with an I-beam support 15, the base 11, the support base 12 and the steel support column 13 are welded structures, which constitute the main support structure of the cantilever of the cover beam 1, and the upper end of the I-beam support 15 is fixedly connected There is an adjusting sand bucket 16 , an adjusting wedge 17 is fixedly connected to the upper end of the adjusting sand bucket 16 , and the adjusting wedge 17 is in contact with the bottom of the cantilever of the cover beam 1 .

钢支撑柱13的中部通过螺栓安装有支撑拉杆14,支撑拉杆14与盖梁1通过螺栓紧固连接,通过支撑拉杆14的安装,可以对钢支撑柱13进行辅助支撑,防止钢支撑柱13发生歪斜,调节楔块17由两个楔块和一个拉杆构成,且拉杆的两侧安装螺母,通过连杆拉动调节楔块17,可以进行组合楔块的调整,方便进行沉降补偿,支撑座12、钢支撑柱13和工字钢支撑15为焊接结构,构成悬臂的支撑结构,导梁4为矩形桁架结构形式,弦杆是由钢板拼焊而成的工字梁,腹杆为槽钢对扣而成的箱形杆件,中支腿7上设有顶升和横移、纵移油缸,可通过油缸进行相关部件的位置调节。A support rod 14 is installed in the middle of the steel support column 13 by bolts, and the support rod 14 is fastened with the cover beam 1 through bolts. For skewness, the adjusting wedge 17 is composed of two wedges and a tie rod, and nuts are installed on both sides of the tie rod, and the adjusting wedge 17 is pulled by the connecting rod to adjust the combined wedge, which is convenient for settlement compensation. The support seat 12, The steel support column 13 and the I-beam support 15 are welded structures, forming a cantilever support structure. The guide beam 4 is in the form of a rectangular truss structure. The chord is an I-beam made of welded steel plates. The box-shaped rod is formed, and the middle outriggers 7 are provided with oil cylinders for lifting, lateral movement and longitudinal movement, and the position of the relevant parts can be adjusted through the oil cylinders.

一种单台节段箱梁架桥机的操作方法,具体步骤包括:A method for operating a single-segment box girder bridge erecting machine, the specific steps comprising:

步骤一:施工下部结构,下部结构完成后通过架桥机吊装中支点墩顶块并进行临时固定;Step 1: Construction of the lower structure, after the completion of the lower structure, the top block of the middle fulcrum pier is hoisted by the bridge erection machine and temporarily fixed;

步骤二:吊装首跨箱梁,调整箱梁节段位置,并进行预拼装;Step 2: Hoist the first span box girder, adjust the position of the box girder segment, and carry out pre-assembly;

步骤三:将前两个箱梁匹配面进行涂摸胶粘结剂,且两个箱梁匹配定位,并施加临时预应力挤紧固化,重复以上步骤拼装至十一号块;Step 3: Apply adhesive on the matching surfaces of the first two box girders, match and position the two box girders, apply temporary prestress to squeeze and tighten, and repeat the above steps to assemble to No. 11 block;

步骤四:安装湿接缝模板,浇筑湿接缝并养生,利用起重天车吊装超前墩墩顶块,并锚固好;Step 4: Install the wet joint formwork, pour the wet joint and maintain it, use the crane to hoist the top block of the advanced pier, and anchor it well;

步骤五:待湿接缝浇筑混凝土达到95%,分批对称张拉体外预应力,完成张拉后,整机卸载,拆除吊挂,并倒运吊挂到地面;Step 5: When the wet joints are poured to 95% of the concrete, the external prestressing is symmetrically tensioned in batches. After the tensioning is completed, the whole machine is unloaded, the hanging is removed, and it is transported upside down and hung to the ground;

步骤六:利用天车进行跨越式倒运后,墩中支腿到超前墩,并锚固好;Step 6: After the overhead crane is used to carry out the reverse transportation by leaps and bounds, the outriggers in the pier are moved to the leading pier and anchored well;

步骤七:架桥机向前纵移,天车位于主框架前方作为配重,纵移到位并调整好架桥机的姿势;Step 7: The bridge erection machine moves forward longitudinally, the crane is located in front of the main frame as a counterweight, and the bridge erection machine is moved longitudinally in place and the posture of the bridge erection machine is adjusted;

步骤八:按首跨顺序拼装中跨主梁,并浇筑湿接缝;Step 8: Assemble the mid-span main beams in the order of the first span, and pour the wet joints;

步骤九:待混凝土强度达到95%,分批对称张拉中跨预应力;Step 9: When the concrete strength reaches 95%, the mid-span prestress is symmetrically tensioned in batches;

步骤十:施工尾跨主梁,完成后张拉负弯矩预应力钢束;Step 10: construct the main beam of the tail span, and tension the prestressed steel bundle with negative bending moment after completion;

步骤十一:桥面铺装及附属设施安装。Step 11: Bridge deck paving and installation of ancillary facilities.

本发明的有益效果为:本方案采用节段拼装架桥机单幅整孔悬挂拼装架设,然后横移完成另一幅整孔悬挂拼装架设,双幅整孔完成后纵移到新的一跨逐跨完成架设。The beneficial effects of the present invention are as follows: in this scheme, the single-width whole-hole suspension assembly and erection of the segment assembly bridge erection machine is adopted, and then another frame of whole-hole suspension, assembly and erection is completed by horizontal movement, and the double-width frame is moved longitudinally to a new span after completion of the whole-hole installation. Cross completed erection.

架桥机采用步履式行走,能自行移位过孔,支腿倒运采用自动跨越式倒腿方式,横移轨道也可自行倒运;架桥机喂梁方式满足桥下喂梁,兼顾前部、尾部喂梁;架桥机能够满足湿接缝施工,自带可移动梁底操作平台,梁底操作平台即可进行湿接缝施工又可进行梁底修饰;架桥机具备自架墩顶(或梁端块)块功能;架桥机前支腿墩前附墩支承架轻便且安全可靠、能快速拆装及转场。The bridge erecting machine adopts the walking type, which can move through the holes by itself. The outriggers are reversed by the automatic leaping type, and the traverse track can also be reversed by themselves; Feed the beam at the tail; the bridge erection machine can meet the construction of wet joints, and it comes with a movable beam bottom operating platform, which can carry out wet joint construction and beam bottom decoration; or beam end block) block function; the pier support frame attached to the front of the front leg pier of the bridge erecting machine is light, safe and reliable, and can be quickly disassembled and transferred.

以上公开的本发明优选实施例只是用于帮助阐述本发明。优选实施例并没有详尽叙述所有的细节,也不限制该发明仅为所述的具体实施方式。显然,根据本说明书的内容,可作很多的修改和变化。本说明书选取并具体描述这些实施例,是为了更好地解释本发明的原理和实际应用,从而使所属技术领域技术人员能很好地理解和利用本发明。本发明仅受权利要求书及其全部范围和等效物的限制。The above-disclosed preferred embodiments of the present invention are provided only to help illustrate the present invention. The preferred embodiments do not exhaust all the details, nor do they limit the invention to only the described embodiments. Obviously, many modifications and variations are possible in light of the content of this specification. The present specification selects and specifically describes these embodiments in order to better explain the principles and practical applications of the present invention, so that those skilled in the art can well understand and utilize the present invention. The present invention is to be limited only by the claims and their full scope and equivalents.

Claims (7)

1.一种单台节段箱梁架桥机,包括盖梁(1)和底座(11),其特征在于:所述盖梁(1)的外侧固定安装有架桥机主梁(2),所述架桥机主梁(2)的上端固定连接有支撑梁(3),所述支撑梁(3)的上端固定连接有导梁(4),所述导梁(4)的上端固定安装有起重天车(5),所述导梁(4)的下端固定连接有前辅助支腿(6),所述导梁(4)的下端固定连接有中支腿(7),所述导梁(4)的下端固定连接有后辅助支腿(8),所述中支腿(7)的下端固定安装有连接梁(9),所述连接梁(9)的下端安装有单台节段箱梁(10);1. A single segment box girder bridge erecting machine, comprising a cover beam (1) and a base (11), characterized in that: the outside of the cover beam (1) is fixedly installed with a bridge erection machine main beam (2) The upper end of the main beam (2) of the bridge erecting machine is fixedly connected with a support beam (3), the upper end of the support beam (3) is fixedly connected with a guide beam (4), and the upper end of the guide beam (4) is fixed A crane (5) is installed, the lower end of the guide beam (4) is fixedly connected with a front auxiliary leg (6), and the lower end of the guide beam (4) is fixedly connected with a middle support leg (7), so The lower end of the guide beam (4) is fixedly connected with a rear auxiliary leg (8), the lower end of the middle leg (7) is fixedly installed with a connecting beam (9), and the lower end of the connecting beam (9) is installed with a single beam. Platform segment box girder (10); 所述底座(11)与地面固定连接,所述底座(11)的上端固定连接有支撑座(12),所述支撑座(12)的上端固定连接有钢支撑柱(13),所述支撑柱(13)的上端固定连接有工字钢支撑(15),所述工字钢支撑(15)的上端固定连接有调节沙筒(16),所述调节沙筒(16)的上端固定连接有调节楔块(17),所述调节楔块(17)与盖梁(1)的悬臂底部接触。The base (11) is fixedly connected to the ground, the upper end of the base (11) is fixedly connected with a support seat (12), and the upper end of the support seat (12) is fixedly connected with a steel support column (13), the support The upper end of the column (13) is fixedly connected with an I-beam support (15), the upper end of the I-beam support (15) is fixedly connected with a regulating sand barrel (16), and the upper end of the regulating sand barrel (16) is fixedly connected There are adjusting wedges (17), which are in contact with the cantilevered bottom of the cover beam (1). 2.根据权利要求1所述的一种单台节段箱梁架桥机,其特征在于,所述钢支撑柱(13)的中部通过螺栓安装有支撑拉杆(14),所述支撑拉杆(14)与盖梁(1)通过螺栓紧固连接。2 . The single-segment box girder bridge erecting machine according to claim 1 , wherein a support rod ( 14 ) is installed in the middle of the steel support column ( 13 ) through bolts, and the support rod ( 14) Fasten the connection with the cover beam (1) by bolts. 3.根据权利要求1所述的一种单台节段箱梁架桥机,其特征在于,所述调节楔块(17)由两个楔块和一个拉杆构成,且拉杆的两侧安装螺母。3. A single-segment box girder bridge erecting machine according to claim 1, characterized in that the adjusting wedge (17) is composed of two wedges and a tie rod, and nuts are installed on both sides of the tie rod . 4.根据权利要求1所述的一种单台节段箱梁架桥机,其特征在于,所述支撑座(12)、支撑柱(13)和工字钢支撑(15)为焊接结构。4 . The single-segment box girder bridge erecting machine according to claim 1 , wherein the support base ( 12 ), the support column ( 13 ) and the I-beam support ( 15 ) are welded structures. 5 . 5.根据权利要求1所述的一种单台节段箱梁架桥机,其特征在于,所述导梁(4)为矩形桁架结构形式,弦杆是由钢板拼焊而成的工字梁,腹杆为槽钢对扣而成的箱形杆件。5 . The single-segment box girder bridge erecting machine according to claim 1 , wherein the guide beam ( 4 ) is in the form of a rectangular truss structure, and the chord is an I-shaped welded steel plate. 6 . The beam and the web rod are box-shaped rods made of channel steel. 6.根据权利要求1所述的一种单台节段箱梁架桥机,其特征在于,所述中支腿(7)上设有顶升和横移、纵移油缸。6 . The single-segment box girder bridge erecting machine according to claim 1 , wherein the middle outriggers ( 7 ) are provided with oil cylinders for jacking up, transverse movement and longitudinal movement. 7 . 7.一种单台节段箱梁架桥机的操作方法,其特征在于,具体步骤包括:7. An operation method of a single segment box girder bridge erecting machine, characterized in that the concrete steps comprise: 步骤一:施工下部结构,下部结构完成后通过架桥机吊装中支点墩顶块并进行临时固定;Step 1: Construction of the lower structure, after the completion of the lower structure, the top block of the middle fulcrum pier is hoisted by the bridge erection machine and temporarily fixed; 步骤二:吊装首跨箱梁,调整箱梁节段位置,并进行预拼装;Step 2: Hoist the first span box girder, adjust the position of the box girder segment, and carry out pre-assembly; 步骤三:将前两个箱梁匹配面进行涂摸胶粘结剂,且两个箱梁匹配定位,并施加临时预应力挤紧固化,重复以上步骤拼装至十一号块;Step 3: Apply adhesive on the matching surfaces of the first two box girders, match and position the two box girders, apply temporary prestress to squeeze and tighten, and repeat the above steps to assemble to No. 11 block; 步骤四:安装湿接缝模板,浇筑湿接缝并养生,利用起重天车吊装超前墩墩顶块,并锚固好;Step 4: Install the wet joint formwork, pour the wet joint and maintain it, use the crane to hoist the top block of the advanced pier, and anchor it well; 步骤五:待湿接缝浇筑混凝土达到95%,分批对称张拉体外预应力,完成张拉后,整机卸载,拆除吊挂,并倒运吊挂到地面;Step 5: When the wet joints are poured to 95% of the concrete, the external prestressing is symmetrically tensioned in batches. After the tensioning is completed, the whole machine is unloaded, the hanging is removed, and it is transported upside down and hung to the ground; 步骤六:利用天车进行跨越式倒运后,墩中支腿到超前墩,并锚固好;Step 6: After the overhead crane is used to carry out the reverse transportation by leaps and bounds, the outriggers in the pier are moved to the leading pier and anchored well; 步骤七:架桥机向前纵移,天车位于主框架前方作为配重,纵移到位并调整好架桥机的姿势;Step 7: The bridge erection machine moves forward longitudinally, the crane is located in front of the main frame as a counterweight, and the bridge erection machine is moved longitudinally in place and the posture of the bridge erection machine is adjusted; 步骤八:按首跨顺序拼装中跨主梁,并浇筑湿接缝;Step 8: Assemble the mid-span main beams in the order of the first span, and pour the wet joints; 步骤九:待混凝土强度达到95%,分批对称张拉中跨预应力;Step 9: When the concrete strength reaches 95%, the mid-span prestress is symmetrically tensioned in batches; 步骤十:施工尾跨主梁,完成后张拉负弯矩预应力钢束;步骤十一:桥面铺装及附属设施安装。Step 10: Construct the main girder of the tail span, and tension the prestressed steel bundles with negative bending moment after completion; Step 11: Pave the bridge deck and install the ancillary facilities.
CN201911265906.5A 2019-12-11 2019-12-11 A single-segment box girder bridge erecting machine and its operation method Pending CN110820602A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201911265906.5A CN110820602A (en) 2019-12-11 2019-12-11 A single-segment box girder bridge erecting machine and its operation method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201911265906.5A CN110820602A (en) 2019-12-11 2019-12-11 A single-segment box girder bridge erecting machine and its operation method

Publications (1)

Publication Number Publication Date
CN110820602A true CN110820602A (en) 2020-02-21

Family

ID=69544751

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201911265906.5A Pending CN110820602A (en) 2019-12-11 2019-12-11 A single-segment box girder bridge erecting machine and its operation method

Country Status (1)

Country Link
CN (1) CN110820602A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112663514A (en) * 2020-12-21 2021-04-16 中建八局第三建设有限公司 Novel pier-beam integrated bridge girder erection machine
CN113403956A (en) * 2021-07-02 2021-09-17 中铁七局集团郑州工程有限公司 Method for erecting end-span trimming beam at point where high-speed railway platform line merges into turnout beam
CN114481844A (en) * 2022-01-21 2022-05-13 中铁十一局集团有限公司 Section-splicing bridge girder erection machine
CN115125849A (en) * 2022-06-24 2022-09-30 西南大学 Detachable front supporting leg structure for wide-body bridge girder erection machine and use method thereof
CN115467237A (en) * 2022-09-28 2022-12-13 河南省交通规划设计研究院股份有限公司 Construction method of mechanical beam-changing type steel structure bridge

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20010054437A (en) * 1999-12-06 2001-07-02 김윤규, 정주영, 심옥진, 정몽헌 Slab form
CN202323720U (en) * 2011-11-08 2012-07-11 云南建工集团有限公司 Capping beam template supporting device
CN107059640A (en) * 2017-05-24 2017-08-18 郑州新大方重工科技有限公司 The Bridge Erector and its construction method constructed by cross for precast segmental beam
CN110552294A (en) * 2019-09-29 2019-12-10 中国建筑第八工程局有限公司 Bridge girder erection machine reverse beam erection construction platform and construction method thereof
CN211420902U (en) * 2019-12-11 2020-09-04 重庆交通建设(集团)有限责任公司 Single-segment box girder bridge girder erection machine

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20010054437A (en) * 1999-12-06 2001-07-02 김윤규, 정주영, 심옥진, 정몽헌 Slab form
CN202323720U (en) * 2011-11-08 2012-07-11 云南建工集团有限公司 Capping beam template supporting device
CN107059640A (en) * 2017-05-24 2017-08-18 郑州新大方重工科技有限公司 The Bridge Erector and its construction method constructed by cross for precast segmental beam
CN110552294A (en) * 2019-09-29 2019-12-10 中国建筑第八工程局有限公司 Bridge girder erection machine reverse beam erection construction platform and construction method thereof
CN211420902U (en) * 2019-12-11 2020-09-04 重庆交通建设(集团)有限责任公司 Single-segment box girder bridge girder erection machine

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112663514A (en) * 2020-12-21 2021-04-16 中建八局第三建设有限公司 Novel pier-beam integrated bridge girder erection machine
CN113403956A (en) * 2021-07-02 2021-09-17 中铁七局集团郑州工程有限公司 Method for erecting end-span trimming beam at point where high-speed railway platform line merges into turnout beam
CN114481844A (en) * 2022-01-21 2022-05-13 中铁十一局集团有限公司 Section-splicing bridge girder erection machine
CN114481844B (en) * 2022-01-21 2024-04-30 中铁十一局集团有限公司 Bridge girder erection machine is pieced together to festival
CN115125849A (en) * 2022-06-24 2022-09-30 西南大学 Detachable front supporting leg structure for wide-body bridge girder erection machine and use method thereof
CN115467237A (en) * 2022-09-28 2022-12-13 河南省交通规划设计研究院股份有限公司 Construction method of mechanical beam-changing type steel structure bridge

Similar Documents

Publication Publication Date Title
CN110820602A (en) A single-segment box girder bridge erecting machine and its operation method
CN101851898B (en) Bridge girder erection machine capable of passing through tunnel and realizing girder erection and bridging process thereof
CN101787678B (en) Large-span section assembling bridge manufacturing machine and assembling construction process thereof
CN110130229A (en) It a kind of several juxtaposed double cantilever erections machines and its sets a roof beam in place and passing method
CN102094389B (en) Separable large-section truss girder hydraulic lifting device
CN105970833B (en) Prefabricated subsection splicing span by span bridge fabrication machine
CN110344334B (en) Construction method of two-span continuous steel-concrete composite bridge using back-cable bridge erecting machine
CN101210419A (en) Small radius curved concrete box girder construction machine with internal and external girder system and its construction method
CN109267490B (en) A kind of long guide beam type mobile formwork and construction method thereof
CN116043715B (en) A construction method for precast segmental beams under complex working conditions
CN101324055A (en) A hoisting device and hoisting method for a box girder integral steel frame
CN109024291A (en) A kind of integration Bridge Erector and its working method
CN112160246B (en) Method for installing composite beam
CN110700098A (en) Safe crossing method for double-guide-beam type bridge girder erection machine
CN100572673C (en) Span continuous beam bridge fabrication machine in a kind of
CN116289620A (en) Combined transport device and method for box girder reinforcement parts
CN105484166B (en) A kind of ladder type masts type cantilever loop wheel machine
CN115897387B (en) A method for erecting curved bridges
CN111851307A (en) Construction method of large-span prefabricated corrugated web composite box girder transport frame
CN211420902U (en) Single-segment box girder bridge girder erection machine
CN205804194U (en) Prefabricated subsection splicing span by span bridge fabrication machine
CN107881926A (en) A kind of combined cradle and its construction method with full circle swinging loop wheel machine
CN205382425U (en) Railway T type bridge adds builds sound barrier beam mold plate girder unwheeling
CN205529915U (en) Ladder type masts type hangs pieces together loop wheel machine
CN101693501B (en) Deck unit erection gantry for hoisting by large deflection angle

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right
TA01 Transfer of patent application right

Effective date of registration: 20200415

Address after: 401120, 4 Jin Xiang Road, Chongqing, Yubei District

Applicant after: CHONGQING COMMUNICATIONS CONSTRUCTION (GROUP) Co.,Ltd.

Applicant after: CHONGQING CONSTRUCTION ENGINEERING GROUP Co.,Ltd.

Address before: 401120, 4 Jin Xiang Road, Chongqing, Yubei District

Applicant before: Zhang Chang

RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20200221