CN117489367A - Tunnel collapse treatment reinforcing structure and method under bad geological conditions of hydropower station - Google Patents

Tunnel collapse treatment reinforcing structure and method under bad geological conditions of hydropower station Download PDF

Info

Publication number
CN117489367A
CN117489367A CN202311547329.5A CN202311547329A CN117489367A CN 117489367 A CN117489367 A CN 117489367A CN 202311547329 A CN202311547329 A CN 202311547329A CN 117489367 A CN117489367 A CN 117489367A
Authority
CN
China
Prior art keywords
collapse
tunnel
area
reinforcing
steel arch
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202311547329.5A
Other languages
Chinese (zh)
Inventor
赵修龙
方丹
补约依呷
万祥兵
李良权
陈鹏
程普
邵兵
陆健健
李鹏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PowerChina Huadong Engineering Corp Ltd
Original Assignee
PowerChina Huadong Engineering Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PowerChina Huadong Engineering Corp Ltd filed Critical PowerChina Huadong Engineering Corp Ltd
Priority to CN202311547329.5A priority Critical patent/CN117489367A/en
Publication of CN117489367A publication Critical patent/CN117489367A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/102Removable shuttering; Bearing or supporting devices therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • E21D11/15Plate linings; Laggings, i.e. linings designed for holding back formation material or for transmitting the load to main supporting members
    • E21D11/152Laggings made of grids or nettings
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • E21D11/18Arch members ; Network made of arch members ; Ring elements; Polygon elements; Polygon elements inside arches
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/20Hydro energy

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Architecture (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Lining And Supports For Tunnels (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

The invention provides a tunnel collapse treatment reinforcing structure under the poor geological condition of a hydropower station, wherein collapse treatment areas are arranged on collapse hole sections in the tunnel, collapse reinforcement areas and collapse transition areas are respectively arranged on adjacent hole sections of the collapse hole sections, backfill concrete is poured on top arches of the collapse treatment areas, and the backfill concrete is filled into collapse cavity cavities; the tunnel is characterized in that a steel arch is arranged in the tunnel along the direction of a hole line on the basis of the original finished system support, an inclined pipe shed advanced support structure is arranged on the periphery of the tunnel, one end of the pipe shed advanced support structure is connected to the steel arch in a collapse reinforcing area, the other end of the pipe shed advanced support structure penetrates through backfill concrete and is connected to a mountain above a collapse transition area, and a lining support layer covering the steel arch is arranged on the surface of a cavity of the tunnel. The method can reliably reinforce the collapse part of the tunnel under the bad geological conditions of the hydropower station, and ensure the safety of the tunnel.

Description

Tunnel collapse treatment reinforcing structure and method under bad geological conditions of hydropower station
Technical Field
The invention relates to the technical field of tunnels of hydropower stations, in particular to a tunnel collapse treatment reinforcing structure and a tunnel collapse treatment reinforcing method under poor geological conditions of hydropower stations.
Background
Hydropower stations with workshops arranged underground relate to more underground tunnels, and comprise factory entering traffic holes, ventilation and safety holes, cable outgoing holes, construction branch holes and the like, wherein tunnel lines are longer, all kinds of complex geological structures need to be penetrated, surrounding rock conditions around the tunnel lines are complex, collapse hole sections with poor geological conditions are difficult to avoid, the collapse hole sections need to be reinforced, and the safety of the tunnels can be guaranteed. Due to the fact that undisturbed surrounding rock is exposed after the tunnel collapses and a slag pile body formed by collapse in the tunnel is piled up, stability of a collapse area is poor, traditional construction measures cannot guarantee that treatment personnel can safely construct under the condition, the achieved treatment effect is not ideal, the traditional process is long in construction period, manufacturing cost is high, and use requirements cannot be met.
Disclosure of Invention
The first object of the present invention is to provide a reinforcement structure for ensuring the safety of tunnels. For this purpose, the invention adopts the following technical scheme:
the method comprises the steps that under the bad geological conditions of a hydropower station, a tunnel collapse treatment reinforcing structure is arranged on a collapse hole section in the tunnel, collapse reinforcing areas and collapse transition areas are respectively arranged on adjacent hole sections of the collapse hole section, backfill concrete is poured on a top arch of the collapse treatment area, and the backfill concrete is filled into a collapse cavity; the tunnel is internally provided with a steel arch frame on the basis of the original finished system support along the direction of a tunnel line, and is used for tunneling along the direction of the tunnel line to form a sequential support operation state of different tunnel sections, the periphery of the tunnel is provided with an inclined pipe-shed advanced support structure, one end of the pipe-shed advanced support structure is connected to the steel arch frame in a collapse reinforcing area, the other end of the pipe-shed advanced support structure penetrates through backfill concrete to be connected to a mountain above the collapse transition area, the peripheries of the collapse reinforcing area, the collapse treatment area and the collapse transition area are also provided with support structures, and the tunnel is provided with lining support layers covering the steel arch frame on the surface of a cavity of the tunnel.
Further: and the steel pipe of the pipe shed advanced support structure is driven into surrounding rock along the periphery of the tunnel roof arch at an external insertion angle of 5 degrees.
Further: the collapse reinforcing area comprises a collapse reinforcing area I, a collapse reinforcing area II and a collapse reinforcing area III which are sequentially arranged, wherein the collapse reinforcing area III is adjacent to the collapse treatment area, and the end part of the steel pipe of the pipe shed advanced support structure is connected to a steel arch frame around the tail end hole of the collapse reinforcing area II.
Further: the supporting structure is provided with radial system grouting small pipes around the collapse treatment area, the collapse reinforcing two areas and the collapse reinforcing three areas.
Further: and the support structure is provided with a small advance guide pipe around the hole in the collapse transition area.
Further: and concrete layers are arranged on the surfaces of the cavities of the collapse reinforcing second area, the collapse reinforcing third area and the collapse treatment area, and lining supporting layers are covered outside the concrete layers.
Further: and the distance between the collapse treatment area and the steel arch in the collapse reinforcement area is smaller than that between the collapse treatment area and the steel arch in the rest areas.
A second object of the present invention is to provide a convenient and efficient reinforcement method. For this purpose, the invention adopts the following technical scheme:
the method for reinforcing the tunnel collapse treatment reinforcing structure under the bad geological conditions of the hydropower station comprises the following specific steps:
s1: adding a steel arch frame to the collapse reinforcement area on the basis of the original system support, arranging an auxiliary arch at the over-digging part of the top arch, spraying concrete to ensure that the auxiliary arch is tightly attached to the rock wall, and pouring concrete in the range of the steel arch frame of the side wall to ensure that the auxiliary arch is tightly attached to the rock wall;
s2: forming a construction channel and a construction platform for the first collapse reinforcing area and the second collapse reinforcing area of the pad slag, and spraying concrete closed slag bodies on the surface of the pad slag and the collapse body slag pile;
s3: two steps are distinguished for collapse reinforcement, the upper half part of the cavity is a first step, the lower half part of the cavity is a second step, the first step adopts a reserved core soil excavation method, firstly, slag bodies in the range of a steel arch frame near an excavation surface are cleaned, then the steel arch frame in the range of the first step is constructed, 2 rows of foot locking anchor rods are additionally arranged at the bottom of the steel arch frame, and finally, a core soil part is excavated;
s4: pouring backfill concrete on the top arch of the collapse treatment area, and constructing a pipe shed advanced support structure on the periphery of the hole along the section of the tail end of the collapse reinforcing two areas after the backfill concrete is poured and formed, so that the end part of a steel pipe of the pipe shed advanced support structure is firmly connected with the steel arch;
s5: the collapse reinforcement three-step excavation is carried out, the upper half part of the cavity is a first step, the lower half part of the cavity is a second step, the first step adopts a reserved core soil excavation method, slag bodies in the range of a steel arch frame near an excavation surface are firstly cleaned, then the steel arch frame in the range of the first step is constructed, 2 rows of foot locking anchor rods are additionally arranged at the bottom of the steel arch frame, then a core soil part is excavated, and finally a radial system grouting small guide pipe in the range of a top arch is constructed;
s6: the collapse treatment is divided into two steps to excavate, the upper half part of a cavity is a first step, the lower half part of the cavity is a second step, the first step adopts a reserved core soil excavation method, slag bodies in the range of a steel arch frame near an excavation surface are firstly cleaned, then the steel arch frame in the range of the first step is constructed, 2 rows of foot locking anchor rods are additionally arranged at the bottom of the steel arch frame, then a core soil part is excavated, and finally a radial system grouting small guide pipe and net hanging shotcrete in the range of a top arch and a side wall of the first step are constructed;
s7: cleaning slag piled bodies in the second step range of the collapse reinforcing second area, the collapse reinforcing third area and the collapse processing area, lengthening the bottom of the steel arch in the range onto a bottom plate of a cavity, then constructing a radial system grouting small conduit in the second step excavation range, and finally implementing lining support layers on the range;
s8: and constructing an advanced small guide pipe before the collapse transition zone is excavated, then excavating the collapse transition zone by adopting short footage and weak blasting, then performing system anchor spraying and supporting, then constructing a steel arch frame, and finally implementing lining supporting layers.
Compared with the prior art, the invention has the following beneficial effects:
according to the invention, backfill concrete is poured on the top arch of the collapse treatment area of the collapse tunnel section, the pipe shed advanced support structure is connected into a mountain body which is not collapsed at the two ends of the collapse cavity through the backfill concrete, and meanwhile, one end of the pipe shed advanced support structure is fixed on the steel arch frame, so that pre-stable support is carried out before the collapse body of the pile slag in the tunnel is excavated, and the pile slag in the tunnel is removed through excavation support circulation in the later stage, so that support construction is carried out, the collapse position of the tunnel can be reliably reinforced under the bad geological condition of the hydropower station, and the tunnel safety is ensured. Meanwhile, the construction channel and the pipe shed construction platform can be formed by laying the slag layer in the collapse reinforcing first area and the collapse reinforcing second area, so that the construction efficiency can be improved.
Drawings
FIG. 1 is a schematic diagram of the overall structure of the present invention;
FIG. 2 is a schematic cross-sectional view of A-A of FIG. 1 in accordance with the present invention;
FIG. 3 is a schematic cross-sectional view of B-B of FIG. 1 in accordance with the present invention;
FIG. 4 is a schematic cross-sectional view of the C-C of FIG. 1 in accordance with the present invention;
FIG. 5 is a schematic cross-sectional view of D-D of FIG. 1 in accordance with the present invention;
FIG. 6 is a schematic cross-sectional view of E-E of FIG. 1 in accordance with the present invention;
FIG. 7 is a schematic cross-sectional view of F-F of FIG. 4 in accordance with the present invention;
FIG. 8 is a schematic cross-sectional view of the G-G of FIG. 5 in accordance with the present invention;
FIG. 9 is a schematic cross-sectional view of H-H of FIG. 6 in accordance with the present invention;
FIG. 10 is a schematic view of a steel pipe for a pipe shed according to the present invention;
FIG. 11 is a schematic view of a steel pipe for a small pipe according to the present invention.
The marks in the drawings are: the system comprises a tunnel 1, a collapse cavity 2, a collapse body 3, a slag layer 4, a collapse reinforcing area 5, a collapse reinforcing area 51, a collapse reinforcing area 52, a collapse reinforcing area 53, a collapse treatment area 6, a collapse transition area 7, a steel arch 8, backfilled concrete 9, a pipe shed advanced support structure 10, a radial system grouting small pipe 12, an advanced small pipe 13, a lining support layer 14 and a concrete layer 15.
Detailed Description
The invention is further illustrated by the following figures and examples, which are not intended to be limiting.
As shown in fig. 1-11, a tunnel collapse treatment reinforcing structure under the bad geological conditions of a hydropower station is provided, a collapse treatment area 6 is arranged on a collapse hole section in a tunnel 1, and a collapse reinforcement area 5 and a collapse transition area 7 are respectively arranged on adjacent hole sections of the collapse hole section, wherein the range of the collapse transition area 7 is determined according to the actual conditions of the site; backfill concrete 9 is poured on the top arch of the collapse treatment area 6, and the backfill concrete 9 is filled into the cavity of the collapse cavity 2, so that the collapse cavity 2 is separated from the inside of the tunnel 1, and broken stone at the top of the collapse cavity 2 is prevented from further falling; arranging a steel arch 8 in the tunnel 1 along the direction of a tunnel line on the basis of the original finished system support, tunneling along the direction of the tunnel line to form a sequential support operation state of different tunnel sections, arranging an inclined pipe shed advanced support structure 10 around the tunnel 1, wherein one end of the pipe shed advanced support structure 10 is connected to the steel arch 8 in the collapse reinforcing area 5, and the other end of the pipe shed advanced support structure passes through backfill concrete 9 and is connected to a mountain above the collapse transition area 7, so that the stability of the tunnel 1 can be improved; supporting structures are further arranged around the collapse reinforcing zone 5, the collapse processing zone 6 and the collapse transition zone 7, and the tunnel 1 is provided with a lining supporting layer 14 which covers the steel arch 8 on the surface of a cavity.
Specifically, the collapse reinforcement area 5 comprises a collapse reinforcement area 51, a collapse reinforcement area 52 and a collapse reinforcement area 53 which are sequentially arranged, the collapse reinforcement area 53 is adjacent to the collapse treatment area 6, and the end part of the pipe shed advanced support structure 10 is connected to the steel arch 8 around the hole at the tail end of the collapse reinforcement area 52, so that a stable connection foundation is provided for the pipe shed advanced support structure 10.
As shown in fig. 8-9, concrete layer 15 is arranged on the cavity surface of the collapse reinforced two areas 52, the collapse reinforced three areas 53 and the collapse treatment area 6, and the lining support layer 14 is covered outside the concrete layer 15. Wherein, for lining structures in the areas of the collapse reinforcing two areas 52, the collapse reinforcing three areas 53 and the collapse processing area 6, the concrete layer 15 adopts sprayed C25 concrete and has a thickness of 27cm; the lining support layer 14 is lined by reinforced concrete and has a thickness of 50cm.
As shown in fig. 1 and 7-9, wherein the collapse treatment zone 6 is spaced from the steel arch 8 in the collapse reinforcing three zone 53 a distance less than the steel arch 8 spacing in the remaining zones. The distance between the collapse treatment area 6 and the steel arch 8 in the collapse reinforcing three area 53 is 0.5m, and the distance between the collapse reinforcing one area 51, the collapse reinforcing two area 52 and the steel arch 8 in the collapse transition area 7 is 1m.
In this embodiment, the support structure is provided with radial system grouting small pipes 12 around the collapse treatment area 6, the collapse reinforcing two areas (52) and the collapse reinforcing three areas 53. The supporting structure is also provided with a small advance duct 13 around the hole of the collapse transition zone 7.
Specifically, the construction requirements of all supporting structures are as follows:
firstly, the construction requirement of the pipe shed advanced support structure 10 is as follows:
the pipe shed advanced support is 30m long and has outer diameterThe front end of the hot rolled seamless steel pipe with the wall thickness of 5mm is in a pointed cone shape, and the tail part of the hot rolled seamless steel pipe is welded with +.>Stiffening hoop and drill ∈four sides of pipe wall>Grouting holes; during construction, the steel pipes are driven into surrounding rocks along the periphery of the tunnel roof arch at an external insertion angle of 5 degrees, and the circumferential arrangement interval is 30cm; the anchor tendons 3C28 and L=30m are inserted into the steel pipes of the pipe shed, the grouting material of the pipe shed adopts 1:1 cement paste, the initial pressure is 0.5-0.75 MPa, the final pressure is 1.0MPa, and grouting can be finished when the grouting pressure reaches the design final pressure; the grouting proportion and grouting pressure can be adjusted according to the construction condition of the on-site grouting, the grouting pressure and the grouting quantity of a grouting pump are required to be observed at any time in the grouting process, the grouting condition is analyzed, pipe blocking, grouting and leakage are prevented, M10 cement mortar is adopted for backfilling after the grouting of the steel pipe is finished, the next circulation excavation can be carried out after the grouting strength reaches at least 70% of the design strength, the excavation footage is not more than 0.5M, and concrete lining is required to be timely supported and constructed.
Secondly, the construction requirement of the radial system grouting small guide pipe 12 is as follows:
when the radial system is adopted for grouting small guide pipe support, the small guide pipe is of the specificationAfter the guide pipe is inserted into the rock body, cement mortar is required to be injected into the steel pipe until the steel pipe is compact, the mortar strength grade is M25, the pressure is 0.3MPa, and the next cycle excavation can be performed after the grouting strength reaches 70% of the design strength.
Thirdly, the grouting construction requirement of the leading small guide pipe 13 support is as follows:
when adopting the advanced small conduit grouting method, the specification of the small conduitThe circumferential center distance is 300mm, the external inserting angle is 20 degrees, the lifting value is 15cm, each small guide pipe is 4.5M long, the effective excavation length is 2.5M, the small guide pipes are lapped front and back by 1.6M respectively, after the guide pipes are inserted into rock bodies, cement mortar needs to be injected into the steel pipes until the steel pipes are compact, the mortar strength grade M25 and the pressure are 0.3MPa, the next cycle excavation can be carried out after the grouting strength reaches 70% of the design strength, and the leading small guide pipes can be excavated according to the following conditionsThe actual situation is replaced by a lead anchor of C25, l=4.5m.
Referring to fig. 1-11, when the tunnel collapse treatment is performed on the poor geological condition of the hydropower station through the reinforcement structure, the specific steps are as follows:
s1: on the basis of the original system support, an I22 a-shaped steel arch 8 is newly added to the collapse reinforcement area 51, the distance is 1m, auxiliary arches are arranged at the positions, which are larger than 50cm, of the top arches in an overexcavation mode, C30 concrete is sprayed to ensure that the auxiliary arches cling to the rock wall, and C30 concrete is poured to the back of the steel arch 8 in the range of the opposite side wall to ensure that the auxiliary arches cling to the rock wall;
s2: forming a collapse body 3 by collapse of the collapse cavity 2 to the piled slag in the tunnel 1, paving a slag layer 4 in a collapse reinforcing first area 51 and a collapse reinforcing second area 52 to form a construction channel and a pipe shed construction platform, and spraying C25 concrete closed slag bodies with the thickness of 10cm on the slag layer 4 and the surface of the piled slag of the collapse body 3;
s3: digging two steps in the collapse reinforcing two areas 52, namely, a first step in a range from 4m to a hole top of a bottom plate of a cavity, and a second step in a range from 4m above the bottom plate of the cavity, wherein the first step adopts a reserved core soil digging method, the length of a reserved core soil hole section is not less than 5m from a face, and a steel arch 8 in the range is constructed by cleaning slag bodies in a range of 50cm near the digging face, and meanwhile, 2 rows of foot locking anchor rods are additionally arranged at the bottom of the steel arch 8, so that the core soil part is dug;
s4: c30 concrete of backfill concrete 9 is poured on the top arch of the collapse treatment area 6, after 7 days of pouring and forming, the backfill concrete 9 is used for constructing a pipe shed advanced support structure 10 around the hole at the tail end of the collapse reinforcing two area 52, and the end part of the pipe shed advanced support structure 10 is firmly welded with the steel arch 8;
s5: digging two steps in the same manner as the two reinforced areas 52 in the collapse reinforced three areas 53, wherein the first step adopts a reserved core soil digging method, the distance between the length of a reserved core soil hole section and the face is not less than 5m, constructing a steel arch 8 in the range by cleaning slag bodies in the range of 50cm near the digging face, simultaneously adding 2 rows of foot locking anchor rods at the bottom of the steel arch 8, digging a core soil part, and then constructing a radial system grouting small guide pipe 12 in the range of the top arch;
s6: digging the collapse treatment area 6 as two steps as the reinforced two areas 52, wherein the first step adopts a reserved core soil digging method, the length of a reserved core soil hole section is not less than 5m away from a tunnel face, 2 rows of foot locking anchor rods are additionally arranged at the bottom of the steel arch 8 by cleaning slag bodies within a range of 50cm near the digging face, so that the core soil part is dug, and finally, grouting small guide pipes 12 and net-hanging shotcrete of a radial system within the ranges of a top arch and side walls of the first step are constructed;
s7: cleaning the slag pile bodies in the second step range of the collapse reinforcing two areas 52, the collapse reinforcing three areas 53 and the collapse processing area 6, lengthening the bottom of the steel arch 8 in the range to the bottom plate of the cavity, then constructing a radial system grouting small duct 12 in the second step excavation range, and finally implementing lining support layers 14 on the range;
s8: the advanced small guide pipe 13 is firstly constructed before the collapse transition zone 7 is excavated, then the collapse transition zone 7 is excavated by adopting short footage and weak blasting, then the system is shotcrete and shotcrete, then the steel arch 8 is constructed, and finally the lining support layer 14 is implemented.
The above embodiment is only one preferred technical solution of the present invention, and it should be understood by those skilled in the art that modifications and substitutions can be made to the technical solution or parameters in the embodiment without departing from the principle and essence of the present invention, and all the modifications and substitutions are covered in the protection scope of the present invention.

Claims (8)

1. Tunnel collapse handles reinforced structure under bad geological conditions of power station, its characterized in that: a collapse treatment area (6) is arranged on a collapse hole section in a tunnel (1), a collapse reinforcement area (5) and a collapse transition area (7) are respectively arranged on adjacent hole sections of the collapse hole section, backfill concrete (9) is poured on a top arch of the collapse treatment area (6), and the backfill concrete (9) is filled into a cavity of the collapse cavity (2);
the tunnel is characterized in that a steel arch (8) is arranged in the tunnel (1) on the basis of the original finished system support along the direction of a hole line, a sequential support operation state of different hole sections is formed by tunneling along the direction of the hole line, an inclined pipe shed advanced support structure (10) is arranged around the tunnel (1), one end of the pipe shed advanced support structure (10) is connected to the steel arch (8) in a collapse reinforcing area (5), the other end of the pipe shed advanced support structure passes through backfill concrete (9) and is connected to a mountain above the collapse transition area (7), support structures are further arranged around the collapse reinforcing area (5), the collapse treatment area (6) and the collapse transition area (7), and a lining support layer (14) covering the steel arch (8) is arranged on the surface of a cavity of the tunnel (1).
2. The reinforced structure for tunnel collapse treatment under poor geological conditions of hydropower station according to claim 1, wherein: the steel pipe of the pipe shed advanced support structure (10) is driven into surrounding rock along the periphery of the roof arch of the tunnel (1) at an external insertion angle of 5 degrees.
3. The reinforced structure for tunnel collapse treatment under poor geological conditions of hydropower station according to claim 1, wherein: the collapse reinforcement area (5) comprises a collapse reinforcement area (51), a collapse reinforcement area (52) and a collapse reinforcement area (53) which are sequentially arranged, the collapse reinforcement area (53) is adjacent to the collapse treatment area (6), and the end part of a steel pipe of the pipe shed advanced support structure (10) is connected to a steel arch (8) around the tail end hole of the collapse reinforcement area (52).
4. A tunnel collapse treatment reinforcing structure under adverse geological conditions of a hydropower station according to claim 3, wherein: the supporting structure is provided with radial system grouting small pipes (12) around the hole of the collapse treatment area (6), the collapse reinforcing two areas (52) and the collapse reinforcing three areas (53).
5. A tunnel collapse treatment reinforcing structure under adverse geological conditions of a hydropower station according to claim 3, wherein: the supporting structure is provided with a small advance duct (13) around the hole of the collapse transition zone (7).
6. A tunnel collapse treatment reinforcing structure under adverse geological conditions of a hydropower station according to claim 3, wherein: and concrete layers (15) are arranged on the surfaces of the cavities of the collapse reinforcing two areas (52), the collapse reinforcing three areas (53) and the collapse treatment area (6), and lining supporting layers (14) are covered outside the concrete layers (15).
7. A tunnel collapse treatment reinforcing structure under adverse geological conditions of a hydropower station according to claim 3, wherein: the distance between the collapse treatment area (6) and the steel arch (8) in the collapse reinforcement three areas (53) is smaller than the distance between the steel arches (8) in the rest areas.
8. The method for reinforcing the tunnel collapse treatment reinforcing structure under the bad geological conditions of the hydropower station is characterized by comprising the following steps: construction of a collapsed tunnel section with a tunnel collapse treatment reinforcing structure under poor geological conditions of a hydropower station according to any one of claims 1 to 7, comprising the following steps:
s1: adding a steel arch frame (8) to the collapse reinforcement area (51) on the basis of the original system support, arranging an auxiliary arch at the over-digging part of the top arch, spraying concrete to ensure that the auxiliary arch is tightly attached to the rock wall, and pouring concrete in the range of the side wall steel arch frame (8) to ensure that the auxiliary arch is tightly attached to the rock wall;
s2: forming a construction channel and a construction platform for the pad slag of the collapse reinforcing first area (51) and the collapse reinforcing second area (52), and spraying concrete closed slag bodies on the surface of the pad slag and the collapse body pile slag;
s3: digging two steps in the collapse reinforcement two areas (52), wherein the upper half part of a cavity is a first step, the lower half part of the cavity is a second step, the first step adopts a reserved core soil digging method, firstly, slag bodies in the range of a steel arch (8) near a digging surface are cleaned, then, the steel arch (8) in the range of the first step is constructed, 2 rows of foot locking anchor rods are additionally arranged at the bottom of the steel arch (8), and finally, a core soil part is dug;
s4: pouring backfill concrete (9) on the top arch of the collapse treatment area (6), pouring and molding the backfill concrete (9) for 7 days, and constructing a pipe shed advanced support structure (10) on the periphery of the hole along the tail end section of the collapse reinforced two areas (52), wherein the end part of a steel pipe of the pipe shed advanced support structure (10) is firmly connected with the steel arch (8);
s5: the collapse reinforcement three areas (53) are excavated by two steps, the upper half part of a cavity is a first step, the lower half part of the cavity is a second step, the first step adopts a reserved core soil excavation method, slag bodies in the range of a steel arch (8) near an excavation surface are firstly cleaned, then the steel arch (8) in the range of the first step is constructed, 2 rows of foot locking anchor rods are additionally arranged at the bottom of the steel arch (8), then a core soil part is excavated, and finally a radial system grouting small guide pipe (12) in the range of a top arch is constructed;
s6: digging two steps in a collapse treatment area (6), wherein the upper half part of a cavity is a first step, the lower half part of the cavity is a second step, the first step adopts a reserved core soil digging method, firstly, slag bodies in the range of a steel arch (8) near a digging surface are cleaned, then the steel arch (8) in the range of the first step is constructed, 2 rows of foot locking anchor rods are additionally arranged at the bottom of the steel arch (8), then a core soil part is dug, and finally, a radial system grouting small guide pipe (12) and a net hanging shotcrete in the ranges of a top arch and a side wall of the first step are constructed;
s7: cleaning slag piled bodies in the second step range of the collapse reinforcing two areas (52), the collapse reinforcing three areas (53) and the collapse processing areas (6), lengthening the bottoms of the steel arches (8) in the range onto a bottom plate of a cavity, then constructing a radial system grouting small duct (12) in the second step excavation range, and finally implementing lining support layers (14) on the range;
s8: and constructing a small advance duct (13) for the collapse transition region (7) before excavating, excavating the collapse transition region (7) by adopting short footage and weak blasting, performing systematic anchor spraying and supporting, constructing a steel arch (8), and finally performing lining supporting layers (14).
CN202311547329.5A 2023-11-20 2023-11-20 Tunnel collapse treatment reinforcing structure and method under bad geological conditions of hydropower station Pending CN117489367A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202311547329.5A CN117489367A (en) 2023-11-20 2023-11-20 Tunnel collapse treatment reinforcing structure and method under bad geological conditions of hydropower station

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202311547329.5A CN117489367A (en) 2023-11-20 2023-11-20 Tunnel collapse treatment reinforcing structure and method under bad geological conditions of hydropower station

Publications (1)

Publication Number Publication Date
CN117489367A true CN117489367A (en) 2024-02-02

Family

ID=89684690

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202311547329.5A Pending CN117489367A (en) 2023-11-20 2023-11-20 Tunnel collapse treatment reinforcing structure and method under bad geological conditions of hydropower station

Country Status (1)

Country Link
CN (1) CN117489367A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117780392A (en) * 2024-02-26 2024-03-29 中国建筑第六工程局有限公司 Airbag grouting treatment method for collapse of underground tunneling hole

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117780392A (en) * 2024-02-26 2024-03-29 中国建筑第六工程局有限公司 Airbag grouting treatment method for collapse of underground tunneling hole
CN117780392B (en) * 2024-02-26 2024-05-17 中国建筑第六工程局有限公司 Airbag grouting treatment method for collapse of underground tunneling hole

Similar Documents

Publication Publication Date Title
CN104047623B (en) A kind of big across cavern excavation construction method
CN103758123B (en) The construction method of manually digging hole filling pile retaining wall lining
CN112228082B (en) Tunnel collapse treatment method by combined grouting of pipe shed and advanced small guide pipe
CN108457656A (en) A kind of unearthed method for tunnel construction
CN113153308B (en) Construction method for collapse section of double-arch tunnel
CN102606168B (en) Construction method for preventing settlement and deformation of shallow-buried-excavation tunnel in excavation
CN112502734B (en) Construction method for water-rich sand layer shield zone connecting channel
CN111502696A (en) Dense-mesh type advanced support system of underground excavation tunnel and construction method
CN112663625A (en) Construction and protection method for shallow-buried bias-pressure weak surrounding rock tunnel portal in alpine region
WO2020259059A1 (en) Tbm parallel heading tunnel trunk construction method
CN117489367A (en) Tunnel collapse treatment reinforcing structure and method under bad geological conditions of hydropower station
JP7394252B1 (en) Protruding type wind duct structure perpendicular to the vertical direction and construction method at deep subway station
CN108386198A (en) A kind of novel tunnel inverted arch basement weak country rock processing method
CN207033463U (en) Mine shield handing-over tunnel folded type joint design in the middle part of marine site
CN114483056B (en) Method for treating collapse roof caving hole of high-speed railway shallow-buried tunnel within 15m of height of collapse cavity
CN105350575B (en) A kind of reversed construction method of diaphram wall
CN114352292A (en) Shallow-buried bias-pressure multi-arch tunnel construction method for weathering phyllite stratum
CN205036388U (en) Block of four encircles knot hunch construction structures that PBA secretly dug subway station
CN109695453B (en) Auxiliary excavation construction method for vertical shaft main tunnel three-dimensional intersection
CN101793027A (en) Core-grouted static pressure anchor rod pile
CN221256796U (en) Tunnel collapse treatment reinforcing structure under bad geological conditions of hydropower station
CN110159276A (en) Tunnel excavation technique in a kind of disintegration in water ultimate soft rock stratum
CN109653193B (en) Reverse construction method for underground continuous wall
CN109736843B (en) Reverse waterproof method for assembling and pouring two linings of small template
CN114320365A (en) Rapid construction method of integral prefabricated reinforced concrete lining tunnel

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination