CN216239154U - Horizontal structure of assembling of prefabricated hollow slat of ardealite - Google Patents

Horizontal structure of assembling of prefabricated hollow slat of ardealite Download PDF

Info

Publication number
CN216239154U
CN216239154U CN202122771861.8U CN202122771861U CN216239154U CN 216239154 U CN216239154 U CN 216239154U CN 202122771861 U CN202122771861 U CN 202122771861U CN 216239154 U CN216239154 U CN 216239154U
Authority
CN
China
Prior art keywords
hollow
main body
phosphogypsum
seismic
shaped steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202122771861.8U
Other languages
Chinese (zh)
Inventor
谭杰
赵在宽
郭庆明
覃昱文
李国星
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Eleventh Construct On Engineering Co ltd Of Guizhou Construction Engineering Corp
Original Assignee
Eleventh Construct On Engineering Co ltd Of Guizhou Construction Engineering Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Eleventh Construct On Engineering Co ltd Of Guizhou Construction Engineering Corp filed Critical Eleventh Construct On Engineering Co ltd Of Guizhou Construction Engineering Corp
Priority to CN202122771861.8U priority Critical patent/CN216239154U/en
Application granted granted Critical
Publication of CN216239154U publication Critical patent/CN216239154U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Building Environments (AREA)

Abstract

The utility model discloses a transverse assembling structure of a phosphogypsum prefabricated hollow slat, which comprises a hollow slat main body, constructional columns and a structural floor, wherein the length direction of the hollow slat main body is parallel to the ground, namely the axis of a hollow hole is parallel to the ground, the width direction of the hollow slat main body is vertical to the structural floor, the bottom edge of the length of the hollow slat main body is connected with the structural floor through an anti-seismic U-shaped steel clip and a special bonding phosphogypsum, one side of the hollow slat main body is connected with the constructional columns through the anti-seismic U-shaped steel clip and the special bonding phosphogypsum, and the upper edge of the length of the hollow slat main body is connected with the previous hollow slat through the special bonding phosphogypsum and an anti-cracking latticed belt until reaching the required height; the anti-seismic U-shaped steel clip and the special bonding phosphogypsum on the other side of the hollow batten main body are connected with the constructional column until the required length is reached. The utility model has transverse assembly construction, so that the bonding gypsum at the joint can be uniformly coated and firmly connected up and down, the integral stability of the wall body is enhanced, and the potential safety hazard of quality is eliminated.

Description

Horizontal structure of assembling of prefabricated hollow slat of ardealite
Technical Field
The utility model belongs to the technical field of building construction, and particularly relates to a transverse assembling structure of a phosphogypsum prefabricated hollow slat.
Background
In order to promote the green development of the phosphorus chemical industry, the comprehensive utilization of phosphogypsum resources is promoted, the novel green building material of the phosphogypsum is also applied to the engineering, the phosphogypsum prefabricated hollow strip plate is a novel wall material which is identified, the phosphogypsum prefabricated hollow strip plate is widely applied to the assembling process of a non-bearing wall body, the common assembling mode is vertical assembling, namely, the axis of a hollow hole is perpendicular to the ground, a plurality of assembling seams exist in the vertical assembling, the bonding gypsum at the seams is easily smeared unevenly during the assembling, the gypsum is easily dropped, and certain potential quality hazards exist at the seams. Therefore, in order to further improve the overall stability of the non-bearing wall body, a transverse assembling structure of the phosphogypsum hollow lath is provided.
Disclosure of Invention
The utility model provides a transverse splicing structure of phosphogypsum prefabricated hollow battens, which aims to solve the problems that gypsum is easy to fall off and is unevenly coated when the joint construction exists in the vertical splicing of the conventional phosphogypsum hollow battens.
The utility model aims to adopt the following technical scheme to form:
a transverse assembling structure of a phosphogypsum prefabricated hollow slat comprises a hollow slat main body, constructional columns and a structural floor, wherein the length direction of the hollow slat main body is parallel to the ground, namely the axis of a hollow hole is parallel to the ground, the width direction of the hollow slat main body is vertical to the structural floor, the bottom edge of the hollow slat main body is connected with the structural floor through an anti-seismic U-shaped steel clip and a special bonding phosphogypsum, one side of the hollow slat main body is connected with the constructional columns through the anti-seismic U-shaped steel clip and the special bonding phosphogypsum, and the upper edge of the hollow slat main body is connected with the previous hollow slat through the special bonding phosphogypsum and an anti-cracking latticed belt until reaching the required height; the anti-seismic U-shaped steel clip and the special bonding phosphogypsum on the other side of the hollow batten main body are connected with the constructional column until the required length is reached.
Length by height of the hollow flight body =2950mm by 600mm by 100 mm.
And one constructional column is correspondingly arranged in the length direction of each 3m of the hollow strip plate main body.
And smearing a plastering layer on the whole wall.
The utility model has the beneficial effects that:
through the construction of transversely assembling of prefabricated phosphorus gypsum board for the junction bonding gypsum can paint even, fundamentally changes the vertical problem of easily falling the gypsum of assembling, and the bonding gypsum fully receives the extrusion of upper portion slat simultaneously, and firm in connection from top to bottom strengthens the overall stability of wall body, eliminates quality potential safety hazard.
Drawings
Figure 1 is a schematic view of the structure of the present invention,
fig. 2 is a sectional view of fig. 1.
FIG. 3 is a partial schematic view of the attachment of the hollow flight body to the structural floor.
The labels in the figure are: 1. the building floor comprises a hollow batten main body, 2, an anti-seismic U-shaped steel clamp, 3, special bonding phosphogypsum, 4, an anti-crack grid belt, 5, a constructional column, 6, a plastering layer and 7, and a structural floor.
Detailed Description
The utility model is further described below by means of figures and examples.
Referring to fig. 1-3, a phosphogypsum prefabricated hollow slat transverse splicing structure comprises a hollow slat main body 1, a constructional column 5 and a structural floor 7, wherein the length direction of the hollow slat main body 1 is parallel to the ground, namely the axis of a hollow hole is parallel to the ground, the width direction of the hollow slat main body 1 is vertical to the structural floor 7, the length bottom edge of the hollow slat main body 1 is connected with the structural floor 7 through an anti-seismic U-shaped steel clip 2 and a special bonding phosphogypsum 3, one side of the hollow slat main body 1 is connected with the constructional column 5 through the anti-seismic U-shaped steel clip 2 and the special bonding phosphogypsum 3, and the length upper edge of the hollow slat main body 1 is connected with the previous hollow slat through the special bonding phosphogypsum 3 and an anti-cracking grid belt 4 until reaching the required height; the anti-seismic U-shaped steel clip 2 and the special bonding phosphogypsum 3 on the other side of the hollow batten main body 1 are connected with the constructional column 5 until the required length is reached.
The length by height =2950mm by 600mm by 100mm of the hollow strip body 1.
The hollow strip body 1 is correspondingly provided with one constructional column 5 every 3m in the length direction.
And smearing a plastering layer 6 on the whole wall.
When the device is used, the positions of the constructional columns and the building floor U-shaped steel clamps are determined according to a design drawing, the corresponding positions of the ground and the constructional columns are roughened and moistened and cleaned, special bonding phosphogypsum is uniformly coated on the joints of the battens, the building floor and the constructional columns, the battens are extruded into the U-shaped steel clamps arranged on the building floor and the side constructional columns by aligning a positioning line, the flatness and the verticality of the surface of each batten are ensured, bonding gypsum is uniformly coated on the top surfaces of the battens which are transversely installed, the next batten is installed, and the like, and the installation of the battens is completed until the last batten is clamped into the building top surface to preset the U-shaped steel clamps. And finally, plastering the wall body after the installation of the anti-cracking grid belts at the splicing part of the phosphogypsum prefabricated ribbon board is finished, and finishing the construction of the phosphogypsum prefabricated hollow slab wall body.
The above description is only a preferred embodiment of the present invention, and is not intended to limit the present invention in any way, and any simple modification, equivalent change and modification made to the above embodiment according to the technical spirit of the present invention are within the scope of the technical solution of the present invention without departing from the technical solution of the present invention.

Claims (4)

1. The utility model provides a structure is transversely assembled to prefabricated hollow slat of ardealite which characterized in that: the anti-cracking hollow batten comprises a hollow batten main body (1), a constructional column (5) and a structural floor (7), wherein the length direction of the hollow batten main body (1) is parallel to the ground, namely the axis of a hollow hole is parallel to the ground, the width direction of the hollow batten main body (1) is vertical to the structural floor (7), the length bottom edge of the hollow batten main body (1) is connected with the structural floor (7) through an anti-seismic U-shaped steel card (2) and a special bonding phosphogypsum (3), one side of the hollow batten main body (1) is connected with the constructional column (5) through the anti-seismic U-shaped steel card (2) and the special bonding phosphogypsum (3), and the length upper edge of the hollow batten main body (1) is connected with a previous hollow batten through the special bonding phosphogypsum (3) and an anti-cracking grid belt (4) until the required height is reached; the anti-seismic U-shaped steel clip (2) and the special bonding phosphogypsum (3) on the other side of the hollow batten main body (1) are connected with the constructional column (5) until the required length is reached.
2. The transverse assembling structure of the phosphogypsum prefabricated hollow lath as claimed in claim 1, is characterized in that: the hollow strip body (1) is long by thick =2950mm by 600mm by 100 mm.
3. The transverse assembling structure of the phosphogypsum prefabricated hollow lath as claimed in claim 1, is characterized in that: the hollow lath main body (1) is correspondingly provided with a constructional column (5) every 3m in the length direction.
4. The transverse assembling structure of the phosphogypsum prefabricated hollow lath as claimed in claim 1, is characterized in that: and a plastering layer (6) is smeared on the whole wall body.
CN202122771861.8U 2021-11-12 2021-11-12 Horizontal structure of assembling of prefabricated hollow slat of ardealite Active CN216239154U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202122771861.8U CN216239154U (en) 2021-11-12 2021-11-12 Horizontal structure of assembling of prefabricated hollow slat of ardealite

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202122771861.8U CN216239154U (en) 2021-11-12 2021-11-12 Horizontal structure of assembling of prefabricated hollow slat of ardealite

Publications (1)

Publication Number Publication Date
CN216239154U true CN216239154U (en) 2022-04-08

Family

ID=80996142

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202122771861.8U Active CN216239154U (en) 2021-11-12 2021-11-12 Horizontal structure of assembling of prefabricated hollow slat of ardealite

Country Status (1)

Country Link
CN (1) CN216239154U (en)

Similar Documents

Publication Publication Date Title
CN110374230B (en) Mounting node of light partition board of outer wall and construction method of mounting node
CN111549995A (en) Environment-friendly wall ceramic tile dry hanging structure and construction method thereof
CN111734016A (en) Anti-cracking inner partition wall applied to assembled steel structure and construction method thereof
CN216239154U (en) Horizontal structure of assembling of prefabricated hollow slat of ardealite
CN110777971A (en) PC wallboard mounting structure and construction method thereof
CN107217783B (en) Assembled integral external wall panel
CN215889114U (en) Assembled wall surface hanging structure
CN110306789B (en) Construction method for erecting side template of roof post-cast strip
CN213509254U (en) Pre-buried groove subassembly structure of preparation roofing rigidity layer parting joint
CN210530149U (en) Inclined roof ceramic tile dry hanging structure
CN209891374U (en) Supporting structure at assembled structure conversion layer
CN210767362U (en) Outer wall light partition plate installation node
CN203514652U (en) Roof batten
CN109868907B (en) Building thermal insulation outer wall and construction method thereof
CN216239153U (en) Non-bearing corner or intersection prefabricated phosphogypsum hollow plate structure
CN221761033U (en) Light partition wall structure suitable for filling high-rise civil buildings
CN217129276U (en) ALC slat window opening structure and connection structure with window frame thereof
CN217782911U (en) Wall brick fixing device for building engineering
CN213087166U (en) Assembled T-shaped plate floor end connecting node structure
CN218622956U (en) Prefabricated roofing structure
CN220848370U (en) Flush joint type sloping roof deformation joint structure
CN217759778U (en) Ceramic tile tray
CN212053486U (en) Waterproof roof
CN115234007B (en) Method for filling light materials on two sides of web plate of I-shaped steel beam of assembled steel structure house
CN215106441U (en) Archaize building roof based on continuous steel purlines

Legal Events