Prior art keywords
construction
site
inspection
construction site
processing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP17147595A
Other languages
Japanese (ja)
Other versions
JPH08338133A (en
Inventor
善範 大上
史朗 芦田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chugoku Electric Power Co Inc
Original Assignee
Chugoku Electric Power Co Inc
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chugoku Electric Power Co Inc filed Critical Chugoku Electric Power Co Inc
Priority to JP17147595A priority Critical patent/JP2816950B2/en
Publication of JPH08338133A publication Critical patent/JPH08338133A/en
Application granted granted Critical
Publication of JP2816950B2 publication Critical patent/JP2816950B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/02Total factory control, e.g. smart factories, flexible manufacturing systems [FMS] or integrated manufacturing systems [IMS]
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/30Computing systems specially adapted for manufacturing

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【産業上の利用分野】本発明は,送電線建設に代表され
る複数の建設現場を管理・支援するためにコンピュータ
を導入した工事管理システム等に係り,詳しくは,建設
管理センターと複数の建設現場事務所と複数の建設現場
との間で一又は複数の商用通信回線を経由して相互接続
可能な構外ネットワークを構築するとともに,これらの
間で工事関連データに基づく建設管理センターからの検
査・判断結果等を送受信することにより工事管理業務,
工事技術計算業務及現場写真伝送による検査業務をオン
ライン処理し,各業務を標準化かつ迅速化して高効率に
処理するようにした送電線建設現場管理システム及び現
場写真伝送方法に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a construction management system and the like in which a computer is introduced to manage and support a plurality of construction sites represented by transmission line construction. An off-premise network that can be interconnected between the site office and a plurality of construction sites via one or more commercial communication lines is constructed, and inspection / By sending and receiving judgment results, construction management work,
The present invention relates to a transmission line construction site management system and a site photo transmission method in which a construction technology calculation operation and an inspection operation by transmitting a site photo are processed online, and each operation is standardized and speeded up so as to be processed efficiently.

【0002】[0002]

【従来の技術】まず,以下1〜5に架空送電線建設現場
を擁する電気事業者の従来的な作業体制又は管理体制を
紹介する。
2. Description of the Related Art First, a conventional work system or management system of an electric power company having an overhead power transmission line construction site will be introduced in 1 to 5 below.

【0003】1.架空送電線の特徴 架空送電線のうち超高圧の基幹送電線は,亘長数十k
m,鉄塔基数百数十基におよび,その経過地は人家,自
然公園等を避けて選定されるため,鉄塔建設位置はその
ほとんどが山間僻地の山頂部に数多く点在している。こ
のことから,建設現場までは車両で移動後さらに徒歩に
より山道をゆく(片道30分〜1時間程度)場合が多
い。
[0003] 1. Characteristics of overhead transmission lines Of the overhead transmission lines, the ultra-high-voltage main transmission lines are several tens of kilometers long.
m, there are hundreds and several dozen towers, and the transition area is selected avoiding houses and natural parks. Therefore, most of the tower construction sites are scattered on mountain peaks in remote mountainous areas. For this reason, after traveling by car to the construction site, the mountain road is often traveled on foot (about 30 minutes to one hour each way) in many cases.

【0004】2.作業体制 送電線建設時には,数多くの基礎班(10名程度の編
成),鉄塔組立班(10名程度の編成),架線班(35
名程度の編成)が,工事進捗に伴い入れ代わって各鉄塔
位置で工事をおこなっている。特に,鉄塔工事(基礎工
事,鉄塔組立工事)時にはほとんどの鉄塔位置で工事を
並行して実施することとなる。
[0004] 2. Work system At the time of transmission line construction, a number of basic teams (composition of about 10 people), a tower assembly group (composition of about 10 people), an overhead wire group (35
) Is being replaced at each tower position as the construction progresses. In particular, at the time of tower construction (foundation construction and tower assembly work), construction will be performed in parallel at most of the tower locations.

【0005】3.管理体制 送電線建設時の管理体制は,建設管理センター(1箇
所)−建設現場事務所(数箇所)−作業班(建設現場百
箇所程度)となるが,その管理要員は,広範囲で数多い
建設現場を受け持つ割には比較的少人数の場合が多い。
[0005] 3. Management system The management system for the construction of transmission lines is the construction management center (1 location)-construction site office (several locations)-work group (about 100 locations on the construction site). In many cases, the number of people is relatively small for the job.

【0006】4.工事中間検査 建設する鉄塔の品質確保のため,工事竣工後には検査で
きない箇所(埋もれて見えない箇所等)をその工事の進
捗に沿って適宜工事中間検査をおこなう必要がある。工
事中間検査の検査員は,建設管理センターの技術者が鉄
塔建設位置まで出向いておこなう現地立会検査が原則で
あるが,全てを現地立会で実施するのは困難で,一部写
真(インスタント写真)による検査で代行する場合もあ
る。いずれの場合でも,鉄塔建設位置までの往復に長時
間を要し,作業員の手待ち(検査待ち)が長く工期にも
影響する。
[0006] 4. Intermediate construction inspection In order to ensure the quality of the steel tower to be constructed, it is necessary to carry out intermediate construction inspections of parts that cannot be inspected after construction is completed (such as buried and invisible parts) as the construction progresses. In principle, the inspectors for the construction inspections are on-site inspections conducted by a technician at the construction management center to go to the tower construction site, but it is difficult to carry out all on-site inspections, and some photos (instant photos) In some cases, the inspection is performed on behalf of the client. In either case, it takes a long time to return to the tower construction position, and the operator has to wait long (wait for inspection), which affects the construction period.

【0007】5.工事中間写真の送り届け したがって,建設現場事務所の技術員が建設現場に出向
き工事中間検査用の写真を撮影して,数十km離れた建
設管理センターに送り届けて,中間検査を写真で受ける
こととなるが,検査結果を建設現場の班長に連絡・指示
するまでの時間は半日程度必要となることが多い。
[0007] 5. Construction of intermediate photo forwarded Therefore, construction site office of the technician to take a picture for the construction intermediate inspection visits to the construction site, and forwarded to construction management center was separated from each other by several tens of km, so that the receive an intermediate inspection at photo However, it often takes about half a day to report and give the inspection results to the team leader at the construction site.

【0008】上述したとおり,従来は,建設管理センタ
ーから遠方にある建設現場に専門技術者を派遣し,工事
工程上のチェックポイントを検査・判断して,その指示
により次工程に進む工事管理方法がとられていた。
As described above, conventionally, a construction management method in which a specialist is dispatched to a construction site far from the construction management center to inspect and judge a check point in the construction process, and proceed to the next process according to the instruction. Was taken.

【0009】また近年は,経費節減の観点から専門技術
者の人員を削減して,工事請負者の技術員が撮影した現
場写真(インスタント写真等)を建設管理センターまで
車などを利用して送り届けてもらい,そこで専門技術者
が検査・判断して指示を出し,その指示により次工程に
進む工事管理方法がとられる場合もあった。
In recent years, the number of professional technicians has been reduced from the viewpoint of cost reduction, and site photographs (instant photographs, etc.) taken by technicians of construction contractors have been sent to the construction management center by car or the like. In some cases, a specialist engineer inspects and makes decisions, issues instructions, and in accordance with the instructions, there is a construction management method that proceeds to the next process.

【0010】上記各方法については,建設管理センター
に多数の専門技術者を配置しておく必要があること,建
設現場事務所に業務連絡用の技術者を多数配置しておく
ことのほか,検査・判断に時間がかかり,現場作業員の
手待ち時間が長いなど,多くの問題点があった。
[0010] In each of the above methods, in addition to the fact that a large number of specialized technicians must be assigned to the construction management center, a large number of technicians for business communication are assigned to the construction site office,・ There were many problems, such as the time required for judgment and the long waiting time for field workers.

【0011】こうしたなかで,送電線建設とは工事内容
を異にするが,建設現場又は建設現場事務所と建設管理
センターにコンピュータを導入して,通信回線を介して
接続し,センター(ホスト)側で作業状況等工事全体を
管理又は支援しようとする試みがあった。
Under these circumstances, the construction is different from the construction of the transmission line, but a computer is introduced into the construction site or the construction site office and the construction management center, connected via a communication line, and connected to the center (host). There was an attempt to manage or support the entire construction such as work status on the side.

【0012】例えば,特開昭62−82455号の「作
業所管理システム」では,作業所(建設現場)における
各作業員の個人情報に基づいて作業所の管理をおこなう
とともに,各作業所に関する工程管理等のデータを収集
し,労務管理及び工程管理を集中管理しようとするもの
である。後に,このシステムにコミュニケーション手段
である「電子黒板を用いた打合せシステム」〔特開平5
−40453号〕を搭載して,異なる場所での作業打合
せ等の利用形態を提案している。
For example, in the "workplace management system" disclosed in Japanese Patent Application Laid-Open No. 62-82455, workplace management is performed based on personal information of each worker at a workplace (construction site), and a process related to each workplace is performed. The purpose is to collect data on management and to centrally manage labor management and process management. Later, in this system, "meeting system using electronic blackboard" which is a communication means [Japanese Unexamined Patent Application Publication No.
No. -40453], and proposes a use form such as work meetings at different places.

【0013】また,建設現場の作業員に小型の入出力装
置を携帯させ,工事管理を管理部(中央制御室)に集中
しようとする提案があった。〔例えば,特開平5−20
335号「作業情報現場入出力装置」及び特開平6−5
2183号「建設工事の進捗・ダメ・出来高管理システ
ム」を参照。〕
[0013] Further, there has been a proposal to carry a small input / output device to a worker at a construction site and concentrate the construction management in a management unit (main control room). [For example, see JP-A-5-20
No. 335 “Work information field input / output device” and JP-A-6-5
See No. 2183, "Construction Work Progress / Damage / Yield Management System". ]

【0014】[0014]

【発明が解決しようとする課題】しかしながら,上記従
来装置はいずれもコンピュータ支援による工事管理シス
テムの一態様といえるものであり,コンピュータを導入
した管理形態としては参考になるが,利用先固有の問題
解決を図るという点で本発明に関する示唆とはなり得な
いものである。
However, any of the above-mentioned conventional apparatuses can be said to be an embodiment of a computer-assisted construction management system, and can be referred to as a management form in which a computer is introduced. It cannot be a suggestion for the present invention in terms of solving it.

【0015】いま,本発明の送電線建設現場を擁する工
事管理に関し,固有の問題解決のための管理対象業務は
以下の3点である。 工事進捗の把握,出来高計算などの管理業務 施工計画書の作成,工事技術計算などの設計支援業務 中間検査・竣工検査などの現場写真伝送業務
Now, with regard to construction management having a transmission line construction site according to the present invention, there are the following three tasks to be managed to solve a unique problem. Management of construction progress, calculation of work volume, etc. Creation of construction plan, design support of construction technical calculation, etc. Transmission of on-site photos such as intermediate inspection and completion inspection

【0016】したがって,送電線建設現場を視野に入れ
た工事管理システムにおいては,電気事業に係る送電線
建設の経過地の地域的な広がりと現場の遠方局地性(建
設管理センターと距離が大きい)を対象としたコミュニ
ケーション手段を確立しなければならない。
Therefore, in a construction management system with a view to the transmission line construction site, the regional spread of the progress of transmission line construction related to the electric power business and the remote locality of the site (the distance to the construction management center is large) ) Must be established.

【0017】こうしたなかで本発明者らは,送電線建設
に係る建設現場事務所および/または建設現場をエンド
ユーザーとする送電線建設現場管理システムを構築する
にあたり,以下の3点を開発の基本的な考え方として鋭
意具体化に取り組んできた。
Under these circumstances, the present inventors have established the following three points in the development of a transmission line construction site management system with a construction site office and / or a construction site as an end user for transmission line construction. I have been working hard to make it concrete.

【0018】1.ネットワーク技術の利用 ネットワーク技術を利用して,中央送変電建設所・工事
所(いずれかを建設管理センターとする。)と共同企業
体(以下,JVといい,建設現場事務所として位置づけ
る。)および/または建設現場との間の意志決定・伝達
の迅速化をはかる。
[0018] 1. Utilization of network technology Using a network technology, a central transmission and substation construction site / construction site (one of which is a construction management center) and a joint venture (hereinafter referred to as JV, which is positioned as a construction site office) and // Speed up decision-making and communication with construction sites.

【0019】2.オープンシステム思想の採用 オープンシステム思想を採用して,市販ソフトウェアを
ベースツールとしたソフト開発をおこない,システムの
自由度の増大をはかる。
[0019] 2. Adoption of open system concept The open system concept is adopted to develop software based on commercially available software to increase the degree of freedom of the system.

【0020】3.グラフィカルユーザーインタフェース
(GUI)の利用 パソコンの命令・機能を直感的に判断できるようにグラ
フィックで表現し,操作の簡易化をはかる。
[0020] 3. Graphical user interface
Use of (GUI) The commands and functions of the personal computer are graphically represented so that the user can intuitively determine the commands and functions to simplify the operation.

【0021】そこで本発明はこのような事情に鑑みなさ
れたものであって,汎用性の高いシステム構築により送
電線建設に係る工事管理上固有の問題解決を図るととも
に多数点在する遠隔地とのコミュニケーション手段とし
て利用可能な送電線建設現場管理システム及び現場写真
伝送方法を提供することを目的とするものである。
The present invention has been made in view of such circumstances, and aims to solve problems inherent in construction management related to transmission line construction by constructing a highly versatile system, and to cope with many remote locations. It is an object of the present invention to provide a transmission line construction site management system and a site photo transmission method that can be used as communication means.

【0022】[0022]

【課題を解決するための手段】上記目的を達成するため
に本発明は,送電線建設に代表される複数の建設現場を
管理・支援するためにコンピュータを導入した送電線建
設現場管理システムであって,建設管理センターと複数
の建設現場事務所と複数の建設現場との間でホストとユ
ーザーの利用関係を結ぶ各所のハードウエア資源が一又
は複数の商用通信回線を介しLAN又はパーソナルコン
ピュータを相互接続可能かつ構外ネットワークを構築可
能な入出力手段及び通信制御手段を含むデータ伝送手段
と,テキストデータ処理手段と,イメージデータ処理手
段を具備するとともに,これらの間でファイル管理のた
めの補助記憶手段を介して工事管理項目処理と,工事技
術計算処理と,現場写真伝送処理の全て又は一部を共有
しオンライン処理することを特徴とするものである。
In order to achieve the above object, the present invention relates to a transmission line construction site management system in which a computer is introduced to manage and support a plurality of construction sites represented by transmission line construction. Therefore, the hardware resources at each location that establish a user-user relationship between the construction management center, the plurality of construction site offices, and the plurality of construction sites can communicate with each other via one or more commercial communication lines via a LAN or personal computer. Data transmission means including input / output means and communication control means capable of establishing a connectable and off-premise network, text data processing means, and image data processing means, and auxiliary storage means for managing files therebetween. All or part of the construction management item processing, construction technology calculation processing, and on-site photo transmission processing are shared via And it is characterized in Rukoto.

【0023】ここで,工事管理項目処理が日報処理,旬
報処理,出来高処理及び社給資材処理等であり,工事技
術計算処理が索道強度計算処理等であり,現場写真伝送
処理が作業状況及び検査箇所等の写真データの送受信処
理等であり,ファイル管理のための補助記憶手段がファ
イルサーバーであって各所のユーザー端末が建設管理セ
ンターのファイルサーバーを介して前記各処理の全て又
は一部を共有するものである。
Here, the construction management item processing is daily report processing, seasonal report processing, volume processing, company supply material processing, etc., the construction technology calculation processing is cableway strength calculation processing, etc., and the site photo transmission processing is work status and inspection. Auxiliary storage means for file management is a file server, and user terminals at various locations share all or a part of the above processing via a file server at the construction management center. Is what you do.

【0024】また,建設管理センターと複数の建設現場
事務所と複数の建設現場との間で一又は複数の商用通信
回線を経由して各所のLAN及びパーソナルコンピュー
タを相互接続可能な構外ネットワークを構築し,ホスト
とユーザー端末間でデジタルデータを送受信し工事管理
項目等の業務処理をオンライン処理するようにした送電
線建設現場管理システムにおける現場写真伝送方法であ
って,現場撮影した検査用写真をデジタルデータ処理
し,商用通信回線を介してホスト側の建設管理センター
にデータ伝送し,検査後の合否結果をデジタルデータ処
理し,商用通信回線を介してユーザー側の複数の建設現
場事務所又は複数の建設現場から検査結果を照会可能に
データベース化し,検査不合格の検査用写真に関するデ
ータを手直し工事後に合格した検査用写真に関するデー
タに更新することを特徴するものである。
In addition, an off-premise network capable of interconnecting LANs and personal computers at various locations between the construction management center, a plurality of construction site offices, and a plurality of construction sites via one or a plurality of commercial communication lines is constructed. A site photo transmission method in a transmission line construction site management system that transmits and receives digital data between a host and a user terminal and performs on-line processing of business operations such as construction management items. Data processing, data transmission to the construction management center on the host side through the commercial communication line, digital processing of the pass / fail result after inspection, and the user's multiple construction site offices or multiple A database is created so that inspection results can be queried from the construction site, and data on inspection photographs that have failed inspection has been revised and after construction Is to, wherein the updating the data relating to passing the photographic examination.

【0025】また,現場写真伝送方法が以下1)〜3)
の処理手順を包含することを特徴するものである。 1)建設現場又は建設現場事務所において,検査項目の
写真データとその内容に関する記事データを小型コンピ
ュータ及び通信回線を介して建設管理センターのファイ
ルサーバーの検査登録ファイルに伝送すること。 2)建設管理センターにおいて,上記ファイルサーバー
の検査登録ファイルの写真データをモニター表示して工
事検査し,検査結果を入力しファイルサーバーの確認状
況一覧ファイルに保管すること。 3)建設現場事務所又は建設現場において,建設管理セ
ンターのファイルサーバーの確認状況一覧ファイルを呼
出し,結果参照ファイルを作成し,検査結果に応じて建
設現場に次の作業を送信指示又は実施すること。
The method of transmitting a photograph on site is as follows:
Is characterized by including the processing procedure of (1). 1) At the construction site or construction site office, the photograph data of the inspection item and the article data relating to the content are transmitted to the inspection registration file of the file server of the construction management center via a small computer and a communication line. 2) At the construction management center, the photograph data of the inspection registration file of the file server is displayed on the monitor and inspected for the construction, and the inspection results are input and stored in the file server confirmation status list file. 3) At the construction site office or construction site, call the confirmation status list file of the file server of the construction management center, create a result reference file, and instruct or carry out the next work to the construction site according to the inspection result. .

【0026】[0026]

【作用】建設管理センターのLANと建設現場事務所の
LANと建設現場のパーソナルコンピュータを相互接続
して構外ネットワークを構築することにより,工事進捗
の把握,出来高計算などの管理項目処理と,施工計画書
の作成,工事技術計算などの設計支援処理と,中間検査
・竣工検査などの現場写真伝送処理をオンライン処理す
る。
[Function] By constructing an off-premise network by interconnecting the LAN of the construction management center, the LAN of the construction site office and the personal computer of the construction site, grasping the progress of construction, processing management items such as work volume calculation, and construction planning On-line processing of design support processing such as creation of documents and calculation of construction technology, and on-site photo transmission processing such as intermediate inspection and completion inspection.

【0027】[0027]

【実施例】本発明の一実施例を添付図面を参照して以下
説明する。ここに例示するのは架空送電線建設現場又は
その建設現場事務所をエンドユーザー(ローカル)とす
る工事管理システムであり,以下の順序で具体的に説明
する。
DESCRIPTION OF THE PREFERRED EMBODIMENTS One embodiment of the present invention will be described below with reference to the accompanying drawings. What is illustrated here is a construction management system in which the overhead transmission line construction site or the construction site office is an end user (local), and will be specifically described in the following order.

【0028】1.送電線建設現場管理システムの導入 2.通信回線の確保 3.システムの概要 4.システム概念図 5. 機器構成 6. ソフトウェア 7. 工事管理処理手順 8. 工事技術計算(索道強度計算)処理手順 9. 現場写真伝送処理手順及び写真伝送速度 (1)現場写真伝送処理手順 (2)写真伝送速度1. 1. Introduction of transmission line construction site management system 2. Secure communication lines. 3. Outline of the system System conceptual diagram 5. Equipment configuration 6. Software 7. Construction management processing procedure 8. Construction technical calculation (cableway strength calculation) processing procedure 9. Site photo transmission processing procedure and photo transmission speed (1) Site photo transmission processing procedure (2) Photo transmission speed

【0029】1.送電線建設現場管理システムの導入 本出願人の事業計画のひとつに,平成10年までに50
0kV西島根幹線,中国第二西幹線,中国第二中幹線を
初めとして総亘長約300kmの超高圧送電線の建設が
ある。これらの送電線建設時には,工事量ピークを迎え
るほか,経過地が広島県・山口県・島根県・鳥取県と広
範囲となるため,本発明の全面的な実施により,送電線
建設全般にわたる効率化・近代化が要請されている。
[0029] 1. Introduction of Transmission Line Construction Site Management System One of the applicant's business plans
There are constructions of ultra-high-voltage transmission lines with a total length of about 300 km, including the 0 kV Nishi-Shimane trunk line, the China Second West trunk line, and the China Second Central trunk line. At the time of construction of these transmission lines, the construction volume will reach its peak, and the progress will be widespread in Hiroshima, Yamaguchi, Shimane and Tottori prefectures.・ Modernization is required.

【0030】現在の実施状況からして,本発明システム
の導入先では当初の目的を十分果たしており,エンハン
スが切望されている。図1は実施例ブロック図である。
ここで,1が入力手段(出力手段は図示省略),2
(2')がデータ伝送手段,3がテキストデータ処理手段
(プロセッサ),4がイメージデータ処理手段(プロセ
ッサ)及び5が補助記憶手段(ファイルサーバー)であ
る。また,図2は建設管理センター,建設現場事務所及
び建設現場の位置関係を例示する説明図である。
In view of the current state of implementation, the destination of the system of the present invention has sufficiently fulfilled its original purpose, and there is a strong need for enhancement. FIG. 1 is a block diagram of the embodiment.
Here, 1 is input means (output means is not shown), 2
(2 ') is a data transmission means, 3 is a text data processing means (processor), 4 is an image data processing means (processor), and 5 is an auxiliary storage means (file server). FIG. 2 is an explanatory view exemplifying the positional relationship between the construction management center, the construction site office and the construction site.

【0031】2.通信回線の確保 本発明システムの実現にあたり,システムのハード,ソ
フトのほか通信回線の確保が不可欠となるが,アナログ
回線,デジタル回線,通信衛星回線などのいずれかの回
線が選択自在に利用できるので,十分効果的な運用が期
待できる。
2. Securing of communication line In order to realize the system of the present invention, it is indispensable to secure the communication line in addition to the hardware and software of the system. However, any one of analog line, digital line and communication satellite line can be used freely. , Can be expected to operate effectively.

【0032】さらに効率的な運用をはかるため,通信所
要時間の短縮対策として,ファイル転送型バーストモー
ドなどのデータ圧縮技術の利用並びに無人発信,回線自
動切断等の機能を付加して装置操作の不慣れ対策,話中
対策,送信者不在対策を実施し効率を上げている。
In order to achieve more efficient operation, as a countermeasure for shortening the communication required time, use of data compression technology such as a file transfer type burst mode and addition of functions such as unattended transmission and automatic line disconnection make the device operation unfamiliar. Measures are taken, busy, and sender absent to improve efficiency.

【0033】3.システムの概要 システムの概要を表1に示し,各業務項目(処理項目)
における機能概要及び開発の目的効果を掲げる。
[0033]3. System overview  Table 1 shows an overview of the system, and each business item (processing item)
The outline of the function and the purpose and effect of the development are listed.

【0034】[0034]

【表1】 [Table 1]

【0035】4.システム概念図 図3に処理機能からみたシステム概念図を示すとおり,
建設管理センターのLANと建設現場事務所のLANと
建設現場のパーソナルコンピュータを相互接続して構外
ネットワークを構築することにより,工事進捗の把握,
出来高計算などの管理項目処理と,施工計画書の作成,
工事技術計算などの設計支援処理と,中間検査・竣工検
査などの現場写真伝送処理をオンライン処理するもので
ある。
[0035] 4. As shown the system conceptual view seen from the processing function to the system conceptual diagram 3,
The construction management center LAN, the construction site office LAN, and the construction site personal computer are interconnected to construct an off-premise network, so that the progress of construction can be grasped.
Management item processing such as yield calculation, construction plan creation,
On-line processing of design support processing such as construction technology calculation and on-site photo transmission processing such as intermediate inspection and completion inspection.

【0036】5. 機器構成 図4に建設現場の装置構成概要図,及び図5に建設管理
センターの装置構成概要図を示す。また,図6に構外ネ
ットワークを構築したシステム構成図,及び図7にその
概念図を示す。
5. Device Configuration FIG. 4 is a schematic diagram of the device configuration at the construction site, and FIG. 5 is a schematic diagram of the device configuration of the construction management center. FIG. 6 shows a system configuration diagram in which an off-premise network is constructed, and FIG. 7 shows a conceptual diagram thereof.

【0037】図示するように,本発明の特徴的構成は,
送電線建設に代表される複数の建設現場を管理・支援す
るためにコンピュータを導入した送電線建設現場管理シ
ステムであって,建設管理センターと複数の建設現場事
務所と複数の建設現場との間でホストとユーザーの利用
関係を結ぶ各所のハードウエア資源が一又は複数の商用
通信回線を介しLAN又はパーソナルコンピュータを相
互接続可能かつ構外ネットワークを構築可能な入出力手
段(1)及び通信制御手段を含むデータ伝送手段(2)
と,テキストデータ処理手段(3)と,イメージデータ
処理手段(4)を具備するとともに,これらの間でファ
イル管理のための補助記憶手段(5)を介して工事管理
項目処理と,工事技術計算処理と,現場写真伝送処理の
全て又は一部を共有しオンライン処理するものである。
As shown, the characteristic structure of the present invention is as follows.
A transmission line construction site management system that introduces a computer to manage and support a plurality of construction sites represented by transmission line construction. The system includes a construction management center, a plurality of construction site offices, and a plurality of construction sites. The input / output means (1) and the communication control means capable of interconnecting a LAN or a personal computer through one or a plurality of commercial communication lines and establishing an off-premise network can be provided with hardware resources at various places connecting the host and the user. Data transmission means including (2)
, Text data processing means (3), and image data processing means (4), among which construction management item processing and construction technology calculation via an auxiliary storage means (5) for file management. All or part of the processing and on-site photograph transmission processing are shared and processed online.

【0038】6. ソフトウェア この説明は省略する。 6. Software This description is omitted.

【0039】7. 工事管理処理手順 工事管理処理項目のうち日報処理に関する建設管理セン
ターと建設現場事務所間の処理手順を表2に示す。
7. Construction Management Processing Procedure Table 2 shows the processing procedure between the construction management center and the construction site office regarding the daily report processing among the construction management processing items.

【0040】[0040]

【表2】 [Table 2]

【0041】工事管理処理項目のうち出来高処理に関す
る建設管理センターと建設現場事務所間の処理手順を表
3に示す。
Table 3 shows the processing procedure between the construction management center and the construction site office regarding the work volume processing among the construction management processing items.

【0042】[0042]

【表3】 [Table 3]

【0043】8. 工事技術計算(索道強度計算)処理手
工事技術計算(索道強度計算)に関する建設管理センタ
ーと建設現場事務所間の処理手順を表4に示す。
8. Processing technology calculation (cableway strength calculation)
Table 4 shows the processing procedure between the construction management center and the construction site office regarding the forward construction technology calculation (cordway strength calculation).

【0044】[0044]

【表4】 [Table 4]

【0045】9. 現場写真伝送処理手順及び写真伝送速
(1)現場写真伝送処理手順(以下〜)
9. On-site photo transmission processing procedure and photo transmission speed
Degree (1) On-site photo transmission processing procedure (below-)

【0046】建設現場における以下の処理; デジタルカードカメラにより検査項目の写真を撮影し
た後,このカメラを液晶テレビに接続し,写真の内容,
写り具合等を確認する。 写真データとその内容に関する記事データを入出力装
置を介して携帯可能な小型コンピュータ内の記憶装置に
格納する。
The following processing at the construction site: After taking a photograph of the inspection item using a digital card camera, this camera is connected to an LCD television, and the contents of the photograph
Check the image quality. Photo data and article data relating to the content are stored in a storage device in a portable small computer via an input / output device.

【0047】建設現場又は建設現場事務所における以下
(共通)の処理;建設現場において, 小型コンピュータ(ノートパソコン)を通信回線に接
続して写真データ及び記事データを建設管理センターの
ファイルサーバーの検査登録ファイルに伝送する。
At the construction site or construction site office, the following (common) processing: At the construction site, a small computer (notebook personal computer) is connected to a communication line and the photograph data and article data are registered for inspection in the file server of the construction management center. Transmit to file.

【0048】又は建設現場事務所において, 小型コンピュータに上記写真データとその内容に関す
る記事データを取り込み,通信回線に接続して写真デー
タ及び記事データを建設管理センターのファイルサーバ
ーの検査登録ファイルに伝送する。
Alternatively, at the construction site office, the above-mentioned photograph data and article data relating to the contents are taken into a small computer and connected to a communication line to transmit the photograph data and article data to the inspection registration file of the file server of the construction management center. .

【0049】建設管理センターにおける以下の処
理; 検査者が,ファイルサーバーの検査登録ファイルの写
真データをモニターに写し出して工事検査をおこなう。 検査結果,例えば検査者氏名と,検査合格の○,不合
格の×及び写真不鮮明の△等を入力しファイルサーバー
の確認状況一覧ファイルとして保管する。
The following processing in the construction management center: The inspector projects the photograph data of the inspection registration file of the file server on the monitor and performs the construction inspection. Inspection results, for example, the name of the inspector, ○ for inspection pass, X for rejection, Δ for unclear photograph, etc. are entered and stored as a check status list file of the file server.

【0050】建設現場事務所又は建設現場における以下
(共通)の処理;建設現場事務所において, 建設現場事務所において,小型コンピュータを通信回
線に接続して建設管理センターのファイルサーバーの確
認状況一覧ファイルを呼出し,結果参照ファイルを作成
する。 結果参照ファイルの検査結果に応じて建設現場に次の
作業指示を送信する。
At the construction site office or at the construction site, the following (common) processing: at the construction site office, at the construction site office, a small computer is connected to the communication line, and the confirmation status list file of the file server at the construction management center And create a result reference file. The next work instruction is transmitted to the construction site according to the inspection result of the result reference file.

【0051】又は建設現場において, 建設現場において,携帯可能な小型コンピュータを通
信回線に接続して上記作業指示を受信するか又は建設管
理センターのファイルサーバーの確認状況一覧ファイル
を呼出して結果参照ファイルを作成する。 結果参照ファイルの検査結果に応じて次の作業を実施
する。
Alternatively, at the construction site, at the construction site, a portable small computer is connected to the communication line to receive the work instruction, or the confirmation status list file of the file server of the construction management center is called to retrieve the result reference file. create. Perform the following operations according to the inspection result of the result reference file.

【0052】上記処理手順を表5にまとめる。Table 5 summarizes the above processing procedure.

【0053】[0053]

【表5】 [Table 5]

【0054】(2)写真伝送速度 写真伝送速度の一例を表5に示す。(2) Photo transmission speed Table 5 shows an example of the photo transmission speed.

【0055】[0055]

【表6】 [Table 6]

【0056】図8は本発明システムにおける現場写真伝
送方法の図による説明図である。
FIG. 8 is an explanatory diagram showing a method of transmitting a photograph of a site in the system of the present invention.

【0057】[0057]

【発明の効果】本発明は以上の構成よりなるものであ
り,これによれば工事管理業務,工事設計業務及び検査
業務の迅速化,効率化及び省力化が果たせる。特に,現
場写真伝送処理による検査時間の大幅短縮及び作業員の
手待ち解消が図れるので,遠隔地の建設現場とのコミュ
ニケーション及びそのためのコスト低減等,経済効果を
含む運用上の効果は極めて高い。
The present invention has the above-mentioned configuration, and according to the present invention, construction management work, construction design work and inspection work can be speeded up, made more efficient and labor-saving. In particular, since the inspection time can be greatly reduced by the on-site photograph transmission processing and the waiting time of the operator can be eliminated, the operational effects including the economic effects such as communication with the remote construction site and the cost reduction for the same are extremely high.

【0058】また,本発明システムのエンドユーザーが
滞在している間は,災害時における写真伝送等情報収集
への活用が可能であり,その他システム稼働時の空き時
間の利用先を拡張することができる。
Further, while the end user of the system of the present invention is staying, the system can be utilized for information collection such as photograph transmission at the time of disaster, and the use destination of the idle time when the system is operating can be expanded. it can.

【0059】さらに,本発明システムの導入により,職
場(送電線建設現場)の合理化及び活性化と,若年層
(未熟練者)の現場教育及び雇用促進が期待できる。
Furthermore, by introducing the system of the present invention, the rationalization and activation of the workplace (transmission line construction site) and the on-site education and employment promotion of young people (unskilled persons) can be expected.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明システムの実施例ブロック図である。FIG. 1 is a block diagram of an embodiment of the system of the present invention.

【図2】建設管理センター,建設現場事務所及び建設現
場の位置関係を例示する説明図である。
FIG. 2 is an explanatory diagram illustrating a positional relationship between a construction management center, a construction site office, and a construction site.

【図3】処理機能からみたシステム概念図である。FIG. 3 is a conceptual diagram of a system viewed from a processing function.

【図4】建設現場の装置構成概略図である。FIG. 4 is a schematic diagram of an apparatus configuration at a construction site.

【図5】建設管理センターの装置構成概略図である。FIG. 5 is a schematic diagram of an apparatus configuration of a construction management center.

【図6】構外ネットワークを構築したシステム構成図で
ある。
FIG. 6 is a system configuration diagram in which an off-premise network is constructed.

【図7】構外ネットワークの概念図である。FIG. 7 is a conceptual diagram of an off-premise network.

【図8】本発明システムにおける現場写真伝送方法を示
す説明図である。
FIG. 8 is an explanatory diagram showing a method for transmitting a photograph of a site in the system of the present invention.

【符号の説明】[Explanation of symbols]

1 入力手段(出力手段は図示省略) 2,2' データ伝送手段 3 テキストデータ処理手段(プロセッサ) 4 イメージデータ処理手段(プロセッサ) 5 補助記憶手段(ファイルサーバー) DESCRIPTION OF SYMBOLS 1 Input means (output means are not shown) 2, 2 'Data transmission means 3 Text data processing means (processor) 4 Image data processing means (processor) 5 Auxiliary storage means (file server)

───────────────────────────────────────────────────── フロントページの続き (58)調査した分野(Int.Cl.6,DB名) E04G 21/00 G06F 15/21──────────────────────────────────────────────────続 き Continued on the front page (58) Field surveyed (Int.Cl. 6 , DB name) E04G 21/00 G06F 15/21

Claims (3)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 送電線建設に代表される複数の建設現場
を管理・支援するためにコンピュータを導入した工事管
理システムにおいて, 建設管理センターと複数の建設現場事務所と複数の建設
現場との間でホストとユーザーの利用関係を結ぶ各所
のハードウエア資源が一又は複数の商用通信回線を介
しLAN又はパーソナルコンピュータを相互接続可能か
つ構外ネットワークを構築可能な入出力手段及び通信制
御手段を含むデータ伝送手段と,テキストデータ処理手
段と,イメージデータ処理手段を具備するとともに, これらの間で建設管理センターに設置したファイルサー
バーを介して,日報処理,旬報処理,出来高処理及び社
給資材処理等の工事管理項目処理と,索道強度計算処理
等の工事技術計算処理と,作業状況及び検査箇所等の検
査用写真のデータ処理を含む現場写真伝送処理の全て又
は一部を共有しオンライン処理することを特徴とする送
電線建設現場管理システム。
1. A construction management system in which a computer is introduced to manage and support a plurality of construction sites typified by transmission line construction, wherein a construction management center, a plurality of construction site offices, and a plurality of construction sites are connected. in, hardware resources each place connecting the use relationship of the host and user, including output means and communication control means capable of constructing the interconnectable and off-premises network LAN or a personal computer via one or more commercial communication line It has data transmission means, text data processing means, and image data processing means, and a file server installed at the construction management center between them.
Through the bar, daily report processing, seasonal report processing, volume processing and company
Construction management item processing such as supply material processing and cableway strength calculation processing
And construction technology calculation processing etc., Ken, such as working conditions and inspection points
A transmission line construction site management system characterized in that all or a part of the site photo transmission process including data processing of inspection photos is shared and processed online.
【請求項2】 請求項1記載の送電線建設現場管理シス
テムにおける現場写真伝送方法であって,現場写真をもって代行する検査業務をコンピュータを援
用して実行処理するために, ユーザー側の複数の建設現場事務所又は建設現場におい
現場撮影した工事中間検査や竣工検査等の検査用写真
それぞれデジタルデータ処理しホスト側の建設管理
センターにデータ伝送し,建設管理センターにおいて,前記検査用写真データを収
録し,各別に表示して目視検査後,その合否を含む各検
査結果をデジタルデータ処理し,データベース化すると
ともに,検査不合格に係る箇所の手直し工事後にデータ
更新し, それぞれの建設現場事務所又は建設現場から前記データ
ベースにアクセスして検査結果を照会・確認する ことを
特徴する現場写真伝送方法。
2. A method for transmitting a photograph of a site in a transmission line construction site management system according to claim 1 , wherein a computer assists inspection work on behalf of the site photograph.
In order to use and execute the process, it is necessary to use multiple construction site offices or construction sites on the user side.
Data Transmission in construction management center of the host side and each digital data processing photographic inspection of such sites photographed construction intermediate inspection and completion inspection Te, the construction management center, yield the inspection photo data
After each inspection, including the pass / fail status,
Digitally processing the inspection results and creating a database
In both cases, data was obtained after repair work on the location related to the inspection failure
Update the data from each construction site office or construction site
An on- site photo transmission method characterized by accessing the base and checking and confirming the inspection results .
【請求項3】 建設管理センターと複数の建設現場事務
所と複数の建設現場との間で一又は複数の商用通信回線
を経由して各所のLAN及びパーソナルコンピュータを
相互接続可能な構外ネットワークを構築し,ホストとユ
ーザー端末間で送受信し工事管理項目等の業務処理をオ
ンライン処理するようにした送電線建設現場管理システ
ムにおける現場写真伝送方法であって,以下1)〜3)
の処理手順を包含することを特徴する現場写真伝送方
法。 1)建設現場又は建設現場事務所において,検査項目の
写真データとその内容に関する記事データを小型コンピ
ュータ及び通信回線を介して建設管理センターのファイ
ルサーバーの検査登録ファイルに伝送すること。 2)建設管理センターにおいて,上記ファイルサーバー
の検査登録ファイルの写真データをモニター表示して工
事検査し,検査結果を入力しファイルサーバーの確認状
況一覧ファイルに保管すること。 3)建設現場事務所又は建設現場において,建設管理セ
ンターのファイルサーバーの確認状況一覧ファイルを呼
出し,結果参照ファイルを作成し,検査結果に応じて建
設現場に次の作業を送信指示又は実施すること。
3. An off-premise network capable of interconnecting LANs and personal computers at various locations between a construction management center, a plurality of construction site offices, and a plurality of construction sites via one or more commercial communication lines. A method for transmitting a photograph of a site in a transmission line construction site management system in which business processes such as construction management items are transmitted and received between a host and a user terminal and processed online, the following 1) to 3)
A method for transmitting an on-site photograph, comprising: 1) At the construction site or construction site office, the photograph data of the inspection item and the article data relating to the content are transmitted to the inspection registration file of the file server of the construction management center via a small computer and a communication line. 2) At the construction management center, the photograph data of the inspection registration file of the file server is displayed on the monitor and inspected for the construction, and the inspection results are input and stored in the file server confirmation status list file. 3) At the construction site office or construction site, call the confirmation status list file of the file server of the construction management center, create a result reference file, and instruct or carry out the next work to the construction site according to the inspection result. .
JP17147595A 1995-06-13 1995-06-13 Transmission line construction site management system and site photo transmission method Expired - Lifetime JP2816950B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP17147595A JP2816950B2 (en) 1995-06-13 1995-06-13 Transmission line construction site management system and site photo transmission method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP17147595A JP2816950B2 (en) 1995-06-13 1995-06-13 Transmission line construction site management system and site photo transmission method

Publications (2)

Publication Number Publication Date
JPH08338133A JPH08338133A (en) 1996-12-24
JP2816950B2 true JP2816950B2 (en) 1998-10-27

Family

ID=15923800

Family Applications (1)

Application Number Title Priority Date Filing Date
JP17147595A Expired - Lifetime JP2816950B2 (en) 1995-06-13 1995-06-13 Transmission line construction site management system and site photo transmission method

Country Status (1)

Country Link
JP (1) JP2816950B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002213080A (en) * 2001-01-16 2002-07-31 Pc Network Plaza:Kk Work management method for construction work

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001297144A (en) * 2000-04-13 2001-10-26 Pc Network Plaza:Kk Method for managing execution verification picture of property under construction
JP2002032430A (en) * 2000-07-14 2002-01-31 Pc Network Plaza:Kk Method for browsing construction verification photograph
US6842534B1 (en) * 2000-09-28 2005-01-11 Itt Manufacturing Enterprises, Inc. Detecting material failures in ground locations

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH05242157A (en) * 1992-02-27 1993-09-21 Sekisui House Ltd Method for retrieving and displaying building photograph
JPH05282330A (en) * 1992-03-31 1993-10-29 Misawa Homes Co Ltd Construction process progress control system
JP2848553B2 (en) * 1993-12-24 1999-01-20 日本電信電話株式会社 Construction work progress management method and system
JPH07247688A (en) * 1994-03-03 1995-09-26 Shimizu Corp Work plan control system based on 3-dimensional data

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002213080A (en) * 2001-01-16 2002-07-31 Pc Network Plaza:Kk Work management method for construction work

Also Published As

Publication number Publication date
JPH08338133A (en) 1996-12-24

Similar Documents

Publication Publication Date Title
CN110276530A (en) A kind of intelligent engineering operation and maintenance supervising method
US9589243B2 (en) Field management and mobile inspection
US6961586B2 (en) Field assessments using handheld data management devices
CN105303306B (en) Electric power material dispatching platform system
CN110147417A (en) Expressway works construction supervision unified platform
JPH1185853A (en) Coping system for recovery from disaster
CN107886287A (en) A kind of decoration construction work Self management system and its control method
CN107423826A (en) A kind of method for inspecting of multi-reservoir, device and system
CN112288903A (en) Card punching system, method and equipment
JP4170000B2 (en) Device connection management system
JP4637729B2 (en) Information processing method, information processing apparatus, and program
JP2816950B2 (en) Transmission line construction site management system and site photo transmission method
JP2002319050A (en) Patrol management system, patrol management method, management device and program
JP2004054716A (en) Work management method and display method for work
JP2004126808A (en) Difficulty categorized subject classifying task supporting device and method, and difficulty categorized subject classifying task supporting program and system
JP7368937B2 (en) Equipment management system
CN208889013U (en) A kind of low-voltage collecting meter reading O&M whole process managing and control system
JP2002004580A (en) Construction quality inspecting system
CN112132300A (en) Transformer substation maintenance method, device and system
CN111585345A (en) Intelligent patrol system for distribution network
Hope et al. Improving co-operative working in the utility industry through mobile context aware geographic information systems
KR20040057068A (en) Integration and superintendence managing system and its method of construction in the network configuration
JP2003233646A (en) Document data linkage method, document data linkage program, document data linkage device and record medium
CN111354071A (en) Internet + -based augmented reality transformer substation and visual archive management method
CN109214775A (en) A kind of information system based on cell phone client

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20080821

Year of fee payment: 10

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20080821

Year of fee payment: 10

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090821

Year of fee payment: 11

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100821

Year of fee payment: 12

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100821

Year of fee payment: 12

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100821

Year of fee payment: 12

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110821

Year of fee payment: 13

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110821

Year of fee payment: 13

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110821

Year of fee payment: 13

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120821

Year of fee payment: 14

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120821

Year of fee payment: 14

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130821

Year of fee payment: 15

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

EXPY Cancellation because of completion of term