CN115387617A - Assembly type integral bathroom installation method based on accurate positioning of drain pipe - Google Patents
Assembly type integral bathroom installation method based on accurate positioning of drain pipe Download PDFInfo
- Publication number
- CN115387617A CN115387617A CN202211026758.3A CN202211026758A CN115387617A CN 115387617 A CN115387617 A CN 115387617A CN 202211026758 A CN202211026758 A CN 202211026758A CN 115387617 A CN115387617 A CN 115387617A
- Authority
- CN
- China
- Prior art keywords
- positioning
- drain
- assembly type
- hole
- bathroom
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000009434 installation Methods 0.000 title claims abstract description 36
- 238000000034 method Methods 0.000 title claims abstract description 13
- 238000004519 manufacturing process Methods 0.000 claims abstract description 10
- 239000003973 paint Substances 0.000 claims abstract description 9
- 238000012545 processing Methods 0.000 claims abstract description 9
- 239000007787 solid Substances 0.000 claims abstract description 7
- 238000005507 spraying Methods 0.000 claims abstract description 6
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims description 16
- 238000004080 punching Methods 0.000 claims description 9
- 238000012360 testing method Methods 0.000 claims description 6
- 238000007789 sealing Methods 0.000 claims description 5
- 239000004575 stone Substances 0.000 claims description 4
- 238000013329 compounding Methods 0.000 claims description 3
- 238000007599 discharging Methods 0.000 claims 1
- 238000005553 drilling Methods 0.000 abstract description 8
- 238000010276 construction Methods 0.000 description 9
- 238000005034 decoration Methods 0.000 description 2
- BQCADISMDOOEFD-UHFFFAOYSA-N Silver Chemical compound [Ag] BQCADISMDOOEFD-UHFFFAOYSA-N 0.000 description 1
- 238000012937 correction Methods 0.000 description 1
- 230000007547 defect Effects 0.000 description 1
- 239000003292 glue Substances 0.000 description 1
- 238000005259 measurement Methods 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000010422 painting Methods 0.000 description 1
- 230000001681 protective effect Effects 0.000 description 1
- 238000010079 rubber tapping Methods 0.000 description 1
- 229910052709 silver Inorganic materials 0.000 description 1
- 239000004332 silver Substances 0.000 description 1
- 238000006467 substitution reaction Methods 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
- E04G21/14—Conveying or assembling building elements
-
- E—FIXED CONSTRUCTIONS
- E03—WATER SUPPLY; SEWERAGE
- E03F—SEWERS; CESSPOOLS
- E03F3/00—Sewer pipe-line systems
- E03F3/06—Methods of, or installations for, laying sewer pipes
Abstract
The invention relates to the technical field of assembly type integral bathrooms, in particular to an assembly type integral bathroom installation method based on accurate positioning of a drain pipe, which comprises the following steps: s1: drawing a processing drawing of the assembled integral bathroom; s2: manufacturing an assembled integral bathroom solid component and a positioning template; s3: positioning and drilling the drain hole on the positioning template; s4: placing the positioning template with the hole at a preset position in a toilet; s5: drawing the edge of the positioning template outside, drawing a chassis positioning line, spraying colored paint on the hole of the drain hole, and manufacturing a drain hole positioning point; s6: according to the positioning points of ground spraying, the drain holes are accurately drilled; s7: installing a drainage pipeline and drilling a concrete hanging hole on the floor slab; s8: after the concrete of the hanging hole reaches the specified strength, mounting the assembled chassis; s9: and installing the assembled wallboard. The invention solves the problem of the installation and positioning precision of the assembled integral bathroom drain pipe and improves the installation efficiency of the assembled integral bathroom.
Description
Technical Field
The invention relates to the technical field of assembly type integrated bathrooms, in particular to an assembly type integrated bathroom installation method based on accurate positioning of a drain pipe.
Background
The existing assembled integral bathroom drain pipe is provided with the following two types;
(1) Before the civil engineering unit reassembling type integral bathroom construction unit enters the field, the drain pipe is installed; the disadvantages are that: after the assembly type integral bathroom construction unit enters the field, the data of all bathroom drain pipes are required to be comprehensively retested, and the deviation of the distance between the drain pipes reserved in civil engineering construction is too large, so that the assembly type integral bathroom chassis cannot be produced in batches, and the production and installation period is severely restricted;
(2) After an assembled integral bathroom manufacturer enters a field, according to negotiation with a decoration construction unit and an installation construction unit on the field, determining standard bathroom drainage data, carrying out manual paying-off and point marking positioning on the bathroom ground one by one, and carrying out water drilling and tapping and installing a drainage pipe by the installation unit according to ground marking; the disadvantages are that: the method needs more manpower, places the line and the points on the ground, is easy to damage artificially, causes overlarge accuracy error of floor plate water drilling and hole forming in an installation unit, causes the conflict of installation size of the assembly type integral bathroom base and the drainage pipeline in the later period, and seriously influences the construction of the assembly type integral bathroom.
Disclosure of Invention
The invention aims to overcome the defects of the prior art and provide an assembly type integral bathroom mounting method based on accurate positioning of a drain pipe.
In order to achieve the purpose, the invention adopts the following technical scheme:
an assembly type integral bathroom installation method based on accurate positioning of a drain pipe comprises the following steps:
s1: drawing a processing drawing of the assembled integral bathroom according to the size of the bathroom;
s2: manufacturing an assembled integral bathroom solid component and a positioning template according to the drawn assembled integral bathroom processing drawing; the solid component comprises an assembly type chassis and an assembly type wallboard;
s3: positioning and punching holes of the drain holes on the positioning template;
s4: placing the positioning template with the hole at a preset position in a toilet;
s5: drawing the edge of the positioning template outside, drawing a chassis positioning line, spraying colored paint on the hole of the drain hole, and manufacturing a drain hole positioning point;
s6: according to a drain hole positioning point made of colored paint sprayed on the ground, precisely drilling a hole on the drain hole;
s7: installing a drainage pipeline at the opening of the drainage hole on the ground of the toilet, and opening a concrete hanging hole on the floor slab;
s8: after the concrete of the hanging hole reaches the specified strength, mounting the assembled chassis;
s9: mounting an assembly type wallboard on the assembly type chassis, and compounding a strong and weak current pipe on the assembly type wallboard;
s10: installing ground door passing stones and a bathroom door;
s11: ceiling and installing sanitary accessories.
Preferably, in step S3, the positioning template is provided with a cross positioning slot when the drainage hole is formed.
Preferably, in step S7, the installation height of the drainage pipeline is greater than the floor of the toilet, and the floor-installed drainage pipeline is subjected to deviation rectification and positioning based on the floor opening cross positioning line and the chassis floor positioning line.
Preferably, in step S7, the excess drain pipe is cut, a water closing test is performed after the drain pipe sealing kit and the floor drain are installed, and the floor protective film is installed after the test is passed.
Preferably, in step S11, a strong and weak circuit is connected to the ceiling, and a cold and hot water pipeline is connected to the ceiling.
Preferably, the bathroom accessories comprise a shower, a lamp, an air port, a wash basin, a silver mirror, a towel bar, a closestool, a shower, a switch, a socket and a sanitary appliance, and the installation position is sealed and glued.
Has the advantages that: the invention solves the problem of the installation and positioning precision of the assembled integral bathroom drain pipe; the hole opening and mounting precision of the drain pipe of the assembled bathroom chassis can be reduced from the original +/-30 mm to +/-5 mm; in addition, the invention can greatly shorten the positioning and mounting time of the assembly type chassis and the drainage pipeline, improve the mounting efficiency of the assembly type integral bathroom and save the labor cost.
Drawings
FIG. 1 is a schematic view of a positioning template placed in a toilet for measurement and positioning;
FIG. 2 is a schematic view of the positioning for painting;
FIG. 3 is a schematic view of drawing out a positioning line and forming a drainage hole according to the location of the paint spraying;
FIG. 4 is a schematic view of the installation of a drain pipe in a drain hole;
FIG. 5 is a schematic view of a fabricated chassis installation;
FIG. 6 is a schematic view of an assembled wallboard installation;
FIG. 7 is a schematic view of a sanitary fixture installation;
in the figure, a toilet 1, a positioning template 2, a positioning line 21, a positioning hole 3, a positioning point 31, a cross positioning groove 32, a drain hole 4, a drain pipe 5, an assembly type chassis 6, a sealing sleeve 7, a floor drain 8, an assembly type wall plate 9, a threaded fixing piece 91, a door passing stone 10, a wash basin 1001, a towel bar 1002, a bathroom door 1003, a closestool 1004 and a shower 1005.
Detailed Description
The invention is further illustrated by the following examples and figures.
Fig. 1 and 7 show an assembly type integrated bathroom installation method based on precise positioning of a drain pipe, comprising the following steps:
s1: drawing a processing drawing of the assembled integral bathroom according to the size of the bathroom 1;
s2: manufacturing a chassis positioning template 2 according to the drawn assembly type integral bathroom processing drawing, and manufacturing an assembly type integral bathroom solid component according to the assembly type integral bathroom processing drawing; the solid components comprise an assembly type chassis 6 and an assembly type wallboard 9;
s3: positioning and drilling a drain hole 4 on the positioning template 2, and forming a positioning hole 3;
s4: placing the positioning template 2 with the hole at a preset position in the toilet 1 as shown in figure 1;
s5: drawing the chassis positioning line 21 on the outer side of the edge of the positioning template 2, spraying colored paint on the hole of the drain hole 4, and manufacturing a positioning point 31 of the drain hole 4 as shown in fig. 2;
s6: according to a positioning point 31 of a drain hole 4 made of colored paint sprayed on the ground, precisely drilling a hole on the drain hole 4, as shown in FIG. 3;
s7: installing a drainage pipeline 5 at the opening of a drainage hole 4 on the ground of the toilet 1, as shown in figure 4, and performing floor slab opening concrete hanging hole;
s8: after the concrete of the hanging hole reaches the specified strength, the assembled chassis 6 is installed, as shown in figure 5;
s9: mounting the assembly type wallboard 9 on the assembly type chassis 6 through a thread fixing piece 91, and compounding a strong current pipe and a weak current pipe on the assembly type wallboard 9 as shown in fig. 6;
s10: installing a ground door stone 10 and a bathroom door 1003;
s11: suspended ceiling and installed bathroom accessories.
In another preferred embodiment, in step S3, the positioning plate 2 is provided with a cross positioning slot 32 when the drainage hole 4 is formed.
In a preferred embodiment, in step S7, the installation height of the drainage pipe 5 is greater than the floor of the toilet 1, and the floor-mounted drainage pipe is located in a deviation-correcting manner based on the floor-opening cross positioning line 21 and the chassis floor positioning line 21.
In a preferred embodiment, in step S7, the excess drain pipe is cut, a water closing test is performed after the drain pipe sealing kit 7 and the floor drain 8 are installed, and the ground protection film is installed after the test is passed.
In another preferred embodiment, in step S11, a strong and weak circuit is connected to the ceiling, and a cold and hot water pipeline is connected to the ceiling.
In another preferred embodiment, as shown in fig. 7, the sanitary accessories include shower, light, air outlet, wash basin 1001, mirror, towel bar 1002, toilet 1004, shower 1005, switch, socket, sanitary ware, and sealing glue at the installation site.
According to the invention, according to the dimension re-measured of an on-site toilet 1, a decoration construction unit and an installation construction unit drawing can be combined, an assembly type integral bathroom standard construction drawing is determined, a bathroom 1 standard positioning template 2 is manufactured according to the drawing, positioning and punching of a water drainage hole 4 of the toilet 1 are carried out on the standard positioning template 2, then the positioning template 2 is placed in the toilet 1, after the positioning of the positioning template 2 is completed, colored paint is sprayed on the water drainage hole 4, the positioning and punching installation can be carried out by two steps, the positioning unit firstly positions all the toilets 1 in a unified manner, then the punching installation unit carries out accurate water drilling and punching according to a water drainage hole 4 positioning point 31 sprayed on the floor surface, after the hole is drilled, a drainage pipeline 5 is installed and a concrete hanging hole is plugged, and secondary manual deviation rectification is carried out on the drainage pipeline 5 before concrete is solidified, so as to ensure the installation accuracy of the drainage pipeline 5 and the assembly type integral bathroom chassis; of course, the punching installation can also be performed in two steps, that is, the punching unit firstly punches according to the positioning point 31 of the positioning unit, the installation unit installs according to the hole punched by the punching unit, and performs the secondary deviation correction. Therefore, the assembly type integral bathroom is installed in a plurality of batches step by step, each batch corresponds to a specific worker, the specific worker is dedicated to a certain processing step, the work is skillful, and the work efficiency is improved.
The invention solves the problem of installation and positioning precision of the assembled integral bathroom drain pipe; the hole opening and mounting precision of the drain pipe of the assembled bathroom chassis can be reduced from the original +/-30 mm to +/-5 mm; in addition, the invention can greatly shorten the positioning and installation time of the assembly type chassis 6 and the drainage pipeline 5, improve the installation efficiency of the assembly type integral bathroom and save the labor cost.
Finally, it should be noted that: the above examples are only intended to illustrate the technical solution of the present invention, but not to limit it; although the present invention has been described in detail with reference to the foregoing embodiments, it will be understood by those of ordinary skill in the art that: the technical solutions described in the foregoing embodiments may still be modified, or some technical features may be equivalently replaced; and these modifications or substitutions do not depart from the spirit of the corresponding technical solutions of the embodiments of the present invention.
Claims (5)
1. An assembly type integral bathroom installation method based on accurate positioning of a drain pipe is characterized by comprising the following steps:
s1: drawing a processing drawing of the assembled integral bathroom according to the size of the bathroom;
s2: manufacturing an assembled integral bathroom solid component and a positioning template according to the drawn assembled integral bathroom processing drawing; the solid component comprises an assembly type chassis and an assembly type wallboard;
s3: positioning and punching holes of the drain holes on the positioning template;
s4: placing the positioning template with the hole at a preset position in a toilet;
s5: drawing the edge of the positioning template outside, drawing a chassis positioning line, spraying colored paint on the hole of the drain hole, and manufacturing a drain hole positioning point;
s6: accurately forming holes on the drain holes according to the positioning points of the drain holes made of the colored paint sprayed on the ground;
s7: installing a drainage pipeline at the opening of the drainage hole on the ground of the toilet, and performing concrete hanging hole on the floor;
s8: after the concrete of the hanging hole reaches the specified strength, mounting the assembled chassis;
s9: mounting an assembly type wallboard on the assembly type chassis, and compounding a strong and weak current pipe on the assembly type wallboard;
s10: installing ground door passing stones and a bathroom door;
s11: ceiling and installing sanitary accessories.
2. The drain pipe accurate positioning-based assembly type bathroom unit installation method according to claim 1, wherein in step S3, the positioning template is provided with a cross positioning groove when a drain hole is formed.
3. The method for installing the assembled bathroom unit based on the precise positioning of the water drainage pipe of claim 1, wherein in step S7, the installation height of the water drainage pipe is greater than the installation height of the bathroom floor, and the floor-installed water drainage pipe is located in a deviation-correcting manner based on the floor opening cross positioning line and the chassis floor positioning line.
4. The assembly type integral bathroom installation method based on drain pipe accurate positioning as claimed in claim 1, wherein in step S7, redundant drain pipes are cut, a water closing test is performed after the drain pipe sealing kit and the floor drain are installed, and a ground protection film is installed after the test is qualified.
5. The method for installing the assembled bathroom unit based on the precise positioning of the water discharging pipe of claim 1, wherein in step S11, a strong and weak circuit is connected to the ceiling, and a cold and hot water pipeline is connected.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202211026758.3A CN115387617A (en) | 2022-08-25 | 2022-08-25 | Assembly type integral bathroom installation method based on accurate positioning of drain pipe |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202211026758.3A CN115387617A (en) | 2022-08-25 | 2022-08-25 | Assembly type integral bathroom installation method based on accurate positioning of drain pipe |
Publications (1)
Publication Number | Publication Date |
---|---|
CN115387617A true CN115387617A (en) | 2022-11-25 |
Family
ID=84123600
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202211026758.3A Pending CN115387617A (en) | 2022-08-25 | 2022-08-25 | Assembly type integral bathroom installation method based on accurate positioning of drain pipe |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN115387617A (en) |
Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
SE7315670L (en) * | 1973-11-20 | 1975-05-21 | Bjaere Element Ab | |
US20060041448A1 (en) * | 2004-08-20 | 2006-02-23 | Patterson Robbie L | Number of new and unique manufacturing and assembley methods and processes to cost effectively refit and market legacy implements like "The Gilhoolie" presently names "The Wili Grip" TM |
WO2018121736A1 (en) * | 2016-12-31 | 2018-07-05 | 濮阳市明锐建筑节能技术有限公司 | Modular same-floor drainage device for building and installing method therefor |
CN109441151A (en) * | 2018-12-19 | 2019-03-08 | 有利华建材(惠州)有限公司 | Prefabricated toilet and its construction and installation method |
CN109797988A (en) * | 2019-02-21 | 2019-05-24 | 北京工业大学 | A kind of co-layer draining hard-cover precast block toilet of outer wall provided pipe line groove hole |
CN110670906A (en) * | 2019-09-16 | 2020-01-10 | 佛山建装建筑科技有限公司 | Installation method of precast concrete integral bathroom |
CN114382295A (en) * | 2022-01-21 | 2022-04-22 | 陕西建工第五建设集团有限公司 | Indoor assembled drainage pipeline modular construction method |
CN114800901A (en) * | 2022-05-07 | 2022-07-29 | 中建八局第二建设有限公司 | Assembled toilet positioning and hole-opening device and construction method |
-
2022
- 2022-08-25 CN CN202211026758.3A patent/CN115387617A/en active Pending
Patent Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
SE7315670L (en) * | 1973-11-20 | 1975-05-21 | Bjaere Element Ab | |
US20060041448A1 (en) * | 2004-08-20 | 2006-02-23 | Patterson Robbie L | Number of new and unique manufacturing and assembley methods and processes to cost effectively refit and market legacy implements like "The Gilhoolie" presently names "The Wili Grip" TM |
WO2018121736A1 (en) * | 2016-12-31 | 2018-07-05 | 濮阳市明锐建筑节能技术有限公司 | Modular same-floor drainage device for building and installing method therefor |
CN109441151A (en) * | 2018-12-19 | 2019-03-08 | 有利华建材(惠州)有限公司 | Prefabricated toilet and its construction and installation method |
CN109797988A (en) * | 2019-02-21 | 2019-05-24 | 北京工业大学 | A kind of co-layer draining hard-cover precast block toilet of outer wall provided pipe line groove hole |
CN110670906A (en) * | 2019-09-16 | 2020-01-10 | 佛山建装建筑科技有限公司 | Installation method of precast concrete integral bathroom |
CN114382295A (en) * | 2022-01-21 | 2022-04-22 | 陕西建工第五建设集团有限公司 | Indoor assembled drainage pipeline modular construction method |
CN114800901A (en) * | 2022-05-07 | 2022-07-29 | 中建八局第二建设有限公司 | Assembled toilet positioning and hole-opening device and construction method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US20110162137A1 (en) | Trench shower drain | |
US6886190B2 (en) | Device and method for alignment of drains with finished covering | |
CN115387617A (en) | Assembly type integral bathroom installation method based on accurate positioning of drain pipe | |
CN204627039U (en) | A kind of integral vacuum toilet | |
CN210034649U (en) | Socket-type waterproof PVC embedded functional part | |
CN108798031B (en) | Construction method of PVC waterproof embedded sleeve of main stand pipe close to wall in kitchen and toilet | |
JP2009215846A (en) | Method of installing sanitary ware | |
CN216690508U (en) | Leveling mechanism suitable for integral bathroom chassis | |
CN205617787U (en) | Avoid in aluminum alloy template opening and climb a positioner who reserves bolt hole | |
US11391023B2 (en) | Concrete form for freestanding bath filler installation and method of use | |
CN212897583U (en) | One-time pre-embedding device for steel sleeve | |
CN114382295A (en) | Indoor assembled drainage pipeline modular construction method | |
KR200418916Y1 (en) | Pipe laying device for attacing valve to house wall | |
CN210857599U (en) | Pipeline separation waterproof heat preservation integration wall body and building that constitutes thereof | |
US10221555B2 (en) | Method and apparatus for installing a floor drain | |
US7174580B1 (en) | Tub/shower installation block | |
CN203684332U (en) | Water pipe mounting auxiliary tool | |
CN102587654A (en) | Construction method for PVC (poly vinyl chloride) drainage direct-buried pipe fitting | |
CN112344091A (en) | Hanging-hole-free drainage pipeline installation method | |
CN216031709U (en) | Opening positioning tool for bottom box and facing of assembled bathroom | |
CN110670880A (en) | House integrated construction system | |
CN110593560A (en) | Concrete wall column inner wire box installation method | |
JP2000230272A (en) | Pre-assembling method for kitchen and sanitary room for building | |
CN103982042A (en) | Split mounting technique of quick home-decoration split mounting engineering | |
CN112806878B (en) | Concrete form for installation of stand-alone bathtub injector and method of use |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20221125 |