CN116641558A - Method for mounting single-layer hollow slat - Google Patents
Method for mounting single-layer hollow slat Download PDFInfo
- Publication number
- CN116641558A CN116641558A CN202211342889.2A CN202211342889A CN116641558A CN 116641558 A CN116641558 A CN 116641558A CN 202211342889 A CN202211342889 A CN 202211342889A CN 116641558 A CN116641558 A CN 116641558A
- Authority
- CN
- China
- Prior art keywords
- slat
- installing
- battens
- mounting
- fixing
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000000034 method Methods 0.000 title claims abstract description 16
- 239000002356 single layer Substances 0.000 title claims abstract description 11
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 11
- 239000000853 adhesive Substances 0.000 claims abstract description 11
- 230000001070 adhesive effect Effects 0.000 claims abstract description 11
- 238000009434 installation Methods 0.000 claims abstract description 11
- 239000010959 steel Substances 0.000 claims abstract description 11
- 239000004568 cement Substances 0.000 claims abstract description 8
- 239000011248 coating agent Substances 0.000 claims abstract description 8
- 238000000576 coating method Methods 0.000 claims abstract description 8
- 239000010410 layer Substances 0.000 claims abstract description 8
- 238000004140 cleaning Methods 0.000 claims abstract description 7
- 239000004744 fabric Substances 0.000 claims abstract description 4
- 238000003825 pressing Methods 0.000 claims description 3
- 238000010276 construction Methods 0.000 abstract description 9
- 239000004035 construction material Substances 0.000 description 1
- 238000005336 cracking Methods 0.000 description 1
- 230000007547 defect Effects 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 238000011900 installation process Methods 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
- E04G21/14—Conveying or assembling building elements
- E04G21/142—Means in or on the elements for connecting same to handling apparatus
- E04G21/145—Means in or on the elements for connecting same to handling apparatus specific for hollow plates
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B2/00—Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
- E04B2/72—Non-load-bearing walls of elements of relatively thin form with respect to the thickness of the wall
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Mechanical Engineering (AREA)
- Physics & Mathematics (AREA)
- Electromagnetism (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
The invention relates to a method for installing a single-layer hollow slat; comprises the steps of 1, cleaning a base layer and paying out; step 2, installing and fixing steel clamps and coating adhesives, fixing U-shaped steel clamps on the structural wall or column, and fully coating adhesives on the base layer and the side edges of the wallboard; step 3, installing a first slat; step 4, mounting other slats and processing the seams, and sequentially mounting subsequent slats according to the mounting method of the first plate; after the battens are installed, cement putty is scraped at the joint of the battens, gridding cloth is pasted, the battens are compacted and firmly stuck, and the surface is scraped with the cement putty. Compared with the traditional and disordered hollow strip plate construction method, the strip plate installation method provided by the invention is simple and convenient to construct and easy to operate, and the on-site installation progress and quality of the single-layer concrete hollow strip plate can be greatly improved.
Description
Technical Field
The invention relates to the technical field of wall construction in buildings, in particular to a method for installing a single-layer hollow slat.
Background
Hollow laths are construction materials commonly used in the construction field, which are commonly used for the construction of non-load bearing walls. However, the current construction of the hollow lath lacks a standardized construction process, so that the problems of cracking, overlarge gaps, position deviation and wall collapse easily occur after the hollow lath is installed.
Disclosure of Invention
The invention aims to overcome the defects and provides an installation process for a single-layer hollow slat.
In order to achieve the above object, the present invention is achieved by:
a method for installing a single-layer hollow slat comprises
Step 1, cleaning and paying off a base layer, cleaning sundries at positions where the laths are required to be arranged, and popping up position lines, wall lines and control lines according to the installation positions of the laths;
step 2, installing and fixing steel clamps and coating adhesives, fixing U-shaped steel clamps on the structural wall or column, and fully coating adhesives on the base layer and the side edges of the wallboard;
and 3, installing a first slat, aligning the slat to the positioning line, standing the slat, and adjusting the verticality and flatness of the wall surface by using a guiding ruler and a prying root after the wallboard is in place. After adjustment, the lower part of the slat is tightly propped by a wooden wedge to play a role of temporary fixation. Fixing a U-shaped steel clamping piece arranged at the upper part of the slat with a beam plate by using a shooting nail, and timely pressing an adhesive extruded out of the slab joint into the slab joint;
and 4, installing other slats and processing the seams, and sequentially installing the subsequent slats according to the installation method of the first plate. After the battens are installed, cement putty is scraped at the joint of the battens, gridding cloth is pasted, the battens are compacted and firmly stuck, and the surface is scraped with the cement putty.
Compared with the traditional and disordered hollow strip plate construction method, the strip plate installation method provided by the invention is simple and convenient to construct and easy to operate, and the on-site installation progress and quality of the single-layer concrete hollow strip plate can be greatly improved.
Drawings
Fig. 1 is a schematic process diagram of the present construction method.
Detailed Description
The invention is further illustrated by the following specific examples.
A method for installing a single-layer hollow slat comprises
Step 1, cleaning and paying off a base layer, cleaning sundries at positions where the laths are required to be arranged, and popping up position lines, wall lines and control lines according to the installation positions of the laths;
step 2, installing and fixing steel clamps and coating adhesives, fixing U-shaped steel clamps on the structural wall or column, and fully coating adhesives on the base layer and the side edges of the wallboard;
and 3, installing a first slat, aligning the slat to the positioning line, standing the slat, and adjusting the verticality and flatness of the wall surface by using a guiding ruler and a prying root after the wallboard is in place. After adjustment, the lower part of the slat is tightly propped by a wooden wedge to play a role of temporary fixation. Fixing a U-shaped steel clamping piece arranged at the upper part of the slat with a beam plate by using a shooting nail, and timely pressing an adhesive extruded out of the slab joint into the slab joint;
and 4, installing other slats and processing the seams, and sequentially installing the subsequent slats according to the installation method of the first plate. After the battens are installed, cement putty is scraped at the joint of the battens, gridding cloth is pasted, the battens are compacted and firmly stuck, and the surface is scraped with the cement putty.
Compared with the traditional and disordered hollow strip plate construction method, the strip plate installation method provided by the invention is simple and convenient to construct and easy to operate, and the on-site installation progress and quality of the single-layer concrete hollow strip plate can be greatly improved.
Claims (1)
1. A method for installing a single-layer hollow slat is characterized in that: comprising
Step 1, cleaning and paying off a base layer, cleaning sundries at positions where the laths are required to be arranged, and popping up position lines, wall lines and control lines according to the installation positions of the laths;
step 2, installing and fixing steel clamps and coating adhesives, fixing U-shaped steel clamps on the structural wall or column, and fully coating adhesives on the base layer and the side edges of the wallboard;
step 3, installing a first slat, aligning the slat to a positioning line rear vertical plate, and adjusting the verticality and flatness of the wall surface by using a guiding ruler and a prying root after the wallboard is in place; after adjustment, the lower part of the slat is tightly propped by a wooden wedge to play a role of temporary fixation; fixing a U-shaped steel clamping piece arranged at the upper part of the slat with a beam plate by using a shooting nail, and timely pressing an adhesive extruded out of the slab joint into the slab joint;
step 4, mounting other slats and processing the seams, and sequentially mounting subsequent slats according to the mounting method of the first plate; after the battens are installed, cement putty is scraped at the joint of the battens, gridding cloth is pasted, the battens are compacted and firmly stuck, and the surface is scraped with the cement putty.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202211342889.2A CN116641558A (en) | 2022-10-31 | 2022-10-31 | Method for mounting single-layer hollow slat |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202211342889.2A CN116641558A (en) | 2022-10-31 | 2022-10-31 | Method for mounting single-layer hollow slat |
Publications (1)
Publication Number | Publication Date |
---|---|
CN116641558A true CN116641558A (en) | 2023-08-25 |
Family
ID=87638746
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202211342889.2A Pending CN116641558A (en) | 2022-10-31 | 2022-10-31 | Method for mounting single-layer hollow slat |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN116641558A (en) |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100682541B1 (en) * | 2005-08-30 | 2007-02-15 | 장강 | A c.f.c board d-wall panel and construct method of wall |
CN101761155A (en) * | 2008-10-27 | 2010-06-30 | 侯向煜 | Construction method for ceramsite concrete light-weight wall boards |
CN106499091A (en) * | 2016-11-22 | 2017-03-15 | 中国建筑第七工程局有限公司 | A kind of assembling type partition wall construction method based on ALC plates |
CN110258862A (en) * | 2019-07-03 | 2019-09-20 | 深圳建中路桥工程有限公司 | A kind of partition wall construction method of hollow lath |
CN114809378A (en) * | 2021-01-19 | 2022-07-29 | 丰屋蔀家科技(深圳)有限公司 | Mounting method of assembled partition board |
-
2022
- 2022-10-31 CN CN202211342889.2A patent/CN116641558A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100682541B1 (en) * | 2005-08-30 | 2007-02-15 | 장강 | A c.f.c board d-wall panel and construct method of wall |
CN101761155A (en) * | 2008-10-27 | 2010-06-30 | 侯向煜 | Construction method for ceramsite concrete light-weight wall boards |
CN106499091A (en) * | 2016-11-22 | 2017-03-15 | 中国建筑第七工程局有限公司 | A kind of assembling type partition wall construction method based on ALC plates |
CN110258862A (en) * | 2019-07-03 | 2019-09-20 | 深圳建中路桥工程有限公司 | A kind of partition wall construction method of hollow lath |
CN114809378A (en) * | 2021-01-19 | 2022-07-29 | 丰屋蔀家科技(深圳)有限公司 | Mounting method of assembled partition board |
Non-Patent Citations (3)
Title |
---|
刘昕;孙威;: "房屋建筑工业灰渣混凝土空心隔墙条板内隔墙的施工技术", 工程质量, no. 05, pages 58 - 61 * |
张富国;宋印秀;: "浅述确保GRC空心条板隔墙施工质量措施", 科技信息, no. 17, pages 290 * |
罗禹;: "GRC条板隔墙裂缝的原因分析及防治措施", 山西建筑, no. 29, pages 153 - 154 * |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107605071B (en) | Light composite batten system and construction method thereof | |
CN112942812A (en) | Positioning device for shear wall template and method for mounting template by using same | |
CN116641558A (en) | Method for mounting single-layer hollow slat | |
CN210263490U (en) | Assembled wall that possesses adjustable extending structure | |
CN117661844A (en) | Light energy-saving wall partition board installation construction method | |
CN114809378A (en) | Mounting method of assembled partition board | |
CN218374567U (en) | Can fix a position ALC wallboard reinforced structure that can exempt from to plaster | |
CN116641557A (en) | Method for mounting double-layer hollow slat | |
CN101538904B (en) | Gypsum powder poured integral wall and manufacturing method thereof | |
CN215759873U (en) | Dry construction concrete external wallboard system applying rain curtain principle | |
CN215253670U (en) | Integrally assembled outer wall with heat insulation layer PCF | |
CN110259144A (en) | A kind of novel energy-saving environment-friendly ash concrete lightweight wall plate construction method | |
EP3020883A1 (en) | System for mounting of wall and/or roof cladding materials and method for mounting of wall and/or roof cladding on a building structure | |
CN202284291U (en) | Concrete overflowing surface template shaped like Chinese character ba | |
CN218952812U (en) | Vertical template positioning structure | |
CN219298535U (en) | Combined light partition board partition system | |
CN219365155U (en) | Prefabricated constructional column structure matched with light partition board | |
CN118564077A (en) | Construction method for light concrete hollow partition wall joint in assembled building | |
CN216239154U (en) | Horizontal structure of assembling of prefabricated hollow slat of ardealite | |
CN219138229U (en) | ALC side fascia fixed knot constructs | |
CN219219543U (en) | Assembled building wallboard | |
CN219973542U (en) | Auxiliary device for pre-paving self-adhesive film waterproof coiled material on side wall | |
CN219732312U (en) | BIM-based residential apartment AAC outer wall slat angle steel inverted installation structure | |
CN115234007B (en) | Method for filling light materials on two sides of web plate of I-shaped steel beam of assembled steel structure house | |
CN114059685B (en) | ALC plate wall body installation method applied after prestressing |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination |