CN2796992Y CN 200420150254 CN200420150254U CN2796992Y CN 2796992 Y CN2796992 Y CN 2796992Y CN 200420150254 CN200420150254 CN 200420150254 CN 200420150254 U CN200420150254 U CN 200420150254U CN 2796992 Y CN2796992 Y CN 2796992Y
Authority
CN
China
Prior art keywords
conveyer
brick
machine
maintenance
track
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN 200420150254
Other languages
Chinese (zh)
Inventor
李良光
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fujian Haiyuan Automatic Machinery Co Ltd
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Family has litigation
First worldwide family litigation filed litigation Critical https://patents.darts-ip.com/?family=36868228&utm_source=google_patent&utm_medium=platform_link&utm_campaign=public_patent_search&patent=CN2796992(Y) "Global patent litigation dataset” by Darts-ip is licensed under a Creative Commons Attribution 4.0 International License.
Application filed by Individual filed Critical Individual
Priority to CN 200420150254 priority Critical patent/CN2796992Y/en
Application granted granted Critical
Publication of CN2796992Y publication Critical patent/CN2796992Y/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Intermediate Stations On Conveyors (AREA)

Abstract

The utility model relates to a device for processing shaping products, particularly a brick automatic production line. The utility model comprises a brick making machine, a stacker, a steam pressurizing kettle, a brick unloading machine and curing dollies. The utility model has the structural feature that the utility model also comprises a first conveying machine and a second conveying machine, wherein the first conveying machine is connected between the brick making machine and the steam pressurizing kettle, the second conveying machine is connected between the steam pressurizing kettle and the brick unloading machine, and the curing dollies are installed on the first conveying machine and the second conveying machine and can move on the first conveying machine and the second conveying machine. The brick automatic production line connects the brick making machine, the autoclave and the brick unloading machine which dispersively and solely carry out production by the conveying machines, causes brick making production to realize automatic production by complete mechanized operation, reduces labor intensity and enhances the quality and the productivity of bricks.

Description

The automatic assembly line of brick
Technical field
The utility model relates to the automatic assembly line of a kind of equipment of machine-shaping goods, particularly a kind of brick.
Background technology
The process of brick generally comprises following four steps: one, and adobe is compression moulding in brickmaking machine; Two, with the mould brick piling on the maintenance dolly; Three, the maintenance dolly pushed carry out maintenance in the still kettle; Four, finished bricks goes out still and stacks.The applicant has applied for multinomial patent before this, comprises cloth brick folding mechanism, stacking machine and the de-hackers of auto-braking brick machine.Have the automatic brick-equipment compression moulding adobe of cloth brick folding mechanism by this, and adobe is placed on the conveyer belt by brick folding mechanism.Then by stacking machine with the fragment of brick piling on the conveyer belt on the maintenance dolly.The maintenance dolly is pushed maintenance in the still kettle.By de-hackers the finished bricks on the maintenance dolly is deposited on the finished bricks stockyard at last.Like this, though improved product quality and productivity ratio, but, the maintenance dolly pushes and release still kettle still to be needed manually to operate, labor intensity is big, and each production stage can't link up and carry out, can not realize the full automation that brickmaking is produced, thereby restrict the further raising of product quality and productivity ratio.
Invention constitutes
The purpose of this utility model is to overcome weak point of the prior art and a kind of labour intensity that can further reduce is provided, and improves the quality and the productivity ratio of brick, realizes the automatic assembly line of the brick of the production automation.
The purpose of this utility model realizes by following approach.
The automatic assembly line of brick, comprise brickmaking machine, stacking machine, still kettle, de-hackers and maintenance dolly, its structural feature is: also comprise first conveyer and second conveyer, first conveyer is connected between brickmaking machine and the still kettle, second conveyer is connected between still kettle and the de-hackers, the maintenance dolly is installed on first conveyer and second conveyer, and moves on first conveyer and second conveyer.
Like this, brick is compression moulding in brickmaking machine, and after the brick folding mechanism by brickmaking machine is placed on the conveyer belt of brickmaking machine, on the maintenance dolly on first conveyer, first conveyer carries out maintenance with the maintenance cart transport to stacking machine to still kettle, after the maintenance with the fragment of brick piling on the conveyer belt, second conveyer shifts out the maintenance dolly again in still kettle, at last, by de-hackers fragment of brick on the maintenance dolly is deposited in finished bricks and stacks in the field, thus the production of complete whole brickmaking.In this whole brickmaking production process, undertaken by mechanized operation fully, realize the automation of production, thereby further reduce labour intensity, improve the quality and the productivity ratio of brick.
The structure of first conveyer described in the utility model and second conveyer can be specially:
First conveyer and second conveyer are a kind of guide rail conveyer, comprise conveying and transport driving, and the maintenance dolly drives it by transport driving and moves on conveying.
Like this, the maintenance dolly is installed on the conveying, drives the maintenance dolly by transport driving and moves on conveying.
Piling is on the maintenance dolly from level to level with brick for stacking machine, and behind the good brick of piling, the maintenance dolly shifts out, and another maintenance dolly just moves to the below of stacking machine, therefore, just in time is positioned at the below of stacking machine for making to care the car, like this:
The stepping controlling organization that also has the promotion maintenance dolly that cooperates with stacking machine between two conveyings of first conveyer.This stepping controlling organization comprises motor, screw mandrel, travelling car and trolley pole, motor is connected with screw mandrel, and screw mandrel is connected with travelling car by a nut, and nut is fixed on the travelling car, trolley pole tilts to be installed on the travelling car by torsionspring, and has two travelling cars and trolley pole.
Like this, two trolley poles push away a maintenance dolly respectively, be positioned at the below of stacking machine when a maintenance dolly, behind the good fragment of brick of stacking machine sign indicating number, motor is connected with screw mandrel by shaft joint and drives screw mandrel and rotate, and screw mandrel rotates and drives nut and move, thereby travelling car moves, trolley pole on the travelling car withstands on the wheel shaft of maintenance dolly wheel, advance thereby promote the maintenance dolly, previous dolly shifts out, and a back dolly just moves to the below of stacking machine, piling fragment of brick again, simultaneously, the motor counter-rotating, travelling car is return original position again, the trolley pole of front just withstands on the back dolly, and the trolley pole of back just withstands on another dolly.Like this, the reciprocation cycle below that constantly the maintenance dolly is pushed into stacking machine stacks bricks.
Structure of the present utility model can be specially:
Also comprise the backhaul conveyer, this backhaul conveyer is between the front end of the end of second conveyer and first conveyer, and backhaul conveyer, first conveyer and second are carried the closed pipeline of unit.
The maintenance dolly is sent still kettle by second conveyer, after de-hackers unloads the fragment of brick on the maintenance dolly, the maintenance dolly is vacant, like this, between second conveyer and first conveyer, be connected a backhaul conveyer, make the backhaul conveyer, first conveyer and second conveyer are formed the pipeline of a closure, the maintenance dolly moves on this closed pipeline, vacant maintenance dolly is delivered on the backhaul conveyer from second conveyer, by the backhaul conveyer vacant maintenance dolly is returned on first conveyer, therefore stacking machine can be with the fragment of brick piling on the maintenance dolly, thereby maintenance dolly reciprocation cycle used.
The structure of backhaul conveyer can be specially:
The backhaul conveyer has track, rotating disk and driving mechanism, and rotating disk is installed on each corner of backhaul conveyer, and has the guide rail that cooperates with track on the rotating disk.
Because the backhaul conveyer is sent the maintenance dolly on first conveyer back to, therefore, the backhaul conveyer need turn to, and the mode that turns to can track be set to circular face and realizes turning to, but the circuit orbit floor space is bigger, and the maintenance dolly is controlled complicated when circuit orbit is walked; The mode that turns to also can be set to rectangle by track, and a kind of rotating disk is installed in four corners of this rectangle, on rotating disk, has the guide rail that cooperates with track, the junction of the backhaul conveyer and second conveyer is provided with a rotating disk, when the maintenance dolly when second conveyer moves on the backhaul conveyer, the guide rail of rotating disk cooperates with the delivery track of second conveyer, therefore the maintenance dolly moves on the rotating disk, dial rotation then, the guide rail of rotating disk is cooperated with the track of backhaul conveyer, the maintenance dolly moves on the backhaul conveyer from rotating disk, thereby realizes turning to of 90 ° in maintenance dolly.In like manner, realize equally that in other three corners of backhaul conveyer 90 ° of the maintenance dolly turn to, thereby the maintenance dolly is returned on first conveyer.
The automatic assembly line of the utility model brick can also further be specially:
Have a plurality of still kettles, all have first conveyer, between each still kettle and de-hackers, all have second conveyer at each still kettle and brickmaking machine.
Like this, because the curing time of adobe in still kettle is longer, therefore, can a plurality of still kettles be set on the automatic assembly line of a brick, a plurality of still kettles are worked simultaneously.As when having three still kettles, at first, stacking machine with the adobe piling on the maintenance dolly, then, the maintenance dolly of three good adobes of sign indicating number enters still kettle simultaneously and carries out maintenance, and simultaneously, stacking machine continues the adobe piling on the maintenance dolly, after maintenance is finished, the adobe of three maintenance dollies also sign indicating number is good, and at this moment, three maintenance dollies in the still kettle go out still, carry out maintenance and other three maintenance dollies advance still kettle, stacked and three maintenance dollies that still kettle comes out just can unload brick.A plurality of still kettles just can be avoided because the long piling that makes of curing time is stagnated wait with unloading brick by being provided with, and production can be carried out fully continuously, further boost productivity.
A plurality of still kettles and first conveyer and second conveyer that are connected with still kettle are arranged in parallel, the front end of first conveyer that is arranged in parallel also comprises reciprocating conveyor, reciprocating conveyor is between the brickmaking machine and first conveyer, and the moving direction of the maintenance dolly on the moving direction of reciprocating conveyor and first conveyer is vertical.
Like this, just can be to each first conveyer by shuttle conveyer with the maintenance cart transport.
Reciprocating conveyor comprises ferry bus, lower railway and ferry-boat track, lower railway is perpendicular to the delivery track of first conveyer, ferry bus is installed on the lower railway, the ferry-boat track is installed on the ferry bus, and the ferry-boat track is vertical with lower railway and be positioned at same horizontal plane with the delivery track of first conveyer.
Because the ferry-boat track on the ferry bus and the delivery track of first conveyer are positioned on the same horizontal plane, therefore, when this shuttle conveyer is installed, at first dig a melt pit on ground, lower railway is installed in the melt pit, the ferry-boat track can be positioned at the delivery track of first conveyer on the same horizontal plane.The maintenance dolly moves on the ferry-boat track, when ferry bus moves back and forth on lower railway, just can with in the maintenance cart transport on the ferry bus to each first conveyer.
In sum, the utility model has the following advantages compared to existing technology: the brickmaking machine of producing separately, stacking machine, still kettle, the de-hackers of each dispersion are connected by conveyer, brickmaking is produced fully by mechanized operation, realize the production of automation, reduce labor intensity, improve the quality and the productivity ratio of brick.
Description of drawings
Fig. 1 is the utility model structural representation.
Fig. 2 is the structural representation of the utility model reciprocating conveyor.
Fig. 3 is the left view of Fig. 2.
Fig. 4 is the utility model stepping controlling organization structural representation.
Wherein, 1 brickmaking machine, 2 stacking machines, 3 still kettles, 4 de-hackers, 5 maintenance dollies, 6 first conveyers, 61 stepping controlling organizations, 611 motors, 612 screw mandrels, 613 travelling cars, 614 trolley poles, 7 second conveyers, 8 reciprocating conveyors, 81 ferry buses, 82 lower railway, 83 ferry-boat tracks, 9 backhaul conveyers, 91 tracks, 92 rotating disks, 921 guide rails.
The specific embodiment
Most preferred embodiment:
With reference to Fig. 1, Fig. 4, the automatic assembly line of brick, comprise brickmaking machine 1, stacking machine 2, still kettle 3, de-hackers 4 and maintenance dolly 5, also comprise first conveyer 6 and second conveyer 7, first conveyer 6 is connected between brickmaking machine 1 and the still kettle 3, second conveyer 7 is connected between still kettle 3 and the de-hackers 4, and maintenance dolly 5 is installed on first conveyer 6 and second conveyer 7, and moves on first conveyer 6 and second conveyer 7.First conveyer 6 and second conveyer 7 are a kind of guide rail conveyer, comprise conveying and transport driving, and maintenance dolly 5 drives it by transport driving and moves on conveying.The stepping controlling organization 61 that also has the promotion maintenance dolly 5 that cooperates with stacking machine 2 between two conveyings of first conveyer 6.This stepping controlling organization 61 comprises motor 611, screw mandrel 612, travelling car 613 and trolley pole 614, motor 611 is connected with screw mandrel 612, screw mandrel 612 is connected with travelling car 613 by a nut, nut is fixed on the travelling car 613, trolley pole 614 tilts to be installed on the travelling car 613 by torsionspring, and has two travelling cars 613 and trolley pole 614.The automatic assembly line of brick described in the utility model also comprises backhaul conveyer 9, this backhaul conveyer 9 between the front end of the end of second conveyer 7 and first conveyer 6, backhaul conveyer 9, first conveyer 6 and 7 groups of closed pipelines of second conveyer.Backhaul conveyer 9 has track 91, rotating disk 92 and driving mechanism, and rotating disk 92 is installed on each corner of backhaul conveyer 9, and has the guide rail 921 that cooperates with track 91 on the rotating disk 92.Track 91 rings of backhaul conveyer 9 surround rectangle, and rotating disk 92 is installed in four corners of rectangle.Have three still kettles 3, all have first conveyer 6 with brickmaking machine 1, between each still kettle 3 and de-hackers 4, all have second conveyer 7 at each still kettle 3.Three still kettles 3 and first conveyer 6 and second conveyer 7 that are connected with still kettle 3 are arranged in parallel, the front end of first conveyer 6 that is arranged in parallel also comprises reciprocating conveyor 8, reciprocating conveyor 8 is between the brickmaking machine 4 and first conveyer 6, and the moving direction of the maintenance dolly 5 on the moving direction of reciprocating conveyor 8 and first conveyer 6 is vertical, just maintenance dolly 5 can be delivered on each first conveyer 6 by shuttle conveyer 8.
With reference to Fig. 2, Fig. 3, reciprocating conveyor comprises ferry bus 81, lower railway 82 and ferry-boat track 83, lower railway 82 is perpendicular to the delivery track of first conveyer 6, ferry bus 81 is installed on the lower railway 82, ferry-boat track 83 is installed on the ferry bus 81, and ferry-boat track 83 and lower railway 82 are vertical and be positioned at same horizontal plane with the delivery track of first conveyer 6.When this shuttle conveyer 8 is installed, at first dig a melt pit, lower railway 82 is installed in the melt pit, ferry-boat track 83 can be positioned at the delivery track of first conveyer 6 on the same horizontal plane on ground.Maintenance dolly 5 moves on ferry-boat track 83, when ferry bus 81 moves back and forth on lower railway 82, just can will be delivered on each first conveyer 6 at the maintenance dolly 5 on the ferry bus 81.
The operation principle of the automatic assembly line of brick: brick compression moulding in brickmaking machine 1, and after the brick folding mechanism by brickmaking machine 1 is placed on the conveyer belt, on first conveyer 6, two trolley poles 614 of stepping controlling organization 61 push away a maintenance dolly 5 respectively, be positioned at the below of stacking machine 2 when a maintenance dolly 5, behind 2 yards good fragments of brick of stacking machine, motor 611 is connected with screw mandrel 612 by shaft joint and drives screw mandrel 612 and rotate, screw mandrel 612 rotates and drives nut and move, thereby travelling car 613 moves, trolley pole 614 on the travelling car 613 withstands on the wheel shaft of maintenance dolly 5 rear wheels, advances thereby promote maintenance dolly 5, and previous maintenance dolly 5 shifts out, the maintenance dolly 5 in back just moves to the below of stacking machine 2, piling fragment of brick again, simultaneously, motor 611 counter-rotatings, travelling car 613 is return original position again, the trolley pole 614 of front just withstands on the back dolly, and the trolley pole 614 of back just withstands on another dolly, and the below that constantly maintenance dolly 5 is pushed into stacking machine stacks bricks.Then, by reciprocating conveyor 8 the maintenance dolly 5 of three good adobes of sign indicating number is delivered to respectively on three first pipelines 6, three maintenance dollies 5 enter still kettle 3 simultaneously at first pipeline 6 and carry out maintenance, at this moment, stacking machine 2 continues the adobe piling on maintenance dolly 5, after maintenance is finished, the adobe of three maintenance dollies 5 also sign indicating number is good, at this moment, three maintenance dollies 5 in the still kettle 3 go out still, and other three maintenance dollies 5 advance still kettle 3 and carry out maintenance, and three maintenance dollies 5 that still kettle 3 comes out unload brick by de-hackers 4 and are deposited in finished bricks and stack.At this moment, maintenance dolly 5 is vacant, vacant maintenance dolly 5 is delivered on the backhaul conveyer 9 from second conveyer 7, when maintenance dolly 5 when second conveyer 7 moves on the backhaul conveyer 9, the guide rail 921 of rotating disk 92 cooperates with the delivery track of second conveyer 7, therefore maintenance dolly 5 moves on the rotating disk 92, rotating disk 92 rotates then, the guide rail 921 of rotating disk 92 is cooperated with the track 91 of backhaul conveyer 9, maintenance dolly 5 moves on the backhaul conveyer 9 from rotating disk 92, thereby realizes turning to of maintenance dolly 5 nine ten degree.In like manner, realize equally that in other three corners of backhaul conveyer 9 90 degree of maintenance dolly 5 turn to, thereby maintenance dolly 5 is returned on first conveyer 6, reciprocation cycle, the complete mechanical operation realizes the brick production automation.
It is same as the prior art that present embodiment is not stated part.

Claims (8)

1. the automatic assembly line of brick, comprise brickmaking machine (1), stacking machine (2), still kettle (3), de-hackers (4) and maintenance dolly (5), it is characterized in that, also comprise first conveyer (6) and second conveyer (7), first conveyer (6) is connected between brickmaking machine (1) and the still kettle (3), second conveyer (7) is connected between still kettle (3) and the de-hackers (4), maintenance dolly (5) is installed on first conveyer (6) and second conveyer (7), and goes up mobile at first conveyer (6) and second conveyer (7).
2. the automatic assembly line of brick according to claim 1, it is characterized in that, first conveyer (6) is a kind of track conveyer with second conveyer (7), comprises conveying and transport driving, and maintenance dolly (5) drives it by transport driving and moves on conveying.
3. the automatic assembly line of brick according to claim 2, it is characterized in that, also comprise stepping controlling organization (61), this stepping controlling organization (61) is installed between first conveyer (6) two conveyings, and be positioned at the below of stacking machine (2), the stepping controlling organization comprises motor (611), screw mandrel (612), travelling car (613) and trolley pole (614), motor (611) is connected with screw mandrel (612), screw mandrel (612) is connected with travelling car (613) by a nut, nut is fixed on the travelling car (613), trolley pole (614) tilts to be installed on the travelling car (613) by torsionspring, and has two travelling cars (613) and trolley pole (614).
4. the automatic assembly line of brick according to claim 1, it is characterized in that, also comprise backhaul conveyer (9), this backhaul conveyer (9) is positioned between the front end of the end of second conveyer (7) and first conveyer (6), backhaul conveyer (9), first conveyer (6) and second conveyer (7) are formed closed pipeline.
5. the automatic assembly line of brick according to claim 4, it is characterized in that, backhaul conveyer (9) has track (91), rotating disk (92) and driving mechanism, rotating disk (92) is installed on each corner of backhaul conveyer (9), and has the guide rail (921) that cooperates with track (91) on the rotating disk (92).
6. the automatic assembly line of brick according to claim 1, it is characterized in that, have a plurality of still kettles (3), all have first conveyer (6), between each still kettle (3) and de-hackers (4), all have second conveyer (7) at each still kettle (3) and brickmaking machine (1).
7. the automatic assembly line of brick according to claim 6, it is characterized in that, also comprise reciprocating conveyor (8), reciprocating conveyor (8) is positioned between brickmaking machine (1) and first conveyer (6), and the moving direction of the maintenance dolly (5) on the moving direction of reciprocating conveyor (8) and first conveyer (6) is vertical.
8. the automatic assembly line of brick according to claim 7, it is characterized in that, reciprocating conveyor (8) comprises ferry bus (81), lower railway (82) and ferry-boat track (83), lower railway (82) is perpendicular to the delivery track of first conveyer (6), ferry bus (81) is installed on the lower railway (82), and ferry-boat track (83) is installed on the ferry bus (81), and ferry-boat track (83) is vertical with lower railway (82) and be positioned at same horizontal plane with the delivery track of first conveyer (6).
CN 200420150254 2004-07-02 2004-07-02 Automatic production line of bricks Expired - Lifetime CN2796992Y (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 200420150254 CN2796992Y (en) 2004-07-02 2004-07-02 Automatic production line of bricks

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 200420150254 CN2796992Y (en) 2004-07-02 2004-07-02 Automatic production line of bricks

Publications (1)

Publication Number Publication Date
CN2796992Y true CN2796992Y (en) 2006-07-19

Family

ID=36868228

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 200420150254 Expired - Lifetime CN2796992Y (en) 2004-07-02 2004-07-02 Automatic production line of bricks

Country Status (1)

Country Link
CN (1) CN2796992Y (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101186079B (en) * 2006-11-17 2010-04-14 怀方林 Composite wire-lacing block-building shaping machine
CN1843734B (en) * 2006-04-26 2010-05-12 福建海源自动化机械股份有限公司 Automatic brick production line
CN102431083A (en) * 2011-09-30 2012-05-02 湖北新发亿盛机械制造有限公司 Building block continuous cutting method and building block continuous cutting apparatus thereof
CN102556399A (en) * 2012-01-02 2012-07-11 洛阳中冶重工机械有限公司 Brick pile packaging method and brick pile packaging production line
CN103171049A (en) * 2013-03-22 2013-06-26 天津市建丰液压机械有限公司 Brick discharging system of automatic production line of brick making machine
CN103465365A (en) * 2013-07-30 2013-12-25 四川省品信机械有限公司 Automatic brick making production line
CN106042163A (en) * 2016-07-20 2016-10-26 安徽省炜思煜智能科技有限公司 Steam pressing building block steamed oxygen cycle system and method
CN110482092A (en) * 2019-08-17 2019-11-22 佛山蓝动力智能科技有限公司 A kind of AGV is without support intelligence storage base system and operation method

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1843734B (en) * 2006-04-26 2010-05-12 福建海源自动化机械股份有限公司 Automatic brick production line
CN101186079B (en) * 2006-11-17 2010-04-14 怀方林 Composite wire-lacing block-building shaping machine
CN102431083A (en) * 2011-09-30 2012-05-02 湖北新发亿盛机械制造有限公司 Building block continuous cutting method and building block continuous cutting apparatus thereof
CN102556399A (en) * 2012-01-02 2012-07-11 洛阳中冶重工机械有限公司 Brick pile packaging method and brick pile packaging production line
CN102556399B (en) * 2012-01-02 2013-10-30 洛阳中冶重工机械有限公司 Brick pile packaging method and brick pile packaging production line
CN103171049A (en) * 2013-03-22 2013-06-26 天津市建丰液压机械有限公司 Brick discharging system of automatic production line of brick making machine
CN103171049B (en) * 2013-03-22 2015-04-08 天津市建丰液压机械有限公司 Brick discharging system of automatic production line of brick making machine
CN103465365A (en) * 2013-07-30 2013-12-25 四川省品信机械有限公司 Automatic brick making production line
CN103465365B (en) * 2013-07-30 2015-08-05 四川省品信机械有限公司 Automation brick production line
CN106042163A (en) * 2016-07-20 2016-10-26 安徽省炜思煜智能科技有限公司 Steam pressing building block steamed oxygen cycle system and method
CN110482092A (en) * 2019-08-17 2019-11-22 佛山蓝动力智能科技有限公司 A kind of AGV is without support intelligence storage base system and operation method

Similar Documents

Publication Publication Date Title
CN1843734A (en) Automatic brick production line
CN2796992Y (en) Automatic production line of bricks
CN202765851U (en) Concrete block full-automatic multi-functional palletizing machine
CN1050801C (en) An apparatus for the manufacture of corrugated tubing from thermoplastic synthetic resin
CN2649535Y (en) Slider type automatic sorting machine
CN106743693A (en) High-order hacking machine
CN2918010Y (en) Automation building block preparing apparatus
CN207061145U (en) A kind of friction starter for sorting induction system
CN201669768U (en) Product transporting device of ceramic high-pressure slip-casting forming machine
CN110666932A (en) Full-automatic ceramic rolling production line
CN206466681U (en) A kind of retainer clamping device of high-order stacking machine
CN103817787B (en) The mill for slats of center partition wall made demoulding divides loop wheel machine
CN212892780U (en) Transfer conveyer
CN112109192A (en) Three-wire combined production line with demolding function
CN218170781U (en) Automatic brick making structure
CN215401348U (en) Ferrying device for conveying plates
CN219928848U (en) Turning device is used in waterproofing membrane production
CN217802375U (en) Intensive high-efficient truss floor carrier plate production line
CN213829825U (en) Sizing material transfer device between banbury mixer
CN216334909U (en) Biomass energy loading device
CN216945213U (en) Special-shaped floor corner feeder
CN219155754U (en) Special loading attachment of special rubber production and processing
CN219749854U (en) Elevator installation mobile device convenient to loading and unloading
CN203712852U (en) Hollow partition batten demolding-classifying crane
CN210735343U (en) Finished product conveying device for palletizing without wooden support

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: HAIYUAN AUTOMATIC MACHINERY EQUIPMENT CO., LTD.,

Free format text: FORMER OWNER: LI LIANGGUANG

Effective date: 20070817

C41 Transfer of patent application or patent right or utility model
TR01 Transfer of patent right

Effective date of registration: 20070817

Address after: 350000 No. 16 Jinzhou North Road, Jinshan Industrial Zone, Fujian, Fuzhou, China

Patentee after: Fujian Haiyaun Automatic Machines Equipment Co., Ltd.

Address before: 350000 No. 54, 160 Gulou District, Fujian, Fuzhou

Patentee before: Li Liangguang

C56 Change in the name or address of the patentee

Owner name: FUJIAN HAIYUAN AUTOMATION MACHINERY CO.

Free format text: FORMER NAME OR ADDRESS: HAIYUAN AUTOMATIC MACHINERY EQUIPMENT CO., LTD., FUJIAN

CP03 Change of name, title or address

Address after: Tieling industrial concentration area, Fujian, Minhou Province, China: 350100

Patentee after: Fujian Haiyuan Automatization Machinery Co., Ltd.

Address before: No. 16, Jinzhou North Road, Jinshan Industrial Zone, Fujian, Fuzhou: 350000

Patentee before: Fujian Haiyaun Automatic Machines Equipment Co., Ltd.

AV01 Patent right actively abandoned

Granted publication date: 20060719

Effective date of abandoning: 20100512