CN115653317A - 一种缓粘结预应力钢筋先装方法 - Google Patents
一种缓粘结预应力钢筋先装方法 Download PDFInfo
- Publication number
- CN115653317A CN115653317A CN202211536117.2A CN202211536117A CN115653317A CN 115653317 A CN115653317 A CN 115653317A CN 202211536117 A CN202211536117 A CN 202211536117A CN 115653317 A CN115653317 A CN 115653317A
- Authority
- CN
- China
- Prior art keywords
- frame beam
- reinforcement
- slow
- bonding prestressed
- firstly
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 230000002787 reinforcement Effects 0.000 title claims abstract description 58
- 238000000034 method Methods 0.000 title claims abstract description 17
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 27
- 239000010959 steel Substances 0.000 claims abstract description 27
- 238000010276 construction Methods 0.000 claims abstract description 23
- 238000003466 welding Methods 0.000 claims abstract description 7
- 238000009434 installation Methods 0.000 claims description 7
- 229910001294 Reinforcing steel Inorganic materials 0.000 claims 4
- 238000004873 anchoring Methods 0.000 abstract description 3
- 238000007689 inspection Methods 0.000 abstract description 2
- 239000004567 concrete Substances 0.000 description 5
- 238000005516 engineering process Methods 0.000 description 5
- 230000003014 reinforcing effect Effects 0.000 description 4
- 239000000853 adhesive Substances 0.000 description 3
- 230000001070 adhesive effect Effects 0.000 description 3
- 239000011513 prestressed concrete Substances 0.000 description 2
- 230000004075 alteration Effects 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000006467 substitution reaction Methods 0.000 description 1
- 210000002435 tendon Anatomy 0.000 description 1
Images
Landscapes
- Reinforcement Elements For Buildings (AREA)
Abstract
本发明公开了一种缓粘结预应力钢筋先装方法,其方法包括以下步骤:A、根据现场情况先进行平台支撑的施工,然后在进行先施工的框架梁主筋和先施工的框架梁箍筋施工;B、将Φ10mm钢筋根据缓粘结预应力钢筋铺设曲线标高焊接在先施工的框架梁箍筋上;C、将缓粘结预应力钢筋装在安装圆笼上,利用安装圆笼在平台支撑上移动。本发明设置了先施工的框架梁主筋、先施工的框架梁箍筋、缓粘结预应力钢筋、Φ10mm钢筋、后施工的框架梁主筋、后施工的框架梁箍筋、框架梁侧模、安装圆笼和平台支撑,可以有效的避免缓粘结预应力钢筋护套肋槽的损坏,保证了缓粘结预应力钢筋粘结锚固性能,且施工便利,检查方便,有效提高了工作效率,进而降低了施工的成本。
Description
技术领域
本发明涉及缓粘结预应力施工技术领域,具体为一种缓粘结预应力钢筋先装方法。
背景技术
预应力是为了改善结构服役表现,在施工期间给结构预先施加的压应力,结构服役期间预加压应力可全部或部分抵消荷载导致的拉应力,避免结构破坏,常用于混凝土结构。预应力混凝土结构,是在结构承受荷载之前,预先对其施加压力,使其在外荷载作用时的受拉区混凝土内产生压应力,用以抵消或减小外荷载产生的拉应力,使结构在正常使用的情况下不产生裂缝或者裂得比较晚。
按粘结方式,预应力混凝土结构分为三类,有粘结预应力、无粘结预应力、缓粘结预应力。
现在常规的民建结构如采用预应力钢筋,大部分都是无粘结预应力钢筋,采用后张法进行张拉,此种无粘结预应力钢筋外护套都是光滑的,因此铺设时都是在框架梁钢筋绑扎完毕后,从一侧梁端采用牵引的方法利用支架将预应力钢筋按设计位置铺设完毕,对外护套损坏较小,经过现场处理后能保证施工质量。
缓粘结预应力技术是继无粘结预应力技术、有粘结预应力技术之后发展起来的一项新的预应力技术。缓粘结预应力吸收了无粘结的施工特点、有粘结的力学特点,施工中缓粘结预应力钢绞线伸缩变形自由、不与周围缓凝粘合剂产生粘结,而在施工完成后的预定时期内预应力筋通过固化的缓凝粘合剂与周围混凝土产生粘结作用,预应力筋与周围混凝土形成一体、共同工作。而要达到预应力筋与周围混凝土形成一体、共同工作,外包护套将是关键,护套肋高将直接影响粘结锚固性能,因此施工中护套肋槽尺寸不得有任何损坏。
发明内容
本发明的目的在于提供一种缓粘结预应力钢筋先装方法,以解决上述背景技术中提出的问题。
为实现上述目的,本发明提供如下技术方案:一种缓粘结预应力钢筋先装方法,其方法包括以下步骤:
A、根据现场情况先进行平台支撑的施工,然后在进行先施工的框架梁主筋和先施工的框架梁箍筋施工;
B、将Φ10mm钢筋根据缓粘结预应力钢筋铺设曲线标高焊接在先施工的框架梁箍筋上;
C、将缓粘结预应力钢筋装在安装圆笼上,利用安装圆笼在平台支撑上移动;
D、将缓粘结预应力钢筋铺设在Φ10mm钢筋上,最后施工后施工的框架梁主筋、后施工的框架梁箍筋和框架梁侧模。
优选的,所述梁支撑的外侧设置有平台支撑,且梁支撑的顶部设置有梁底模。
优选的,所述梁底模的顶部设置有先施工的框架梁箍筋,且先施工的框架梁箍筋内侧的顶部和底部均设置有先施工的框架梁主筋。
优选的,所述先施工的框架梁箍筋的表面焊接有Φ10mm钢筋,且Φ10mm钢筋的表面设置有缓粘结预应力钢筋,同时,缓粘结预应力钢筋的表面设置有安装圆笼。
优选的,所述平台支撑采用模板支撑替代,且平台支撑的表面设置有框架梁侧模。
优选的,所述框架梁侧模的内侧设置有后施工的框架梁箍筋,且后施工的框架梁箍筋的内侧设置有后施工的框架梁主筋。
优选的,所述安装圆笼采用现场钢筋制做。
与现有技术相比,本发明的有益效果如下:
本发明设置了先施工的框架梁主筋、先施工的框架梁箍筋、缓粘结预应力钢筋、Φ10mm钢筋、后施工的框架梁主筋、后施工的框架梁箍筋、框架梁侧模、安装圆笼和平台支撑,可以有效的避免缓粘结预应力钢筋护套肋槽的损坏,保证了缓粘结预应力钢筋粘结锚固性能,且施工便利,检查方便,有效提高了工作效率,进而降低了施工的成本。
附图说明
图1为预应力钢筋安装前的横断面图;
图2为预应力钢筋安装中的横断面图;
图3为预应力钢筋安装后的横断面图。
图中:先施工的框架梁主筋1、先施工的框架梁箍筋2、缓粘结预应力钢筋3、Φ10mm钢筋4、后施工的框架梁主筋5、后施工的框架梁箍筋6、框架梁侧模7、安装圆笼8、平台支撑9。
具体实施方式
下面将结合本发明实施例中的附图,对本发明实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例仅仅是本发明一部分实施例,而不是全部的实施例。基于本发明中的实施例,本领域普通技术人员在没有做出创造性劳动前提下所获得的所有其他实施例,都属于本发明保护的范围。
在本申请的描述中,需要说明的是,除非另有明确的规定和限定,术语“安装”、“设置有”、“连接”等,应做广义理解,例如“连接”,可以是固定连接,也可以是可拆卸连接,或一体地连接;可以是机械连接,也可以是电连接;可以是直接相连,也可以通过中间媒介间接相连,可以是两个元件内部的连通。对于本领域的普通技术人员而言,可以具体情况理解上述术语在本申请中的具体含义。
请参阅图1-3,一种缓粘结预应力钢筋先装方法,其方法包括以下步骤:
A、根据现场情况先进行平台支撑9的施工,然后在进行先施工的框架梁主筋1和先施工的框架梁箍筋2施工;
B、将Φ10mm钢筋4根据缓粘结预应力钢筋铺设曲线标高焊接在先施工的框架梁箍筋2上;
C、将缓粘结预应力钢筋3装在安装圆笼8上,利用安装圆笼8在平台支撑9上移动;
D、将缓粘结预应力钢筋3铺设在Φ10mm钢筋4上,最后施工后施工的框架梁主筋5、后施工的框架梁箍筋6和框架梁侧模7。
梁支撑的外侧设置有平台支撑9,且梁支撑的顶部设置有梁底模。
梁底模的顶部设置有先施工的框架梁箍筋2,且先施工的框架梁箍筋2内侧的顶部和底部均设置有先施工的框架梁主筋1。
先施工的框架梁箍筋2的表面焊接有Φ10mm钢筋4,且Φ10mm钢筋4的表面设置有缓粘结预应力钢筋3,同时,缓粘结预应力钢筋3的表面设置有安装圆笼8。
平台支撑9采用模板支撑替代,且平台支撑9的表面设置有框架梁侧模7。
框架梁侧模7的内侧设置有后施工的框架梁箍筋6,且后施工的框架梁箍筋6的内侧设置有后施工的框架梁主筋5。
安装圆笼8采用现场钢筋制做。
尽管已经示出和描述了本发明的实施例,对于本领域的普通技术人员而言,可以理解在不脱离本发明的原理和精神的情况下可以对这些实施例进行多种变化、修改、替换和变型,本发明的范围由所附权利要求及其等同物限定。
Claims (7)
1.一种缓粘结预应力钢筋先装方法,其特征在于:其方法包括以下步骤:
A、根据现场情况先进行平台支撑(9)的施工,然后在进行先施工的框架梁主筋(1)和先施工的框架梁箍筋(2)施工;
B、将Φ10mm钢筋(4)根据缓粘结预应力钢筋铺设曲线标高焊接在先施工的框架梁箍筋(2)上;
C、将缓粘结预应力钢筋(3)装在安装圆笼(8)上,利用安装圆笼(8)在平台支撑(9)上移动;
D、将缓粘结预应力钢筋(3)铺设在Φ10mm钢筋(4)上,最后施工后施工的框架梁主筋(5)、后施工的框架梁箍筋(6)和框架梁侧模(7)。
2.根据权利要求1所述的一种缓粘结预应力钢筋先装方法,其特征在于:所述梁支撑的外侧设置有平台支撑(9),且梁支撑的顶部设置有梁底模。
3.根据权利要求2所述的一种缓粘结预应力钢筋先装方法,其特征在于:所述梁底模的顶部设置有先施工的框架梁箍筋(2),且先施工的框架梁箍筋(2)内侧的顶部和底部均设置有先施工的框架梁主筋(1)。
4.根据权利要求1所述的一种缓粘结预应力钢筋先装方法,其特征在于:所述先施工的框架梁箍筋(2)的表面焊接有Φ10mm钢筋(4),且Φ10mm钢筋(4)的表面设置有缓粘结预应力钢筋(3),同时,缓粘结预应力钢筋(3)的表面设置有安装圆笼(8)。
5.根据权利要求1所述的一种缓粘结预应力钢筋先装方法,其特征在于:所述平台支撑(9)采用模板支撑替代,且平台支撑(9)的表面设置有框架梁侧模(7)。
6.根据权利要求1所述的一种缓粘结预应力钢筋先装方法,其特征在于:所述框架梁侧模(7)的内侧设置有后施工的框架梁箍筋(6),且后施工的框架梁箍筋(6)的内侧设置有后施工的框架梁主筋(5)。
7.根据权利要求1所述的一种缓粘结预应力钢筋先装方法,其特征在于:所述安装圆笼(8)采用现场钢筋制做。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202211536117.2A CN115653317A (zh) | 2022-12-02 | 2022-12-02 | 一种缓粘结预应力钢筋先装方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202211536117.2A CN115653317A (zh) | 2022-12-02 | 2022-12-02 | 一种缓粘结预应力钢筋先装方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN115653317A true CN115653317A (zh) | 2023-01-31 |
Family
ID=85019082
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202211536117.2A Pending CN115653317A (zh) | 2022-12-02 | 2022-12-02 | 一种缓粘结预应力钢筋先装方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN115653317A (zh) |
Citations (18)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
FR2240635A5 (en) * | 1973-08-10 | 1975-03-07 | Stup Procedes Freyssinet | Method of handling concrete prestressing cables - involves winding on reel which has adjustably spaced flanges |
US6247501B1 (en) * | 2000-09-29 | 2001-06-19 | John L. Kaines | Clip-on stirrup mat |
JP2008280730A (ja) * | 2007-05-10 | 2008-11-20 | Sumitomo Denko Steel Wire Kk | Pc鋼より線の供給装置及び敷設方法 |
CN102003071A (zh) * | 2009-12-29 | 2011-04-06 | 中交第一航务工程局有限公司 | 后张法预应力梁的预应力孔道制孔定位施工工艺 |
CN102449247A (zh) * | 2009-12-22 | 2012-05-09 | 三菱重工业株式会社 | 半预制楼板及使用该半预制楼板的板材的构筑方法 |
US20130322799A1 (en) * | 2011-02-25 | 2013-12-05 | Schaeffler Technologies AG & Co. KG | Tapered roller bearing with cage |
CN103850441A (zh) * | 2014-03-19 | 2014-06-11 | 郭成顺 | 一种预应力混凝土结构的张拉施工方法及张拉装置 |
CN107100069A (zh) * | 2017-06-12 | 2017-08-29 | 广西路建工程集团有限公司 | 一种混凝土圆柱墩盖梁和系梁逆序施工方法 |
CN207272058U (zh) * | 2017-10-09 | 2018-04-27 | 广东省长大公路工程有限公司 | 一种提高钢筋笼自动成型机加工精度的工具 |
CN211396286U (zh) * | 2019-09-20 | 2020-09-01 | 中国华冶科工集团有限公司 | 无粘结预应力钢绞线定位支架 |
KR102203826B1 (ko) * | 2020-03-26 | 2021-01-15 | (주)인터컨스텍 | Psc 스플라이스드 거더교 및 그 시공방법 |
CN112832512A (zh) * | 2021-01-07 | 2021-05-25 | 中铁三局集团建筑安装工程有限公司 | 大跨度缓粘结预应力钢筋混凝土梁及施工方法 |
CN113123629A (zh) * | 2021-03-30 | 2021-07-16 | 中国建筑第八工程局有限公司 | 既有结构抽柱后梁增大截面预应力加固施工方法 |
CN113199624A (zh) * | 2021-05-18 | 2021-08-03 | 上海市城市建设设计研究总院(集团)有限公司 | 适用于智能建造的预制梁腹板构造与建造方法 |
CN114232614A (zh) * | 2022-01-31 | 2022-03-25 | 中铁六局集团广州工程有限公司 | 一种基于缓粘结预应力钢绞线的抗浮桩施工方法 |
CN114687512A (zh) * | 2022-04-20 | 2022-07-01 | 池州建投鼎晟预制构件有限公司 | 一种预应力混凝土梁及预应力混凝土梁预制方法 |
CN217924422U (zh) * | 2022-04-15 | 2022-11-29 | 深圳天安骏业投资发展(集团)有限公司 | 一种预应力混凝土梁、屋面结构及伞状悬挑建筑 |
CN219034078U (zh) * | 2022-12-02 | 2023-05-16 | 中国三冶集团有限公司 | 一种缓粘结预应力钢筋护套肋槽保护结构 |
-
2022
- 2022-12-02 CN CN202211536117.2A patent/CN115653317A/zh active Pending
Patent Citations (18)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
FR2240635A5 (en) * | 1973-08-10 | 1975-03-07 | Stup Procedes Freyssinet | Method of handling concrete prestressing cables - involves winding on reel which has adjustably spaced flanges |
US6247501B1 (en) * | 2000-09-29 | 2001-06-19 | John L. Kaines | Clip-on stirrup mat |
JP2008280730A (ja) * | 2007-05-10 | 2008-11-20 | Sumitomo Denko Steel Wire Kk | Pc鋼より線の供給装置及び敷設方法 |
CN102449247A (zh) * | 2009-12-22 | 2012-05-09 | 三菱重工业株式会社 | 半预制楼板及使用该半预制楼板的板材的构筑方法 |
CN102003071A (zh) * | 2009-12-29 | 2011-04-06 | 中交第一航务工程局有限公司 | 后张法预应力梁的预应力孔道制孔定位施工工艺 |
US20130322799A1 (en) * | 2011-02-25 | 2013-12-05 | Schaeffler Technologies AG & Co. KG | Tapered roller bearing with cage |
CN103850441A (zh) * | 2014-03-19 | 2014-06-11 | 郭成顺 | 一种预应力混凝土结构的张拉施工方法及张拉装置 |
CN107100069A (zh) * | 2017-06-12 | 2017-08-29 | 广西路建工程集团有限公司 | 一种混凝土圆柱墩盖梁和系梁逆序施工方法 |
CN207272058U (zh) * | 2017-10-09 | 2018-04-27 | 广东省长大公路工程有限公司 | 一种提高钢筋笼自动成型机加工精度的工具 |
CN211396286U (zh) * | 2019-09-20 | 2020-09-01 | 中国华冶科工集团有限公司 | 无粘结预应力钢绞线定位支架 |
KR102203826B1 (ko) * | 2020-03-26 | 2021-01-15 | (주)인터컨스텍 | Psc 스플라이스드 거더교 및 그 시공방법 |
CN112832512A (zh) * | 2021-01-07 | 2021-05-25 | 中铁三局集团建筑安装工程有限公司 | 大跨度缓粘结预应力钢筋混凝土梁及施工方法 |
CN113123629A (zh) * | 2021-03-30 | 2021-07-16 | 中国建筑第八工程局有限公司 | 既有结构抽柱后梁增大截面预应力加固施工方法 |
CN113199624A (zh) * | 2021-05-18 | 2021-08-03 | 上海市城市建设设计研究总院(集团)有限公司 | 适用于智能建造的预制梁腹板构造与建造方法 |
CN114232614A (zh) * | 2022-01-31 | 2022-03-25 | 中铁六局集团广州工程有限公司 | 一种基于缓粘结预应力钢绞线的抗浮桩施工方法 |
CN217924422U (zh) * | 2022-04-15 | 2022-11-29 | 深圳天安骏业投资发展(集团)有限公司 | 一种预应力混凝土梁、屋面结构及伞状悬挑建筑 |
CN114687512A (zh) * | 2022-04-20 | 2022-07-01 | 池州建投鼎晟预制构件有限公司 | 一种预应力混凝土梁及预应力混凝土梁预制方法 |
CN219034078U (zh) * | 2022-12-02 | 2023-05-16 | 中国三冶集团有限公司 | 一种缓粘结预应力钢筋护套肋槽保护结构 |
Non-Patent Citations (1)
Title |
---|
冯若愚;陈瑛;雷海鹏;: "内衬涂塑预应力钢筒混凝土管应力分析", 力学与实践, no. 02, 8 April 2016 (2016-04-08) * |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN219034078U (zh) | 一种缓粘结预应力钢筋护套肋槽保护结构 | |
CN110847044B (zh) | 一种半预制装配式盖梁施工方法 | |
CN101672070B (zh) | 缓粘结预应力装配整体式框架节点体系 | |
CN212561133U (zh) | 一种预制节段式高烈度区拼装桥墩 | |
CN108914778B (zh) | 一种对组合梁上翼缘的混凝土板施加预压力的方法 | |
KR101064731B1 (ko) | 포물선 형상의 웨브와 거푸집형 플랜지를 가지는 강재 빔과 콘크리트로 이루어진 강합성 거더 및 그 제작방법 | |
CN103210148A (zh) | 具有开口断面上弦杆的桁架构造物及其制作方法,以及利用具有开口断面上弦杆的桁架构造物的桁架桥以及其施工方法 | |
JP4826375B2 (ja) | コンクリート構造体の塑性ヒンジ構造及びプレキャスト型枠の製造方法 | |
JP2012057443A (ja) | 鋼管・鉄筋コンクリート複合杭及びその製造方法 | |
CN117188606A (zh) | 一种预应力装配式混凝土梁柱节点及其施工方法 | |
CN110524675B (zh) | 一种先张法预制工字梁及其施工方法 | |
CN115653317A (zh) | 一种缓粘结预应力钢筋先装方法 | |
CN111424525A (zh) | 高速铁路大跨度叠合梁及其施工方法 | |
JP2003213623A6 (ja) | 橋梁の上部構造 | |
CN113585620B (zh) | 一种预应力双腹板型钢混凝土梁 | |
KR101754301B1 (ko) | 순차 결속식 복합 트러스보 시공방법 | |
CN113265953A (zh) | 一种预制分节盖梁 | |
KR100561034B1 (ko) | 분절된 프리스트레스트 프리플렉스 강합성빔의 일체화방법 | |
CN201581496U (zh) | 缓粘结预应力装配整体式框架节点体系 | |
KR20160078150A (ko) | 분절형 프리스트레스트 콘크리트 거더 및 이의 시공방법 | |
KR100655653B1 (ko) | 브라켓을 이용한 프리스트레스 합성보의 현장제작방법 | |
CN215563846U (zh) | 一种预制装配式预应力双波纹腹板型钢混凝土梁 | |
CN108589916A (zh) | 一种预制预应力装配式干式节点及装配方法 | |
KR101585745B1 (ko) | 분절형 프리스트레스트 콘크리트 거더 | |
KR20140105914A (ko) | 절곡부재를 거푸집으로 겸용하는 합성거더 및 이의 제작 방법 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination |