CN1702244A - 一种钢管混凝土的施工工艺 - Google Patents

一种钢管混凝土的施工工艺 Download PDF

Info

Publication number
CN1702244A
CN1702244A CN 200510018794 CN200510018794A CN1702244A CN 1702244 A CN1702244 A CN 1702244A CN 200510018794 CN200510018794 CN 200510018794 CN 200510018794 A CN200510018794 A CN 200510018794A CN 1702244 A CN1702244 A CN 1702244A
Authority
CN
China
Prior art keywords
steel pipe
concrete
pipe
big
steer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN 200510018794
Other languages
English (en)
Other versions
CN1324205C (zh
Inventor
胡曙光
丁庆军
何永佳
吕林女
王发洲
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wuhan University of Technology WUT
Original Assignee
Wuhan University of Technology WUT
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wuhan University of Technology WUT filed Critical Wuhan University of Technology WUT
Priority to CNB2005100187945A priority Critical patent/CN1324205C/zh
Publication of CN1702244A publication Critical patent/CN1702244A/zh
Application granted granted Critical
Publication of CN1324205C publication Critical patent/CN1324205C/zh
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

本发明涉及一种钢管混凝土的施工工艺。一种钢管混凝土的施工工艺,其特征在于包括如下步骤:1).在灌注前,将待灌注的大钢管顶端封闭,在待浇灌的大钢管上端开一直径为10cm-20cm的小孔,并在小孔处垂直于大钢管壁焊上一与小孔直径相应的小钢管,将小钢管用软管与真空泵相连;2).在大钢管下端开始泵送施工:当灌注高度达1.5m以上之后,真空泵开始抽真空;当混凝土灌注到距大钢管顶端1m处时,将真空泵关闭,迅速取下软管,直至排出1 m3以上混凝土为止,停止泵送施工,将小钢管割除后将开口小孔焊死。本发明可以降低泵送难度,同时增强核心混凝土与钢管壁之间粘结的密实性,提高钢管与核心混凝土的协同承载能力。

Description

一种钢管混凝土的施工工艺
技术领域
本发明涉及一种钢管混凝土的施工工艺。
背景技术
钢管混凝土具有承载能力高、塑性和韧性好,施工方便,耐火性能和经济效益好等优点,近年来在高层和大跨度结构中迅速得到推广应用。自1990年在我国四川省建成了跨度110m的钢管混凝土拱桥—旺苍大桥以来,钢管混凝土拱桥在我国快速发展,在较短的时间内,相继建成了200多座钢管混凝土拱桥。而且,随着工程结构朝更高层、更大跨度发展,钢管混凝土管径越来越大,高度和跨度也快速增加。这导致钢管混凝土泵送施工难度加大。更重要的是,钢管壁与核心混凝土之间的紧密结合是钢管混凝土结构发挥协同承载作用的关键所在,而通常的钢管混凝土施工工艺容易在硬化核心混凝土与钢管壁之间形成一层气膜,影响钢管和核心混凝土协同承载能力的发挥。解决钢管混凝土泵送施工难题以及钢管壁与核心混凝土之间形成气膜的问题对于提高钢管混凝土施工效率,改善钢管混凝土质量具有重要意义。
发明内容
针对上述钢管混凝土泵送施工难题以及钢管壁和核心混凝土间气膜的问题,本发明的目的在于提供一种降低泵送难度,同时增强核心混凝土与钢管壁之间粘结的密实性,提高钢管与核心混凝土的协同承载能力的钢管混凝土的施工工艺。
为了实现上述目的,本发明的技术方案是:一种钢管混凝土的施工工艺,包括如下步骤:1).在灌注前,将待灌注的大钢管顶端封闭,在待浇灌的大钢管上端开一直径为10cm-20cm的小孔,并在小孔处垂直于大钢管壁焊上一与小孔直径相应的小钢管,将小钢管用软管与真空泵相连;2).在大钢管下端开始泵送施工:先泵入润滑用水,再接着泵入除无粗集料外其余组分与待灌注的混凝土相同的砂浆,紧接着泵入待灌注的混凝土,当灌注高度达1.5m以上之后,真空泵开始抽真空;当混凝土灌注到距大钢管顶端1m处时,将真空泵关闭,迅速取下软管,继续泵送混凝土至润滑用水和无粗集料的砂浆全部从焊接的小钢管排空,直至排出1m3以上混凝土为止,停止泵送施工,将小钢管割除后将开口小孔焊死。
所述的小钢管长度为20cm-30cm。
若待灌注的大钢管长度达200m以上时,大钢管内焊分仓板,在分仓板两侧钢管壁分别开一直径为10cm-20cm的小孔,并在小孔处垂直于大钢管壁焊上一与小孔直径相应的小钢管,将小钢管用软管与真空泵相连,进行分仓灌注。
本发明在混凝土进行顶升泵送施工的同时,待灌注的大钢管上端的真空泵将钢管内部的空气排出,一方面在钢管中形成负压减轻混凝土在钢管内部上升的阻力,降低泵送难度;另一方面避免钢管壁与核心混凝土之间形成气膜,增强钢管壁与混凝土之间粘结的紧密性,提高钢管与核心混凝土的协同承载能力。
与现有技术相比,本发明具有施工效率高,施工质量好的显著特点。
具体实施方式
实施例1:
进行某建筑物钢管混凝土柱的混凝土灌注施工,该柱直径0.5m,高度50m。步骤如下:1).在灌注前,将待灌注的大钢管顶端封闭,在待浇灌的大钢管上端开一直径为10cm的小孔,并在小孔处垂直于大钢管壁焊上一直径为10cm、长度为20cm的的小钢管,检查焊缝质量,保证其气密性;软管直径与小钢管直径相对应,用软管将小钢管与一台功率3kw的真空泵相连。2).完成上述准备工作之后,在大钢管下端开始泵送施工:先泵入0.2m3的润滑用水,再接着泵入0.5m3除无粗集料外其余组分与待灌注的混凝土相同的砂浆,紧接着泵入待灌注的混凝土,当灌注高度到1.5m时,真空泵开始抽真空;当混凝土灌注到距大钢管顶端1m处时,将真空泵关闭,将软管迅速从小钢管上拨出,继续泵送混凝土至润滑用水和无粗集料的砂浆全部从焊接的小钢管排空,直至排出1m3以上混凝土为止(直到质量均匀的混凝土从小孔冒出),停止泵送施工,将小钢管割除后将开口小孔焊死。
实施例2:
进行某钢管拱桥混凝土灌注施工,钢管拱弧长400m,直径1m。对钢管拱进行两侧对称顶升泵送施工,在两侧距拱脚200m弧长处(拱顶处)进行分仓,内焊分仓板,检查焊缝保证气密性。在距拱脚200m弧长处分仓板(拱顶分仓板)两侧钢管壁分别开一直径20cm的小孔,并在小孔上垂直于钢管壁方向焊一截直径20cm、长度30cm的小钢管,检查焊缝质量,保证其气密性;用软管将小钢管与一台功率5kw的真空泵相连。完成上述准备工作之后,在钢管下端开始泵送施工。将泵管接至分仓板下侧灌注口,先泵入0.3m3水,再接着泵入1m3除无粗集料外其余组分与待灌注的混凝土相同的砂浆,紧接着泵入设计标号的混凝土。待混凝土灌注到1.5m高度时,打开真空泵开始抽真空。待混凝土灌注至距分仓板1m时,关闭真空泵,将软管迅速从小钢管上拨出,继续泵送混凝土至润滑用水及砂浆完全排出小孔,直到质量均匀的混凝土从小孔冒出,停止泵送施工,将小钢管割除后将开口小孔焊死。将泵管接至分仓板上侧灌注口,按上述程序继续进行顶升灌注施工直至完成。

Claims (3)

1.一种钢管混凝土的施工工艺,其特征在于包括如下步骤:1).在灌注前,将待灌注的大钢管顶端封闭,在待浇灌的大钢管上端开一直径为10cm-20cm的小孔,并在小孔处垂直于大钢管壁焊上一与小孔直径相应的小钢管,将小钢管用软管与真空泵相连;2).在大钢管下端开始泵送施工:先泵入润滑用水,再接着泵入除无粗集料外其余组分与待灌注的混凝土相同的砂浆,紧接着泵入待灌注的混凝土,当灌注高度达1.5m以上之后,真空泵开始抽真空;当混凝土灌注到距大钢管顶端1m处时,将真空泵关闭,迅速取下软管,继续泵送混凝土至润滑用水和无粗集料的砂浆全部从焊接的小钢管排空,直至排出1m3以上混凝土为止,停止泵送施工,将小钢管割除后将开口小孔焊死。
2.根据权利要求1所述的一种钢管混凝土的施工工艺,其特征在于:所述的小钢管长度为20cm-30cm。
3.根据权利要求1所述的一种钢管混凝土的施工工艺,其特征在于:若待灌注的大钢管长度达200m以上时,大钢管内焊分仓板,在分仓板两侧钢管壁分别开一直径为10cm-20cm的小孔,并在小孔处垂直于大钢管壁焊上一与小孔直径相应的小钢管,将小钢管用软管与真空泵相连,进行分仓灌注。
CNB2005100187945A 2005-05-27 2005-05-27 一种钢管混凝土的施工工艺 Expired - Fee Related CN1324205C (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNB2005100187945A CN1324205C (zh) 2005-05-27 2005-05-27 一种钢管混凝土的施工工艺

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNB2005100187945A CN1324205C (zh) 2005-05-27 2005-05-27 一种钢管混凝土的施工工艺

Publications (2)

Publication Number Publication Date
CN1702244A true CN1702244A (zh) 2005-11-30
CN1324205C CN1324205C (zh) 2007-07-04

Family

ID=35632180

Family Applications (1)

Application Number Title Priority Date Filing Date
CNB2005100187945A Expired - Fee Related CN1324205C (zh) 2005-05-27 2005-05-27 一种钢管混凝土的施工工艺

Country Status (1)

Country Link
CN (1) CN1324205C (zh)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102296818A (zh) * 2011-05-19 2011-12-28 中铁第四勘察设计院集团有限公司 真空灌注钢管内混凝土方法
CN102587663A (zh) * 2011-12-16 2012-07-18 中国建筑第六工程局有限公司 一种超高层建筑钢管柱混凝土施工工艺
CN103240802A (zh) * 2013-05-16 2013-08-14 淮海工学院 一种预应力钢管混凝土的生产方法
CN106835998A (zh) * 2017-03-29 2017-06-13 贵州桥梁建设集团有限责任公司 一种钢管混凝土拱桥管内混凝土下灌上顶工艺

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CH687399A5 (de) * 1992-04-06 1996-11-29 Eidgenoessische Materialpruefung Verfahren und Vorrichtung zur Schubverstaerkung an einem Bauwerkteil.
CN1538012A (zh) * 2003-10-23 2004-10-20 孔凡营 空心钢管混凝土

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102296818A (zh) * 2011-05-19 2011-12-28 中铁第四勘察设计院集团有限公司 真空灌注钢管内混凝土方法
CN102587663A (zh) * 2011-12-16 2012-07-18 中国建筑第六工程局有限公司 一种超高层建筑钢管柱混凝土施工工艺
CN103240802A (zh) * 2013-05-16 2013-08-14 淮海工学院 一种预应力钢管混凝土的生产方法
CN103240802B (zh) * 2013-05-16 2015-07-08 淮海工学院 一种预应力钢管混凝土的生产方法
CN106835998A (zh) * 2017-03-29 2017-06-13 贵州桥梁建设集团有限责任公司 一种钢管混凝土拱桥管内混凝土下灌上顶工艺

Also Published As

Publication number Publication date
CN1324205C (zh) 2007-07-04

Similar Documents

Publication Publication Date Title
CN1324205C (zh) 一种钢管混凝土的施工工艺
CN102758531B (zh) 大型钢管混凝土结构管内混凝土真空辅助灌注方法及灌注系统
CN1837482A (zh) 钢管混凝土拱圈钢管管内混凝土灌注方法及灌注装置
CN104790436A (zh) 高层建筑地下室顶板沉降后浇带超前止水施工方法
CN114197877A (zh) 一种墙、柱混凝土交界位置分隔装置及施工方法
CN109750832A (zh) 一种构造柱砼自密实的施工方法
CN110863953A (zh) 圆环形钢管混凝土组合风电机组塔架结构
CN217123486U (zh) 一种蒸汽加压混凝土板的加强机构
CN201554155U (zh) 一种钢管砼柱结构
CN206769201U (zh) 一种钢筋混凝土组合柱结构
CN214497906U (zh) 一种可开关钢管柱侧灌封堵装置
CN209779452U (zh) 一种墩身大体积混凝土温控施工装置
CN207619808U (zh) 一种钢管拱肋混凝土浇注结构
CN206829433U (zh) 一种干挂文化石幕墙结构
CN206539052U (zh) 一种既有阳台的加固改造结构
CN207331771U (zh) 一种地下室外墙后浇带的高效节能封堵结构
CN101851899A (zh) 一种h型预应力混凝土柱及其生产方法
CN203284928U (zh) 一种组装式轻质填充构件
CN207920101U (zh) 高层建筑浇筑混凝土输送管清洗系统
CN1538012A (zh) 空心钢管混凝土
CN207144496U (zh) 钢管砼柱混凝土顶升灌注装置
CN207161949U (zh) 一种混凝土泵管防爆管装置
CN216740742U (zh) 一种钢管柱混凝土侧向高抛结构
CN217924912U (zh) 一种新型钢柱混凝土顶升口连接装置
CN218621817U (zh) 一种大跨径钢管混凝土拱桥施工系统

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20070704

Termination date: 20150527

EXPY Termination of patent right or utility model