CN1851183A - Finished product building system, and its assembling and dismounting method - Google Patents

Finished product building system, and its assembling and dismounting method Download PDF

Info

Publication number
CN1851183A
CN1851183A CN 200610026198 CN200610026198A CN1851183A CN 1851183 A CN1851183 A CN 1851183A CN 200610026198 CN200610026198 CN 200610026198 CN 200610026198 A CN200610026198 A CN 200610026198A CN 1851183 A CN1851183 A CN 1851183A
Authority
CN
China
Prior art keywords
finished product
building
framework structure
product building
main
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN 200610026198
Other languages
Chinese (zh)
Other versions
CN100476093C (en
Inventor
苏运升
蔡航
孔晡虹
景秋成
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Tongji Urban Planning & Design Institute
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CNB2006100261986A priority Critical patent/CN100476093C/en
Publication of CN1851183A publication Critical patent/CN1851183A/en
Application granted granted Critical
Publication of CN100476093C publication Critical patent/CN100476093C/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Residential Or Office Buildings (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention is a finished building system, comprising a main building framework structural body divided into plural units, where the structural body is provided with corresponding finished building interfaces; and finished building able to be contained in a transport carrier. As the transport carrier is raised to a corresponding unit, the finished building in the transport carrier is spliced into the unit and connected with the finished building interface. And it uses container or other containing device as finished building transport carrier, according with the current international large-scale freight transport mode and able to fully implement convenient and quick transport of finished building products.

Description

A kind of finished product building system and assembling thereof and method for dismounting
Technical field
The present invention relates to a kind of finished product building system, especially relate to a kind of accommodation apparatus such as container that utilize as transport agent, can be rapidly and efficiently the contamination-freely finished product building system of Assembly And Disassembly and assembling thereof and method for dismounting.
Background technology
The container construction thing that some quick assembled types are arranged in the market mainly is spliced with the main composition unit of container as building, and container is as the ingredient of building, and its casing uses as wall face, smallpox and the floor of building.Relative technical scheme sees also the disclosed technical scheme of Chinese patent CN00134669.5: a kind of method for assembling of container-type building, comprise the steps: to make container construction thing functional unit, and to make the length sum of several functional units be the length of an ISO freight container; Several container construction thing functional units are connected into the integral body with ISO freight container size with linkage, transport to building installation scene after, remove linkage, be reduced into single container construction thing functional unit; Each container construction thing functional unit is made up in the erecting bed, arranges and be fixed on the ground, form required building.
Because its tank material often can't satisfy the physics requirement of conventional building, therefore, the container construction thing is not generally considered as permanent construction, and is general as provisional or semipermanent construction of structures or facility.The typical application industry scope of these facilities is less, as being employed in construction sites such as mining, exploration, or is used for provisional functions such as displaying as particular facility.
Summary of the invention
The object of the present invention is to provide a kind of prefabricated assembled finished product building products system, utilize containerized traffic, realize rapidly and efficiently free of contamination assembly unit and dismounting, a kind of assembly method and method for dismounting of finished product building system is provided simultaneously.
The present invention is achieved by the following technical solutions: a kind of finished product building system, comprise the main building framework structure that is divided into a plurality of unit, and described main building framework structure is provided with corresponding finished building interface; Can be contained in the finished product building in the transport agent; When described transport agent was raised to corresponding unit, the finished product Building assembling in the transport agent was in the unit of main building framework structure, and described finished product building links to each other with the finished product building interface of main building framework structure.
Wherein, finished product building system also comprises suspension system, promotes the transport agent that the finished product building is housed.
Suspension system is arranged on the main building framework structure.Perhaps, suspension system is arranged on the outer mobile boom hoisting of main building framework structure.
The main building framework structure is provided with fastening devices, fixedly the transport agent of suspension system lifting.
Described transport agent is a container.The unit cut size of main building framework structure is the integer multiple of Container Dimensions.
The main building framework structure also comprises frame construction, basic piping facility structure, floor slab structure and traffic unit structure.
Each structure of main building framework structure links to each other with corresponding finished product building by finished product building interface, makes finished product build plug and play.
The finished product building comprises functional wall system, whole kitchen and defends facility system, storage space, floor system and ceiling system, external wall system.
The length of functional wall system is 2300-6900mm, is 2300-2700mm highly, and the thickness after packing up is 300-600mm.
The functional wall system comprises multiple bodies of wall such as a cabinet functional wall, amusement function wall, daily life and food and drink functional wall.
The functional wall system comprises all kinds of pipeline passways and the interface that links to each other with the main building framework structure.
The kitchen and bath facilities system has unified pipeline interface.
Ceiling system comprises electric wire, embedded light fixture and chute.
Floor system comprises electric wire, pipeline, geothermal system and chute.
Functional wall can move flexibly by self or the pulley gear that adds.
The present invention also provides another kind of technical scheme: a kind of finished product building system assembly method, comprise the steps: that (1) foundation is divided into the main building framework structure of a plurality of unit, described main building framework structure is provided with corresponding finished building interface; (2) transport agent that finished product building will be housed by suspension system is promoted to the corresponding units of main building framework structure; (3) the finished product Building assembling in the transport agent is in the unit of main building framework structure, and described finished product building links to each other with the finished product building interface of main building framework structure; (4) suspension system hangs the main building framework structure with transport agent.
Wherein, suspension system is arranged on the main building framework structure or is arranged on the outer mobile boom hoisting of main building framework structure.
Described transport agent is a container, and the unit cut size of main building framework structure is the integer multiple of Container Dimensions.
The main building framework structure also comprises frame construction, basic piping facility structure, floor slab structure and traffic unit structure.
Each structure of main building framework structure links to each other with corresponding finished product building by finished product building interface, makes finished product build plug and play.
The finished product building comprises functional wall system, whole kitchen and defends facility system, storage space, floor system and ceiling system, external wall system.
In addition, the present invention also provides another kind of technical scheme: a kind of finished product building system method for dismounting, comprise the steps: that (1) foundation is divided into the main building framework structure of a plurality of unit, described main building framework structure is provided with corresponding finished building interface; (2) transport agent is promoted to the corresponding units of main building framework structure by suspension system; (3) in the unit of main building framework structure, dismantle in the transport agent with the finished product building that finished product building interface links to each other; (4) suspension system transport agent that finished product building will be housed hangs the main building framework structure.
Wherein, suspension system is arranged on the main building framework structure or is arranged on the outer mobile boom hoisting of main building framework structure.
Described transport agent is a container, and the unit cut size of main building framework structure is the integer multiple of Container Dimensions.
The main building framework structure also comprises frame construction, basic piping facility structure, floor slab structure and traffic unit structure.
The finished product building comprises functional wall system, whole kitchen and defends facility system, storage space, floor system and ceiling system, external wall system.
The present invention utilizes the transport agent of accommodation apparatus such as container as the finished product building; fully carry out design, transportation and the installation of finished product building system with reference to its box sizes; meet the extensive mode of freight transportation in the present world, can fully realize the convenient transportation of finished product building products group.Simultaneously, standardized component in the finished product building system is reasonably put into internal container through product design and packaging technology design, realize modular installation, dismounting, reorganization by finished product building interface, the poor efficiency that has changed that non-disconnectable that upholster in the past (part of decorateing especially firmly) can only " go into wall and go into ground " moves, existed in the upholster construction disperses, pollutes (noise, dust) important disadvantages, reaches the inhabitation and the life style of hommization more, freeing.
Description of drawings
Fig. 1 is a finished product building system schematic diagram of the present invention;
Fig. 2 is a finished product building schematic diagram;
Fig. 3 is that a cabinet functional wall is packed up and the open mode schematic diagram;
Fig. 4 is that the main building framework structure constitutes schematic diagram;
Fig. 5 is that the finished product building is assembled schematic diagram in the structure unit.
The specific embodiment
See also Fig. 1, Fig. 1 is a kind of finished product building system schematic diagram, and this finished product building system has a main building framework structure 10, and main building framework structure 10 is divided into a plurality of unit 100.Suspension system 30 also is installed on the main building framework structure 10, and suspension system 30 can be raised to transport agent 20 to deserved certain unit 100.In the present invention, suspension system 30 can also be arranged on the outer mobile boom hoisting of main building framework structure 10, and mobile boom hoisting is applicable to that main building framework structure 10 is not under the very high situation.
Transport agent 20 can be container or similar casing, for the ease of transportations such as vehicle 80, boats and ships, and the container of mainly adopting international standards, fixed dimension is 2350 * 2720 * 12029mm 3Be placed with finished product building in the transport agent 20 through modularized design, when transport agent 20 is suspended system 30 and is promoted to corresponding unit 100 on the main building framework structure 10, can be by the fastening devices on the main building framework structure 10, fix the transport agent 20 that suspension system 30 promotes, finished product in the transport agent 20 is built assembly unit successively in the unit 100 of main building framework structure 10 then, in the present invention, the size of unit 100 is designed to the integer multiple of standard container.
See also Fig. 2, Fig. 2 is a finished product building schematic diagram.The finished product building comprises floor system 201, external wall system 209, amusement function wall 205, monolithic washroom 202, monolithic kitchen 203, storage space 204, bed cabinet functional wall 207, daily life and food and drink functional wall 206 and ceiling system 208 etc.
1) functional wall system
By customization, integrated supplier centralized purchasing TV, sofa, bed, wardrobe, bookshelf etc. be in interior necessary house living facilities, and be integrated into " functional wall " of multiple function by integrated supplier.Comprise multiple bodies of wall such as amusement function wall 205, bed cabinet functional wall 207, daily life and food and drink functional wall 206.The above-mentioned functions wall has been gathered necessary at home equipment and facility, and various functional wall contents can be by customization.
The Design of length of functional wall system is controlled between the 2300-6900mm, highly is controlled at 2300-2700mm, and packing up back thickness is 300-600mm., guarantees that it can pack into the container and adjustment use in the same building unitary space smoothly.
" functional wall " is according to different instructions for uses, integrated all kinds of pipeline passways and interfaces such as its necessary water, electricity, gas, communication, as amusement function wall, the office function body of wall of assembling household electrical appliances be provided with that built-in power supply is thrown light on wire signal reception, air-conditioning tube drainage, wall lamp, winding displacements such as the cabling of multi-channel audio system and broadband connections line, telephone wire.
2) whole kitchen and bath facilities system
The kitchen and bath facilities system comprises monolithic washroom 202, monolithic kitchen 203.Adopt the integration kitchen guarding technology of existing maturation, by integrated supplier formulation standard customization.According to customer demand, form some specifications.Monolithic washroom 202 and monolithic kitchen 203 have unified pipeline interface.
3) floors/ceilings system
The floors/ceilings system comprises two parts, i.e. floor system 201 and ceiling system 208.The floors/ceilings system unifies the customization of formulation standard by integrator.
Systems such as floor system 201 integrated electric wires, pipeline, underground heat.Ceiling system 208 integrated electric wires, embedded light fixture do not have weight-bearing function.Functional wall can be between ceiling and floor, moves flexibly by self or the pulley gear that adds.
The unification of finished product building products production size is according to the Container Dimensions setting, and group of products mainly can be divided into the functional wall system, floors/ceilings system, whole kitchen and bath facilities system three parts.Wherein, the functional wall system convention is of a size of 2300 * 4600 * 600mm; The floors/ceilings system convention is of a size of 2300mm * 6900mm * 150m; Whole kitchen and bath facilities system convention is of a size of 2300mm * 2300mm * 2300mm.
See also Fig. 3, Fig. 3 is that a cabinet functional wall is packed up and the open mode schematic diagram.
With bed cabinet functional wall is example, and bed cabinet functional wall has been gathered the necessary installations and facilities in bedroom, comprises bed, wardrobe, and side table, light fixture or the like, these installations and facilities present the state of packing up in body of wall inside in transportation and installation process, thereby are convenient to transportation and installation.After installation, these installations and facilities are rendered as the state of the furniture in a common room by being arranged at the rotating shaft upset of function body of wall inside.
See also Fig. 4, Fig. 4 is that the main building framework structure constitutes schematic diagram.
The main building framework structure also comprises frame construction, basic piping facility structure, floor slab structure and traffic unit structure etc. except a plurality of divided unit.In the main building framework structure, be provided with corresponding finished building interface.
Wherein, floor slab structure comprises floor topping 101 and floor rib 102, and both form the floor integral body of double-layer hollow, and reserving hole 107 passes for pipeline on the rib; Basis piping facility structure comprises concentrates upper and lower conduit road well 103; Monolithic kitchen guarding system and main building framework structure have unified pipeline passway interface 104; Concentrate circuit piping shaft 105, the electric wire of pulling out spare interface 106 on smallpox or floor is connected on the functional wall.
The finished product that the main building framework structure passes through to reserve is built interface, links to each other with corresponding finished product building as pipeline passway interface 104, concentrated circuit piping shaft 105, functional wall interface 106 etc., makes finished product build plug and play.
See also Fig. 5, Fig. 5 is that the finished product building is assembled schematic diagram in the structure unit.This finished product building comprises a series of floor panel assembly 201, a series of ceiling structure 208, a series of exterior wall unit 209, a monolithic kitchen 203, a monolithic washroom 202, a slice daily life and food and drink functional wall 206, a slice amusement function wall 205, a slice bed cabinet functional wall 207, and a storage space 204.
At first these parts in the transport agent are pulled out in a certain order one by one, be positioned over corresponding position, and connect: floor 201 is pulled out successively according to numbering be positioned over ground, fix with the corresponding interface of floor by the interface of correspondence; According to certain numbering, the suspension rod by correspondence is fixed in floor below, upper strata successively with ceiling 208; Monolithic kitchen 203 is pulled out, be fixed on the corresponding interface, and join in the pipeline passway of reserving; Monolithic washroom 202 is pulled out, be fixed on the corresponding interface, and join in the pipeline passway of reserving; Storage space 204 is pulled out, be fixed on the corresponding interface; Functional wall amusement function wall 205, daily life and food and drink functional wall 206, bed cabinet functional wall 207 are pulled out, be fixed on the corresponding interface, and join in the pipeline passway of reserving; Exterior wall assembly 209 is pulled out, be fixed on the corresponding interface, wherein A is the middle part exterior wall and being connected of functional wall, and B is the connection that is embedded in exterior wall outward, and C is being connected of bight exterior wall and functional wall; The installations and facilities upset of functional wall inside is opened, become spendable room space.
Above-described embodiment only is explanation technological thought of the present invention and characteristics; its purpose makes those skilled in the art can understand content of the present invention and is implementing according to this; can not limit protection scope of the present invention with this; promptly the equalization of doing according to disclosed spirit changes or modifies, and must be encompassed in protection scope of the present invention.

Claims (28)

1, a kind of finished product building system is characterized in that: described finished product building system comprises
Be divided into the main building framework structure of a plurality of unit, described main building framework structure is provided with corresponding finished building interface;
Can be contained in the finished product building in the transport agent;
When described transport agent was raised to corresponding unit, the finished product Building assembling in the transport agent was in the unit of main building framework structure, and described finished product building links to each other with the finished product building interface of main building framework structure.
2, finished product building system as claimed in claim 1 is characterized in that: finished product building system also comprises suspension system, promotes the transport agent that the finished product building is housed.
3, finished product building system as claimed in claim 2 is characterized in that: suspension system is arranged on the main building framework structure.
4, finished product building system as claimed in claim 2 is characterized in that: suspension system is arranged on the outer mobile boom hoisting of main building framework structure.
5, finished product building system as claimed in claim 1 is characterized in that: the main building framework structure is provided with fastening devices, fixedly the transport agent of suspension system lifting.
6, as claim 1 or 2 or 5 described finished product building systems, it is characterized in that: described transport agent is a container.
7, finished product building system as claimed in claim 1 is characterized in that: the unit cut size of main building framework structure is the integer multiple of Container Dimensions.
8, finished product building system as claimed in claim 1 is characterized in that: the main building framework structure also comprises frame construction, basic piping facility structure, floor slab structure and traffic unit structure.
9, finished product building system as claimed in claim 8 is characterized in that: each structure of main building framework structure links to each other with corresponding finished product building by finished product building interface, makes finished product build plug and play.
10, finished product building system as claimed in claim 1 is characterized in that: the finished product building comprises functional wall system, whole kitchen and defends facility system, storage space, floor system and ceiling system, external wall system.
11, finished product building system as claimed in claim 10 is characterized in that: the length of functional wall system is 2300-6900mm, is 2300-2700mm highly, and the thickness after packing up is 300-600mm.
12, finished product building system as claimed in claim 10 is characterized in that: the functional wall system comprises multiple bodies of wall such as a cabinet functional wall, amusement function wall, daily life and food and drink functional wall.
13, finished product building system as claimed in claim 12 is characterized in that: the functional wall system comprises all kinds of pipeline passways and the interface that links to each other with the main building framework structure.
14, finished product building system as claimed in claim 10 is characterized in that: the kitchen and bath facilities system has unified pipeline interface.
15, finished product building system as claimed in claim 10 is characterized in that: ceiling system comprises electric wire, embedded light fixture and chute.
16, finished product building system as claimed in claim 10 is characterized in that: floor system comprises electric wire, pipeline, geothermal system and chute.
17, as claim 15 or 16 described finished product building systems, it is characterized in that: functional wall can move flexibly by self or the pulley gear that adds.
18, a kind of finished product building system assembly method is characterized in that: comprise the steps
(1) set up the main building framework structure that is divided into a plurality of unit, described main building framework structure is provided with corresponding finished building interface;
(2) transport agent that finished product building will be housed by suspension system is promoted to the corresponding units of main building framework structure;
(3) the finished product Building assembling in the transport agent is in the unit of main building framework structure, and described finished product building links to each other with the finished product building interface of main building framework structure;
(4) suspension system hangs the main building framework structure with transport agent.
19, finished product building system assembly method as claimed in claim 18 is characterized in that: suspension system is arranged on the main building framework structure or is arranged on the outer mobile boom hoisting of main building framework structure.
20, finished product building system assembly method as claimed in claim 18, it is characterized in that: described transport agent is a container, the unit cut size of main building framework structure is the integer multiple of Container Dimensions.
21, finished product building system assembly method as claimed in claim 18 is characterized in that: the main building framework structure also comprises frame construction, basic piping facility structure, floor slab structure and traffic unit structure.
22, finished product building system assembly method as claimed in claim 21 is characterized in that: each structure of main building framework structure links to each other with corresponding finished product building by finished product building interface, makes finished product build plug and play.
23, finished product building system assembly method as claimed in claim 18 is characterized in that: the finished product building comprises functional wall system, whole kitchen and defends facility system, storage space, floor system and ceiling system, external wall system.
24, a kind of finished product building system method for dismounting is characterized in that: comprise the steps
(1) set up the main building framework structure that is divided into a plurality of unit, described main building framework structure is provided with corresponding finished building interface;
(2) transport agent is promoted to the corresponding units of main building framework structure by suspension system;
(3) in the unit of main building framework structure, dismantle in the transport agent with the finished product building that finished product building interface links to each other;
(4) suspension system transport agent that finished product building will be housed hangs the main building framework structure.
25, finished product building system method for dismounting as claimed in claim 24 is characterized in that: suspension system is arranged on the main building framework structure or is arranged on the outer mobile boom hoisting of main building framework structure.
26, finished product building system method for dismounting as claimed in claim 24, it is characterized in that: described transport agent is a container, the unit cut size of main building framework structure is the integer multiple of Container Dimensions.
27, finished product building system method for dismounting as claimed in claim 24 is characterized in that: the main building framework structure also comprises frame construction, basic piping facility structure, floor slab structure and traffic unit structure.
28, finished product building system method for dismounting as claimed in claim 24 is characterized in that: the finished product building comprises functional wall system, whole kitchen and defends facility system, storage space, floor system and ceiling system, external wall system.
CNB2006100261986A 2006-04-28 2006-04-28 Finished product building system, and assembling and dismounting method thereof Active CN100476093C (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNB2006100261986A CN100476093C (en) 2006-04-28 2006-04-28 Finished product building system, and assembling and dismounting method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNB2006100261986A CN100476093C (en) 2006-04-28 2006-04-28 Finished product building system, and assembling and dismounting method thereof

Publications (2)

Publication Number Publication Date
CN1851183A true CN1851183A (en) 2006-10-25
CN100476093C CN100476093C (en) 2009-04-08

Family

ID=37132684

Family Applications (1)

Application Number Title Priority Date Filing Date
CNB2006100261986A Active CN100476093C (en) 2006-04-28 2006-04-28 Finished product building system, and assembling and dismounting method thereof

Country Status (1)

Country Link
CN (1) CN100476093C (en)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102405376A (en) * 2008-11-18 2012-04-04 伊莱克斯家用产品股份有限公司 Oven, especially domestic oven
CN101725196B (en) * 2008-10-23 2013-09-11 上海同济城市规划设计研究院 Functional wall with user customized furniture and manufacturing method thereof
CN104131711A (en) * 2013-05-03 2014-11-05 张弘 Building based on integrated modules
CN105569378A (en) * 2015-12-29 2016-05-11 青岛辉宏置业有限公司 Steel structure temporarily built board room structure and construction process
CN106023779A (en) * 2016-06-27 2016-10-12 安徽省艺凌模型设计有限公司 Modular building model
WO2017020583A1 (en) * 2015-08-06 2017-02-09 蔡櫂隆 Modular container house building structure
CN106567565A (en) * 2016-10-19 2017-04-19 中建三局安装工程有限公司 Method for installing super-long warehouse plates
CN109505359A (en) * 2018-11-30 2019-03-22 上海宝冶集团有限公司 The structural system and its installation method of assembled interval module
CN111927131A (en) * 2020-07-16 2020-11-13 江西省储建工程技术有限公司 Decoration dismounting device
CN112196110A (en) * 2020-08-18 2021-01-08 杭州龙皓工程咨询有限公司 Folding board house

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101725196B (en) * 2008-10-23 2013-09-11 上海同济城市规划设计研究院 Functional wall with user customized furniture and manufacturing method thereof
CN102405376A (en) * 2008-11-18 2012-04-04 伊莱克斯家用产品股份有限公司 Oven, especially domestic oven
CN104131711A (en) * 2013-05-03 2014-11-05 张弘 Building based on integrated modules
WO2017020583A1 (en) * 2015-08-06 2017-02-09 蔡櫂隆 Modular container house building structure
CN105569378A (en) * 2015-12-29 2016-05-11 青岛辉宏置业有限公司 Steel structure temporarily built board room structure and construction process
CN106023779A (en) * 2016-06-27 2016-10-12 安徽省艺凌模型设计有限公司 Modular building model
CN106567565A (en) * 2016-10-19 2017-04-19 中建三局安装工程有限公司 Method for installing super-long warehouse plates
CN109505359A (en) * 2018-11-30 2019-03-22 上海宝冶集团有限公司 The structural system and its installation method of assembled interval module
CN111927131A (en) * 2020-07-16 2020-11-13 江西省储建工程技术有限公司 Decoration dismounting device
CN112196110A (en) * 2020-08-18 2021-01-08 杭州龙皓工程咨询有限公司 Folding board house

Also Published As

Publication number Publication date
CN100476093C (en) 2009-04-08

Similar Documents

Publication Publication Date Title
CN1851183A (en) Finished product building system, and its assembling and dismounting method
US7183501B2 (en) Recessed poke-thru fitting
US20070074465A1 (en) Combinational housing structure
EP1534901A2 (en) Structure having preinstalled utilities and amenities
CN1792713A (en) Shipping cabin unit and mfg. method thereof
CN1101882C (en) Method for assembling container-type building
CN201896417U (en) Environment-friendly base anchor convenient for wiring
CN203967648U (en) Stack cable collating unit
US11365540B2 (en) Functional modular building cartridges and methods
US20110146198A1 (en) Modular seismically restrained distribution system and method of installing the same
CN201829873U (en) Wire harness branching device for electrical appliance
CN203179576U (en) Foldable cable
CN206282735U (en) A kind of large value capacitor group of new single column structure
CN210123845U (en) External anti-drop structure for electric appliance cabinet
CN110872053A (en) Suspension type operating system is put to over-and-under type express delivery case
WO2019218223A1 (en) House having electrical wire separate from main structure
CN215073259U (en) Intelligent household system supporting multi-gateway mutual control
CN216598415U (en) Electric automatization engineering is with clean and tidy type intelligent power distribution cabinet of energy-concerving and environment-protective
CN103683143A (en) Distribution box
CN107516860A (en) A kind of reinforced cable bridge
CN215330711U (en) Combined wall body of integrated household electrical control center
CN2430801Y (en) Connection box for single or three phase user's line
CN210264035U (en) Assembled building site office room
CN207719615U (en) A kind of compact DC feeder cabinet
CN206506167U (en) A kind of power distribution cabinet of integrated 10KV transformers

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: SHANGHAI TONGJI URBAN PLANNING + DESIGN INSTITUTE

Free format text: FORMER OWNER: SU YUNSHENG

Effective date: 20110927

C41 Transfer of patent application or patent right or utility model
COR Change of bibliographic data

Free format text: CORRECT: ADDRESS; FROM: 200092 YANGPU, SHANGHAI TO: 200092 HONGKOU, SHANGHAI

TR01 Transfer of patent right

Effective date of registration: 20110927

Address after: 200092 Shanghai Guokang Road No. 38

Patentee after: Shanghai Tongji Urban Planning & Design Institute

Address before: 200092, building 708, building C, School of architecture and urban planning, Siping Road, 1239, Shanghai, Yangpu District

Patentee before: Su Yunsheng

EE01 Entry into force of recordation of patent licensing contract

Application publication date: 20061025

Assignee: Bengbu Anhui building installation Engineering Group Co Ltd

Assignor: Shanghai Tongji Urban Planning & Design Institute

Contract record no.: 2015310000102

Denomination of invention: Finished product building system, and its assembling and dismounting method

Granted publication date: 20090408

License type: Exclusive License

Record date: 20151016

LICC Enforcement, change and cancellation of record of contracts on the licence for exploitation of a patent or utility model