CN1470709A - Reinforced bored concrete pile construction method - Google Patents

Reinforced bored concrete pile construction method Download PDF

Info

Publication number
CN1470709A
CN1470709A CNA021253617A CN02125361A CN1470709A CN 1470709 A CN1470709 A CN 1470709A CN A021253617 A CNA021253617 A CN A021253617A CN 02125361 A CN02125361 A CN 02125361A CN 1470709 A CN1470709 A CN 1470709A
Authority
CN
China
Prior art keywords
pile
cement
reinforced
concrete pile
concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CNA021253617A
Other languages
Chinese (zh)
Inventor
峻 曹
曹峻
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CNA021253617A priority Critical patent/CN1470709A/en
Publication of CN1470709A publication Critical patent/CN1470709A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The method for reinforcing soft soil ground base is characterized by that in the ground base to be reinforced a deep-layer stirring method is adopted to infiltrate dried cement powder or cement slurry into soil layer, then a cement soil pile is made by means of stirring process, and the central position of said cement soil pile is drilled by spiral drilling machine, and then the concrete can be deposited to obtain the invented reinforced compresol pile.

Description

Reinforced bored concrete pile construction method
The present invention relates to foundation reinforcement method, promptly a kind of composite pile construction.
In order to reinforce soft soil property base, existing traditional method is varied.The stake of cement mix is exactly one of method, but the mix stake pile strength that this construction technology is made is low, can not adapt to the needs of engineering.
Purpose of the present invention is exactly that a kind of worker's method that improves cement mix stake pile strength will be provided, and can accomplish effectively, and environmental protection does not disturb residents.
The object of the present invention is achieved like this: in the cement mix pile center of having solidified,, take out the slag charge of boring with auger jewel hole pore-forming, with concrete pump in the hole from bottom to top concrete perfusion make reinforced bored concrete pile.
Along with the raising of people's environmental consciousness, the problem that construction disturbs residents is sharp-pointed all the more, and particularly the pile-driving method that some disturbs residents in the metropolis is in fact unworkable.The present invention is because to be to use the characteristics of its maximum of auger boring be noiselessness, friction, and the welcome of surrounding resident of being constructed does not deeply disturb residents.
Pile body length of the present invention has three kinds of situations in the construction: promptly with auger when the cement earth pile centre-drilling hole system concrete pile that has solidified, the length of cement earth pile pile body can be less than the concrete pile at its center, and the concrete pile stake that also can be equal to or greater than its center is long.Below in conjunction with accompanying drawing the present invention is described.
Fig. 1 is a reinforced bored concrete pile schematic diagram of the present invention.Shown in the figure be: soft earthen foundation 1, the cement earth pile made from deep mixing method water leaking-in mud dry powder or cement paste 2 at the concrete perfusion 3 then of sodified water earth pile center jewel hole pore-forming, and is put into reinforcing cage 4 with auger, makes reinforced bored concrete pile.
Figure 2 shows that three kinds of pile body length combination of the reinforced concrete pile at cement earth pile and its center.

Claims (2)

1, a kind of foundation reinforcement method is characterized in that making reinforced bored concrete pile in the cement mix pile center of having solidified with auger bore and concrete perfusion.
2, foundation reinforcement method according to claim 1 is characterized in that the length of cement earth pile pile body can be less than the concrete pile at its center, and the concrete pile stake that also can be equal to or greater than its center is long.
CNA021253617A 2002-07-26 2002-07-26 Reinforced bored concrete pile construction method Pending CN1470709A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNA021253617A CN1470709A (en) 2002-07-26 2002-07-26 Reinforced bored concrete pile construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNA021253617A CN1470709A (en) 2002-07-26 2002-07-26 Reinforced bored concrete pile construction method

Publications (1)

Publication Number Publication Date
CN1470709A true CN1470709A (en) 2004-01-28

Family

ID=34142861

Family Applications (1)

Application Number Title Priority Date Filing Date
CNA021253617A Pending CN1470709A (en) 2002-07-26 2002-07-26 Reinforced bored concrete pile construction method

Country Status (1)

Country Link
CN (1) CN1470709A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN100371537C (en) * 2006-01-05 2008-02-27 江苏南水土建工程公司 Novel method for reinforcing deep soft foundition-cencrete core sand stone pile compound foundition method
CN102127910A (en) * 2010-06-02 2011-07-20 山东省建筑科学研究院 Method for constructing soil-cement composite foundation pile as core tubular pile
CN105804062A (en) * 2016-03-02 2016-07-27 广州市第四建筑工程有限公司 Mixing rotary-jet concrete-embedded stiffening pile and construction method thereof
CN113481974A (en) * 2021-07-30 2021-10-08 广东康润达建设工程有限公司 Construction method of mucky soil carrier pile

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN100371537C (en) * 2006-01-05 2008-02-27 江苏南水土建工程公司 Novel method for reinforcing deep soft foundition-cencrete core sand stone pile compound foundition method
CN102127910A (en) * 2010-06-02 2011-07-20 山东省建筑科学研究院 Method for constructing soil-cement composite foundation pile as core tubular pile
CN102127910B (en) * 2010-06-02 2012-02-01 山东省建筑科学研究院 Method for constructing soil-cement composite foundation pile as core tubular pile
CN105804062A (en) * 2016-03-02 2016-07-27 广州市第四建筑工程有限公司 Mixing rotary-jet concrete-embedded stiffening pile and construction method thereof
CN113481974A (en) * 2021-07-30 2021-10-08 广东康润达建设工程有限公司 Construction method of mucky soil carrier pile
CN113481974B (en) * 2021-07-30 2022-03-22 广东康润达建设工程有限公司 Construction method of mucky soil carrier pile

Similar Documents

Publication Publication Date Title
CN101532290B (en) Granule grouting pile of ripple plastic sleeve with hole for strengthening soft soil foundation and strengthening method
CN101446088B (en) Construction method for pole and tower foundation in Gobi Desert gravelly soil area
CN101775814B (en) Anti-slip cement soil pile soil blocking structure and construction method thereof
CN101798810A (en) Cement-soil composite pile inserted into reinforced concrete core materials
CN106996104A (en) Injection forming club-footed pile and its construction method
CN1441124A (en) High-pressure rotary spraying and core inserting process to form pedestal pile
CN102635110B (en) Construction method for concrete pile
CN105386610A (en) Protective construction method for natural-foundation ancient architectures at top of asymmetric deep foundation pit
CN101012654A (en) Self-draining reinforced pipe supporting structure and construction method thereof
CN1470709A (en) Reinforced bored concrete pile construction method
CN109680682A (en) A kind of soft soil foundation Manual excavated pile structure and construction method
CN203594023U (en) Enhanced type long auger drilling pressure-grouting concrete pile
CN201411687Y (en) Corrugated plastic sleeve pipe granule grouting pile with hole
CN1247920A (en) Expandable nole drilling mechanism for deposited reinforced concrete pile
CN1366114A (en) Technology for boring and prefabricating cast piles for foundation of building
CN206220121U (en) Assembled point anchor barricade
CN206233232U (en) A kind of upper and lower part expansion type soil cement is combined pile tube
CN215715241U (en) Novel post-tensioned prestressing rectangular cast-in-place pile
CN205012333U (en) Recoverable FRP stock with enlarged footing
CN205399410U (en) Dig first slip casting club -footed pile of drilling soon
CN110306538B (en) CFG pile for tower crane soft foundation and construction method
CN201056691Y (en) Static pressure cloven-footed pile with compound carrier
CN206495202U (en) A kind of top expansion type cement-soil composite pile
CN102926384A (en) Prefabricated broaching pile adopting post grouting and construction method thereof
CN208023566U (en) A kind of screw thread rammed bulb pile

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication