CN115233745A - Geotextile wrapping method for preventing penetration around pile body of pipe pile of revetment structure - Google Patents

Geotextile wrapping method for preventing penetration around pile body of pipe pile of revetment structure Download PDF

Info

Publication number
CN115233745A
CN115233745A CN202210884987.2A CN202210884987A CN115233745A CN 115233745 A CN115233745 A CN 115233745A CN 202210884987 A CN202210884987 A CN 202210884987A CN 115233745 A CN115233745 A CN 115233745A
Authority
CN
China
Prior art keywords
pile body
geotextile
pile
wrapping
layer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202210884987.2A
Other languages
Chinese (zh)
Other versions
CN115233745B (en
Inventor
吴轶群
胡宁晨
鲁枝虎
王广生
包中军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
No3 Engineering Co Ltd Of Cccc Third Harbor Engineering Co ltd
CCCC Third Harbor Engineering Co Ltd
Original Assignee
No3 Engineering Co Ltd Of Cccc Third Harbor Engineering Co ltd
CCCC Third Harbor Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by No3 Engineering Co Ltd Of Cccc Third Harbor Engineering Co ltd, CCCC Third Harbor Engineering Co Ltd filed Critical No3 Engineering Co Ltd Of Cccc Third Harbor Engineering Co ltd
Priority to CN202210884987.2A priority Critical patent/CN115233745B/en
Publication of CN115233745A publication Critical patent/CN115233745A/en
Application granted granted Critical
Publication of CN115233745B publication Critical patent/CN115233745B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • E02D31/06Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against corrosion by soil or water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • E02D31/02Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against ground humidity or ground water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Structural Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Hydrology & Water Resources (AREA)
  • Revetment (AREA)

Abstract

The invention discloses a geotextile wrapping method for preventing seepage around a pile body of a bank protection structure tubular pile. Belonging to the technical field of civil construction; the operation steps are as follows: cleaning the pile body; a piece of geotextile is perforated according to the diameter of a pile body, sleeved into the pile body, and another piece of geotextile is laid on a bank slope; brushing an asphalt bonding layer on the pile body; wrapping the geotextile on the pile body, firmly bonding, and overlapping with the geotextile below; and sewing the lap joint and the sealing part of the geotextile to form a cuff type wrapping layer. The invention is characterized in that: during the subsequent construction of the inverted filter structure layer, the pile body can be protected, and the phenomenon that two pieces of stones and block stones directly impact the pile body to damage the pile foundation and influence the bearing capacity is avoided; the pile body geotextile and the bank slope geotextile form a complete impermeable layer, so that the sand loss is prevented, the integral stability of the bank slope is enhanced, and the durability of the wharf is improved. The technology can enable the geotextile to form a whole, is not easy to damage and move in subsequent construction, and improves the integrity of the inverted filter layer.

Description

Geotextile wrapping method for preventing penetration around pile body of pipe pile of revetment structure
Technical Field
The invention belongs to the technical field of civil construction, and relates to a geotextile wrapping technology for preventing seepage around a pile body of a bank protection structure pipe pile; in particular to a geotextile wrapping method for preventing seepage around a pile body of a pile of a bank protection structure.
Background
In the prior art, when the shore protection structure pile is used for construction in wharf (building material wharf) engineering, as the geotextile inverted filter layer is randomly laid around the pile body, the gap around the pile is easy to be overlarge, the lap joint length is insufficient, the lap joint position is not fixed firmly, the geotextile is displaced in the construction of the upper structure layer, and the lap joint part drops or is separated, so that upper water flows permeate, the sandy soil layer under the geotextile is lost, the scouring phenomenon along the pile periphery is generated, and the shore protection structure is damaged; therefore, how to adopt an innovative geotextile laying technology can effectively prevent the sandy soil from losing becomes a matter which needs to be considered by technicians at present.
Disclosure of Invention
The purpose of the invention is as follows: the invention aims to provide a geotextile wrapping method for preventing seepage around a pile body of a bank protection structure tubular pile.
The technical scheme is as follows: according to the geotextile wrapping method for preventing seepage around the pile body of the bank protection structure tubular pile, the geotextile of the pile body and the geotextile of the bank slope form a complete seepage-preventing layer, so that the geotextile of the pile body and the geotextile of the bank slope are not easy to damage and move in subsequent construction, the integrity of a reversed filter layer is improved, the sandy soil is prevented from being lost, the integral stability of the bank slope is enhanced, and the durability of a wharf is improved; the specific operation steps are as follows:
(1) Cleaning the pile body, cleaning soil and the like on the surface layer of the pile body, washing the pile body with clean water, and wiping the water with dry rags;
(2) Measuring the elevation of the pile body by a measuring worker, determining the top position of the geotechnical cloth wrapping the pile body, and marking and positioning the pile body;
(3) Preparing a piece of geotextile, perforating the geotextile according to the diameter of the pile body, sleeving the pile body after perforating, and laying a piece of geotextile on the bank slope;
(4) Coating an asphalt bonding layer on the pile body, wherein the coating range is from above the mud surface to the marked elevation line, and the coating in the area must be complete and uniform without missing coating;
(5) Pulling the holed geotextile upwards until the geotextile is completely wrapped on the pile body coated with the asphalt bonding layer, and firmly adhering the geotextile and the asphalt;
(6) And sewing the sealing position of the geotextile sleeved in the pile body, the lap joint position of the geotextile sleeved in the pile body and the geotextile laid on the bank slope, thereby forming the cuff type wrapping layer.
Further, in the step (1), soil and the like on the surface layer of the pile body are cleaned, washed clean by clean water and wiped dry.
Further, in the step (2), the pile body is subjected to elevation measurement, the top position of the geotextile wrapping the pile body is determined, the height of the geotextile is more than or equal to 0.5m, and the geotextile is marked and positioned.
Further, in the step (3), the diameter of the outer wall of the pile body is matched with the diameter of the hole wall of the geotextile after the hole is opened, and the diameter of the opened hole of the geotextile is slightly larger than the diameter of the outer wall of the pile body.
Further, in the step (4), the pile body is coated with the asphalt bonding layer in a range from above the mud surface to the marked elevation line, and the coating is complete and uniform and has no missing coating.
Further, in the step (5), the geotextile with the holes is wrapped on the pile body, the height of the geotextile is more than or equal to 0.5m, and the geotextile and the pile body are firmly and smoothly bonded without non-bonded parts.
Further, in the step (6), the length of the lap joint between the geotextile wrapped on the pile body and the geotextile below is more than or equal to 2m. The sealing position of the geotextile sleeved in the pile body, the lap joint position of the geotextile sleeved in the pile body and the geotextile laid on the bank slope are sewn by nylon ropes.
The principle of the invention is as follows: according to the technology, the geotextile is wrapped on the pile body, the geotextile is firmly bonded with the pile body by adopting the asphalt, meanwhile, the lap joint is sewn and reinforced, and meanwhile, the geotextile is effectively connected with the revetment geotextile inverted filter layer to form the integral anti-seepage inverted filter layer. The technology can effectively prevent the sand around the pile body from losing under the water flow scouring, reduces the scouring of the bank slope, avoids the slip of the bank slope, and reduces the overall damage to the engineering structure.
Has the advantages that: compared with the prior art, the invention has the characteristics that: 1) After the geotextile wraps the pile body, the pile body can be protected during the subsequent construction of the inverted filter structure layer, and the two pieces of stones and the block stones are prevented from directly impacting the pile body, so that the pile foundation is prevented from being damaged, and the bearing capacity is prevented from being influenced; 2) The pile body geotextile and the bank slope geotextile can form a finished impermeable layer, so that the sand loss is effectively prevented, the integral stability of the bank slope is enhanced, and the durability of the wharf is improved; 3) The technology can enable the geotextile to form a whole, is not easy to damage and move in subsequent construction, and improves the integrity of the inverted filter.
Detailed Description
In order to more clearly illustrate the technical solution of the present invention, the following further detailed description is made on the technical solution of the present invention:
example 1:
in the first-stage wharf (building material wharf) engineering of a certain pool in a certain operation area of a certain port area, the revetment structure layer is a rock block revetment, a geotextile inverted filter layer, graded broken stones, two pieces of stones and a rock block revetment, and the pile foundation at the revetment position is a cast-in-place pile and a PHC (prestressed high-strength concrete) pipe pile. The sand soil layer loss can be caused by overlarge gaps and infirm lap joint due to the fact that the geotextile cloth is paved around the pile body in a surrounding mode, and the sand soil loss can be effectively prevented only by adopting an innovative geotextile cloth paving technology.
The implementation steps are as follows:
(1) Cleaning the pile body after the bank slope is excavated, cleaning soil and the like on the surface layer of the pile body, washing the pile body by using clean water, and wiping water by using a dry cleaning cloth;
(2) Measuring the elevation of the pile body by a measuring worker, determining the top position of the geotechnical cloth wrapping the pile body, and marking and positioning the pile body;
(3) Preparing a piece of geotextile, perforating the geotextile according to the diameter of the pile body, sleeving the pile body after perforating, and paving a piece of geotextile on the bank slope;
(4) Coating an asphalt bonding layer on the pile body, wherein the coating range is from above the mud surface to the marked elevation line, and the coating in the area must be complete and uniform without coating leakage;
(5) Pulling the geotextile with the holes upwards until the geotextile is completely wrapped on the pile body coated with the asphalt bonding layer, and firmly adhering the geotextile and the asphalt;
(6) And sewing the sealing position of the geotextile sleeved in the pile body, the lap joint position of the geotextile sleeved in the pile body and the geotextile laid on the bank slope, thereby forming the cuff type wrapping layer.
(7) And checking the bonding and lapping quality of the geotextile, and performing subsequent construction of the bank protection structure layer after meeting the requirements.
The above are only preferred embodiments of the present invention, and the scope of the present invention is not limited to the above examples, and all technical solutions that fall under the spirit of the present invention belong to the scope of the present invention. It should be noted that modifications and embellishments within the scope of the invention may be made by those skilled in the art without departing from the principle of the invention.

Claims (8)

1. A geotextile wrapping method for preventing seepage around a pile body of a bank protection structure tubular pile is characterized by comprising the following specific operation steps:
(1) Cleaning the pile body until the surface layer of the pile body is free of impurities;
(2) The measuring personnel perform elevation measurement on the pile body, determine the top position of the geotechnical cloth wrapping the pile body, and mark and position the pile body;
(3) Preparing a piece of geotextile, perforating the geotextile according to the diameter of the pile body, sleeving the pile body after perforating, and paving a piece of geotextile on the bank slope;
(4) Coating an asphalt bonding layer on the pile body;
(5) Pulling the holed geotextile upwards until the geotextile is completely wrapped on the pile body of the plastic-coated asphalt bonding layer;
(6) And sewing the sealing position of the geotextile sleeved in the pile body, the lap joint position of the geotextile sleeved in the pile body and the geotextile laid on the bank slope, thereby forming the cuff type wrapping layer.
2. The geotextile wrapping method for preventing seepage around the pile body of the pile of the revetment structure according to claim 1,
in the step (1), the step of cleaning the pile body is as follows: cleaning up impurities on the surface layer of the pile body, washing the pile body with clear water, and wiping water with a dry rag; until the surface layer has no impurities.
3. The geotextile wrapping method for preventing seepage around the pile body of the pile of the revetment structure according to claim 1,
in the step (2), the pile body is subjected to elevation measurement, the top position of the geotechnical cloth wrapping the pile body is determined, the height of the geotechnical cloth is more than or equal to 0.5m, and the geotechnical cloth is marked and positioned.
4. The geotextile wrapping method for preventing seepage around the pile body of the pile of the revetment structure according to claim 1,
in the step (3), the diameter of the outer wall of the pile body is matched with the diameter of the hole wall of the geotextile after the hole is formed, and the diameter of the hole of the geotextile is larger than the diameter of the outer wall of the pile body.
5. The geotextile wrapping method for preventing seepage around the pile body of the pile of the revetment structure according to claim 1,
in the step (4), the brushing range of the asphalt bonding layer on the pile body is from above the mud surface to the marked elevation line.
6. The geotextile wrapping method for preventing seepage around the pile body of the pile of the revetment structure according to claim 1,
in the step (5), the height of the geotextile wrapped on the pile body after the hole is opened is more than or equal to 0.5m, and the geotextile and the pile body are firmly bonded without an unbonded part.
7. The geotextile wrapping method for preventing seepage around the pile body of the pile of the revetment structure according to claim 1,
in the step (6), the length of the lap joint of the geotextile wrapped on the pile body and the geotextile below is more than or equal to 2m.
8. The geotextile wrapping method for preventing seepage around the pile body of the pile of the revetment structure according to claim 1,
in the step (6), the sealing position of the geotextile sleeved in the pile body, the lap joint position of the geotextile sleeved in the pile body and the geotextile laid on the bank slope are sewn by nylon ropes.
CN202210884987.2A 2022-07-26 2022-07-26 Geotextile wrapping method for preventing permeation around pile body of pile in revetment structure Active CN115233745B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210884987.2A CN115233745B (en) 2022-07-26 2022-07-26 Geotextile wrapping method for preventing permeation around pile body of pile in revetment structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210884987.2A CN115233745B (en) 2022-07-26 2022-07-26 Geotextile wrapping method for preventing permeation around pile body of pile in revetment structure

Publications (2)

Publication Number Publication Date
CN115233745A true CN115233745A (en) 2022-10-25
CN115233745B CN115233745B (en) 2023-06-30

Family

ID=83676358

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210884987.2A Active CN115233745B (en) 2022-07-26 2022-07-26 Geotextile wrapping method for preventing permeation around pile body of pile in revetment structure

Country Status (1)

Country Link
CN (1) CN115233745B (en)

Citations (22)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4896993A (en) * 1987-10-20 1990-01-30 Bohnhoff William W Mat for providing a stabilized surface over sand or other loose soil and method of fabricating the same
CN2069434U (en) * 1990-03-11 1991-01-16 山西省交通厅 Earthwork cloth roller anti-scouring automatic submerged laying device
US5697736A (en) * 1994-08-03 1997-12-16 Custom Precast Concrete, L.L.C. Seawalls and shoreline reinforcement systems
DE202008000025U1 (en) * 2008-03-11 2008-08-14 S. Schulze und S. Matthes GbR (vertretungsberechtigter Gesellschafter: Herr Dipl.-Ing. Siegfried Matthes, 10963 Berlin) Green outer skin of a slope, in which parts of the outer skin are covered with a textile fabric or knitted fabric layer
CN101289860A (en) * 2008-04-10 2008-10-22 中交三航局第二工程有限公司 Underwater slope protection construction method for foundation ditch in water
WO2009126214A1 (en) * 2008-04-11 2009-10-15 Eastman Kodak Company Production of silver sulfate grains in presence of aqueous soluble fluorinated additives
CN101713182A (en) * 2009-11-18 2010-05-26 河海大学 Method for forming ecological embankment of vertical revetment live branch bundles
CN202830872U (en) * 2012-08-30 2013-03-27 浙江华东环境发展有限公司 Ecological revetment capable of preventing soil erosion
CN205775680U (en) * 2016-03-02 2016-12-07 杭州江润科技有限公司 A kind of comprehensive ecological roadbed system
CN206844050U (en) * 2017-04-26 2018-01-05 江苏省太湖水利规划设计研究院有限公司 A kind of peg board ecological revetment structure
CN208328950U (en) * 2018-06-04 2019-01-04 深圳市勘察测绘院有限公司 A kind of In-pit water drainage friction pile suitable for dregs loose structure slope
CN109306676A (en) * 2018-11-13 2019-02-05 四川港航建设工程有限公司 The construction method of bank slump reparation structure
CN208717975U (en) * 2018-09-13 2019-04-09 张健 A kind of anchor structure of large-scale oil storage tank ringwall basis HDPE antiseepage film
CN110409407A (en) * 2019-07-11 2019-11-05 中交一航局第一工程有限公司 A kind of laying process of long piled wharf lower section geotextiles
WO2019218666A1 (en) * 2018-05-18 2019-11-21 山东交通学院 Anti-clogging strengthened water-permeable pile and construction method
CN112176853A (en) * 2020-11-04 2021-01-05 武汉大学 Pile-supported damping reinforced earth abutment and construction method thereof
CN214695414U (en) * 2021-04-12 2021-11-12 上海市水利工程集团有限公司 Full prefabricated square pile type ecological retaining wall revetment
CN214783653U (en) * 2021-06-01 2021-11-19 上海嘉定水务工程设计有限公司 Reinforced river bank protection structure
CN215518633U (en) * 2021-06-25 2022-01-14 江西省港航建设投资集团有限公司 High prevention of seepage earth-rock cofferdam structure
CN215715012U (en) * 2021-05-26 2022-02-01 中国电建集团西北勘测设计研究院有限公司 Bank protection structure
CN215801392U (en) * 2021-07-06 2022-02-11 广东中灏勘察设计咨询有限公司 Ecological pine-imitating pile view revetment
CN216474804U (en) * 2021-05-14 2022-05-10 河海大学 Novel sheet pile type revetment structure

Patent Citations (22)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4896993A (en) * 1987-10-20 1990-01-30 Bohnhoff William W Mat for providing a stabilized surface over sand or other loose soil and method of fabricating the same
CN2069434U (en) * 1990-03-11 1991-01-16 山西省交通厅 Earthwork cloth roller anti-scouring automatic submerged laying device
US5697736A (en) * 1994-08-03 1997-12-16 Custom Precast Concrete, L.L.C. Seawalls and shoreline reinforcement systems
DE202008000025U1 (en) * 2008-03-11 2008-08-14 S. Schulze und S. Matthes GbR (vertretungsberechtigter Gesellschafter: Herr Dipl.-Ing. Siegfried Matthes, 10963 Berlin) Green outer skin of a slope, in which parts of the outer skin are covered with a textile fabric or knitted fabric layer
CN101289860A (en) * 2008-04-10 2008-10-22 中交三航局第二工程有限公司 Underwater slope protection construction method for foundation ditch in water
WO2009126214A1 (en) * 2008-04-11 2009-10-15 Eastman Kodak Company Production of silver sulfate grains in presence of aqueous soluble fluorinated additives
CN101713182A (en) * 2009-11-18 2010-05-26 河海大学 Method for forming ecological embankment of vertical revetment live branch bundles
CN202830872U (en) * 2012-08-30 2013-03-27 浙江华东环境发展有限公司 Ecological revetment capable of preventing soil erosion
CN205775680U (en) * 2016-03-02 2016-12-07 杭州江润科技有限公司 A kind of comprehensive ecological roadbed system
CN206844050U (en) * 2017-04-26 2018-01-05 江苏省太湖水利规划设计研究院有限公司 A kind of peg board ecological revetment structure
WO2019218666A1 (en) * 2018-05-18 2019-11-21 山东交通学院 Anti-clogging strengthened water-permeable pile and construction method
CN208328950U (en) * 2018-06-04 2019-01-04 深圳市勘察测绘院有限公司 A kind of In-pit water drainage friction pile suitable for dregs loose structure slope
CN208717975U (en) * 2018-09-13 2019-04-09 张健 A kind of anchor structure of large-scale oil storage tank ringwall basis HDPE antiseepage film
CN109306676A (en) * 2018-11-13 2019-02-05 四川港航建设工程有限公司 The construction method of bank slump reparation structure
CN110409407A (en) * 2019-07-11 2019-11-05 中交一航局第一工程有限公司 A kind of laying process of long piled wharf lower section geotextiles
CN112176853A (en) * 2020-11-04 2021-01-05 武汉大学 Pile-supported damping reinforced earth abutment and construction method thereof
CN214695414U (en) * 2021-04-12 2021-11-12 上海市水利工程集团有限公司 Full prefabricated square pile type ecological retaining wall revetment
CN216474804U (en) * 2021-05-14 2022-05-10 河海大学 Novel sheet pile type revetment structure
CN215715012U (en) * 2021-05-26 2022-02-01 中国电建集团西北勘测设计研究院有限公司 Bank protection structure
CN214783653U (en) * 2021-06-01 2021-11-19 上海嘉定水务工程设计有限公司 Reinforced river bank protection structure
CN215518633U (en) * 2021-06-25 2022-01-14 江西省港航建设投资集团有限公司 High prevention of seepage earth-rock cofferdam structure
CN215801392U (en) * 2021-07-06 2022-02-11 广东中灏勘察设计咨询有限公司 Ecological pine-imitating pile view revetment

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
殷锴毅: "布袋桩施工技术及应用探讨", 广州建筑, no. 03 *
胡友好;: "航道整治护岸工程施工工艺及质量控制", 中国水运(下半月), no. 08 *
龙燕;: "钻孔灌注桩施工", 科技传播, no. 16 *

Also Published As

Publication number Publication date
CN115233745B (en) 2023-06-30

Similar Documents

Publication Publication Date Title
CN104806272B (en) Tunnel shunting combined type guarded drainage integrated system and construction method and using method
CN204572015U (en) A kind of tunnel shunting combined type waterproof and water drainage system
CN107676107A (en) Tunnel reinforcement crack treatment method
CN202787329U (en) Large leakage treatment structure for underground continuous wall
CN107513995A (en) A kind of bridge struction pile post grouting construction method
CN107044129A (en) A kind of bottomless single wall steel boxed cofferdam of piecemeal pin-connected panel and its construction method
CN110952586A (en) Construction process for bearing platform below expressway
CN110629770B (en) Reservoir side slope hydro-fluctuation belt seepage-proofing slope protection structure and construction method thereof
CN206554099U (en) A kind of bottomless single wall steel boxed cofferdam of piecemeal pin-connected panel
CN106884436A (en) A kind of construction method of the waterproof connecting structure of foundation ditch uplift pile and structure base slab
CN214883611U (en) Bearing pile or uplift pile with multiple main ribs
CN115233745A (en) Geotextile wrapping method for preventing penetration around pile body of pipe pile of revetment structure
CN112176954A (en) Construction method for newly excavated channel
CN208023406U (en) A kind of asphalt bridge floor discharge structure
CN111206566A (en) Ground diaphragm wall I-shaped steel joint water stop control structure and construction method thereof
CN106592514A (en) Construction method of old city riverway piling wall integrated vertical type retaining wall
CN105951892A (en) Deep-water-covered open-cut structure roof waterproof structure and construction method thereof
CN215630186U (en) Basement high water level precast pile head waterproof construction
CN111519647A (en) Novel foundation suitable for marine soft foundation treatment and reinforcement and construction method
KR100375495B1 (en) repair method of being injured bridge pier
CN112982372A (en) Inner drilling pipe insertion pipe compaction grouting reinforcement method based on pipe gallery bottom plate cavity
CN209816867U (en) A supporting construction for peripheral foundation ditch of existing building
KR100300230B1 (en) Anti-Scouring and Erosion Fabric Form for Bridge
CN219621839U (en) Waterproof structure of anti-floating anchor rod end
CN113700013A (en) High-pressure jet grouting and clay core wall combined earth-rock cofferdam seepage-proofing construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant