CN1366264A - Project management method of constructional engineering - Google Patents

Project management method of constructional engineering Download PDF

Info

Publication number
CN1366264A
CN1366264A CN 01121144 CN01121144A CN1366264A CN 1366264 A CN1366264 A CN 1366264A CN 01121144 CN01121144 CN 01121144 CN 01121144 A CN01121144 A CN 01121144A CN 1366264 A CN1366264 A CN 1366264A
Authority
CN
China
Prior art keywords
engineering
data
during
database
process chart
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN 01121144
Other languages
Chinese (zh)
Inventor
小林隆逸
秋山政俊
加藤竜介
瀧口裕史
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PC NETWORK MANSION CO Ltd
Original Assignee
PC NETWORK MANSION CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PC NETWORK MANSION CO Ltd filed Critical PC NETWORK MANSION CO Ltd
Publication of CN1366264A publication Critical patent/CN1366264A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

To provide a work management method for construction work. In this work management method for construction work, the work information related to the construction work is divisionally held in a work daily report database, a work photographic database and a work drawing database, and the data concerned is stored in each database or divisionally for a plurality of work periods. All daily report data concerned, all photographic data, or all drawing data are read from each database and grasped, and any one of the daily report data, any one of the photographic data, and any one of the drawing data within a specified work period are read from the databases, respectively, and grasped.

Description

The project management method of construction work
The present invention relates to engineering information with construction work distinguishes during according to engineering and is made into e-file, the project management method of reading, managing.
Past, the engineering information of construction work is made into e-file, the method of reading and managing, be to utilize computer, with day's work daily paper data and project photograph data, process chart data, be delivered to server from engineering site, then in this server with these engineering daily paper data and project photograph data, process chart data, according to engineering daily paper database and project photograph database, process chart database, preserve with chronological order (order of delivering letters).Utilize computer at engineering site, specify in these engineering daily paper databases and project photograph database, the process chart database each, from this database, access each of the engineering daily paper data of specific date and project photograph data, process chart data again, read and engineering management.
Yet, in construction begins during be completed, engineering daily paper data, project photograph data or the process chart data of a certain particular day of can only reading.And, can not the appointed day, but after must accessing all-work daily paper data, project photograph data and process chart data during the engineering, from total data, check and seek out required data.Like this, just be difficult to the comprehensive project progress state of managing between a certain given period of constructing in being completed of holding.
The present invention is the correlation engineering information with construction work about the project management method of construction work, preserves respectively by engineering daily paper database, project photograph database, process chart database.
In above-mentioned engineering daily paper database, during the engineering daily paper data and the 2nd, the 3rd during the 1st engineering ... preserve engineering daily paper data respectively.
Equally, in above-mentioned project photograph database, also according to during the 1st engineering and during the 2nd, the 3rd ... the project photograph data are preserved respectively.
Equally, in above-mentioned process chart database, according to during the 1st engineering and during the 2nd, the 3rd ... the process chart data are preserved respectively.
First kind of information assurance method is: from above-mentioned engineering daily paper database, during the unified engineering daily paper data and the 2nd, the 3rd that access during the 1st engineering or the like, hold the engineering daily paper data during the above-mentioned all-work.
Equally, from above-mentioned project photograph database, during the unified project photograph data and the 2nd, the 3rd that access during the 1st engineering or the like, hold the project photograph data during the above-mentioned all-work.
Equally, from above-mentioned process chart database, during the unified process chart data and the 2nd, the 3rd that access during the 1st engineering or the like, hold the process chart data during the above-mentioned all-work.
Second kind of information assurance method is: from above-mentioned engineering daily paper database, project photograph database, process chart database, engineering daily paper data, the project photograph data during the 1st engineering and the process chart data during the 1st engineering during the 1st engineering be can access, thereby all-work daily paper data, project photograph data and process chart data during the 1st engineering held.
Equally, from above-mentioned engineering daily paper database, project photograph database, process chart database, engineering daily paper data, the project photograph data during the 2nd engineering and the process chart data during the 1st engineering during the 2nd engineering be can access, thereby all-work daily paper data, project photograph data and process chart data during the 2nd engineering held.
Equally, from above-mentioned engineering daily paper database, project photograph database, process chart database, engineering daily paper data, the project photograph data during the 3rd engineering and the process chart data during the 3rd engineering during the 3rd engineering be can access, thereby all-work daily paper data, project photograph data and process chart data during the 3rd engineering held.
First kind of information assurance method according to the invention described above implemented, construction can be begun during the whole engineering of being completed, to be divided between each given period, reading engineering daily paper data, project photograph data or process chart data, thus the progress situation of holding engineering conscientiously with go wrong.
Second kind of information assurance method according to the invention described above implemented, and construction can be begun to be divided between each given period during the whole engineering of being completed reading engineering daily paper data and corresponding engineering picture data and process chart data.Thereby hold the relevance between engineering daily paper data and project photograph data, the process chart data conscientiously, and on the system clear and definite problem place.
Following according to Fig. 1-Fig. 5, the working of an invention form is described.
Fig. 1 is in the project management method of construction work, the presentation graphs of server and terminal relation.
The pie graph of Fig. 2 server memory.
In the project management method of Fig. 3 construction work, the frame diagram of the disposal route of server and terminal.
Fig. 4 A, what B, C represented is to utilize first kind of information assurance method picture displayed.
Fig. 5 A, what B, C represented is to utilize second kind of information assurance method picture displayed.
S among Fig. 1 is a server.In the storer 1 of this server S, as shown in Figure 2, the correlation engineering information of construction work is preserved respectively by engineering daily paper database 2, project photograph database 3, process chart database 4.And preserve edit routine 5 and terminal supervisory program 7.
Progress along with engineering, almost all can pass through communication line every day, with above-mentioned engineering daily paper data 21,22,23 ... with project photograph data 31,32,33 ... and process chart data 41,42,43 ... etc. information, pass to above-mentioned server S from the terminal 10 of the machineries such as computer of engineering site.These data 21,22,23,31,32,33,41,42,43 ...,, processed in master controller (CPU) by external interface 9.Judge these data 21,22,23,31,32,33,41,42,43 by edit routine 5 ... which belongs in engineering daily paper database 2, project photograph database 3, the process chart database 4.And, judge to belong to during which engineering of each database 2,3,4, and be stored in and deserve part.
As shown in Figure 3, in above-mentioned engineering daily paper database 2, with engineering daily paper data 23 during engineering daily paper data the 22, the 3rd engineering during engineering daily paper data the 21, the 2nd engineering during the 1st engineering ... preserve respectively.
Suppose to go into operation, construct, be completed during three with being divided into during the whole engineering.Engineering daily paper data when at this moment, going into operation just are equivalent to engineering daily paper data 21 during above-mentioned the 1st engineering.Engineering daily paper data during construction just are equivalent to engineering daily paper data 22 during above-mentioned the 2nd engineering.Engineering daily paper data during completion just are equivalent to engineering daily paper data 23 during above-mentioned the 3rd engineering.
Equally, in above-mentioned project photograph database 3, with project photograph data 33 during project photograph data the 32, the 3rd engineering during the 31, the 2nd engineering of project photograph data during the 1st engineering ... preserve respectively.
Suppose be divided into during the whole engineering go into operation, construct, be completed during.Project photograph data when at this moment, going into operation just are equivalent to project photograph data 31 during above-mentioned the 1st engineering.Project photograph data during construction just are equivalent to project photograph data 32 during above-mentioned the 2nd engineering.Project photograph data during completion just are equivalent to project photograph data 33 during above-mentioned the 3rd engineering.
Equally, in above-mentioned process chart database 4, with process chart data 43 during process chart data the 42, the 3rd engineering during the 41, the 2nd engineering of process chart data during the 1st engineering ... preserve respectively.
Suppose be divided into during the whole engineering go into operation, construct, be completed during.Process chart data when at this moment, going into operation just are equivalent to process chart data 41 during above-mentioned the 1st engineering.Process chart data during construction just are equivalent to process chart data 42 during above-mentioned the 2nd engineering.Process chart data during completion just are equivalent to process chart data 43 during above-mentioned the 3rd engineering.
As shown in Figure 3, adopt first kind of information assurance method: utilize terminal 10 to select the 1st menu 11, in the above-mentioned engineering daily paper database 2 from server S, unified access the engineering daily paper data 23 during the engineering during engineering daily paper data 21 during the 1st engineering and the engineering daily paper data the 22, the 3rd during the 2nd engineering ...Shown in Fig. 4 A, on the picture 8 of terminal 10, these data presentation are the 1st expression 11 '.By this information of reading, hold the engineering daily paper data 21,22,23 during above-mentioned whole specific engineering
As shown in Figure 2, if above-mentioned the 1st menu 11, and following the 2nd to the 6th menu 12,13,14 that will narrate, 15,16 have visit, and terminal supervisory program 7 just can be as requested, on terminal 10, from engineering daily paper database 2, project photograph database 3 or process chart database 4, select the corresponding data of reading.
Equally, as shown in Figure 3, utilize terminal 10 to select the 2nd menu 12, in the above-mentioned project photograph database 3 from server S, unifiedly access the project photograph data 33 during the engineering during project photograph data 31 during the 1st engineering and the project photograph data during the 2nd engineering the 32, the 3rd ...Shown in Fig. 4 B, on the picture 8 of terminal 10, these data presentation are the 2nd expression 12 '.By this information of reading, hold the project photograph data 31,32,33 during above-mentioned whole specific engineering
Equally, as shown in Figure 3, utilize terminal 10 to select the 3rd menu 13, in the above-mentioned process chart database 4 from server S, unifiedly access the process chart data 43 during the engineering during process chart data 41 during the 1st engineering and the process chart data during the 2nd engineering the 42, the 3rd ...Shown in Fig. 4 C, on the picture 8 of terminal 10, these data presentation are the 3rd expression 13 '.By this information of reading, hold the process chart data 31,32,33 during above-mentioned whole specific engineering
As shown in Figure 3, adopt second kind of information assurance method: utilize terminal 10 to select the 4th menu 14, in above-mentioned engineering daily paper database 2 from server S, project photograph database 3, the process chart database 4, access the process chart data 41 during the engineering during engineering daily paper data 21 during the 1st engineering and the project photograph data the 31, the 1st during the 1st engineering.Shown in Fig. 5 A, on the picture 8 of terminal 10, these data presentation are the 4th expression 14 '.By this information of reading, hold all-work daily paper data 21 during the 1st engineering, project photograph data 31, process chart data 41.
Equally, utilize terminal 10 to select the 5th menu 15, in above-mentioned engineering daily paper database 2 from server S, project photograph database 3, the process chart database 4, access the process chart data 42 during the engineering during engineering daily paper data 22 during the 2nd engineering and the project photograph data the 32, the 2nd during the 2nd engineering.Shown in Fig. 5 B, on the picture 8 of terminal 10, these data presentation are the 5th expression 15 '.By this information of reading, hold all-work daily paper data 22 during the 2nd engineering, project photograph data 32, process chart data 42.
Equally, utilize terminal 10 to select the 6th menu 16, in above-mentioned engineering daily paper database 2 from server S, project photograph database 3, the process chart database 4, access the process chart data 43 during the engineering during engineering daily paper data 23 during the 3rd engineering and the project photograph data the 33, the 3rd during the 3rd engineering.Shown in Fig. 5 C, on the picture 8 of terminal 10, these data presentation are the 6th expression 16 '.By this information of reading, hold all-work daily paper data 23 during the 3rd engineering, project photograph data 33, process chart data 43.
First kind of information assurance method according to the invention described above implemented, and can be divided between each given period reading engineering daily paper data 21,22 with going into operation during the whole engineering of being completed, 23 ..., and project photograph data 31,32,33 ... process chart data 41,42,43 ...Thereby the progress situation of holding engineering conscientiously with go wrong.
Implement second kind of information assurance method of the invention described above, can during the whole engineering of being completed, be divided between each given period, reading engineering daily paper data 21,22 going into operation, 23 ..., and corresponding engineering picture data 31,32,33 ... with process chart data 41,42,43 ...Thereby hold the relevance between engineering daily paper data and project photograph data, the process chart data conscientiously, and on the system clear and definite problem place.

Claims (1)

1, a kind of project management method of construction work is characterized in that: will preserve respectively by engineering daily paper database, project photograph database, process chart database about the engineering information of construction work; And, in above-mentioned engineering daily paper database, during the engineering daily paper data and the 2nd, the 3rd during the 1st engineering ... engineering daily paper data preserve respectively; Equally, above-mentioned project photograph database is also according to during the 1st engineering and during the 2nd, the 3rd ... the project photograph data are preserved respectively; Above-mentioned process chart database is according to during the 1st engineering and during the 2nd, the 3rd ... the process chart data are preserved respectively; Like this, just can be from above-mentioned engineering daily paper database, access respectively during the engineering daily paper data and the 2nd, the 3rd during the 1st engineering or the like, hold the engineering daily paper data during the above-mentioned all-work.Equally, from above-mentioned project photograph database, access respectively during the project photograph data and the 2nd, the 3rd during the 1st engineering or the like, hold the project photograph data during the above-mentioned all-work; From above-mentioned process chart database, access respectively during the process chart data and the 2nd, the 3rd during the 1st engineering or the like, hold the process chart data during the above-mentioned all-work; And, from above-mentioned engineering daily paper database, project photograph database, process chart database, engineering daily paper data, the project photograph data during the 1st engineering and the process chart data during the 1st engineering during the 1st engineering be can access, thereby all-work daily paper data, project photograph data and process chart data during the 1st engineering held; Equally, from above-mentioned engineering daily paper database, project photograph database, process chart database, access engineering daily paper data, the project photograph data during the 2nd engineering and the process chart data during the 2nd engineering during the 2nd engineering, thereby hold all-work daily paper data, project photograph data and process chart data during the 2nd engineering; From engineering daily paper database, project photograph database, process chart database, access engineering daily paper data, the project photograph data during the 3rd engineering and the process chart data during the 3rd engineering during the 3rd engineering, thereby hold all-work daily paper data, project photograph data and process chart data during the 3rd engineering.
CN 01121144 2001-01-16 2001-06-05 Project management method of constructional engineering Pending CN1366264A (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
JP2001007474A JP3715534B2 (en) 2001-01-16 2001-01-16 Construction management method in construction work
JP007474/01 2001-01-16

Publications (1)

Publication Number Publication Date
CN1366264A true CN1366264A (en) 2002-08-28

Family

ID=18875220

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 01121144 Pending CN1366264A (en) 2001-01-16 2001-06-05 Project management method of constructional engineering

Country Status (2)

Country Link
JP (1) JP3715534B2 (en)
CN (1) CN1366264A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105144208A (en) * 2013-04-19 2015-12-09 阿科尼克斯有限公司 Social project management
CN105825331A (en) * 2016-03-08 2016-08-03 河南理工大学 Management system for different projects of civil construction
TWI576777B (en) * 2016-04-01 2017-04-01 zhi-da Luo Engineering management system

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100844467B1 (en) 2007-10-22 2008-07-07 주식회사 디디알소프트 A simulation system and method for construction progression state with 3d

Family Cites Families (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08263336A (en) * 1995-03-24 1996-10-11 Babcock Hitachi Kk Design job support system and data base processor for the support system
JPH08314954A (en) * 1995-05-16 1996-11-29 Canon Inc Method and device for processing information
JP3285734B2 (en) * 1995-04-21 2002-05-27 株式会社イトーキクレビオ Sales management system
JP2816950B2 (en) * 1995-06-13 1998-10-27 中国電力株式会社 Transmission line construction site management system and site photo transmission method
JP3471526B2 (en) * 1995-07-28 2003-12-02 松下電器産業株式会社 Information provision device
JPH09138823A (en) * 1995-09-11 1997-05-27 Hitachi Ltd Progress control method for design and development and its system, control method for designing and developing project and its system
JPH09330117A (en) * 1996-06-10 1997-12-22 Yokogawa Electric Corp Batch plant control system
JP3445470B2 (en) * 1997-07-09 2003-09-08 株式会社東芝 Maintenance information management support apparatus and method
JP2000001986A (en) * 1998-06-15 2000-01-07 Fujita Corp Construction control system

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105144208A (en) * 2013-04-19 2015-12-09 阿科尼克斯有限公司 Social project management
CN105825331A (en) * 2016-03-08 2016-08-03 河南理工大学 Management system for different projects of civil construction
TWI576777B (en) * 2016-04-01 2017-04-01 zhi-da Luo Engineering management system

Also Published As

Publication number Publication date
JP2002213080A (en) 2002-07-31
JP3715534B2 (en) 2005-11-09

Similar Documents

Publication Publication Date Title
US9384174B1 (en) Automated system for assisting the architectural process
CN1213379C (en) Real-time detabase object statistics collection
EP1979844A2 (en) A portable dataport device and method for retrieving, inter-relating, annotating and managing electronic documents at a point of need
WO2004053635A2 (en) Method and system for managing metadata
CN1721143A (en) Robot system provided with robot controller
US20050159990A1 (en) Systems and methods for managing projects
US20170228346A9 (en) Portable dataport device and method for retrieving, interrelating, annotating and managing electronic documents at a point of need
CN101064027A (en) Architectural engineering construction technique normalizing knowledge base data structure
CN1624702A (en) Method and system for enterprise-wide migration
US20050171963A1 (en) Systems and methods for managing projects
Fruchter et al. Knowledge management for reuse
CN1366264A (en) Project management method of constructional engineering
CN1475950A (en) Item management system and method
CN1680931A (en) Method for automatic modeling a process control system and corresponding process control system
CN1311338C (en) Method for reducing holding of internal memory in using table
CN1315070C (en) Data base access method and system in management information base of network management protocol
US20080313175A1 (en) Method and system for interaction-based expertise reporting
CN1485775A (en) Display processing system and method for node data of tree structure
US20100146002A1 (en) Capturing enterprise architectures
CN1423217A (en) Patent fee managenment system and method
US7574329B1 (en) Object model for decision and issue tracking
CN1521669A (en) Document management system and method
CN1828579A (en) Patent analyzing system
US8880988B2 (en) System and method for dynamic creation of images
CN1393771A (en) Method for quickly eliminating different information in database

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication