CN1253198A - Method for suspending guys of twisted steel cable for cable stayed bridge - Google Patents

Method for suspending guys of twisted steel cable for cable stayed bridge Download PDF

Info

Publication number
CN1253198A
CN1253198A CN 98121419 CN98121419A CN1253198A CN 1253198 A CN1253198 A CN 1253198A CN 98121419 CN98121419 CN 98121419 CN 98121419 A CN98121419 A CN 98121419A CN 1253198 A CN1253198 A CN 1253198A
Authority
CN
China
Prior art keywords
extension
cable
anchor slab
steel strand
stayed bridge
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN 98121419
Other languages
Chinese (zh)
Other versions
CN1107147C (en
Inventor
梁来
穆成君
唐明翰
李义
刘璇
秦立方
方中予
黄芳玮
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
OUWEIMU ARCHITECTURAL MACHINERY CO Ltd LIUZHOU
Original Assignee
OUWEIMU ARCHITECTURAL MACHINERY CO Ltd LIUZHOU
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by OUWEIMU ARCHITECTURAL MACHINERY CO Ltd LIUZHOU filed Critical OUWEIMU ARCHITECTURAL MACHINERY CO Ltd LIUZHOU
Priority to CN 98121419 priority Critical patent/CN1107147C/en
Publication of CN1253198A publication Critical patent/CN1253198A/en
Application granted granted Critical
Publication of CN1107147C publication Critical patent/CN1107147C/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

A method for suspending the stay cable of steel strand for the cable-stayed bridge includes such steps as suspending three parallel ropes uniformly distributed to three periphery holes on anchor plate, fixing the one end of each of three stay cables to upper anchor plate by clamps, fixing their other ends to lower anchor plate by clamps making upper and lower anchor plates parallel, suspending other stay cables by passing them through upper anchor plate then lower anchor plate one by one, and applying required force to each stay cable after it is suspended. Its advantages are parallel contact planes of upper and lower anchor plates and upper and lower bearing plates, and uniform stress for all stay cables.

Description

A kind of extension Suo Fangfa of guy of twisted steel cable for cable stayed bridge
The present invention relates to a kind of extension rope job practices of cable stayed bridge suspension cable, particularly a kind of extension Suo Fangfa of sheet clamping type group anchor guy of twisted steel cable.
It all is to hang to wear under the situation that anchor slab does not have to fix up and down that the extension of sheet clamping type group anchor guy of twisted steel cable is in the past worn, stress application, at last anchor slab, down anchor slab is with last loaded plate, under loaded plate contact surface irrelevancy is capable down the situation, give in the steel strand application of force process, the angle of last anchor slab and last loaded plate contact surface changes, make steel strand pressure after angle changes of existing stress take place to reduce or increase, the inhomogeneities of suffered stress between each steel strand is increased, easily cause steel strand to rupture in advance.
The object of the present invention is to provide a kind of extension Suo Fangfa of guy of twisted steel cable for cable stayed bridge, it can guarantee the contact surface keeping parallelism of upper and lower anchor slab and upper and lower loaded plate, and makes that suffered stress keeps evenly between each steel strand.
For reaching above-mentioned purpose, solution of the present invention is: adopt and to hang three parallel ropes earlier, its position on equally distributed three perimeter holes on the anchor slab, the method for formally hanging rope according to the order of sequence again.
Earlier an end of three steel strand is locked with intermediate plate admittedly at last anchor slab, then the other end of steel strand is locked with intermediate plate admittedly at following anchor slab.These three steel strand apply certain prestressing force for three steel strand at last anchor slab, be evenly distributed on the anchor slab down, the tension force of steel strand by intermediate plate, go up anchor slab, down anchor slab, go up loaded plate, loaded plate passes on tower or the beam down.
The extension Suo Fangfa of the present invention's guy of twisted steel cable for cable stayed bridge, owing to there are three steel strand that evenly carry to be locked in admittedly on anchor slab, the following anchor slab, 3 of causes are fixed a plane, the fixed-site of anchor slab then, hang the suffered stress of steel strand wear stress application after making and exempt from rocking and change with anchor slab, the suffered stress of each steel strand is even, and easy fracture has not prolonged application life.
Below, the feature to the present invention is described further in conjunction with the accompanying drawings and embodiments.
Accompanying drawing: the extension Suo Fangfa schematic diagram of guy of twisted steel cable for cable stayed bridge of the present invention.
Embodiment
A kind of extension Suo Fangfa of guy of twisted steel cable for cable stayed bridge.The steps include: 1) hang three parallel ropes earlier, its position is on equally distributed three perimeter holes on the anchor slab; Earlier three steel strand 5 1, 5 2, 5 3An end at last anchor slab 2 usefulness intermediate plates 3 solid locks, then steel strand 5 1, 5 2, 5 3The other end following anchor slab 9 usefulness intermediate plates 3 solid locks, so that make upper and lower anchor slab 9 keeping parallelisms; Give three parallel rope steel strand 5 1, 5 2, 5 3Apply certain prestressing force, steel strand 5 1, 5 2, 5 3Tension force by intermediate plate 3, go up anchor slab 2, down anchor slab 9, go up loaded plate 6, loaded plate 8 passes on tower 1 or the beam 7 down; 2) extension is worn other ropes according to the order of sequence: by extension is put on anchor slab 2 earlier, extension is worn the order of anchor slab 9 again, hang earlier and wear intermediate vertical one row's steel strand, press order from top to bottom again, about row wear (referring to accompanying drawing) to become claiming ground to hang, every extension has been worn steel strand, promptly in time apply desired power, wear until extension and finish to it; 3) mend again and execute prestressing force at first hanging three parallel ropes wearing.

Claims (3)

1, a kind of extension Suo Fangfa of guy of twisted steel cable for cable stayed bridge is characterized in that: hang three parallel ropes earlier, its position hangs other ropes again on equally distributed three perimeter holes on the anchor slab; During construction, earlier three steel strand (5 1), (5 2), (5 3) an end at last anchor slab (2) with the solid lock of intermediate plate (3), then steel strand (5 1), (5 2), (5 3) the other end at following anchor slab (9) with the solid lock of intermediate plate (3), so that make upper and lower anchor slab keeping parallelism.
2, the extension Suo Fangfa of guy of twisted steel cable for cable stayed bridge according to claim 1, it is characterized in that: the extension Suo Shunxu of other steel strand is: by extension is put on anchor slab (2) earlier, extension is worn the order of anchor slab (9) again, hang earlier and wear intermediate vertical one row's steel strand, again by from top to bottom order, about row wear becoming to claim ground to hang; Every extension has been worn steel strand, promptly in time applies desired power to it, wears until extension to finish.
3, the extension Suo Fangfa of guy of twisted steel cable for cable stayed bridge as claimed in claim 1 or 2 is characterized in that: each root steel strand hang wear finish after, mend again and execute prestressing force at first hanging three parallel ropes wearing.
CN 98121419 1998-11-09 1998-11-09 Method for suspending guys of twisted steel cable for cable stayed bridge Expired - Fee Related CN1107147C (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 98121419 CN1107147C (en) 1998-11-09 1998-11-09 Method for suspending guys of twisted steel cable for cable stayed bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 98121419 CN1107147C (en) 1998-11-09 1998-11-09 Method for suspending guys of twisted steel cable for cable stayed bridge

Publications (2)

Publication Number Publication Date
CN1253198A true CN1253198A (en) 2000-05-17
CN1107147C CN1107147C (en) 2003-04-30

Family

ID=5227089

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 98121419 Expired - Fee Related CN1107147C (en) 1998-11-09 1998-11-09 Method for suspending guys of twisted steel cable for cable stayed bridge

Country Status (1)

Country Link
CN (1) CN1107147C (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101864725A (en) * 2010-07-16 2010-10-20 四川省交通厅公路规划勘察设计研究院 FRP (Fiber Reinforce Plastic) tendon and steel strand connector and compound stay cable
CN102121231A (en) * 2010-12-31 2011-07-13 上海浦江缆索股份有限公司 Direct cable weaving and hanging method for cable strand of suspension bridge
CN103015320A (en) * 2012-12-24 2013-04-03 东南大学 Stay cable device for kilometric cable stayed bridge and mounting method thereof
CN104762880A (en) * 2015-05-03 2015-07-08 李孟平 Improved bridge inhaul cable structure and hanging method thereof
CN105239509A (en) * 2015-11-06 2016-01-13 柳州欧维姆工程有限公司 Tensioner for parallel steel strand stay cables and construction method thereof
US9828419B2 (en) 2011-08-19 2017-11-28 Ostrich Pharma Kk Antibody and antibody-containing composition
CN110241736A (en) * 2019-06-17 2019-09-17 中交路桥华南工程有限公司 Suspension cable Fast Installation construction method
CN111593674A (en) * 2020-06-12 2020-08-28 安徽省公路桥梁工程有限公司 Suspended casting beam cable construction structure and construction method for n-shaped beam bridge

Cited By (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101864725A (en) * 2010-07-16 2010-10-20 四川省交通厅公路规划勘察设计研究院 FRP (Fiber Reinforce Plastic) tendon and steel strand connector and compound stay cable
CN102121231A (en) * 2010-12-31 2011-07-13 上海浦江缆索股份有限公司 Direct cable weaving and hanging method for cable strand of suspension bridge
CN102121231B (en) * 2010-12-31 2015-05-06 上海浦江缆索股份有限公司 Direct cable weaving and hanging method for cable strand of suspension bridge
US9828419B2 (en) 2011-08-19 2017-11-28 Ostrich Pharma Kk Antibody and antibody-containing composition
US11041016B2 (en) 2011-08-19 2021-06-22 Ostrich Pharma Kk Compositions containing anti-HIV ostrich antibodies
US10428138B2 (en) 2011-08-19 2019-10-01 Ostrich Pharma Kk Antibody and antibody-containing composition
US10106599B2 (en) 2011-08-19 2018-10-23 Ostrich Pharma Kk Antibody and antibody-containing composition
CN103015320B (en) * 2012-12-24 2015-01-28 东南大学 Stay cable device for kilometric cable stayed bridge and mounting method thereof
CN103015320A (en) * 2012-12-24 2013-04-03 东南大学 Stay cable device for kilometric cable stayed bridge and mounting method thereof
CN104762880A (en) * 2015-05-03 2015-07-08 李孟平 Improved bridge inhaul cable structure and hanging method thereof
CN105239509B (en) * 2015-11-06 2017-03-22 柳州欧维姆工程有限公司 Tensioner for parallel steel strand stay cables and construction method thereof
CN105239509A (en) * 2015-11-06 2016-01-13 柳州欧维姆工程有限公司 Tensioner for parallel steel strand stay cables and construction method thereof
CN110241736A (en) * 2019-06-17 2019-09-17 中交路桥华南工程有限公司 Suspension cable Fast Installation construction method
CN111593674A (en) * 2020-06-12 2020-08-28 安徽省公路桥梁工程有限公司 Suspended casting beam cable construction structure and construction method for n-shaped beam bridge

Also Published As

Publication number Publication date
CN1107147C (en) 2003-04-30

Similar Documents

Publication Publication Date Title
US8627530B2 (en) Constructing method of cable-stayed bridge and temporary cable therefor
CN207862749U (en) A kind of novel combination type sunpender
CN110205940A (en) 0# block construction bracket and its reverse drawing preloading method
CN1253198A (en) Method for suspending guys of twisted steel cable for cable stayed bridge
CN110241734A (en) A kind of prestressing bend beam applies stress device and its construction method
CN207878295U (en) Suspension bridge changes rope device
CN101487344B (en) Transverse stretching method for prestressed fiber cloth reinforced concrete column
CN116446262A (en) Self-replacement arch bridge suspender and cable force control method
CN115724331A (en) Prefabricated box girder hoisting device and rapid construction method
CN101487346B (en) Transverse stretching method for prestressed fiber cloth reinforced concrete column
CN209817203U (en) Outward-inclined type point-connection full-glass curtain wall inhaul cable fixing device
CN107503527B (en) Detachable anchorage device for prestressed carbon fiber plates
KR20080004293A (en) Apparatus and method for strengthening by wire tensioning
KR20020029233A (en) Central vertical stress type method to reinforce the endurance force of structure and there of apparatus
CN113846792A (en) Workshop steel structure roof, hoisting device and hoisting method thereof
CN210176297U (en) Adjusting screw device for large heavy-load steel wire rope connection winch lifting equipment
CN105714682B (en) Operating system for tensioning stay cable in small-space cable tower
CN211547407U (en) Steel strand stay cable reeving device
KR100496198B1 (en) Preflex beam manufacturing method to prevent the loss of compressive stress and Loading Apparatus therefor
CN217229937U (en) Hoisting device of anode plate of electric dust remover
CN106481109B (en) A kind of cooling tower X inclined struts segmentation self-balancing construction method
CN206090314U (en) Steel anchor beam lifting sling
CN217426122U (en) Active balance type cable tower concrete tooth block anchoring structure
CN110316649A (en) A kind of suspender and hanging method suitable for irregular truss
CN103938555A (en) Method for designing prestress adjustable support for detecting and strengthening

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
C19 Lapse of patent right due to non-payment of the annual fee
CF01 Termination of patent right due to non-payment of annual fee