CN1843734B - Automatic brick production line - Google Patents

Automatic brick production line Download PDF

Info

Publication number
CN1843734B
CN1843734B CN200610040081A CN200610040081A CN1843734B CN 1843734 B CN1843734 B CN 1843734B CN 200610040081 A CN200610040081 A CN 200610040081A CN 200610040081 A CN200610040081 A CN 200610040081A CN 1843734 B CN1843734 B CN 1843734B
Authority
CN
China
Prior art keywords
conveyer
brick
track
maintenance
assembly line
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN200610040081A
Other languages
Chinese (zh)
Other versions
CN1843734A (en
Inventor
李良光
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fujian Haiyuan Intelligent Equipment Co ltd
Jiangxi Haiyuan Composite Material Technology Co ltd
Original Assignee
Fujian Haiyuan Automatic Machinery Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fujian Haiyuan Automatic Machinery Co Ltd filed Critical Fujian Haiyuan Automatic Machinery Co Ltd
Priority to CN200610040081A priority Critical patent/CN1843734B/en
Publication of CN1843734A publication Critical patent/CN1843734A/en
Application granted granted Critical
Publication of CN1843734B publication Critical patent/CN1843734B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The invention relates to a device for processing molded product, especially providing an automatic product line of brick. It comprises a brick maker, a palletizing device, an autoclave, a brick discharger and a maintaining vehicle. It is characterized in contained first feeder and second feeder, wherein, the first feeder is arranged between the brick maker and the autoclave; the second feeder is arranged between the autoclave and the brick discharger; said maintaining vehicle is mounted on the first and second feeders to move between them; said invention uses feeders to connect independent brick maker, palletizing device, autoclave and brick discharge to realize mechanical operation, automatic production, reduced labor force and improved brick quality.

Description

The automatic assembly line of brick
Technical field
The present invention relates to the automatic assembly line of a kind of equipment of machine-shaping goods, particularly a kind of brick.
Technical background
The process of brick generally comprises following four steps: one, and adobe is compression moulding in brickmaking machine; Two, with the mould brick piling on the maintenance dolly; Three, the maintenance dolly pushed carry out maintenance in the still kettle; Four, finished bricks goes out still and stacks.The applicant has applied for multinomial patent before this, comprises cloth brick folding mechanism, stacking machine and the de-hackers of auto-braking brick machine.Have the automatic brick-equipment compression moulding adobe of cloth brick folding mechanism by this, and adobe is placed on the conveyer belt by brick folding mechanism.Then by stacking machine with the fragment of brick piling on the conveyer belt on the maintenance dolly.The maintenance dolly is pushed maintenance in the still kettle.By de-hackers the finished bricks on the maintenance dolly is deposited on the finished bricks stockyard at last.Like this, though improved product quality and productivity ratio, but, the maintenance dolly pushes and release still kettle still to be needed manually to operate, labor intensity is big, and each production stage can't link up and carry out, can not realize the full automation that brickmaking is produced, thereby restrict the further raising of product quality and productivity ratio.
Summary of the invention
Technical problem to be solved by this invention is to provide a kind of can further reduce labour intensity, improves the quality and the productivity ratio of brick, realizes the automatic assembly line of the brick of the production automation.
The present invention is achieved through the following channels.
The automatic assembly line of brick, comprise brickmaking machine, stacking machine, still kettle, de-hackers and maintenance dolly, its structural feature is: also comprise first conveyer and second conveyer, first conveyer is connected between brickmaking machine and the still kettle, second conveyer is connected between still kettle and the de-hackers, the maintenance dolly is installed on first conveyer and second conveyer, and moves on first conveyer and second conveyer.
Like this, brick is compression moulding in brickmaking machine, and after the brick folding mechanism by brickmaking machine is placed on the conveyer belt of brickmaking machine, on the maintenance dolly on first conveyer, first conveyer carries out maintenance with the maintenance cart transport to stacking machine to still kettle, after the maintenance with the fragment of brick piling on the conveyer belt, second conveyer shifts out the maintenance dolly again in still kettle, at last, by de-hackers fragment of brick on the maintenance dolly is deposited in finished bricks and stacks in the field, thus the production of complete whole brickmaking.In this whole brickmaking production process, undertaken by mechanized operation fully, realize the automation of production, thereby further reduce labour intensity, improve the quality and the productivity ratio of brick.
The structure of first conveyer of the present invention and second conveyer can be specially:
First conveyer and second conveyer are a kind of guide rail conveyer, comprise conveying and transport driving, and the maintenance dolly drives it by transport driving and moves on conveying.
Like this, the maintenance dolly is installed on the conveying, drives the maintenance dolly by transport driving and moves on conveying.
Piling is on the maintenance dolly from level to level with brick for stacking machine, and behind the good brick of piling, the maintenance dolly shifts out, and another maintenance dolly just moves to the below of stacking machine, therefore, just in time is positioned at the below of stacking machine for making to care the car, like this:
The stepping controlling organization that also has the promotion maintenance dolly that cooperates with stacking machine between two conveyings of first conveyer. this stepping controlling organization comprises motor, screw mandrel, travelling car and trolley pole, motor is connected with screw mandrel, screw mandrel is connected with travelling car by a nut, nut is fixed on the travelling car, trolley pole tilts to be installed on the travelling car by torsionspring, and has two travelling cars and trolley pole.
Like this, two trolley poles push away a maintenance dolly respectively, be positioned at the below of stacking machine when a maintenance dolly, behind the good fragment of brick of stacking machine sign indicating number, motor is connected with screw mandrel by shaft joint and drives screw mandrel and rotate, and screw mandrel rotates and drives nut and move, thereby travelling car moves, trolley pole on the travelling car withstands on the wheel shaft of maintenance dolly wheel, advance thereby promote the maintenance dolly, previous dolly shifts out, and a back dolly just moves to the below of stacking machine, piling fragment of brick again, simultaneously, the motor counter-rotating, travelling car is return original position again, the trolley pole of front just withstands on the back dolly, and the trolley pole of back just withstands on another dolly.Like this, the reciprocation cycle below that constantly the maintenance dolly is pushed into stacking machine stacks bricks.
Structure of the present invention can be specially:
Also comprise the backhaul conveyer, this backhaul conveyer is between the front end of the end of second conveyer and first conveyer, and backhaul conveyer, first conveyer and second are carried the closed pipeline of unit.
The maintenance dolly is sent still kettle by second conveyer, after de-hackers unloads the fragment of brick on the maintenance dolly, the maintenance dolly is vacant, like this, between second conveyer and first conveyer, be connected a backhaul conveyer, make the backhaul conveyer, first conveyer and second conveyer are formed the pipeline of a closure, the maintenance dolly moves on this closed pipeline, vacant maintenance dolly is delivered on the backhaul conveyer from second conveyer, by the backhaul conveyer vacant maintenance dolly is returned on first conveyer, therefore stacking machine can be with the fragment of brick piling on the maintenance dolly, thereby maintenance dolly reciprocation cycle used.
The structure of backhaul conveyer can be specially:
The backhaul conveyer has track, rotating disk and driving mechanism, and rotating disk is installed on each corner of backhaul conveyer, and has the guide rail that cooperates with track on the rotating disk.
Because the backhaul conveyer is sent the maintenance dolly on first conveyer back to, therefore, the backhaul conveyer need turn to, and the mode that turns to can track be set to circular face and realizes turning to, but the circuit orbit floor space is bigger, and the maintenance dolly is controlled complicated when circuit orbit is walked; The mode that turns to also can be set to rectangle by track, and a kind of rotating disk is installed in four corners of this rectangle, on rotating disk, has the guide rail that cooperates with track, the junction of the backhaul conveyer and second conveyer is provided with a rotating disk, when the maintenance dolly when second conveyer moves on the backhaul conveyer, the guide rail of rotating disk cooperates with the delivery track of second conveyer, therefore the maintenance dolly moves on the rotating disk, dial rotation then, the guide rail of rotating disk is cooperated with the track of backhaul conveyer, the maintenance dolly moves on the backhaul conveyer from rotating disk, thereby realizes turning to of 90 ° in maintenance dolly.In like manner, realize equally that in other three corners of backhaul conveyer 90 ° of the maintenance dolly turn to, thereby the maintenance dolly is returned on first conveyer.
The automatic assembly line of brick of the present invention can also further be specially:
Have a plurality of still kettles, all have first conveyer, between each still kettle and de-hackers, all have second conveyer at each still kettle and brickmaking machine.
Like this, because the curing time of adobe in still kettle is longer, therefore, a plurality of still kettles can be set on the automatic assembly line of a brick, a plurality of still kettles are worked simultaneously. as when having three still kettles, at first, stacking machine with the adobe piling on the maintenance dolly, then, the maintenance dolly of three good adobes of sign indicating number enters still kettle simultaneously and carries out maintenance, simultaneously, stacking machine continues the adobe piling on the maintenance dolly, and after maintenance was finished, the adobe of three maintenance dollies also sign indicating number was good, at this moment, three maintenance dollies in the still kettle go out still, and other three maintenance dollies advance still kettle and carry out maintenance, and three maintenance dollies that still kettle comes out just can unload brick and stacked. by being provided with that a plurality of still kettles just can be avoided because curing time is long makes piling and unload brick and stagnate wait, production can be carried out fully continuously, further boosts productivity.
A plurality of still kettles and first conveyer and second conveyer that are connected with still kettle are arranged in parallel, the front end of first conveyer that is arranged in parallel also comprises reciprocating conveyor, reciprocating conveyor is between the brickmaking machine and first conveyer, and the moving direction of the maintenance dolly on the moving direction of reciprocating conveyor and first conveyer is vertical.
Like this, just can be to each first conveyer by shuttle conveyer with the maintenance cart transport.
Reciprocating conveyor comprises ferry bus, lower railway and ferry-boat track, lower railway is perpendicular to the delivery track of first conveyer, ferry bus is installed on the lower railway, the ferry-boat track is installed on the ferry bus, and the ferry-boat track is vertical with lower railway and be positioned at same horizontal plane with the delivery track of first conveyer.
Because the ferry-boat track on the ferry bus and the delivery track of first conveyer are positioned on the same horizontal plane, therefore, when this shuttle conveyer is installed, at first dig a melt pit on ground, lower railway is installed in the melt pit, the ferry-boat track can be positioned at the delivery track of first conveyer on the same horizontal plane.The maintenance dolly moves on the ferry-boat track, when ferry bus moves back and forth on lower railway, just can with in the maintenance cart transport on the ferry bus to each first conveyer.
In sum, the present invention has the following advantages compared to existing technology: the brickmaking machine of producing separately, stacking machine, still kettle, the de-hackers of each dispersion are connected by conveyer, brickmaking is produced fully by mechanized operation, realize the production of automation, reduce labor intensity, improve the quality and the productivity ratio of brick.
Description of drawings
Fig. 1 is a structural representation of the present invention.
Fig. 2 is the structural representation of reciprocating conveyor of the present invention.
Fig. 3 is the left view of Fig. 2.
Fig. 4 is a stepping controlling organization structural representation of the present invention.
Wherein, 1 brickmaking machine, 2 stacking machines, 3 still kettles, 4 de-hackers, 5 maintenance dollies, 6 first conveyers, 61 stepping controlling organizations, 611 motors, 612 screw mandrels, 613 travelling cars, 614 trolley poles, 7 second conveyers, 8 reciprocating conveyors, 81 ferry buses, 82 lower railway, 83 ferry-boat tracks, 9 backhaul conveyers, 91 tracks, 92 rotating disks, 921 guide rails.
The specific embodiment
Most preferred embodiment:
With reference to Fig. 1, Fig. 4, the automatic assembly line of brick, comprise brickmaking machine 1, stacking machine 2, still kettle 3, de-hackers 4 and maintenance dolly 5, also comprise first conveyer 6 and second conveyer 7, first conveyer 6 is connected between brickmaking machine 1 and the still kettle 3, second conveyer 7 is connected between still kettle 3 and the de-hackers 4, maintenance dolly 5 is installed on first conveyer 6 and second conveyer 7, and on first conveyer 6 and second conveyer 7, moving. first conveyer 6 and second conveyer 7 are a kind of guide rail conveyer, comprise conveying and transport driving, maintenance dolly 5 moves driving it by transport driving on the conveying. and stepping controlling organization 61. these stepping controlling organizations 61 that also have the promotion maintenance dolly 5 that cooperates with stacking machine 2 between two conveyings of first conveyer 6 comprise motor 611, screw mandrel 612, travelling car 613 and trolley pole 614, motor 611 is connected with screw mandrel 612, screw mandrel 612 is connected with travelling car 613 by a nut, nut is fixed on the travelling car 613, trolley pole 614 tilts to be installed on the travelling car 613 by torsionspring, and automatic assembly line with two travelling cars 613 and trolley pole 614. bricks of the present invention, also comprise backhaul conveyer 9, this backhaul conveyer 9 is between the front end of the end of second conveyer 7 and first conveyer 6, backhaul conveyer 9,7 groups of closed pipelines of first conveyer 6 and second conveyer. backhaul conveyer 9 has track 91, rotating disk 92 and driving mechanism, rotating disk 92 is installed on each corner of backhaul conveyer 9, and track 91 rings that have the guide rail 921. backhaul conveyers 9 that cooperate with track 91 on the rotating disk 92 surround rectangle, rotating disk 92 is installed in four corners of rectangle. have three still kettles 3, all has first conveyer 6 at each still kettle 3 with brickmaking machine 1, first conveyer 6 and second conveyer 7 that all have 7. 3 still kettles of second conveyer 3 and be connected with still kettle 3 between each still kettle 3 and de-hackers 4 are arranged in parallel, the front end of first conveyer 6 that is arranged in parallel also comprises reciprocating conveyor 8, reciprocating conveyor 8 is between the brickmaking machine 4 and first conveyer 6, and the moving direction of the maintenance dolly 5 on the moving direction of reciprocating conveyor 8 and first conveyer 6 is vertical, just maintenance dolly 5 can be delivered on each first conveyer 6 by shuttle conveyer 8.
With reference to Fig. 2, Fig. 3, reciprocating conveyor comprises ferry bus 81, lower railway 82 and ferry-boat track 83, lower railway 82 is perpendicular to the delivery track of first conveyer 6, ferry bus 81 is installed on the lower railway 82, ferry-boat track 83 is installed on the ferry bus 81, and ferry-boat track 83 and lower railway 82 are vertical and be positioned at same horizontal plane with the delivery track of first conveyer 6.When this shuttle conveyer 8 is installed, at first dig a melt pit, lower railway 82 is installed in the melt pit, ferry-boat track 83 can be positioned at the delivery track of first conveyer 6 on the same horizontal plane on ground.Maintenance dolly 5 moves on ferry-boat track 83, when ferry bus 81 moves back and forth on lower railway 82, just can will be delivered on each first conveyer 6 at the maintenance dolly 5 on the ferry bus 81.
The operation principle of the automatic assembly line of brick: brick compression moulding in brickmaking machine 1, and after the brick folding mechanism by brickmaking machine 1 is placed on the conveyer belt, on first conveyer 6, two trolley poles 614 of stepping controlling organization 61 push away a maintenance dolly 5 respectively, be positioned at the below of stacking machine 2 when a maintenance dolly 5, behind 2 yards good fragments of brick of stacking machine, motor 611 is connected with screw mandrel 612 by shaft joint and drives screw mandrel 612 and rotate, screw mandrel 612 rotates and drives nut and move, thereby travelling car 613 moves, trolley pole 614 on the travelling car 613 withstands on the wheel shaft of maintenance dolly 5 rear wheels, advances thereby promote maintenance dolly 5, and previous maintenance dolly 5 shifts out, the maintenance dolly 5 in back just moves to the below of stacking machine 2, piling fragment of brick again, simultaneously, motor 611 counter-rotatings, travelling car 613 is return original position again, the trolley pole 614 of front just withstands on the back dolly, and the trolley pole 614 of back just withstands on another dolly, and the below that constantly maintenance dolly 5 is pushed into stacking machine stacks bricks.Then, by reciprocating conveyor 8 the maintenance dolly 5 of three good adobes of sign indicating number is delivered to respectively on three first pipelines 6, three maintenance dollies 5 enter still kettle 3 simultaneously at first pipeline 6 and carry out maintenance, at this moment, stacking machine 2 continues the adobe piling on maintenance dolly 5, after maintenance is finished, the adobe of three maintenance dollies 5 also sign indicating number is good, at this moment, three maintenance dollies 5 in the still kettle 3 go out still, and other three maintenance dollies 5 advance still kettle 3 and carry out maintenance, and three maintenance dollies 5 that still kettle 3 comes out unload brick by de-hackers 4 and are deposited in finished bricks and stack.At this moment, maintenance dolly 5 is vacant, vacant maintenance dolly 5 is delivered on the backhaul conveyer 9 from second conveyer 7, when maintenance dolly 5 when second conveyer 7 moves on the backhaul conveyer 9, the guide rail 921 of rotating disk 92 cooperates with the delivery track of second conveyer 7, therefore maintenance dolly 5 moves on the rotating disk 92, rotating disk 92 rotates then, the guide rail 921 of rotating disk 92 is cooperated with the track 91 of backhaul conveyer 9, maintenance dolly 5 moves on the backhaul conveyer 9 from rotating disk 92, thereby realizes turning to of maintenance dolly 5 nine ten degree.In like manner, realize equally that in other three corners of backhaul conveyer 9 90 degree of maintenance dolly 5 turn to, thereby maintenance dolly 5 is returned on first conveyer 6, reciprocation cycle, the complete mechanical operation realizes the brick production automation.
It is same as the prior art that present embodiment is not stated part.

Claims (8)

1. the automatic assembly line of brick, comprise brickmaking machine (1), stacking machine (2), still kettle (3), de-hackers (4) and maintenance dolly (5), it is characterized in that, also comprise first conveyer (6) and second conveyer (7), first conveyer (6) is connected between brickmaking machine (1) and the still kettle (3), second conveyer (7) is connected between still kettle (3) and the de-hackers (4), maintenance dolly (5) is installed on first conveyer (6) and second conveyer (7), and goes up mobile at first conveyer (6) and second conveyer (7).
2. the automatic assembly line of brick according to claim 1, it is characterized in that, first conveyer (6) is a kind of track conveyer with second conveyer (7), comprises conveying and transport driving, and maintenance dolly (5) drives it by transport driving and moves on conveying.
3. the automatic assembly line of brick according to claim 2, it is characterized in that, also comprise stepping controlling organization (61), this stepping controlling organization (61) is installed between first conveyer (6) two conveyings, and be positioned at the below of stacking machine (2), the stepping controlling organization comprises motor (611), screw mandrel (612), travelling car (613) and trolley pole (614), motor (611) is connected with screw mandrel (612), screw mandrel (612) is connected with travelling car (613) by a nut, nut is fixed on the travelling car (613), trolley pole (614) tilts to be installed on the travelling car (613) by torsionspring, and has two travelling cars (613) and trolley pole (614).
4. the automatic assembly line of brick according to claim 1, it is characterized in that, also comprise backhaul conveyer (9), this backhaul conveyer (9) is positioned between the front end of the end of second conveyer (7) and first conveyer (6), backhaul conveyer (9), first conveyer (6) and second conveyer (7) are formed closed pipeline.
5. the automatic assembly line of brick according to claim 4, it is characterized in that, backhaul conveyer (9) has track (91), rotating disk (92) and driving mechanism, rotating disk (92) is installed on each corner of backhaul conveyer (9), and has the guide rail (921) that cooperates with track (91) on the rotating disk (92).
6. the automatic assembly line of brick according to claim 1, it is characterized in that, have a plurality of still kettles (3), all have first conveyer (6), between each still kettle (3) and de-hackers (4), all have second conveyer (7) at each still kettle (3) and brickmaking machine (1).
7. the automatic assembly line of brick according to claim 6, it is characterized in that, also comprise reciprocating conveyor (8), reciprocating conveyor (8) is positioned between brickmaking machine (1) and first conveyer (6), and the moving direction of the maintenance dolly (5) on the moving direction of reciprocating conveyor (8) and first conveyer (6) is vertical.
8. the automatic assembly line of brick according to claim 7, it is characterized in that, reciprocating conveyor (8) comprises ferry bus (81), lower railway (82) and ferry-boat track (83), lower railway (82) is perpendicular to the delivery track of first conveyer (6), ferry bus (81) is installed on the lower railway (82), and ferry-boat track (83) is installed on the ferry bus (81), and ferry-boat track (83) is vertical with lower railway (82) and with the conveying of first conveyer (6)
Track is positioned at same horizontal plane.
CN200610040081A 2006-04-26 2006-04-26 Automatic brick production line Active CN1843734B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN200610040081A CN1843734B (en) 2006-04-26 2006-04-26 Automatic brick production line

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN200610040081A CN1843734B (en) 2006-04-26 2006-04-26 Automatic brick production line

Publications (2)

Publication Number Publication Date
CN1843734A CN1843734A (en) 2006-10-11
CN1843734B true CN1843734B (en) 2010-05-12

Family

ID=37062717

Family Applications (1)

Application Number Title Priority Date Filing Date
CN200610040081A Active CN1843734B (en) 2006-04-26 2006-04-26 Automatic brick production line

Country Status (1)

Country Link
CN (1) CN1843734B (en)

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103465365B (en) * 2013-07-30 2015-08-05 四川省品信机械有限公司 Automation brick production line
CN105329634A (en) * 2015-11-02 2016-02-17 卓达新材料科技集团有限公司 Moving system for wet plates
CN105538491A (en) * 2015-12-11 2016-05-04 李谟清 Full-automatic cement brick curing system and curing technological process
CN107520953A (en) * 2017-09-30 2017-12-29 群峰智能机械股份公司 A kind of building block brick automatic production line
CN111300628B (en) * 2020-05-12 2020-09-18 湖南三一快而居住宅工业有限公司 Autoclaved aerated concrete production line
CN114524284B (en) * 2022-04-25 2023-03-10 佛山市科达机电有限公司 Automatic pile up neatly unit, automatic pile up neatly system and lithium carbonate calcination production line

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3038509A1 (en) * 1980-10-11 1982-05-06 Dorstener Maschinenfabrik Ag, 4270 Dorsten Automatic, programmed placing of brick blanks on platform - in plant contg. conveyor belt and transfer devices
DE3508235A1 (en) * 1985-03-08 1986-09-11 Dorstener Maschinenfabrik Ag, 4270 Dorsten Device for gripping ready-pressed green bricks at the end faces
CN2528749Y (en) * 2001-08-31 2003-01-01 北京东方新强设备制造有限公司 Automatic blank stacking machine
CN2796992Y (en) * 2004-07-02 2006-07-19 李良光 Automatic production line of bricks

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3038509A1 (en) * 1980-10-11 1982-05-06 Dorstener Maschinenfabrik Ag, 4270 Dorsten Automatic, programmed placing of brick blanks on platform - in plant contg. conveyor belt and transfer devices
DE3508235A1 (en) * 1985-03-08 1986-09-11 Dorstener Maschinenfabrik Ag, 4270 Dorsten Device for gripping ready-pressed green bricks at the end faces
CN2528749Y (en) * 2001-08-31 2003-01-01 北京东方新强设备制造有限公司 Automatic blank stacking machine
CN2796992Y (en) * 2004-07-02 2006-07-19 李良光 Automatic production line of bricks

Also Published As

Publication number Publication date
CN1843734A (en) 2006-10-11

Similar Documents

Publication Publication Date Title
CN1843734B (en) Automatic brick production line
CN106005995B (en) A kind of charging and discharging mechanism
CN105460623A (en) Automatic stacking conveying line
CN101524822B (en) Tile-shaped magnet internal and external cambers and double-line bidirectional automatic chamfering compound grinding machine
CN102335957A (en) Concrete building block cutting device
CN103171049B (en) Brick discharging system of automatic production line of brick making machine
CN207058867U (en) Concrete prefabricated automatic production device
CN108907745A (en) A kind of copper bus-bar process units with Combined production line
CN202399411U (en) Concrete block cutting device
CN101642890B (en) Pushing type tile shape magnet internal and external cambered surface and mongline bidirectional automatic chamfering compound grinding machine
CN2796992Y (en) Automatic production line of bricks
CN108972861A (en) A kind of wallboard production line
CN205169666U (en) Loading attachment of battery module kludge
CN106829365A (en) Ferry bus before a kind of air-entraining concrete production line steam-cured kettle
CN103754588A (en) Automatic transporting and packing system
CN201669768U (en) Product transporting device of ceramic high-pressure slip-casting forming machine
CN211194285U (en) Concrete prefabricated section processing equipment
CN110666932A (en) Full-automatic ceramic rolling production line
CN108908674A (en) A kind of automatic storage is transported, is poured, the complete set of equipments of vibrated concrete
CN211074099U (en) Concrete prefabricated part material distributor
CN103817787B (en) The mill for slats of center partition wall made demoulding divides loop wheel machine
CN211645047U (en) Whole-body stone-like glass mosaic forming equipment
CN215401348U (en) Ferrying device for conveying plates
CN212892780U (en) Transfer conveyer
CN203712852U (en) Hollow partition batten demolding-classifying crane

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
ASS Succession or assignment of patent right

Owner name: HAIYUAN AUTOMATIC MACHINERY EQUIPMENT CO., LTD.,

Free format text: FORMER OWNER: LI LIANGGUANG

Effective date: 20070824

C41 Transfer of patent application or patent right or utility model
TA01 Transfer of patent application right

Effective date of registration: 20070824

Address after: 350000 No. 16 Jinzhou North Road, Jinshan Industrial Zone, Fujian, Fuzhou, China

Applicant after: Fujian Haiyuan Automatic Machinery Equipment Co.,Ltd.

Address before: 350000 No. 54, 160 Gulou District, Fujian, Fuzhou

Applicant before: Li Liangguang

C14 Grant of patent or utility model
GR01 Patent grant
CP03 Change of name, title or address

Address after: 350100 No. 2 Tieling North Road, Jingxi Town, Minhou, Fuzhou, Fujian

Patentee after: Fujian Haiyuan Composite Materials Technology Co.,Ltd.

Address before: 350100 Fujian Minhou Tieling industrial concentration area

Patentee before: FUJIAN HAIYUAN AUTOMATIC EQUIPMENTS Co.,Ltd.

CP03 Change of name, title or address
CP01 Change in the name or title of a patent holder

Address after: 350100 No. 2 Tieling North Road, Jingxi Town, Minhou, Fuzhou, Fujian

Patentee after: Jiangxi Haiyuan composite material technology Co.,Ltd.

Address before: 350100 No. 2 Tieling North Road, Jingxi Town, Minhou, Fuzhou, Fujian

Patentee before: Fujian Haiyuan Composite Materials Technology Co.,Ltd.

CP01 Change in the name or title of a patent holder
TR01 Transfer of patent right

Effective date of registration: 20220130

Address after: 350100 No. 2 Tieling North Road, Jingxi Town, Minhou, Fuzhou, Fujian

Patentee after: Fujian Haiyuan Intelligent Equipment Co.,Ltd.

Address before: 350100 No. 2 Tieling North Road, Jingxi Town, Minhou, Fuzhou, Fujian

Patentee before: Jiangxi Haiyuan composite material technology Co.,Ltd.

TR01 Transfer of patent right