CN112982372A - Inner drilling pipe insertion pipe compaction grouting reinforcement method based on pipe gallery bottom plate cavity - Google Patents

Inner drilling pipe insertion pipe compaction grouting reinforcement method based on pipe gallery bottom plate cavity Download PDF

Info

Publication number
CN112982372A
CN112982372A CN202110265545.5A CN202110265545A CN112982372A CN 112982372 A CN112982372 A CN 112982372A CN 202110265545 A CN202110265545 A CN 202110265545A CN 112982372 A CN112982372 A CN 112982372A
Authority
CN
China
Prior art keywords
grouting
pipe
hole
bottom plate
steel plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202110265545.5A
Other languages
Chinese (zh)
Inventor
罗志浩
戴小锋
陈新喜
陈勇
陈华
屈坤玉
李赟
潘钧俊
俞晨龙
刘笃兴
黄青蕾
董超
余少乐
吴振东
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Eighth Engineering Division Co Ltd
Original Assignee
China Construction Eighth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Eighth Engineering Division Co Ltd filed Critical China Construction Eighth Engineering Division Co Ltd
Priority to CN202110265545.5A priority Critical patent/CN112982372A/en
Publication of CN112982372A publication Critical patent/CN112982372A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00Improving or preserving soil or rock, e.g. preserving permafrost soil
    • E02D3/12Consolidating by placing solidifying or pore-filling substances in the soil
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/10Tunnels or galleries specially adapted to house conduits, e.g. oil pipe-lines, sewer pipes ; Making conduits in situ, e.g. of concrete ; Casings, i.e. manhole shafts, access or inspection chambers or coverings of boreholes or narrow wells

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • Chemical & Material Sciences (AREA)
  • Oil, Petroleum & Natural Gas (AREA)
  • Agronomy & Crop Science (AREA)
  • Soil Sciences (AREA)
  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

The invention discloses an inner drilling and inserting pipe compaction grouting reinforcement method based on a pipe gallery bottom plate cavity, which comprises the following steps: positioning and marking grouting hole points on the bottom plate of the pipe gallery; placing a steel plate at the marked point position and fixing the steel plate by using expansion bolts, and forming a hole in the center of the steel plate, wherein the hole diameter is not smaller than that of the grouting hole; drilling a central opening of the steel plate downwards to penetrate through the bottom plate of the pipe gallery to form a hole by a grouting hole, and forming the hole to the bottom of the cushion layer of the bottom plate; inserting a grouting pipe into the formed grouting hole, and compacting the gap around the grouting pipe; high-pressure grouting is carried out in the grouting pipe, and grouting slurry is pressed into the soil layer below the bottom plate of the pipe gallery to compact the soil layer; and when the grout in the grouting hole is solidified and has no water leakage, cutting off the grouting pipe along the upper opening of the steel plate, and welding and sealing the grouting hole by adopting a plugging plate. The problem of cavities in the bottom plate of the pipe gallery is solved; eliminate utility tunnel structure quality hidden danger to remedy the bottom plate cavity defect through slip casting reinforcement mode, prevent that utility tunnel later stage from taking place infiltration and crack structure destruction phenomenon and taking place.

Description

Inner drilling pipe insertion pipe compaction grouting reinforcement method based on pipe gallery bottom plate cavity
Technical Field
The invention relates to the technical field of building construction, in particular to a pipe gallery bottom plate cavity-based inner drilling and pipe inserting pipe compaction grouting reinforcement method.
Background
With the vigorous development of municipal infrastructure, the construction projects of the comprehensive pipe gallery in China are like bamboo shoots in spring after rain; however, for the construction of the comprehensive pipe gallery with the underground space structure, the cavity of the bottom plate of the pipe gallery is a common fault faced by the comprehensive pipe gallery, and particularly, the influence is more obvious for soft soil geology and some coastal impact mud pond geology; in addition, in the piping lane work progress, the construction rainy season and the intermittent type nature of relevant operation all can aggravate the enlargement of piping lane bottom plate cavitation. Piping lane bottom plate cavity formation reason lies in the serious loss of appearance direct influence piping lane bottom plate soil and water of piping lane foundation ditch infiltration, and the balanced system of mechanics of interact is broken between the soil and water to lead to the piping lane to take place to gush the sand phenomenon at construction bottom plate in-process, lead to the piping lane bottom plate to come to nothing, finally influence the safe quality system and the functional usability of whole piping lane structure.
When facing the piping lane cavity problem, at present, usually adopt geological drilling rig pore-forming retreat formula compacting slip casting mode on the ground, carry out high-pressure slip casting in the drilling of piping lane outside, thereby its thick liquid reaches the bottom plate cavity sealing effect through SMW worker method stake and piping lane side wall structure diffusion to the piping lane bottom.
However, such conventional methods have the following drawbacks: (1) the method depends on a slurry diffusion mode, and has the advantages of long slurry conveying path, low grouting efficiency and long operation duration; (2) the grouting flow is small, and a good remediation effect cannot be achieved for the defect of a large cavity of the bottom plate of the pipe gallery; (3) the mode easily causes the pipe blockage phenomenon in the implementation process, and pipe cleaning treatment is needed, so that the continuity of grouting operation is influenced, and the work load of operators is increased.
Disclosure of Invention
In order to overcome the defects in the prior art, the invention provides an inner drilling and intubation compaction grouting reinforcement method based on a pipe gallery bottom plate cavity, which aims to solve the problem of the pipe gallery bottom plate cavity; eliminate utility tunnel structure quality hidden danger to remedy the bottom plate cavity defect through slip casting reinforcement mode, prevent that utility tunnel later stage from taking place infiltration and crack structure destruction phenomenon and taking place.
In order to realize the technical effects, the invention adopts the technical scheme that:
an inner drilling and inserting pipe compaction grouting reinforcement method based on a pipe gallery bottom plate cavity comprises the following steps:
positioning grouting hole point positions on a pipe gallery bottom plate at intervals in the longitudinal direction of the mileage of the pipe gallery and marking;
placing a steel plate at the marked point position and fixing the steel plate by using expansion bolts, and forming a hole in the center of the steel plate, wherein the hole diameter is not smaller than that of the grouting hole;
drilling downwards through the pipe gallery bottom plate in the central opening of the steel plate to form a hole through a grouting hole, and forming the hole to the bottom of the bottom plate cushion layer;
inserting a grouting pipe into the formed grouting hole, and compacting the gap around the grouting pipe;
high-pressure grouting is carried out in the grouting pipe, and grouting slurry is pressed into the soil layer below the bottom plate of the pipe gallery to compact the soil layer;
and when the grout in the grouting hole is solidified and has no water leakage, cutting off the grouting pipe along the upper opening of the steel plate, and welding and sealing the grouting hole by adopting a plugging plate.
As a preferred technical scheme of the grouting reinforcement method, before the step of placing the steel plate and fixing the steel plate by using the expansion bolts, the method further comprises the following steps of:
cutting and chiseling the top surface of the pipe gallery bottom plate at the marked point position to obtain a groove with the shape consistent with that of the steel plate;
and fixing the steel plate at the bottom of the groove through an expansion bolt.
As a preferable technical scheme of the grouting reinforcement method, a rubber pad is placed at the bottom of the steel plate.
As a preferred technical scheme of the grouting reinforcement method, before the step of forming the hole by the grouting hole, the method further comprises the following steps of: and carrying out waterproof treatment on the marked point positions.
As a preferred technical solution of the grouting reinforcement method of the present invention, the aperture of the central opening of the steel plate is larger than the aperture of the grouting hole, the grouting pipe includes a small-diameter pipe section and a large-diameter pipe section, the outer diameter of the small-diameter pipe section is consistent with the aperture of the grouting hole, the large-diameter pipe section is integrally formed at the upper end of the small-diameter pipe section and has an outer diameter consistent with the aperture of the central opening of the steel plate, and the lower end of the small-diameter pipe section is not higher than the bottom of the bottom plate cushion layer.
As a preferred technical scheme of the grouting reinforcement method, a grouting connecting pipe opening and a pressure valve are arranged on the large-pipe-diameter pipe section.
As a preferable technical scheme of the grouting reinforcement method, the grouting slurry is prepared from PO42.5 ordinary portland cement.
As a preferable technical scheme of the grouting reinforcement method, the grouting pressure is 3.0-5.0 MPa, and the water-cement ratio of grouting slurry is 0.50.
As a preferred technical scheme of the grouting reinforcement method, after the step of welding and sealing the grouting hole by adopting the plugging plate, the method further comprises the following steps: and pouring fine stone concrete to fill the grooves in the bottom of the pipe gallery.
As a preferred technical scheme of the grouting reinforcement method, in the step of performing high-pressure grouting in the grouting pipe, grouting is completed one by one according to the longitudinal direction of the mileage of the pipe gallery.
The method has the advantages that grouting holes are scientifically distributed on the pipe gallery bottom plate according to local conditions and are measured and positioned according to the cavity conditions of the pipe gallery bottom plate in different degrees, the inner drilling hole insertion pipe compaction equipment is installed on the part to be drilled, and the configured cement slurry is continuously operated through the grouting pipes; and sequentially performing grouting operation according to the hole positions in the grouting process, and finally, solidifying the grout in the grouting holes to finish the grouting operation. The method for reinforcing the inner drilling hole by inserting the pipe and performing compaction grouting has the advantages that: (1) the method has short grouting slurry conveying path and high operation efficiency; (2) the method has the advantages that the opening depth of the grouting hole is small, the operation time is shortened, and the construction cost is saved; (3) the method has the advantages of large grouting flow, strong slurry conveying continuity and high floor cavity remediation quality; (4) the method avoids the influence of the separability of the cement-soil mixing pile and the side wall, and the pipe blockage phenomenon is not easy to occur.
Drawings
In order to more clearly illustrate the technical solutions in the embodiments of the present invention, the drawings needed to be used in the description of the embodiments will be briefly introduced below, and it is obvious that the drawings in the following description are only some embodiments of the present invention, and it is obvious for those skilled in the art to obtain other drawings based on these drawings without creative efforts.
Fig. 1 is a schematic longitudinal section view of a grouting of a bottom plate of a pipe gallery in the method for reinforcing the inner drilling, inserting and compacting grouting of the pipe in the embodiment of the invention.
Fig. 2 is an enlarged schematic view of the node a in fig. 1.
Fig. 3 is a schematic plan view of a grouting hole position of a bottom plate of a pipe gallery in the embodiment of the invention.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
Referring to fig. 1-3, the invention provides a pipe gallery bottom plate cavity-based inner drilling pipe insertion pipe compaction grouting reinforcement method, which is used for solving the problem of the pipe gallery bottom plate cavity; the method for remedying the cavity of the pipe gallery bottom plate adopts an inner drilling hole insertion pipe compaction grouting mode, grouting holes are distributed on the pipe gallery bottom plate 11 for drilling and grouting, and hole sealing and grouting work are completed after slurry is solidified.
Inside 11 structures of pipe gallery bottom plate, handle through the mode of bottom plate drilling high pressure slip casting, mainly be through high pressure with liquid grout liquid notes (press) go into inside the soil layer to reach closely knit soil layer, improve soil layer performance, improve effects such as ground bearing capacity and soil body fill, main reinforcement scope is around the pipe gallery bottom plate.
Specifically, the invention relates to a pipe gallery bottom plate cavity-based inner drilling and intubation compaction grouting reinforcement method, which comprises the following steps:
firstly, positioning grouting hole points 12 on a pipe gallery bottom plate 11 at intervals according to the longitudinal direction of the mileage of the pipe gallery and marking;
specifically, a temporary grouting hole point 12 is arranged on a bottom plate of the pipe gallery according to a length of 10 m in the longitudinal direction by using the gauge on site, and is marked by red paint. If the point position cannot be grouted in the construction process, other point positions can be adjusted according to actual conditions to continue hole patching. During actual construction, point positions and quantity of grouting holes are adjusted according to grouting effects, and when soil is loose and grouting is smooth, the grouting holes can be encrypted.
Placing a steel plate 13 at the marked point position 12, fixing the steel plate by using an expansion bolt 131, and opening a hole in the center of the steel plate, wherein the hole diameter is not smaller than that of the grouting hole;
before that, cutting and chiseling the top surface of the pipe gallery bottom plate 11 at the marked point position to obtain a groove 14 with the shape consistent with that of the steel plate 13, wherein if the steel plate 13 is a rectangular steel plate, the groove 14 is also a rectangular groove, and the size of the steel plate 13 is consistent with that of the groove 14; then, a rubber pad and a steel plate 13 are placed on the bottom of the recess 14 and fixed by an expansion bolt 131.
Thirdly, drilling a pipe gallery bottom plate 11 downwards in the central opening of the steel plate 13 to form a hole through a grouting hole, and forming the hole to the bottom of a bottom plate cushion layer 15 below the pipe gallery bottom plate 11;
specifically, before formally drilling gallery bottom plate 11, carry out water repellent according to the position of mark earlier and set up, set up and adopt the electric drill to bore through gallery bottom plate 11 and carry out the pore-forming after accomplishing, drilling diameter 30mm, drilling depth is in order to get into the bottom of the bottom plate bedding.
Inserting a grouting pipe 16 into the formed grouting hole, and compacting gaps around the grouting pipe;
specifically, the grouting pipe 16 is manufactured by seamless steel pipe and is driven into the soil area to be grouted from the opening of the bottom plate of the pipe gallery according to the design requirement. A seamless steel pipe with the diameter of 30mm and the wall thickness of 4mm is adopted, and the length of the grouting pipe 16 is set according to the depth of a drilled hole. After the grouting pipe 16 is put in place, the gap around the grouting pipe 16 is compacted, and grouting is started after the completion.
The hole diameter of the central hole of the steel plate 13 is slightly larger than the hole diameter of the grouting hole, the grouting pipe 16 comprises a small-diameter pipe section 161 and a large-diameter pipe section 162, the outer diameter of the small-diameter pipe section 161 is consistent with the hole diameter of the grouting hole, the large-diameter pipe section 162 is integrally formed at the upper end of the small-diameter pipe section 161, the outer diameter of the large-diameter pipe section is consistent with the hole diameter of the central hole of the steel plate 13, and the lower end of the small-diameter pipe section 161 is suitable to extend into the bottom of the bottom plate cushion layer. Preferably, the upper end of the large-diameter pipe section 162 extends upward beyond the top surface of the pipe gallery floor 11 and is provided with a grouting nozzle 163 and a pressure valve 164, the grouting nozzle 163 being used in conjunction with a grouting machine, the grouting rate of the grouting pipe being controlled by the pressure valve 164. After the grouting pipe is put in place, the lower opening of the large-pipe-diameter pipe section 162 and the central opening of the steel plate 13 are welded tightly, and grouting is started after the completion. On the one hand, the compacting effect is better, and on the other hand, the center hole of the steel plate 13 can be utilized to play a certain degree of horizontal positioning effect on the grouting pipe.
Fifthly, high-pressure grouting is carried out in the grouting pipe 16, and grouting slurry is pressed into the soil layer below the pipe gallery bottom plate 11 to compact the soil layer;
specifically, the grouting machine can be opened for grouting after all work is done, when the grouting pressure is continuously stable, no grouting is performed, the grouting amount is small, or grouting is discharged from an exhaust hole, grouting can be stopped, an orifice valve is closed, and then a pipeline is dismantled and cleaned to enter the next hole for construction.
The grouting slurry is cement slurry prepared by PO42.5 ordinary portland cement. The grouting working pressure is generally about 3.0-5.0 MPa, and the water-cement ratio is 0.50. The slurry can be injected by pressure only after being fully and uniformly stirred by the stirrer, and the slurry is continuously and slowly stirred in the grouting process, wherein the stirring time is less than the initial setting time of the slurry.
And step six, when the grout in the grouting hole is solidified and no water leakage exists, cutting off the grouting pipe 16 along the upper opening of the steel plate 13, and welding and sealing the grouting hole by adopting a sealing plate which can be a steel plate with a smaller size.
Specifically, when grout in the grouting holes is solidified and the positions of the grouting holes are free of water leakage, the grouting pipes are cut off along the upper openings of the large steel plates, the small steel plates are adopted to weld and seal the grouting holes, and then the fine aggregate concrete recovery pipe gallery bottom plates and the upper leveling layers are poured. And cleaning and clearing the peripheral concrete to finish grouting work.
According to the internal drilling pipe insertion pipe compaction grouting method adopted based on the problem of the cavity of the pipe gallery, grouting holes are scientifically distributed on the bottom plate of the pipe gallery according to local conditions and are measured and positioned according to the cavity conditions of different degrees of the bottom plate of the pipe gallery, internal drilling pipe insertion pipe compaction equipment is installed on a position to be perforated, and drilling, pipe connection and slurry preparation are completed; carrying out continuous operation on the prepared cement slurry through a grouting pipe; and sequentially performing grouting operation according to the hole positions in the grouting process, and finally, solidifying the grout in the grouting holes to finish the grouting operation.
The method for reinforcing the inner drilling hole insertion pipe by compaction grouting has the advantages that:
(1) compared with the traditional grouting mode for repairing the cavity of the bottom plate, the grouting operation surface of the method is the bottom plate of the pipe gallery, the drilling depth is low, the construction workload is reduced, the construction efficiency is improved, the operation time is shortened, and the construction cost is saved;
(2) compared with the traditional method, the grouting flow of the method is large, and the overall repairing and forming and quality effects of the cavity of the bottom plate are greatly improved due to the high efficiency and short time of the fluidity of the cavity of the bottom plate;
(3) the method has the advantages that the slurry conveying line is short, the operation efficiency is high, compared with the traditional grouting method, the method avoids the influence of the separability of the cement soil mixing pile and the side wall, and the pipe blockage phenomenon is not easy to occur;
(4) in the implementation process of the bottom plate cavity remediation, grouting holes are scientifically distributed according to local conditions according to the bottom plate cavity conditions, and the operation mode is flexible.
It should be noted that, in this document, terms such as "comprises," "comprising," or any other variation thereof, are intended to cover a non-exclusive inclusion, such that a process, method, article, or apparatus that comprises a list of elements does not include only those elements but may include other elements not expressly listed or inherent to such process, method, article, or apparatus. Without further limitation, an element defined by the phrase "comprising an … …" does not exclude the presence of other identical elements in a process, method, article, or apparatus that comprises the element.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (10)

1. The utility model provides an inner drill hole intubate compaction slip casting reinforcing method based on piping lane bottom plate cavity which characterized in that includes the step:
positioning grouting hole point positions on a pipe gallery bottom plate at intervals in the longitudinal direction of the mileage of the pipe gallery and marking;
placing a steel plate at the marked point position and fixing the steel plate by using expansion bolts, and forming a hole in the center of the steel plate, wherein the hole diameter is not smaller than that of the grouting hole;
drilling downwards through the pipe gallery bottom plate in the central opening of the steel plate to form a hole through a grouting hole, and forming the hole to the bottom of the bottom plate cushion layer;
inserting a grouting pipe into the formed grouting hole, and compacting the gap around the grouting pipe;
high-pressure grouting is carried out in the grouting pipe, and grouting slurry is pressed into the soil layer below the bottom plate of the pipe gallery to compact the soil layer;
and when the grout in the grouting hole is solidified and has no water leakage, cutting off the grouting pipe along the upper opening of the steel plate, and welding and sealing the grouting hole by adopting a plugging plate.
2. The method for strengthening the pipe gallery floor cavity based on the pipe gallery floor pipe penetration pipe compaction grouting according to claim 1, wherein before the step of placing the steel plate and fixing the steel plate by using the expansion bolts, the method further comprises the following steps:
cutting and chiseling the top surface of the pipe gallery bottom plate at the marked point position to obtain a groove with the shape consistent with that of the steel plate;
and fixing the steel plate at the bottom of the groove through an expansion bolt.
3. The pipe gallery floor cavity-based inner drilling and intubation compaction grouting reinforcement method of claim 1 or 2, wherein a rubber pad is placed at the bottom of the steel plate.
4. The pipe gallery floor cavity-based inner drilling and intubation compaction grouting reinforcement method of claim 1, further comprising, before the step of forming the grouting hole, the steps of: and carrying out waterproof treatment on the marked point positions.
5. The pipe rack floor cavity-based inner drilling and pipe inserting compaction grouting reinforcement method according to claim 1, wherein the diameter of a central opening of the steel plate is larger than that of the grouting hole, the grouting pipe comprises a small-diameter pipe section and a large-diameter pipe section, the outer diameter of the small-diameter pipe section is consistent with that of the grouting hole, the large-diameter pipe section is integrally formed at the upper end of the small-diameter pipe section and is consistent with that of the central opening of the steel plate, and the lower end of the small-diameter pipe section is not higher than the bottom of the floor mat.
6. The pipe gallery floor cavity-based inner drilling and intubation compaction grouting reinforcement method according to claim 5, wherein a grouting connecting pipe opening and a pressure valve are arranged on the large-pipe-diameter pipe section.
7. The pipe gallery floor cavity-based inner drilling and inserting pipe compaction grouting reinforcement method of claim 1, wherein the grouting slurry is cement slurry prepared by PO42.5 ordinary portland cement.
8. The pipe gallery floor cavity-based inner drilling pipe insertion pipe compaction grouting reinforcement method according to claim 7, wherein grouting pressure is 3.0-5.0 MPa, and the water cement ratio of grouting slurry is 0.50.
9. The method for reinforcing the pipe gallery floor cavity by means of the pipe-inserting pipe compaction grouting, according to claim 2, wherein after the step of welding and sealing the grouting hole by using the sealing plate, the method further comprises the following steps: and pouring fine stone concrete to fill the grooves in the bottom of the pipe gallery.
10. The pipe rack floor cavity-based inner drilling and inserting pipe compacting grouting reinforcement method according to claim 1, characterized in that in the step of performing high-pressure grouting into the grouting pipe, grouting is completed one by one according to the longitudinal direction of the mileage of the pipe rack.
CN202110265545.5A 2021-03-11 2021-03-11 Inner drilling pipe insertion pipe compaction grouting reinforcement method based on pipe gallery bottom plate cavity Pending CN112982372A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110265545.5A CN112982372A (en) 2021-03-11 2021-03-11 Inner drilling pipe insertion pipe compaction grouting reinforcement method based on pipe gallery bottom plate cavity

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110265545.5A CN112982372A (en) 2021-03-11 2021-03-11 Inner drilling pipe insertion pipe compaction grouting reinforcement method based on pipe gallery bottom plate cavity

Publications (1)

Publication Number Publication Date
CN112982372A true CN112982372A (en) 2021-06-18

Family

ID=76336377

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110265545.5A Pending CN112982372A (en) 2021-03-11 2021-03-11 Inner drilling pipe insertion pipe compaction grouting reinforcement method based on pipe gallery bottom plate cavity

Country Status (1)

Country Link
CN (1) CN112982372A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116006217A (en) * 2022-12-27 2023-04-25 中铁十四局集团隧道工程有限公司 Pipe curtain structure and construction method thereof

Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5671581A (en) * 1994-12-07 1997-09-30 Nagahama; Shigeo Water cut-off process for concrete structure
CN101624910A (en) * 2009-07-31 2010-01-13 广州市建筑机械施工有限公司 Method for reinforcing concealed tunnel
CN105735331A (en) * 2016-03-21 2016-07-06 上海长凯岩土工程有限公司 Grouting reinforcement construction method for underground engineering
CN106049204A (en) * 2016-08-03 2016-10-26 中铁十七局集团第三工程有限公司 Grooved formwork for pouring of reinforced concrete base of ballastless track
CN208056108U (en) * 2018-03-30 2018-11-06 云南建投基础工程有限责任公司 A kind of prefabricated assembled underground pipe gallery depression Disease Treatment structure
CN208256464U (en) * 2018-04-24 2018-12-18 马鞍山天磁磁业有限公司 A kind of positioning device that auxiliary permanent ferrite magnetizes
CN109184750A (en) * 2018-11-15 2019-01-11 中铁二十局集团轨道交通工程有限公司 A kind of tunnel radial grouting device and method
CN110042838A (en) * 2019-04-25 2019-07-23 中建四局第一建筑工程有限公司 A kind of reversed grouting construction method of floor structure
CN111022082A (en) * 2020-01-14 2020-04-17 辽宁科技学院 Tunnel concrete two-lining void grouting hole sealing device
CN210958977U (en) * 2019-08-29 2020-07-07 依利安达(广州)电子有限公司 Drilling platform suitable for multilayer circuit board
CN111501428A (en) * 2020-05-26 2020-08-07 中铁上海设计院集团有限公司 Direct-buried fastener and construction method thereof
CN211893491U (en) * 2020-02-15 2020-11-10 浙江瓯络信息科技有限公司 Take shock-absorbing function's delivery case

Patent Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5671581A (en) * 1994-12-07 1997-09-30 Nagahama; Shigeo Water cut-off process for concrete structure
CN101624910A (en) * 2009-07-31 2010-01-13 广州市建筑机械施工有限公司 Method for reinforcing concealed tunnel
CN105735331A (en) * 2016-03-21 2016-07-06 上海长凯岩土工程有限公司 Grouting reinforcement construction method for underground engineering
CN106049204A (en) * 2016-08-03 2016-10-26 中铁十七局集团第三工程有限公司 Grooved formwork for pouring of reinforced concrete base of ballastless track
CN208056108U (en) * 2018-03-30 2018-11-06 云南建投基础工程有限责任公司 A kind of prefabricated assembled underground pipe gallery depression Disease Treatment structure
CN208256464U (en) * 2018-04-24 2018-12-18 马鞍山天磁磁业有限公司 A kind of positioning device that auxiliary permanent ferrite magnetizes
CN109184750A (en) * 2018-11-15 2019-01-11 中铁二十局集团轨道交通工程有限公司 A kind of tunnel radial grouting device and method
CN110042838A (en) * 2019-04-25 2019-07-23 中建四局第一建筑工程有限公司 A kind of reversed grouting construction method of floor structure
CN210958977U (en) * 2019-08-29 2020-07-07 依利安达(广州)电子有限公司 Drilling platform suitable for multilayer circuit board
CN111022082A (en) * 2020-01-14 2020-04-17 辽宁科技学院 Tunnel concrete two-lining void grouting hole sealing device
CN211893491U (en) * 2020-02-15 2020-11-10 浙江瓯络信息科技有限公司 Take shock-absorbing function's delivery case
CN111501428A (en) * 2020-05-26 2020-08-07 中铁上海设计院集团有限公司 Direct-buried fastener and construction method thereof

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116006217A (en) * 2022-12-27 2023-04-25 中铁十四局集团隧道工程有限公司 Pipe curtain structure and construction method thereof
CN116006217B (en) * 2022-12-27 2024-01-23 中铁十四局集团隧道工程有限公司 Pipe curtain structure and construction method thereof

Similar Documents

Publication Publication Date Title
CN104846810B (en) Self-circulating posterior grouting bored pile construction method
CN106759297A (en) A kind of construction method of support pile and three pipe high-pressure rotary jet grouting pile deep basal pits
CN108677924B (en) Double-row miniature steel pipe pile grouting wall-forming partition structure and method
CN104929114A (en) High pressure jet grouting pile waterproof curtain construction device and method
JP7257086B2 (en) Comprehensive Construction Method for Low Overburden Sections of Tunnels
CN109519150B (en) Dewatering well plugging device and method for large water yield
CN111576431A (en) Excavation method for foundation pit of four-layer subway station
CN105155550A (en) Construction method for digging deep foundation pit in large-thickness highly weathered sandstone stratum in combined supporting mode
CN105735323B (en) The inverse deep footing groove enclosing structure for making to combine with Percussion Piles of spray anchor and its construction method
CN110374068A (en) A kind of sluice force reduction pool bottom draining hole construction method preventing blocking
CN114808990A (en) High-pressure pre-filling karst cave pile foundation construction method
CN201538975U (en) Seepage-proofing joint of underground continuous wall
CN112144559A (en) Well construction method in high water-rich loess sandy gravel stratum transformer tube well
CN109723055B (en) Underground diaphragm wall bottom reinforcing structure and construction method thereof
CN102235007B (en) Method for supporting deep foundation with upper nail-lower pile combination
CN207862925U (en) A kind of slip casting casing device
CN112982372A (en) Inner drilling pipe insertion pipe compaction grouting reinforcement method based on pipe gallery bottom plate cavity
CN117345944A (en) Buried installation process of large-caliber PCCP pipeline on complex foundation
CN105484270B (en) Reinforcement protection construction method of high steep old rubble retaining wall adjacent to deep foundation pit
CN111254877A (en) Channel deep ballast rapid construction method
CN110820756A (en) Shield well and vertical shaft deep foundation pit excavation safety construction method
CN110258600A (en) A kind of vertical cofferdam construction engineering method suitable for deep water waters
CN114607386A (en) Single-layer well wall with connecting and water stopping structure and grouting system and construction method thereof
CN113202110A (en) Construction method for supporting and protecting finite space railway bridge and culvert prefabricated foundation pit
CN113186768A (en) Construction method for improving roadbed backfill quality after existing line demolition of frame structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20210618

RJ01 Rejection of invention patent application after publication