CN1107147C - Method for suspending guys of twisted steel cable for cable stayed bridge - Google Patents

Method for suspending guys of twisted steel cable for cable stayed bridge Download PDF

Info

Publication number
CN1107147C
CN1107147C CN 98121419 CN98121419A CN1107147C CN 1107147 C CN1107147 C CN 1107147C CN 98121419 CN98121419 CN 98121419 CN 98121419 A CN98121419 A CN 98121419A CN 1107147 C CN1107147 C CN 1107147C
Authority
CN
China
Prior art keywords
steel strand
anchor slab
extension
hang
twisted steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 98121419
Other languages
Chinese (zh)
Other versions
CN1253198A (en
Inventor
梁来
穆成君
唐明翰
李义
刘璇
秦立方
方中予
黄芳玮
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
OUWEIMU ARCHITECTURAL MACHINERY CO Ltd LIUZHOU
Original Assignee
OUWEIMU ARCHITECTURAL MACHINERY CO Ltd LIUZHOU
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by OUWEIMU ARCHITECTURAL MACHINERY CO Ltd LIUZHOU filed Critical OUWEIMU ARCHITECTURAL MACHINERY CO Ltd LIUZHOU
Priority to CN 98121419 priority Critical patent/CN1107147C/en
Publication of CN1253198A publication Critical patent/CN1253198A/en
Application granted granted Critical
Publication of CN1107147C publication Critical patent/CN1107147C/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The present invention relates to a method for suspending a guy cable of twisted steel cables for an oblique pulling bridge, which comprises the steps: 1) three parallel cables are suspended firstly, the positions of the three parallel cables are arranged at three periphery holes uniformly distributed on anchor plates, one end of each of the three twisted steel cables is fixedly locked on the upper anchor plate 2 by a clamping sheet 3 firstly, then the other end of each of the twisted steel cables 5 is fixedly locked on the lower anchor plate 9 by another clamping sheet 3, and the upper anchor plate and the lower anchor plate can be parallel; 2) other cables are suspended in sequences according to a sequence that the upper anchor plate 2 is suspended and penetrated firstly and the lower anchor plate 9 is suspended and penetrated successively, and each of the twisted steel cables is impressed with required force after being suspended and penetrated. The method can guarantee the contact surfaces of the upper anchor plate, the lower anchor plate, an upper bearing plate and a lower bearing plate to be parallel, and the subjected stress among all the twisted steel cables can be maintained uniformly.

Description

A kind of extension Suo Fangfa of guy of twisted steel cable for cable stayed bridge
Technical field
The present invention relates to a kind of extension Suo Fangfa of guy of twisted steel cable for cable stayed bridge, particularly a kind of extension Suo Fangfa of sheet clamping type group anchor guy of twisted steel cable.
Background technology
It all is to hang to wear under the situation that anchor slab does not have to fix up and down that the extension of sheet clamping type group anchor guy of twisted steel cable is in the past worn, stress application, at last anchor slab, down anchor slab is with last loaded plate, under loaded plate contact surface irrelevancy is capable down the situation, give in the steel strand application of force process, the angle of last anchor slab and last loaded plate contact surface changes, make steel strand pressure after angle changes of existing stress take place to reduce or increase, the inhomogeneities of suffered stress between each steel strand is increased, easily cause steel strand to rupture in advance.
Summary of the invention
The object of the present invention is to provide a kind of extension Suo Fangfa of guy of twisted steel cable for cable stayed bridge, it can guarantee the contact surface keeping parallelism of upper and lower anchor slab and upper and lower loaded plate, and makes that suffered stress keeps evenly between each steel strand.
For reaching above-mentioned purpose, solution of the present invention is: adopt and to hang three parallel ropes earlier, its position on equally distributed three perimeter holes on the anchor slab, the method for formally hanging rope according to the order of sequence again.
Earlier an end of three steel strand is locked with intermediate plate admittedly at last anchor slab, then the other end of steel strand is locked with intermediate plate admittedly at following anchor slab.These three steel strand apply certain prestressing force for three steel strand at last anchor slab, be evenly distributed on the anchor slab down, the tension force of steel strand by intermediate plate, go up anchor slab, down anchor slab, go up loaded plate, loaded plate passes on tower or the beam down.Hang other rope afterwards again, the extension Suo Shunxu of other steel strand is: hang earlier and put on anchor slab, hang and wear anchor slab; Hang earlier and wear intermediate vertical one row's steel strand, again by from top to bottom order, about row hang steel strand symmetrically; Every extension has been worn steel strand, promptly in time applies desired power to it, wears until extension to finish.Each root steel strand hang wear finish after, mend again and execute prestressing force at first hanging three parallel ropes wearing.
The extension Suo Fangfa of the present invention's guy of twisted steel cable for cable stayed bridge, owing to there are three steel strand that evenly carry to be locked in admittedly on anchor slab, the following anchor slab, 3 of causes are fixed a plane, the fixed-site of anchor slab then, hang the suffered stress of steel strand wear stress application after making and exempt from rocking and change with anchor slab, the suffered stress of each steel strand is even, and easy fracture has not prolonged application life.
Description of drawings
Fig. 1 is the extension Suo Fangfa schematic diagram of guy of twisted steel cable for cable stayed bridge of the present invention.
The specific embodiment
Below, the feature to the present invention is described further in conjunction with the accompanying drawings and embodiments.
Shown in Figure 1, a kind of extension Suo Fangfa of guy of twisted steel cable for cable stayed bridge.The steps include: 1) hang three parallel ropes earlier, its position is on equally distributed three perimeter holes on the anchor slab; Earlier three steel strand 5 1, 5 2, 5 3An end at last anchor slab 2 usefulness intermediate plates 3 solid locks, then steel strand 5 1, 5 2, 5 3The other end following anchor slab 9 usefulness intermediate plates 3 solid locks, so that make upper and lower anchor slab 9 keeping parallelisms; Give three parallel rope steel strand 5 1, 5 2, 5 3Apply certain prestressing force, steel strand 5 1, 5 2, 5 3Tension force by intermediate plate 3, go up anchor slab 2, down anchor slab 9, go up loaded plate 6, loaded plate 8 passes on tower 1 and the beam 7 down; 2) extension is worn other ropes according to the order of sequence: put on anchor slab 2 by hanging earlier, hang the order of wearing anchor slab 9 again, hang earlier and wear intermediate vertical one row's steel strand, press order from top to bottom again, about row hang symmetrically and wear (referring to accompanying drawing), every extension has been worn steel strand, promptly in time applies desired power to it, wears until extension to finish; 3) mend again and execute prestressing force at first hanging three parallel ropes wearing.

Claims (1)

1, a kind of extension Suo Fangfa of guy of twisted steel cable for cable stayed bridge is characterized in that:
Hang three parallel ropes earlier, three steel strand (5 1), (5 2), (5 3) three perimeter holes on last anchor slab (2), all distributing of an end in the solid lock of intermediate plate (3), then three steel strand (5 1), (5 2), (5 3) the other end go up in equally distributed three perimeter holes with the solid lock of intermediate plate (3) at following anchor slab (9), apply certain prestressing force for these three parallel steel stranded wires, make anchor slab (2) and following anchor slab (9) keeping parallelism;
Hang other rope again, the extension Suo Shunxu of other steel strand is: extension is put on anchor slab (2) earlier, extension is worn anchor slab (9) again; Hang earlier and wear intermediate vertical one row's steel strand, again by from top to bottom order, about row hang steel strand symmetrically; Every extension has been worn steel strand, promptly in time applies desired power to it, wears until extension to finish;
Each root steel strand hang wear finish after, mend again and execute prestressing force at first hanging three parallel ropes wearing.
CN 98121419 1998-11-09 1998-11-09 Method for suspending guys of twisted steel cable for cable stayed bridge Expired - Fee Related CN1107147C (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 98121419 CN1107147C (en) 1998-11-09 1998-11-09 Method for suspending guys of twisted steel cable for cable stayed bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 98121419 CN1107147C (en) 1998-11-09 1998-11-09 Method for suspending guys of twisted steel cable for cable stayed bridge

Publications (2)

Publication Number Publication Date
CN1253198A CN1253198A (en) 2000-05-17
CN1107147C true CN1107147C (en) 2003-04-30

Family

ID=5227089

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 98121419 Expired - Fee Related CN1107147C (en) 1998-11-09 1998-11-09 Method for suspending guys of twisted steel cable for cable stayed bridge

Country Status (1)

Country Link
CN (1) CN1107147C (en)

Families Citing this family (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101864725B (en) * 2010-07-16 2011-12-28 四川省交通运输厅公路规划勘察设计研究院 FRP (Fiber Reinforce Plastic) tendon and steel strand connector and compound stay cable
CN102121231B (en) * 2010-12-31 2015-05-06 上海浦江缆索股份有限公司 Direct cable weaving and hanging method for cable strand of suspension bridge
MY166794A (en) 2011-08-19 2018-07-23 Ostrich Pharma Kk Antibody and antibody-containing composition
CN103015320B (en) * 2012-12-24 2015-01-28 东南大学 Stay cable device for kilometric cable stayed bridge and mounting method thereof
CN104762880B (en) * 2015-05-03 2016-08-31 朱玉新 The bridge dragline structure of a kind of improvement and hang method
CN105239509B (en) * 2015-11-06 2017-03-22 柳州欧维姆工程有限公司 Tensioner for parallel steel strand stay cables and construction method thereof
CN110241736A (en) * 2019-06-17 2019-09-17 中交路桥华南工程有限公司 Suspension cable Fast Installation construction method
CN111593674A (en) * 2020-06-12 2020-08-28 安徽省公路桥梁工程有限公司 Suspended casting beam cable construction structure and construction method for n-shaped beam bridge

Also Published As

Publication number Publication date
CN1253198A (en) 2000-05-17

Similar Documents

Publication Publication Date Title
CN1107147C (en) Method for suspending guys of twisted steel cable for cable stayed bridge
US20120216357A1 (en) Constructing method of cable-stayed bridge and temporary cable therefor
CN109736213B (en) Tool for quickly replacing clamping piece group anchor type steel strand inhaul cable and dismantling construction method thereof
CN207878295U (en) Suspension bridge changes rope device
CN116446262A (en) Self-replacement arch bridge suspender and cable force control method
CN109457614A (en) Parallel steel stranded wire stayed Cable Construction Suo Li uniformity monitors system and construction method
CN101059071A (en) Lifting weight balance beam type oil pump
CN111924720A (en) Wind cable anchoring system of cable crane tower and construction method
CN109629402B (en) Construction method of three-tower four-span suspension bridge girder
CN202214681U (en) Suspension bridge sling replacing device
CN107503527B (en) Detachable anchorage device for prestressed carbon fiber plates
CN102286943B (en) Suspension bridge sling replacing device
CN211547407U (en) Steel strand stay cable reeving device
CN211292320U (en) Clamping piece type anchorage for closed cable Z-shaped steel wire test
CN210176297U (en) Adjusting screw device for large heavy-load steel wire rope connection winch lifting equipment
CN210457155U (en) Vertical precast concrete slab lifting device of prefabricated building
CN210134355U (en) Conversion adjusting device for anchor main cable traction system of super-large and large inclination angle tunnel
CN209584872U (en) The double interim rope self-balancings of pin ear formula pull formula suspension bridge sling replacing underpinning device
CN209837061U (en) Device for quickly pressing underwater steel cofferdam of reinforced bridge
CN207063331U (en) A kind of post-stressed steel strand wires flat anchorage
CN206090314U (en) Steel anchor beam lifting sling
CN220813462U (en) Bridge steel strand wires cable stretch-draw rotation preventing device
CN219636708U (en) Tool for quickly mounting double-row vertical steel strand prestress
CN216765640U (en) Bridge midspan closure device
CN110823686A (en) Clamping piece type anchorage for closed cable Z-shaped steel wire test

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
C19 Lapse of patent right due to non-payment of the annual fee
CF01 Termination of patent right due to non-payment of annual fee