CN116892289A - Template supporting system for integrally pouring beam plate and beam bottom L-shaped hanging plate - Google Patents

Template supporting system for integrally pouring beam plate and beam bottom L-shaped hanging plate Download PDF

Info

Publication number
CN116892289A
CN116892289A CN202310906150.8A CN202310906150A CN116892289A CN 116892289 A CN116892289 A CN 116892289A CN 202310906150 A CN202310906150 A CN 202310906150A CN 116892289 A CN116892289 A CN 116892289A
Authority
CN
China
Prior art keywords
hanging plate
shaped hanging
plate
support
vertical
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202310906150.8A
Other languages
Chinese (zh)
Inventor
耿秋红
刘伟
王濮
秦万军
赵鑫
赵睿泽
吉盼盼
焦阳
马战飞
胡楠
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanxi Sanjian Group Construction Engineering Co ltd
Original Assignee
Shanxi Sanjian Group Construction Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanxi Sanjian Group Construction Engineering Co ltd filed Critical Shanxi Sanjian Group Construction Engineering Co ltd
Priority to CN202310906150.8A priority Critical patent/CN116892289A/en
Publication of CN116892289A publication Critical patent/CN116892289A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G13/00Falsework, forms, or shutterings for particular parts of buildings, e.g. stairs, steps, cornices, balconies foundations, sills
    • E04G13/04Falsework, forms, or shutterings for particular parts of buildings, e.g. stairs, steps, cornices, balconies foundations, sills for lintels, beams, or transoms to be encased separately; Special tying or clamping means therefor
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G11/00Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
    • E04G11/36Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for floors, ceilings, or roofs of plane or curved surfaces end formpanels for floor shutterings
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G11/00Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
    • E04G11/36Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for floors, ceilings, or roofs of plane or curved surfaces end formpanels for floor shutterings
    • E04G11/48Supporting structures for shutterings or frames for floors or roofs
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G17/00Connecting or other auxiliary members for forms, falsework structures, or shutterings
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G17/00Connecting or other auxiliary members for forms, falsework structures, or shutterings
    • E04G17/06Tying means; Spacers ; Devices for extracting or inserting wall ties
    • E04G17/065Tying means, the tensional elements of which are threaded to enable their fastening or tensioning
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G25/00Shores or struts; Chocks
    • E04G25/02Shores or struts; Chocks non-telescopic

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

The invention discloses a formwork support system for integrally pouring a beam slab and an L-shaped hanging plate at the bottom of the beam, which solves the problem of how to construct a support structure of the formwork system for integrally pouring the beam slab and the L-shaped hanging plate below the beam slab; a pre-cast L-shaped hanging plate bottom formwork support beam (4) is arranged on a full framing (1) right below a pre-cast concrete beam space (23), an inner side clamping steel pipe (29), the L-shaped hanging plate bottom formwork support beam (4) and an outer side clamping steel pipe (18) form a U-shaped space for constructing a beam and a beam bottom L-shaped hanging plate, a beam plate integrated casting formwork system convenient to assemble and disassemble is constructed in the U-shaped space, the integrally cast concrete space is divided into the following three areas, and a horizontal plate casting space (25) of the L-shaped hanging plate, a vertical plate casting space (24) of the L-shaped hanging plate and a top beam plate casting space; the segmented integral pouring process is matched with the formwork support system in a coordinated manner, so that integral pouring is realized.

Description

Template supporting system for integrally pouring beam plate and beam bottom L-shaped hanging plate
Technical Field
The invention relates to a beam slab pouring formwork support system in a cast-in-place concrete factory building, in particular to a formwork support system for integrally pouring a beam slab and a beam bottom L-shaped hanging plate.
Background
For a concrete frame structure factory building with high cast-in-situ large-span layer height (for example, a factory building with the layer height of more than 6 meters and the span of more than 8 meters), the conventional construction method is as follows: firstly pouring a foundation slab of a factory building, building a pouring template support frame of an upper frame beam slab on the completed foundation slab, constructing a concrete pouring template system of an upper frame beam and slab on the upper part of the pouring template support frame, and pouring concrete after binding steel bars of the beam and slab to form an integral structure of the upper concrete beam and slab; the large-span high-rise factory building, under the peripheral outside roof beam of upper concrete beam slab, there is large-span door and window generally designed, because the high range of about 3 meters of door and window of large-span is high, in order to lighten the load of the upper concrete frame beam, there is L-shaped cast-in-place concrete link plate between roof and upper frame beam bottom of large-span door and window, L-shaped cast-in-place concrete link plate and concrete beam on its roof, form a C-shaped concrete integral structure, install the large-span door and window again below L-shaped cast-in-place concrete link plate; the structure not only reduces the load of the upper layer concrete beam and saves the concrete member material, but also meets the installation requirement of doors and windows of a factory building; aiming at the commonly adopted concrete beam and the lower L-shaped hanging plate structure, the prior art is to finish construction by respectively supporting a concrete pouring template of a beam plate and a concrete pouring template of an L-shaped hanging plate and adopting a mode of pouring the concrete beam plate and the lower hanging plate step by step, namely, firstly supporting the concrete pouring template of an upper frame beam plate and finishing concrete pouring, after the concrete strength of the upper frame beam plate reaches the dismantling standard, dismantling the pouring template of the upper frame beam plate, secondly supporting the template of the L-shaped cast-in-place concrete hanging plate, and secondarily pouring the L-shaped cast-in-place concrete hanging plate; when the concrete pouring of the L-shaped cast-in-place concrete hanging plate is carried out, as the top of the concrete hanging plate is sealed by the poured concrete beam, only a concrete pouring hopper which is inclined outwards can be arranged, so that the casting of the L-shaped cast-in-place concrete hanging plate is realized; the conventionally employed construction method has the following problems: (1) The beam slab and the L-shaped hanging plate are erected and poured in a repeated mode, so that the time consumption is long, and the construction time is greatly prolonged; (2) The concrete of the beam plate and the L-shaped hanging plate is poured in batches, and a stubble joint gap is formed at the joint of the beam plate and the L-shaped hanging plate, so that the water leakage phenomenon is easy to occur; (3) After the pouring of the L-shaped concrete hanging plate is completed, chiseling and removing treatment is required to be carried out on the concrete convex blocks formed by the pouring hopper, so that time and material are consumed, and the appearance of the outer vertical face of the factory building is influenced; if the concrete pouring templates of the beam slab and the beam bottom L-shaped hanging plate are designed into an integrated template supporting structure form, and an integrated concrete pouring method is adopted, the following problems are presented: (1) A sealing template is required to be arranged at the upper part of a concrete horizontal plate of the pre-cast beam bottom L-shaped hanging plate so as to ensure that the concrete cannot overflow at the position of the beam bottom L-shaped hanging plate in the concrete pouring process; however, the sealing template makes the vibration of the concrete at the horizontal plate of the beam bottom L-shaped hanging plate not normally performed; (2) In the concrete pouring process, as the pouring template of the vertical plate of the beam bottom L-shaped hanging plate is slender and vertically arranged, the top end of the internal space of the vertical template is communicated with the large-area beam plate space, and in the concrete pouring process, a large impact force is generated on the templates on the two sides of the vertical plate of the beam bottom L-shaped hanging plate, so that the expansion phenomenon is easy to occur; (3) Because the pre-poured beam bottom L-shaped hanging plate and the pre-poured upper beam are in a C-shaped shape, how to construct a stable template supporting structure in the C-shaped groove and how to stably support the template at the upper end in the C-shaped opening and stably transfer supporting force to the full-hall supporting frame becomes a problem to be solved on site.
Disclosure of Invention
The invention provides a formwork support system for integrally pouring a beam slab and an L-shaped hanging plate at the beam bottom, which solves the technical problems of how to construct a support structure of the formwork system for integrally pouring the beam slab and the L-shaped hanging plate below the beam slab and reliably complete the integral pouring.
The invention solves the technical problems by the following technical proposal:
the general conception of the invention is that: constructing a full-hall support frame system of a beam slab pouring template below the precast beam slab, and integrally fusing the pouring template support system of the precast beam bottom L hanging plate and the full-hall support frame system; a vertical supporting column is arranged in a C-shaped opening formed by a pre-cast beam bottom L-shaped hanging plate and a pre-cast upper layer beam plate, the lower end of the vertical supporting column is supported on a rice-shaped base steel bar support, the rice-shaped base steel bar support is arranged on a pouring bottom formwork of a horizontal plate of the pre-cast L-shaped hanging plate, meanwhile, a horizontal beam steel bar is arranged at the upper part of the column of the rice-shaped base steel bar support, the horizontal beam steel bar is used as a supporting bracket of a vertical inner side formwork of the L-shaped hanging plate, a reinforcing vertical supporting column is arranged right below the vertical supporting column arranged in the C-shaped opening, and the reinforcing supporting column is fixed on a full-hall supporting frame of the beam plate pouring bottom formwork, so that a stable cast-in-place load capable of pouring the beam above the C-shaped opening is constructed, and a stable force transmission supporting system sequentially transferred to the full-hall supporting frame is ensured through the vertical supporting column, the rice-shaped base steel bar support, the horizontal section pouring bottom formwork of the L-shaped hanging plate and the lower reinforcing supporting column, and the stable bearing system of the whole concrete pouring system of the beam bottom L-shaped hanging plate; in the whole concrete pouring process of the beam slab and the beam bottom L-shaped hanging plate below the beam slab, a construction process of sectional pouring is adopted, and the whole poured concrete space is divided into the following three areas, namely a horizontal plate pouring space of the L-shaped hanging plate, a vertical plate pouring space of the L-shaped hanging plate and a top beam slab pouring space; concrete pouring is carried out on the horizontal plate pouring space of the L-shaped hanging plate, and when the top surface of the concrete pouring layer of the horizontal plate pouring space of the L-shaped hanging plate is initially set and has no bleeding phenomenon and a vibrating rod can be inserted into the bottom surface of the concrete pouring layer, the concrete pouring of the vertical plate pouring space of the L-shaped hanging plate is immediately carried out; when the top surface of the concrete pouring layer in the vertical plate pouring space of the L-shaped hanging plate has no bleeding phenomenon and the vibrating rod can be inserted into the concrete pouring layer, pouring the concrete floor plate pouring space and the concrete beam pouring space; the sectional integral pouring process is matched with the formwork support system, so that integral pouring is realized, the phenomenon of concrete overflow does not occur, and the defect that the pouring formwork of the L-shaped hanging plate is easy to have the phenomenon of expanding mould is creatively overcome.
The formwork support system for integrally pouring beam slabs and beam bottom L-shaped hanging plates comprises a full-hall support frame, wherein an upper floor slab pouring bottom formwork and an upper floor beam pouring left vertical formwork are respectively arranged at the top end of the full-hall support frame, a precast concrete floor slab space is arranged on the upper floor slab pouring bottom formwork, a steel pipe support top transverse steel bar is arranged at the upper part of the steel pipe support, a precast concrete beam space is arranged at the right side of the upper floor beam pouring left vertical formwork, a precast L-shaped hanging plate bottom formwork support beam is arranged on a full-hall support frame right below the precast concrete beam space, an L-shaped hanging plate bottom formwork support beam is arranged on the L-shaped hanging plate bottom formwork support beam, an L-shaped hanging plate bottom formwork longitudinal support beam is arranged on the L-shaped hanging plate bottom formwork, a steel pipe support frame of a rice-shaped base is arranged on the L-shaped hanging plate bottom formwork, a steel pipe support is arranged at the upper part of the steel pipe support frame top transverse steel bar, a C-shaped opening inner support column is sleeved on the top end of the steel pipe support frame, an adjustable cantilever beam is arranged at the top end of the top of the cantilever floor slab, and a horizontal cantilever beam is arranged at the top end of the cantilever floor; the method comprises the steps that the right side of a steel pipe upright post is supported in a C-shaped opening, left support back edges of an L-shaped hanging plate left side vertical template are arranged at intervals, the right side of the left support back edges of the L-shaped hanging plate left side vertical template is provided with an L-shaped hanging plate left side vertical template, the lower end of the L-shaped hanging plate left side vertical template is supported at the right end of a transverse steel bar at the top of an upright post support, the upper end of the L-shaped hanging plate left side vertical template is butted with the right end of a precast beam bottom template, the right side of the L-shaped hanging plate left side vertical template is provided with a pre-cast vertical plate space of the L-shaped hanging plate, the right side of the vertical plate space of the L-shaped hanging plate is provided with a shared right side vertical template of the L-shaped hanging plate, the right side vertical template is provided with an L-shaped hanging plate outer support back edge, the right side of the left side template is supported at the right side of the left side of the upright edge of the L-shaped hanging plate outer template, an outer clamping steel pipe is arranged between the outer clamping steel pipe and the C-shaped opening inner support upright post, the left side vertical template is provided with an L-shaped hanging plate vertical plate and a left side vertical bolt, and a left side vertical support frame is arranged between the left side vertical template and a left side vertical girder is provided with a vertical bolt; the left side of the lower end of the vertical template on the left side of the L-shaped hanging plate is provided with a horizontal plate space of the pre-poured L-shaped hanging plate, the top end of the horizontal plate space is provided with a vibration reserved area, and the pre-poured concrete floor plate space, the pre-poured concrete beam space, the vertical plate space of the pre-poured L-shaped hanging plate and the horizontal plate space of the pre-poured L-shaped hanging plate are communicated together.
A vertical supporting upright rod is arranged on a full-hall support frame right below the horizontal plate space of the pre-poured L-shaped hanging plate, an adjustable jackscrew at the top end of the vertical supporting upright rod is arranged at the top end of the vertical supporting upright rod, and the upper end of the adjustable jackscrew at the top end of the vertical supporting upright rod is propped against a pre-poured L-shaped hanging plate bottom template supporting cross beam; the load of the beam concrete poured in the precast concrete beam space is sequentially transferred to the lower floor slab through the precast beam bottom formwork support wood ridge, the horizontal cantilever beam steel pipe, the C-shaped in-mouth support steel pipe upright post, the reinforced steel upright post support of the rice-shaped base, the L-shaped hanging plate bottom formwork longitudinal support wood ridge, the precast L-shaped hanging plate bottom formwork support beam and the vertical support upright post.
A method for integrally cast-in-situ construction of a beam slab and a beam bottom L-shaped hanging plate comprises the following steps:
the formwork support system for integrally pouring the beam slab and the L-shaped hanging plate at the beam bottom is firstly erected, and comprises the following steps: arranging a precast L-shaped hanging plate bottom formwork support beam on a full-hall support frame right below a precast concrete beam space, arranging an L-shaped hanging plate bottom formwork longitudinal support wood beam on the L-shaped hanging plate bottom formwork support beam, arranging an L-shaped hanging plate bottom formwork on the L-shaped hanging plate bottom formwork longitudinal support wood beam, arranging a reinforced column support of a rice-shaped base on the L-shaped hanging plate bottom formwork, arranging a column support top transverse reinforced bar on the upper part of the reinforced column support, sleeving a C-shaped mouth inner support steel tube column on the reinforced column top transverse reinforced bar, arranging a height-adjustable top support on the top of the C-shaped mouth inner support steel tube column, propping a horizontal cantilever beam steel tube on the left side of the horizontal cantilever beam steel tube, fixedly connecting the full-hall support frame, longitudinally arranging a precast beam bottom formwork support wood beam on the horizontal cantilever beam steel tube, and arranging a precast beam bottom formwork on the precast beam bottom formwork support wood beam; the method comprises the steps that L-shaped hanging plate left side vertical templates are arranged on the right side of a C-shaped opening inner support steel pipe upright post at intervals, L-shaped hanging plate left side vertical templates are arranged on the right side of the L-shaped hanging plate left side vertical templates, the lower ends of the L-shaped hanging plate left side vertical templates are supported at the right ends of transverse steel bars at the tops of upright post brackets, the upper ends of the L-shaped hanging plate left side vertical templates are butted with the right ends of precast beam bottom templates, a precast L-shaped hanging plate vertical plate space is arranged on the right side of the L-shaped hanging plate left vertical templates, a shared outer side vertical template of the L-shaped hanging plate is arranged on the right side of the L-shaped hanging plate vertical plate space, L-shaped hanging plate right side vertical templates are arranged on the right side of the shared outer side vertical templates, outer side clamping steel pipes are arranged on the right sides of the L-shaped hanging plate right side vertical templates, an L-shaped hanging plate vertical template vertical side opposite to the right ends of the steel pipes are arranged between the outer clamping steel pipes and the C-shaped opening inner support steel pipe upright posts, a precast L-shaped hanging plate vertical template vertical bolts are arranged between the outer side clamping steel pipes and the outer side vertical beams; the left side of the lower end of the vertical template at the left side of the L-shaped hanging plate is provided with a horizontal plate space of a pre-poured L-shaped hanging plate, the top end of the horizontal plate space of the L-shaped hanging plate is provided with a top vibration reserved area, and the pre-poured concrete floor plate space, the pre-poured concrete beam space, the vertical plate space of the pre-poured L-shaped hanging plate and the horizontal plate space of the pre-poured L-shaped hanging plate are communicated together; setting a vertical support upright rod on a full framing right below a horizontal plate space of a pre-poured L-shaped hanging plate, and setting an adjustable jackscrew at the top end of the vertical support upright rod;
then, the integral pouring of the beam plate and the L-shaped hanging plate at the beam bottom is sequentially completed according to the following steps:
firstly, pouring concrete in a horizontal plate space of an L-shaped hanging plate, and vibrating the poured concrete through a vibrating reserved area at the top end of the horizontal plate space of the L-shaped hanging plate;
secondly, when the top surface of the concrete pouring layer in the horizontal plate space of the L-shaped hanging plate has no bleeding phenomenon, and a vibrating rod can be inserted into the lower bottom surface in the concrete pouring layer, concrete pouring in the vertical plate space of the L-shaped hanging plate is carried out;
and thirdly, pouring the concrete floor slab space and the concrete beam space when the top surface of the concrete pouring layer of the vertical slab space of the L-shaped hanging plate has no bleeding phenomenon and the vibrating rod can be inserted into the concrete pouring layer.
A vertical supporting upright rod is arranged on a full-hall support frame under the horizontal plate space of the pre-poured L-shaped hanging plate, the top end of the vertical supporting upright rod is connected with a top-end adjustable jackscrew of the vertical supporting upright rod, and the upper end of the top-end adjustable jackscrew of the vertical supporting upright rod is propped against a pre-poured L-shaped hanging plate bottom template support beam; the load of the beam concrete poured in the precast concrete beam space is sequentially transferred to the lower floor slab through the precast beam bottom formwork support wood ridge, the horizontal cantilever beam, the C-shaped in-mouth support upright post, the steel bar upright post support of the Mi Zi-shaped base, the L-shaped hanging plate bottom formwork longitudinal support wood ridge, the precast L-shaped hanging plate bottom formwork support beam and the vertical support upright post.
And a scissor stay bar is arranged between the vertical support upright rod and the outer clamping steel pipe, and the upper end and the lower end of the scissor stay bar are respectively and fixedly connected with the full framing.
After the integrally poured beam slab and the beam bottom L-shaped hanging plate are finally solidified, the height-adjustable top support is separated from the horizontal cantilever beam by rotating the height-adjustable top support, the C-shaped intraoral support steel pipe upright post, the left-side support back edge of the L-shaped hanging plate left-side vertical formwork and the left-side vertical formwork of the L-shaped hanging plate are removed (after the horizontal cantilever beam and the pre-poured beam bottom formwork support wood edge and the pre-poured beam bottom formwork on the horizontal cantilever beam are removed, then the top adjustable top screw of the vertical support upright post is rotated, the top connection of the top adjustable top screw of the vertical support upright post to the L-shaped hanging plate bottom formwork support beam is released, the L-shaped hanging plate bottom formwork support beam and the L-shaped hanging plate bottom formwork longitudinal support wood edge and the L-shaped hanging plate bottom formwork are removed, and finally the full-hall support frame is removed, so that the beam slab and the beam bottom L-shaped hanging plate are constructed.
According to the invention, the special support is arranged in the C-shaped groove of the hanging plate, the upper part of the vertical rod at the bottom of the beam is inserted into the adjustable top support to adjust the height, so that the load of the cast-in-situ beam is vertically transferred to the lower supporting structure through the vertical rod, the technical problem that the upper beam is difficult to support is solved, the cast-in-situ beam at the upper part and the hanging plate at the lower part can be supported by a template at one time, and the beam plate and the hanging plate at the bottom of the beam are cast at one time.
Drawings
Fig. 1 is a schematic structural view of the present invention.
Description of the embodiments
The invention is described in detail below with reference to the attached drawing figures:
the template supporting system for integrally casting the beam slab and the beam bottom L-shaped hanging plate comprises a full-hall supporting frame 1, wherein an upper floor slab casting bottom template 2 and an upper beam casting left side vertical template 3 are respectively arranged at the top end of the full-hall supporting frame 1, a precast concrete floor slab space 22 is arranged on the upper floor slab casting bottom template 2, a precast concrete beam space 23 is arranged on the right side of the upper beam casting left side vertical template 3, a precast L-shaped hanging plate bottom template supporting beam 4 is arranged on the full-hall supporting frame 1 right below the precast concrete beam space 23, and the beam casting template and the L-shaped concrete hanging plate casting template are erected by taking the L-shaped hanging plate bottom template supporting beam 4 as a bottom support; an L-shaped hanging plate bottom template longitudinal support wood beam 5 is arranged on an L-shaped hanging plate bottom template support beam 4, an L-shaped hanging plate bottom template 6 is arranged on the L-shaped hanging plate bottom template longitudinal support wood beam 5, a reinforced bar column support 7 of a rice-shaped base is arranged on the L-shaped hanging plate bottom template 6, a column support top transverse reinforced bar 8 is arranged on the upper part of the reinforced bar column support 7, the top end of the reinforced bar column above the column support top transverse reinforced bar 8 is sleeved with a C-shaped opening inner support steel tube column 9, the top end of the C-shaped opening inner support steel tube column 9 is provided with a height-adjustable top support 10, the top end of the height-adjustable top support 10 is connected with a horizontal cantilever beam steel tube 11, the left side of the horizontal cantilever beam steel tube 11 is fixedly connected to a full-hall support frame 1, a precast beam bottom template support wood beam 12 is arranged on the horizontal cantilever beam steel tube 11, a precast beam bottom template 13 is arranged on the precast beam bottom template 12, and the left side end of the precast beam bottom template 13 is butted with the lower end of the upper layer 3; the right side of a steel pipe upright post 9 is supported in a C-shaped opening, an L-shaped hanging plate left side upright template left supporting back edge 14 is arranged at intervals, an L-shaped hanging plate left side upright template 15 is arranged on the right side of the L-shaped hanging plate left side upright template left supporting back edge 14, the lower end of the L-shaped hanging plate left side upright template 15 is supported at the right end of a transverse steel bar 8 at the top of an upright post bracket, the upper end of the L-shaped hanging plate left side upright template 15 is butted with the right end of a precast beam bottom template 13, a precast L-shaped hanging plate vertical template right side is arranged on the right side of the L-shaped hanging plate left side upright template 15, a precast L-shaped hanging plate vertical plate space 24 is arranged on the right side of the L-shaped hanging plate vertical plate space 24, an L-shaped hanging plate vertical plate and a beam shared right side upright template 16 are arranged on the right side of the shared right side upright template right side, an L-shaped hanging plate right side upright template outer supporting back edge 17 is arranged on the right side of the L-shaped hanging plate outer supporting back edge 17, an outer side clamping 18 is arranged on the right side of the L-shaped hanging plate outer side upright template outer supporting back edge 17, a left side clamping bolt 18 is arranged between the outer side clamping plate and the precast beam bottom template and the left side upright post 18, a left side clamping bolt 20 is arranged between the left side supporting beam and the left side vertical template and the left side supporting upright post and the left side supporting frame is arranged, and the left side clamping bolt 18 is arranged between the left side and the steel pipe upright frame and the left side supporting frame and the steel pipe upright plate and the vertical frame and the steel pipe upright frame is arranged; a horizontal plate space 25 of the pre-poured L-shaped hanging plate is arranged on the left side of the lower end of the left vertical template 15 of the L-shaped hanging plate, a vibration reserved area 26 is arranged at the top end of the horizontal plate space 25, and a pre-poured concrete floor plate space 22, a pre-poured concrete beam space 23, a vertical plate space 24 of the pre-poured L-shaped hanging plate and the horizontal plate space 25 of the pre-poured L-shaped hanging plate are communicated; the upper beam pouring left side vertical template 3 and the shared right side vertical template 16 are fixed in the left-right direction through the inner side clamping steel pipe 29 in the full-hall support frame 1; the inner clamping steel pipe 29, the L-shaped hanging plate bottom template supporting cross beam 4 and the outer clamping steel pipe 18 form a U-shaped space for constructing a beam and an L-shaped hanging plate at the beam bottom, and a beam plate integrated pouring template system which is convenient to disassemble and assemble is constructed in the U-shaped space, so that the invention contributes to the creative contribution of the prior art.
A vertical support upright rod 21 is arranged on the full-hall support frame 1 under the horizontal plate space 25 of the pre-poured L-shaped hanging plate, a vertical support upright rod top end adjustable top support 27 is arranged at the top end of the vertical support upright rod 21, the upper end of the vertical support upright rod top end adjustable top support 27 is propped against the pre-poured L-shaped hanging plate bottom template support beam 4, and a plurality of vertical support upright rods 21 can be arranged according to the load; the load of the beam concrete poured in the precast concrete beam space 23 is transmitted to the lower floor plate sequentially through the precast beam bottom template supporting wood ridge 12, the horizontal cantilever beam steel pipe 11, the C-shaped in-opening supporting steel pipe column 9, the reinforced steel column support 7 of the rice-shaped base, the L-shaped hanging plate bottom template 6, the L-shaped hanging plate bottom template longitudinal supporting wood ridge 5, the precast L-shaped hanging plate bottom template supporting cross beam 4 and the vertical supporting upright rod 21.
A method for integrally cast-in-situ construction of a beam slab and a beam bottom L-shaped hanging plate comprises the following steps:
the formwork support system for integrally pouring the beam slab and the L-shaped hanging plate at the beam bottom is firstly erected, and comprises the following steps: a full hall support frame 1 right below a precast concrete beam space 23 is provided with a precast L-shaped hanging plate bottom formwork support beam 4, an L-shaped hanging plate bottom formwork longitudinal support wood beam 5 is arranged on the L-shaped hanging plate bottom formwork support beam 4, an L-shaped hanging plate bottom formwork 6 is arranged on the L-shaped hanging plate bottom formwork longitudinal support wood beam 5, a reinforced column support 7 of a rice-shaped base is arranged on the L-shaped hanging plate bottom formwork 6, a column support top transverse reinforced bar 8 is arranged at the upper part of the reinforced column support 7, a reinforced column top end above the column support top transverse reinforced bar 8 is sleeved with a C-shaped opening inner support steel tube column 9, a height-adjustable top support 10 is arranged at the top end of the C-shaped opening inner support steel tube column 9, a horizontal cantilever beam steel tube 11 is propped, the left side of the horizontal cantilever beam steel tube 11 is fixedly connected to the full hall support frame 1, a precast beam bottom formwork support wood beam 12 is longitudinally arranged on the horizontal cantilever beam steel tube 11, and a precast beam bottom formwork support wood beam 12 is arranged on the precast beam bottom formwork support 13; the method comprises the steps that L-shaped hanging plate left side vertical formwork left support back ribs 14 are arranged at intervals on the right side of a C-shaped opening inner support steel pipe upright post 9, L-shaped hanging plate left side vertical formwork 15 is arranged on the right side of the L-shaped hanging plate left side vertical formwork left support back rib 14, the lower end of the L-shaped hanging plate left side vertical formwork 15 is supported at the right end of a transverse steel bar 8 at the top of an upright post bracket, the upper end of the L-shaped hanging plate left side vertical formwork 15 is butted with the right end of a precast beam bottom formwork 13, a precast L-shaped hanging plate left side vertical formwork 15 is arranged on the right side of the L-shaped hanging plate left side vertical formwork 15, a precast L-shaped hanging plate vertical plate space 24 is arranged on the right side of the L-shaped hanging plate vertical plate space 24, a common outer side vertical formwork 16 of the L-shaped hanging plate is arranged on the right side of the common outer vertical formwork 16, an outer side steel pipe clamping 18 is arranged on the right side of the L-shaped hanging plate right support back rib 17, a precast steel pipe clamping 18 is arranged between the outer side clamping 18 and the C-shaped opening inner support beam bottom formwork 13, a pull-up end of the L-shaped hanging plate is arranged between the two upright posts and the two upright posts 20; the left side of the lower end of the left vertical template 15 of the L-shaped hanging plate is provided with a horizontal plate space 25 of a pre-poured L-shaped hanging plate, the top end of the horizontal plate space 25 of the L-shaped hanging plate is provided with a top vibration reserved area 26, and the pre-poured concrete floor plate space 22, the pre-poured concrete beam space 23, the vertical plate space 24 of the pre-poured L-shaped hanging plate and the horizontal plate space 25 of the pre-poured L-shaped hanging plate are communicated together; a vertical support upright rod 21 is arranged on a full-hall support frame 1 under a horizontal plate space 25 of a pre-poured L-shaped hanging plate, and an adjustable top support 27 at the top end of the vertical support upright rod 21 is arranged at the top end of the vertical support upright rod;
then, the integral pouring of the beam plate and the L-shaped hanging plate at the beam bottom is sequentially completed according to the following steps:
firstly, pouring concrete in a horizontal plate space 25 of an L-shaped hanging plate, and vibrating the poured concrete through a vibrating reserved area 26 at the top end of the horizontal plate space 25 of the L-shaped hanging plate;
secondly, when the top surface of the concrete pouring layer of the horizontal plate space 25 of the L-shaped hanging plate is initially set and has no bleeding phenomenon, and a vibrating rod can be inserted into the lower bottom surface of the concrete pouring layer, concrete pouring is carried out on the vertical plate space 24 of the L-shaped hanging plate;
and thirdly, pouring the concrete floor slab space 22 and the concrete beam space 23 when the top surface of the concrete pouring layer of the vertical slab space 24 of the L-shaped hanging plate is initially set and has no bleeding phenomenon, and a vibrating rod can be inserted into the concrete pouring layer.
A vertical support upright rod 21 is arranged on a full-hall support frame 1 under a horizontal plate space 25 of a pre-poured L-shaped hanging plate, the top end of the vertical support upright rod 21 is connected with a top end adjustable jackscrew 27 of the vertical support upright rod, and the upper end of the top end adjustable jackscrew 27 of the vertical support upright rod is propped against a pre-poured L-shaped hanging plate bottom template support beam 4; the load of the beam concrete poured in the precast concrete beam space 23 is sequentially transferred to the lower floor plate through the precast beam bottom template supporting wood ridge 12, the horizontal cantilever beam steel pipe 11, the C-shaped in-opening supporting steel pipe column 9, the steel bar column support 7 of the Mi Zi-shaped base, the L-shaped hanging plate bottom template 6, the L-shaped hanging plate bottom template longitudinal supporting wood ridge 5, the precast L-shaped hanging plate bottom template supporting cross beam 4 and the vertical supporting upright rod 21.
A scissor brace 28 is arranged between the vertical support upright rod 21 and the outer clamping steel pipe 18, and the upper end and the lower end of the scissor brace 28 are respectively and fixedly connected with the full-hall support frame 1.
After the integrally poured beam slab and the beam bottom L-shaped hanging plate are finally solidified, the height-adjustable top support 10 is separated from the horizontal cantilever beam steel pipe 11 by rotating the height-adjustable top support 10, and after the C-shaped intraoral support steel pipe upright post 9, the left support back ridge 14 of the left side vertical template of the L-shaped hanging plate and the left vertical template 15 of the L-shaped hanging plate are removed, the horizontal cantilever beam steel pipe 11, the pre-poured beam bottom template support wood ridge 12 and the pre-poured beam bottom template 13 on the horizontal cantilever beam steel pipe are removed; then, the top adjustable top support 27 of the vertical support upright rod is rotated to release the top connection of the top adjustable top support 27 of the vertical support upright rod to the L-shaped hanging plate bottom formwork support beam 4, and the L-shaped hanging plate bottom formwork support beam 4, the L-shaped hanging plate bottom formwork longitudinal support wood ridge 5 and the L-shaped hanging plate bottom formwork 6 are removed; and finally, dismantling the full framing 1 to construct the beam plate and the L-shaped hanging plate at the beam bottom.

Claims (2)

1. The utility model provides a template braced system that beam slab and beam bottom L shape link plate integrally cast, including filling in hall support frame (1), be provided with upper floor slab casting die table (2) and upper beam casting left side upright template (3) respectively in the top of filling in hall support frame (1), be provided with concrete floor slab space (22) of pouring in advance on upper floor slab casting die table (2), right side of upper beam casting left side upright template (3) is provided with concrete beam space (23) of pouring in advance, characterized in that, on filling in hall support frame (1) under concrete beam space (23) of pouring in advance, be provided with L shape link plate end template bracing beam (4) of pouring in advance, be provided with L shape link plate end template longitudinal support wood stupefied (5) on L shape link plate end template longitudinal support wood stupefied (5), be provided with meter base's stand (7) on L shape link plate end template (6), stand (7) of setting up in a pair of stand, stand top (8) in a stand top of steel pipe (8) can cup joint in the top of steel bar port in the top of the stand (9) of steel bar, the top of steel bar top of the stand (9) is cup jointed, the top end of the height-adjustable top support (10) is propped with a horizontal cantilever beam steel pipe (11), the left side of the horizontal cantilever beam steel pipe (11) is fixedly connected to the full-hall support frame (1), the horizontal cantilever beam steel pipe (11) is provided with a precast beam bottom formwork support wood ridge (12), the precast beam bottom formwork support wood ridge (12) is provided with a precast beam bottom formwork (13), and the left end of the precast beam bottom formwork (13) is butted with the lower end of the upper beam pouring left side vertical formwork (3); the steel pipe support is characterized in that the right side of a steel pipe upright post (9) is supported in a C-shaped opening, L-shaped hanging plate left side vertical templates are arranged at intervals, L-shaped hanging plate left side vertical templates (14) are arranged on the right side of the L-shaped hanging plate left side vertical templates, L-shaped hanging plate left side vertical templates (15) are arranged on the right side of the L-shaped hanging plate left side vertical templates, the lower ends of the L-shaped hanging plate left side vertical templates (15) are supported at the right ends of transverse steel bars (8) at the tops of upright post brackets, the upper ends of the L-shaped hanging plate left side vertical templates (15) are butted with the right ends of pre-cast beam bottom templates (13), a pre-cast L-shaped hanging plate vertical plate space (24) is arranged on the right side of the L-shaped hanging plate left side vertical templates (15), a shared right side vertical plate and a beam vertical plate (16) of the L-shaped hanging plate are arranged, an L-shaped hanging plate right side vertical supporting back supporting template (17) is arranged on the right side of the shared right side of the vertical template (16), a clamping vertical plate (18) is arranged on the outer side of the two steel pipe upright posts (18), and a clamping bolt (18) is arranged between the two outer side vertical plates (18) and the outer side of the steel pipe support upright post (18), and the two outer side vertical templates are clamped tightly; the left side of the lower end of the left vertical template (15) of the L-shaped hanging plate is provided with a horizontal plate space (25) of the pre-poured L-shaped hanging plate, the top end of the horizontal plate space (25) is provided with a vibrating reserved area (26), and the pre-poured concrete floor plate space (22), the pre-poured concrete beam space (23), the vertical plate space (24) of the pre-poured L-shaped hanging plate and the horizontal plate space (25) of the pre-poured L-shaped hanging plate are communicated together.
2. The formwork support system for integrally casting a beam slab and an L-shaped hanging plate at the beam bottom according to claim 1 is characterized in that a vertical support upright rod (21) is arranged on a full-hall support frame (1) right below a horizontal plate space (25) of the pre-cast L-shaped hanging plate, a vertical support upright rod top end adjustable top support (27) is arranged at the top end of the vertical support upright rod (21), and the upper end of the vertical support upright rod top end adjustable top support (27) is propped against a pre-cast L-shaped hanging plate bottom formwork support beam (4); the load of the beam concrete poured in the precast concrete beam space (23) is sequentially transferred to the lower floor plate through the precast beam bottom template supporting wood ridge (12), the horizontal cantilever beam steel pipe (11), the C-shaped intraoral supporting steel pipe column (9), the reinforced steel column support (7) of the rice-shaped base, the L-shaped hanging plate bottom template (6), the L-shaped hanging plate bottom template longitudinal supporting wood ridge (5), the precast L-shaped hanging plate bottom template supporting cross beam (4) and the vertical supporting upright rod (21).
CN202310906150.8A 2023-07-24 2023-07-24 Template supporting system for integrally pouring beam plate and beam bottom L-shaped hanging plate Pending CN116892289A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202310906150.8A CN116892289A (en) 2023-07-24 2023-07-24 Template supporting system for integrally pouring beam plate and beam bottom L-shaped hanging plate

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202310906150.8A CN116892289A (en) 2023-07-24 2023-07-24 Template supporting system for integrally pouring beam plate and beam bottom L-shaped hanging plate

Publications (1)

Publication Number Publication Date
CN116892289A true CN116892289A (en) 2023-10-17

Family

ID=88311961

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202310906150.8A Pending CN116892289A (en) 2023-07-24 2023-07-24 Template supporting system for integrally pouring beam plate and beam bottom L-shaped hanging plate

Country Status (1)

Country Link
CN (1) CN116892289A (en)

Similar Documents

Publication Publication Date Title
CN111335181A (en) Mounting support frame and mounting method for cast-in-place concrete structure template of steel-concrete composite beam flange plate
CN111335620B (en) Assembled template and construction method thereof
CN114214917A (en) Steel pipe concrete tied arch bridge and construction method
CN113482007A (en) Waist beam supporting structure and construction method thereof
CN220451424U (en) Template supporting system for integrally pouring beam plate and beam bottom L-shaped hanging plate
CN115110685B (en) Support system of prefabricated assembly component and construction method thereof
CN116892289A (en) Template supporting system for integrally pouring beam plate and beam bottom L-shaped hanging plate
CN216893447U (en) Hidden back edge non-dismantling formwork for forming reinforced concrete member
CN107882243B (en) A kind of cassette ceiling and construction method of concrete-filled rectangular steel tube waffle beam structure
CN111851318B (en) Cantilever bridge side span formwork system and construction method thereof
CN115741984A (en) Preparation method of steel tube concrete edge constraint superposed shear wall
CN215167163U (en) Shear structure and maintenance structure integrated prefabricated hoisting wallboard unit
CN116657898A (en) Integral cast-in-situ construction method for beam plate and beam bottom L-shaped hanging plate
CN109610707A (en) A kind of design and rapid constructing method of prefabricated girder steel and floor fit flush
CN212025941U (en) Cast-in-place concrete structure formwork mounting support frame for steel-concrete composite beam flange plate
CN115058976A (en) Aluminum alloy internal mold system containing diaphragm plate and variable cross-section cast-in-place box girder and construction method thereof
CN210916968U (en) Cast-in-place box girder supporting structure
CN114197856A (en) Hidden back edge dismantling-free template for forming reinforced concrete member and construction process
CN112982968A (en) Inverted ridge template structure and construction method thereof
CN113338614A (en) Adjustable template structure for column caps of beamless floor
CN101324086A (en) Construction method of large-span box variable cross-section reinforcement concrete arch
CN112878204A (en) Construction process of cast-in-place anchor beam hanger system
CN220414314U (en) Formwork support structure for concrete retaining wall construction
CN218375212U (en) Frame beam slab pouring construction structure
CN214883009U (en) Viaduct jacking bearing platform pier stud upgrading structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination