CN1364961A CN 02104259 CN02104259A CN1364961A CN 1364961 A CN1364961 A CN 1364961A CN 02104259 CN02104259 CN 02104259 CN 02104259 A CN02104259 A CN 02104259A CN 1364961 A CN1364961 A CN 1364961A
Authority
CN
China
Prior art keywords
immersed tube
pile
foundation
filler
cement
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN 02104259
Other languages
Chinese (zh)
Inventor
王光明
王恩远
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
WANG GUANGMIGN
Original Assignee
WANG GUANGMIGN
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by WANG GUANGMIGN filed Critical WANG GUANGMIGN
Priority to CN 02104259 priority Critical patent/CN1364961A/en
Publication of CN1364961A publication Critical patent/CN1364961A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The foundation reinforcing method for loose and soft soil includes depositing straight sunken tube into loose and soft soil through vibration or other process, throwing stuffing, such as sand and stone, mine refuse, clay, etc. mixed with cement and water, into the sunken tube, hammering to density and form piles, and final spreading stuffing cushion in the top of the piles to form composite foundation with high strength cement piles. The method is simple in construction and low in cost, and has wide application range and no environmental pollution.

Description

A kind of foundation reinforcement method
Technical field
The present invention relates to a kind of foundation reinforcement method that is used for soft soil horizon.
Background technology
At present in construction work, processing to soft foundations such as mud, mucky soil, loosening sand, silt, cohesive soil, plain fill, miscellaneous fills, except that adopting pile foundation, still can adopt vertical enhancing bluk recombination ground to carry out consolidation process, the vibrosinking pile method is particularly arranged, the sand-gravel pile method, CFG method, cement-soil paddling process etc.But existing pile reinforcement means such as the disclosed construction technology of Chinese patent CN1153847A " a kind of concrete pipe base construction technology and equipment " have following steps: the pore-forming of A. pile body and last load dish, the making of B, force-bearing table, C, the making of load dish down, D, descending reinforcing cage, the fluid concrete pile.The construction equipment of this pile foundation comprises casing, and there is the last load disc molding punch plate of a reverse frustoconic its stack shell upper end, places below the charge door.With the efficient compacted steel concrete bearing peg of this worker's method and equipment construction, bearing capacity is big, but construction the time need be adopted special casing, and needs dig a hole in advance on ground, and pile body is a steel concrete, and cost is higher, and influence is promoted the use of.The also many defectiveness of other worker's method.
Summary of the invention
The objective of the invention is to reinforce worker's method restricted application at existing pile, the pile quality instability, intensity is lower, construction technology equipment requires and the cost height, and the shortcoming of unfavorable popularization provides a kind of being applicable to reinforce various soft foundations, job practices is easy, do not need special equipment, cost is low, the foundation reinforcement method that consolidation effect is good.
Foundation reinforcement method of the present invention is as follows:
A, treating on the consolidated subsoil immersed tube to be inserted foundation soil to projected depth,
B, in immersed tube, drop into and have the filler of cement, and use the tamping pile,
C, extract immersed tube, pile body sclerosis back forms cement high bond strength pile composite foundation.
In the ground stabilization process, the filler that drops in immersed tube can be gathered materials on the spot, and adopts various sandstone material. the ore deposit quarrel. and native aggregate chips or clay.With the cement of going into be the 1/10-1/5 of filler weight, and mix the water of the 1/10-1/8 of filler weight.
For making immersed tube enter foundation soil, can the taper shoe be set in straight barrel type immersed tube lower end, vibration sinking tube makes it into foundation soil; Also can be at immersed tube lower end filling fragment of brick, impact in pipe with weight, form the brick plug that only becomes silted up after, continuation impact brick plug makes immersed tube fill in foundation soil with brick; Can also impact the foundation soil pore-forming with pile monkey in immersed tube, static pressure, immersed tube is gone into foundation soil simultaneously.
The pile mode both can be in immersed tube fed batch, the immersed tube pile is extracted in compaction in layers at last; Also can fed batch hammering in immersed tube, the layering tube drawing rams and expands pile.
After treating on the consolidated subsoil to make the stake of whole cement high bond strength by design stake position, can more than the design elevation of stake top, will make the filler mattress layer with the filler tiling compacting that cement and water are arranged, form cement high bond strength pile composite foundation.
This worker method is with simple and easy construction equipments such as straight barrel type immersed tube, post hammers, ramming the expansion filler by the post hammer obtains higher pile strength and enlarges the stake footpath, in formation of pile, inter-pile soil obtains compacted, thereby raising consolidation effect, because filler is interior and cement is arranged, thereby can solidify to form the high bond strength pile composite foundation.These worker's method materials are extensive, can gather materials on the spot, and cost is low, and the pile strength height does not have mud and discharges during construction, free from environmental pollution, has wide range of applications.
Description of drawings
The cement high bond strength pile composite foundation schematic diagram that Fig. 1 forms for foundation reinforcement method of the present invention
Fig. 2 is the immersed tube schematic diagram of band shoe
Fig. 3 is the immersed tube schematic diagram of band brick plug
Fig. 4 is the punching of post hammer, the static pressure, immersed tube schematic diagram that buries
Fig. 5 is a fed batch, and immersed tube pile schematic diagram is extracted in compaction in layers at last
Fig. 6 is a fed batch, hammering. the layering tube drawing. and ram and expand among the pile schematic diagram figure, 1 filler mattress layer, 2 cement high bond strength stakes, 3 soft foundations, 4 straight barrel type immersed tube, 5 shoes, 6 posts hammer, 7 brick plugs, 8 fillers, 9 rubbles
The specific embodiment
Arrange that the stake position inserts ground 3 to projected depth with immersed tube 4 waiting to reinforce on the soft foundation 3, generally can reach about 15 meters.The immersed tube mode can be following several one of.
A. in straight barrel type immersed tube 4 lower ends taper shoe 5 is set, vibrates 4 immersed tube then, make it to go deep into soft foundation soil 3,
B. impact earlier at immersed tube 4 lower end filling fragments of brick, and with post hammer 6, make fragment of brick jam-pack immersed tube 4 lower ends, form the brick plug 7 that only becomes silted up, continue impact brick plug 7 then, make immersed tube 4 enter foundation soil 3 with brick plug 7,
C. impact foundation soil 3 pore-formings with post hammer 6 in immersed tube 4, static pressure, immersed tube 4 enters foundation soil 3 simultaneously,
When immersed tube 4 enters foundation soil 3 to projected depth, in immersed tube 4, drop into filler 8 in batches, hammer 6 compactions in layers into shape with post, last tube drawing pile; Also can be in immersed tube 4 fed batch, hammering, layering tube drawing, compacting pile.Also can drop into rubble 9 rammer expansions before fed batch earlier in immersed tube 4 builds at the end.The filler 8 that drops in immersed tube 4 is gathered materials on the spot as far as possible, can be sandstone material, ore deposit quarrel, native aggregate chips, clay etc., simultaneously with the cement of going into to account for filler weight 1/10-1/5 and the water that accounts for filler weight 1/10-1/8, can also wait to reinforce more than the stake top design elevation of soft foundation 3 at last, will with the filler that cement and water are arranged, filler mattress layer 1 is made in the tiling compacting, thereby forms cement high bond strength pile composite foundation.

Claims (5)

1, a kind of foundation reinforcement method is characterized in that:
A, treating on the consolidated subsoil immersed tube to be gone into foundation soil to projected depth,
B, in immersed tube, drop into and have the filler of cement and water, and use the tamping pile,
C, extract immersed tube, pile body sclerosis back forms cement high bond strength pile composite foundation.
2, according to claim 1 described foundation reinforcement method, it is characterized in that the said filler that drops into is the sandstone material in immersed tube, or slag, or native aggregate chips, or clay and the cement of going into is the 1/10-1/5 of filler weight, mixes the water of filler weight 1/10-1/8 simultaneously.
3, according to claim 1 described foundation reinforcement method, it is characterized in that the said mode that immersed tube is sunk to foundation soil be following several one of:
A, the tapered pile boots are set under immersed tube, vibration sinking tube is gone into foundation soil;
B, at immersed tube lower end filling fragment of brick, form the brick plug that only becomes silted up with the post hammering blow, continue the impact brick plug, make immersed tube fill in foundation soil with brick;
C, in immersed tube with post hammering blow foundation soil pore-forming, simultaneously static pressure, immersed tube is gone into foundation soil.
4,, it is characterized in that described pile mode is one of following two kinds according to claim 1 or 3 described foundation reinforcement methods:
A, in immersed tube fed batch, the immersed tube pile is extracted in compaction in layers at last;
B, fed batch hammering in immersed tube, the layering tube drawing rams and expands pile.
5, according to claim 1 described foundation reinforcement method, base is characterised in that more than the design elevation of stake top will manufacture the filler mattress layer with the filler tiling compacting that cement and water are arranged, and form cement high bond strength pile composite foundation.
CN 02104259 2002-02-28 2002-02-28 Foundation reinforcing mode Pending CN1364961A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 02104259 CN1364961A (en) 2002-02-28 2002-02-28 Foundation reinforcing mode

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 02104259 CN1364961A (en) 2002-02-28 2002-02-28 Foundation reinforcing mode

Publications (1)

Publication Number Publication Date
CN1364961A true CN1364961A (en) 2002-08-21

Family

ID=4740053

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 02104259 Pending CN1364961A (en) 2002-02-28 2002-02-28 Foundation reinforcing mode

Country Status (1)

Country Link
CN (1) CN1364961A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN100424272C (en) * 2006-07-11 2008-10-08 南京工业大学 Composite foundation prestress construction method for granular material static pressure pile
CN102864712A (en) * 2012-10-16 2013-01-09 中铁第四勘察设计院集团有限公司 Method and structure for micro-disturbance renovating of existing high speed railway subgrade deformation disease
CN104695417A (en) * 2015-01-19 2015-06-10 上海市政工程设计研究总院(集团)有限公司 Post-grouting gravel pile composite foundation, post-grouting gravel pile and manufacturing method of post-grouting gravel pile
CN105113478A (en) * 2015-08-31 2015-12-02 山东省城乡建设勘察设计研究院 Dynamic compaction treatment method of deep foundation displacement
CN105714773A (en) * 2016-03-01 2016-06-29 江苏东合南岩土科技股份有限公司 Foundation treatment method
CN113969577A (en) * 2021-11-29 2022-01-25 何学礼 Pile sinking construction method for precast pile

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN100424272C (en) * 2006-07-11 2008-10-08 南京工业大学 Composite foundation prestress construction method for granular material static pressure pile
CN102864712A (en) * 2012-10-16 2013-01-09 中铁第四勘察设计院集团有限公司 Method and structure for micro-disturbance renovating of existing high speed railway subgrade deformation disease
CN102864712B (en) * 2012-10-16 2014-11-26 中铁第四勘察设计院集团有限公司 Method and structure for micro-disturbance renovating of existing high speed railway subgrade deformation disease
CN104695417A (en) * 2015-01-19 2015-06-10 上海市政工程设计研究总院(集团)有限公司 Post-grouting gravel pile composite foundation, post-grouting gravel pile and manufacturing method of post-grouting gravel pile
CN104695417B (en) * 2015-01-19 2017-03-01 上海市政工程设计研究总院(集团)有限公司 A kind of manufacture method of grouting behind shaft or drift lining broken stone pile
CN105113478A (en) * 2015-08-31 2015-12-02 山东省城乡建设勘察设计研究院 Dynamic compaction treatment method of deep foundation displacement
CN105714773A (en) * 2016-03-01 2016-06-29 江苏东合南岩土科技股份有限公司 Foundation treatment method
CN113969577A (en) * 2021-11-29 2022-01-25 何学礼 Pile sinking construction method for precast pile

Similar Documents

Publication Publication Date Title
Smoltczyk Geotechnical Engineering Handbook, Procedures
CN108914912A (en) A kind of Foundation Treatment engineering method of column-hammer forced tamping displacement
CN100441781C (en) Salinized-soil-strong tamping and water-discharging pile foundation processing method
KR100762991B1 (en) Precast piling method injected with high-strength mortar
CN104746505A (en) Method for treating miscellaneous fill foundation combing dynamic consolidation and compaction grouting
CN106522191A (en) Transformer substation foundation treatment method and application thereof
CN105714773A (en) Foundation treatment method
CN102400462A (en) Secondary grouting small pile construction process in foundation anti-seismic reinforcement treatment
CN104329020B (en) A kind of reinforced long spire embedding rock construction equipment and technique thereof
CN1052284C (en) Method for construction of concrete pile
CN1621626A (en) Construction method for concrete pile
CN1743561A (en) Column-hammer forced tamping substitution method
CN102251514A (en) Multi-section type variable cross-section dynamic compaction method
CN101349052A (en) Saline soil area combined drain system and combined water drain forced ramming foundation treating method thereof
CN1137314C (en) Construction method of concrete pile
CN201339186Y (en) Soft rock concrete replacement pile composite foundation
CN1364961A (en) Foundation reinforcing mode
CN1030581C (en) Foundation treatment method and special equipment thereof
CN1563604A (en) Construction method for concrete pile
RU2275470C1 (en) Method of floating pile load-bearing capacity increase
HU225407B1 (en) Procedure for augmentation physical parameters and bearing capacity of ground and for diminution time of consolidation and expected consolidation settlement of thereof
CN205776209U (en) The construction equipment of concrete-pile
CN1047716A (en) Utilize the method and the facility of industrial residue comprehensive treatment soft foundation
CN1095517C (en) Method for reinforcement of foundation ground
CN1076064C (en) Method for handling foundation

Legal Events

Date Code Title Description
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C06 Publication
PB01 Publication
C02 Deemed withdrawal of patent application after publication (patent law 2001)