CN115199052A CN202210918674.4A CN202210918674A CN115199052A CN 115199052 A CN115199052 A CN 115199052A CN 202210918674 A CN202210918674 A CN 202210918674A CN 115199052 A CN115199052 A CN 115199052A
Authority
CN
China
Prior art keywords
wallboard
alc
alc wallboard
cracking
fixing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202210918674.4A
Other languages
Chinese (zh)
Inventor
张超
朱崇解
白代成
粘金龙
陈豪
李俊楠
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Qingdao Zhongjia Construction Group Co Ltd
Original Assignee
Qingdao Zhongjia Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Qingdao Zhongjia Construction Group Co Ltd filed Critical Qingdao Zhongjia Construction Group Co Ltd
Priority to CN202210918674.4A priority Critical patent/CN115199052A/en
Publication of CN115199052A publication Critical patent/CN115199052A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/62Insulation or other protection; Elements or use of specified material therefor
    • E04B1/66Sealings
    • E04B1/68Sealings of joints, e.g. expansion joints
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/62Insulation or other protection; Elements or use of specified material therefor
    • E04B1/66Sealings
    • E04B1/68Sealings of joints, e.g. expansion joints
    • E04B1/6801Fillings therefor
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/56Load-bearing walls of framework or pillarwork; Walls incorporating load-bearing elongated members
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • E04G21/16Tools or apparatus
    • E04G21/167Tools or apparatus specially adapted for working-up plates, panels or slab shaped building elements
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02WCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO WASTEWATER TREATMENT OR WASTE MANAGEMENT
    • Y02W30/00Technologies for solid waste management
    • Y02W30/50Reuse, recycling or recovery technologies
    • Y02W30/91Use of waste materials as fillers for mortars or concrete

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Mechanical Engineering (AREA)
  • Finishing Walls (AREA)

Abstract

The invention discloses a fixed installation and construction method of an anti-cracking ALC wallboard, which comprises the following steps: step one, fixing a base frame; step two, wallboard treatment; step three, installing the wallboard; step four, fixing the wall plate; step five, wedge removal and filling; step six, bonding treatment; step seven, anti-cracking treatment; according to the invention, the ALC wallboard is supported in an auxiliary way in the construction process by filling the layer of building binder between the ALC wallboards, so that the construction difficulty is reduced, the installation stability of the ALC wallboard is improved, the wood wedge is taken out after the mortar is filled, and the supplementary mortar is filled in the gap, so that the ALC wallboard is prevented from being affected with damp and damaged due to the fact that the wood wedge is remained at the bottom of the wallboard, the service life of the ALC wallboard is prolonged, alkali-resistant grid cloth is filled in the gap between the ALC wallboards, and the ALC wallboard after installation is subjected to anti-cracking treatment, so that the joint of the ALC wallboard is prevented from cracking in the use process, and the installation quality of the ALC wallboard is further ensured.

Description

Anti-cracking ALC wallboard fixed installation construction method
Technical Field
The invention relates to the technical field of ALC wallboard installation, in particular to a fixed installation construction method of an anti-cracking ALC wallboard.
Background
ALC is autoclaved lightweight concrete, one kind of high performance autoclaved aerated concrete, ALC wallboard is a porous concrete forming plate material which is cured by high pressure steam and is made of fly ash, cement, lime and the like, the ALC wallboard is reinforced by processed reinforcing steel bars, can be used as a wall material and a roof board, and is widely used in the building industry as a novel building material with superior performance.
Disclosure of Invention
The invention aims to provide an anti-cracking ALC wallboard fixed installation construction method to solve the problems in the background technology.
In order to achieve the purpose, the invention provides the following technical scheme: a fixed installation and construction method of an anti-cracking ALC wallboard comprises the following steps: step one, fixing a base frame; step two, wallboard treatment; step three, installing the wallboard; step four, fixing the wall board; step five, wedge removal and filling; step six, bonding treatment; step seven, anti-cracking treatment;
fixing a main body connecting steel plate on the frame column by using an expansion anchor bolt, welding connecting angle steel on the main body connecting steel plate according to a wallboard typesetting positioning diagram and a wallboard paying-off position, and painting a layer of antirust paint at the welding position of the connecting steel plate and the connecting angle steel after welding;
placing the ALC wallboard on the hand-turning vehicle, cutting the ALC wallboard on the hand-turning vehicle according to the wallboard typesetting and positioning diagram, punching angle steel connecting holes on the ALC wallboard after cutting, fixing wallboard accessories on the ALC wallboard, nailing U-shaped pipe clamps on the frame columns according to the paying-off positions of the wallboards, and fixing the U-shaped pipe clamps by using fixing anchor bolts;
in the third step, a hook bolt is sleeved on the angle steel connecting hole, the ALC wallboard is fixed on the main body connecting steel plate through the hook bolt, and the ALC wallboard is assisted and fixed through the U-shaped pipe clamp;
in the fourth step, a lifting rope is installed to detect the verticality, a 2m guiding rule is used to detect the flatness, the verticality and the flatness are adjusted through a crowbar, a support wood wedge is embedded into the bottom of the ALC wallboard after adjustment, and then a hook bolt is welded on a main body connecting steel plate;
coating a layer of antirust paint at the welding position of the hook bolt and the main body connecting steel plate, pouring filling mortar at the bottom of the ALC wallboard, taking out the wood wedge, and filling supplementary mortar in a wood wedge hole;
in the sixth step, a layer of masonry adhesive is filled between the ALC wallboards, then wide wallboards are adhered to two sides of the door opening to serve as placing points of the door upper shelf, and then the door upper shelf is installed at the top of the wide door panel;
and seventhly, embedding and installing PE rods in gaps on two sides of the ALC wallboard, filling PU foaming adhesive into the gaps, filling anti-crack mortar into the gaps, plastering, repairing edges and corners of the ALC wallboard by using repair powder, filling alkali-resistant grid cloth into the gaps on the top of the ALC wallboard, filling anti-crack mortar into the gaps, plastering and finishing the fixed installation of the ALC wallboard.
Preferably, in the first step, the expansion anchor bolts used for fixing the main body connecting steel plates are M12 expansion anchor bolts, the distance between the expansion anchor bolts is 600mm, the size model of the main body connecting steel plates is 100 × 100 × 6mm, the distance between the main body connecting steel plates and the installation sideline of the wall plate is 1-2 mm, the size model of the connecting angle steel is 63 × 63 × 6mm, and the thickness of the coated anti-rust paint is 0.2-0.5 mm.
Preferably, in the second step, the angle steel connecting hole is located in the center of the upper end and the lower end of the ALC wallboard, the boundary distance between the angle steel connecting hole and the ALC wallboard is 3-4 mm, the distance between the fixed wallboard fittings is 45-50 mm, and an M8 fixing anchor bolt is used for fixing the U-shaped pipe clamp.
Preferably, in the third step, the hook bolt that uses is the hook bolt of specification M12, and the coupler bolt and the junction of ALC wallboard cup joints the gasket of specification D50.
Preferably, in the fourth step, the verticality and the flatness of the ALC wallboard are adjusted to 0-5 mm through the crowbar, the flatness of the ALC wallboard is adjusted to 0-3 mm, the thickness of the support wood wedges is 8-10 mm, and the distance between the support wood wedges is 500mm.
Preferably, in the fifth step, the welding position of the hook bolt and the main body connecting steel plate is coated with the antirust paint with the thickness of 0.2-0.5 mm, the poured filling mortar is the cement mortar of 1:3, and when the strength of the filling mortar reaches 1.20N/mm 2 When the wood wedge is taken out, the filled supplementary mortar is 1:3 cement mortar.
Preferably, in the sixth step, the thickness of the filling and building adhesive is 3-4 mm, the thickness of the wide wallboard is 100mm, and the width of the wide wallboard is consistent with that of the ALC wallboard.
Compared with the prior art, the invention has the beneficial effects that: this prevent ALC wallboard fixed mounting construction method of fracture, through filling one deck between ALC wallboard and building the binder, carry out the auxiliary stay to ALC wallboard in the in-process of construction, the construction degree of difficulty has been reduced, the installation stability of ALC wallboard has been improved, through taking out the wood wedge after filling the mortar, and fill in the gap and supply the mortar, prevent that the wood wedge from remaining and leading to ALC wallboard to wet the damage in the bottom of wallboard, thereby the life of ALC wallboard has been prolonged, through filling alkali-resistant net cloth in the clearance between ALC wallboard, reuse anti-crack mortar to fill in and wipe one's face, prevent that the junction of ALC wallboard from appearing the fracture in the use, and then ensured the installation quality of ALC wallboard.
Drawings
FIG. 1 is a flow chart of the construction method of the present invention;
FIG. 2 is a schematic view of a wall panel fixing node according to the present invention;
FIG. 3 is a schematic view of the construction of the wallboard in the pretreatment process of the present invention;
FIG. 4 is a schematic view of the construction of the wall panel of the present invention in the vertical position;
FIG. 5 is a schematic view of the construction in the course of the bonding treatment in the present invention;
FIG. 6 is a schematic view of the construction of the wallboard gap treatment process of the present invention;
fig. 7 is a schematic construction diagram of the anti-cracking treatment process in the invention.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
Referring to fig. 1-7, an embodiment of the present invention is shown: a fixed installation construction method of an anti-cracking ALC wallboard comprises the following steps: step one, fixing a base frame; step two, wallboard treatment; step three, installing the wallboard; step four, fixing the wall plate; step five, wedge removal and filling; step six, bonding treatment; step seven, anti-cracking treatment;
in the first step, as shown in fig. 2, main body connecting steel plates with the size and model of 100 × 100 × 3mm are fixed on a frame column by using expansion anchor bolts with the specification of M12, the distance between the expansion anchor bolts is 600mm, the distance between the main body connecting steel plates and a wall board mounting side line is 1-2 mm, then connecting angle steel with the size and model of 100 × 100 × 3mm is welded on the main body connecting steel plates according to a wall board typesetting positioning diagram and a wall board paying-off position, and a layer of antirust paint with the thickness of 0.2-0.5 mm is coated at the welding position of the connecting steel plates and the connecting angle steel after welding;
in the second step, as shown in fig. 3, the ALC wallboard is placed on the hand-turning vehicle, then the ALC wallboard on the hand-turning vehicle is cut according to the wallboard typesetting and positioning diagram, then angle steel connecting holes are drilled in the cut ALC wallboard, the angle steel connecting holes are located in the centers of the upper end and the lower end of the ALC wallboard, the boundary distance between the angle steel connecting holes and the ALC wallboard is 3-4 mm, then wallboard accessories are fixed on the ALC wallboard, the distance between the fixed wallboard accessories is 45-50 mm, then a U-shaped pipe clamp is nailed into the frame column according to the line laying position of the wallboard, and then the U-shaped pipe clamp is fixed by using a fixing anchor bolt with the specification of M8;
in the third step, a hook head bolt with the specification of M12 is sleeved on the angle steel connecting hole, a gasket with the specification of D50 is sleeved at the connecting part of the hook head bolt and the ALC wallboard, then the ALC wallboard is fixed on the main body connecting steel plate through the hook head bolt, and meanwhile, the ALC wallboard is assisted and fixed through the U-shaped pipe clamp;
wherein in the fourth step, the installation lifting rope carries out the straightness that hangs down and detects, uses 2m guiding ruler to carry out the roughness simultaneously and detects, then adjusts straightness and roughness through the crowbar, adjusts the straightness that hangs down of ALC wallboard to 0 ~ 5mm, adjusts the roughness of ALC wallboard to 0 ~ 3mm simultaneously, imbeds the support wooden wedge at the bottom of ALC wallboard after the adjustment, as shown in FIG. 4. The thickness of the supporting wooden wedges is 8-10 mm, the distance between the supporting wooden wedges is 500mm, and then the hook bolt is welded on the main body connecting steel plate;
in the fifth step, a layer of antirust paint with the thickness of 0.2-0.5 mm is coated at the welding position of the hook bolt and the main body connecting steel plate, then filling mortar is poured at the bottom of the ALC wallboard, and the used filling mortar is the cement mortar of 1:3, as shown in FIG. 4. When the strength of the filling mortar reaches 1.20N/mm 2 Taking out the wooden wedge, and filling supplementary mortar into the hole of the wooden wedgeThe supplementary mortar is 1:3 cement mortar;
in the sixth step, a layer of masonry adhesive with the thickness of 3-4 mm is filled between the ALC wallboards, then as shown in figure 5, wide wallboards are adhered to two sides of the door opening to serve as placing points of the door upper shelf, the thickness of each wide wallboard is 100mm, the width of each wide wallboard is consistent with that of the ALC wallboards, and then the door upper shelf is installed at the top of each wide wallboard;
in the seventh step, as shown in fig. 6, PE rods are embedded and installed in the gaps on both sides of the ALC wallboard, and then PU foam adhesive is filled into the gaps. And then, as shown in fig. 7, adhering an anti-cracking reinforcing net at the joint of the wall board, then using anti-cracking mortar to perform filling and plastering, then using repair powder to repair the corners of the ALC wall board, then filling alkali-resistant grid cloth in the gap at the top of the ALC wall board, and then using anti-cracking mortar to perform filling and plastering, thereby completing the fixed installation of the ALC wall board.
Based on the above, the method has the advantages that when the method is used, the ALC wallboard is supported in an auxiliary mode by the aid of the building adhesive layer filled between the ALC wallboards, an auxiliary adhesive structure is formed, the ALC wallboards are supported in an auxiliary mode in the construction process, the construction difficulty is reduced, the installation stability of the ALC wallboards is improved, the wood wedges are taken out after the mortar is filled, the residual gaps are filled with the filling mortar, the ALC wallboards are prevented from being affected with damp and damaged due to the fact that the wood wedges are remained at the bottoms of the wallboards, the service life of the ALC wallboards is prolonged, the gaps between the ALC wallboards are filled with the alkali-resistant grid cloth, the anti-crack mortar is used for filling and plastering, the ALC wallboards after installation are subjected to anti-cracking treatment, cracking at the joints of the ALC wallboards in the using process is prevented, and the installation quality of the ALC wallboards is guaranteed.
It will be evident to those skilled in the art that the invention is not limited to the details of the foregoing illustrative embodiments, and that the present invention may be embodied in other specific forms without departing from the spirit or essential attributes thereof. The present embodiments are therefore to be considered in all respects as illustrative and not restrictive, the scope of the invention being indicated by the appended claims rather than by the foregoing description, and all changes which come within the meaning and range of equivalency of the claims are therefore intended to be embraced therein. Any reference sign in a claim should not be construed as limiting the claim concerned.

Claims (7)

1. A fixed installation and construction method of an anti-cracking ALC wallboard comprises the following steps: step one, fixing a base frame; step two, wallboard treatment; step three, installing the wallboard; step four, fixing the wall board; step five, wedge removal and filling; step six, bonding treatment; step seven, anti-cracking treatment; the method is characterized in that:
in the first step, an expansion anchor bolt is used for fixing an L-shaped connecting piece on the frame beam according to the wallboard typesetting positioning diagram and the paying-off position of the wallboard, and the L-shaped connecting piece is provided with a bolt hole; then, according to the line-releasing position of the wall plate, nailing a U-shaped pipe clamp on the frame column, and then fixing the U-shaped pipe clamp by using a fixing anchor bolt;
placing the ALC wallboard on the hand-turning vehicle, cutting the ALC wallboard on the hand-turning vehicle according to the wallboard typesetting and positioning diagram, and then punching an angle steel connecting hole on the cut ALC wallboard;
in the third step, the ALC wallboard is installed in place by using a trolley and an auxiliary tool, the verticality and the flatness are detected by using a detection instrument, then the verticality and the flatness are adjusted by using a crowbar, meanwhile, bolt holes in the L-shaped connecting piece are aligned with bolt holes in the wallboard, and after adjustment, support wood wedges are embedded into the bottom of the ALC wallboard for preliminary fixing;
in the fourth step, a hook bolt is sleeved on the angle steel connecting hole, the ALC wallboard is fixed on the connecting angle steel through the hook bolt and the connecting steel plate, and the ALC wallboard is assisted and fixed through the U-shaped pipe clamp; then, smearing special bonding mortar on the side surface (splicing surface) of the installed first ALC wallboard in batches, and installing 3I-shaped connecting pieces at the upper, middle and lower positions;
in the fifth step, repeating the first step to the fourth step until the front wall is installed, then filling dry and hard cement mortar at the bottom of the ALC wallboard, taking out the wood wedge after the mortar is solidified, and filling supplementary mortar in the wood wedge hole;
in the sixth step, a layer of building adhesive is filled between the ALC wallboards, then wide wallboards are adhered to two sides of the door opening to be used as laying points of the upper shelf of the door, and then the upper shelf of the door is installed at the top of the wide door panel;
and seventhly, embedding and installing PE rods in gaps on two sides of the ALC wallboard, filling PU foaming glue in the gaps, filling anti-crack mortar for plastering, repairing edges and corners of the ALC wallboard by using repair powder, filling alkali-resistant grid cloth in the gaps on the top of the ALC wallboard, filling anti-crack mortar for plastering, and finishing the fixed installation of the ALC wallboard.
2. The fixed installation and construction method of the anti-cracking ALC wallboard as claimed in claim 1, characterized in that: in the first step, the expansion anchor bolts used for fixing the L-shaped connecting pieces are M8 expansion anchor bolts, each connecting piece is provided with 2 expansion anchor bolts so as to ensure that the mounting positions of the connecting pieces are accurate and do not deviate, the size model of each L-shaped connecting piece is 100 multiplied by 60 multiplied by 3mm, the distance between each connecting piece and a mounting sideline of the wallboard is 1-2 mm, the size model of each connecting angle steel is 63 multiplied by 6mm, and the thickness of the coated antirust paint is 0.2-0.5 mm.
3. Fixing an L-shaped connecting piece on the frame beam by using an expansion anchor bolt according to the wallboard typesetting positioning drawing and the wallboard paying-off position, wherein the connecting piece is provided with a bolt hole; then, according to the line-releasing position of the wall plate, nailing a U-shaped pipe clamp on the frame column, and then fixing the U-shaped pipe clamp by using a fixing anchor bolt;
the fixed installation and construction method of the anti-cracking ALC wallboard as claimed in claim 1, characterized in that: in the second step, the angle steel connecting holes are located in the centers of the upper end and the lower end of the ALC wallboard, the boundary distance between the angle steel connecting holes and the ALC wallboard is 3-4 mm, the distance between the fixed wallboard fittings is 45-50 mm, and M8 fixing anchor bolts are used for fixing the U-shaped pipe clamps.
4. The fixed installation and construction method of the anti-cracking ALC wallboard as claimed in claim 1, characterized in that: in the third step, the used hook bolt is the hook bolt with the specification of M12, and the joint of the hook bolt and the ALC wallboard is sleeved with the gasket with the specification of D50.
5. The fixed installation and construction method of the anti-cracking ALC wallboard as claimed in claim 1, characterized in that: in the fourth step, the verticality and the flatness of the ALC wallboard are adjusted to 0-5 mm through the crowbar, the flatness of the ALC wallboard is adjusted to 0-3 mm, the thickness of the support wood wedges is 8-10 mm, and the distance between the support wood wedges is 500mm.
6. The fixed installation and construction method of the anti-cracking ALC wallboard as claimed in claim 1, characterized in that: in the fifth step, the welding position of the hook bolt and the main body connecting steel plate is coated with the antirust paint with the thickness of 0.2-0.5 mm, the poured filling mortar is the cement mortar of 1:3, and when the strength of the filling mortar reaches 1.20N/mm 2 When the wood wedge is taken out, the filled supplementary mortar is 1:3 cement mortar.
7. The fixed installation and construction method of the anti-cracking ALC wallboard as claimed in claim 1, characterized in that: in the sixth step, the thickness of the filling and building adhesive is 3-4 mm, the thickness of the wide wallboard is 100mm, and the width of the wide wallboard is consistent with that of the ALC wallboard.
CN202210918674.4A 2022-08-02 2022-08-02 Anti-cracking ALC wallboard fixed installation construction method Pending CN115199052A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210918674.4A CN115199052A (en) 2022-08-02 2022-08-02 Anti-cracking ALC wallboard fixed installation construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210918674.4A CN115199052A (en) 2022-08-02 2022-08-02 Anti-cracking ALC wallboard fixed installation construction method

Publications (1)

Publication Number Publication Date
CN115199052A true CN115199052A (en) 2022-10-18

Family

ID=83586087

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210918674.4A Pending CN115199052A (en) 2022-08-02 2022-08-02 Anti-cracking ALC wallboard fixed installation construction method

Country Status (1)

Country Link
CN (1) CN115199052A (en)

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH10266439A (en) * 1997-03-27 1998-10-06 Onoda Autoclaved Light Weight Concrete Co Ltd Structure for attaching autoclaved lightweight concrete wall panel to concrete surface
CN104746772A (en) * 2015-04-16 2015-07-01 重庆建工第三建设有限责任公司 Ash concrete hollow partition board anti-cracking construction method
CN106223516A (en) * 2016-09-08 2016-12-14 北京城建深港建筑装饰工程有限公司 ALC steam-pressing aero-concrete batten tilts curtain wall structure and construction method
CN106499091A (en) * 2016-11-22 2017-03-15 中国建筑第七工程局有限公司 A kind of assembling type partition wall construction method based on ALC plates
CN106869502A (en) * 2017-04-20 2017-06-20 中铁七局集团第四工程有限公司 The accurate building block method for controlling crack of steam pressure sand aerated concrete
CN206815590U (en) * 2017-03-31 2017-12-29 中民筑友科技投资有限公司 A kind of wallboard installation node based on frame system
CN111549932A (en) * 2020-04-30 2020-08-18 中国一冶集团有限公司 Connecting structure of lightweight concrete wallboard and foundation structure and construction method
CN111576890A (en) * 2020-05-28 2020-08-25 重庆市中科大业建筑科技有限公司 Construction method of assembled ALC partition wall
CN212224297U (en) * 2020-05-13 2020-12-25 中建八局天津建设工程有限公司 Prefabricated autoclaved aerated concrete outer wall plate structure system
CN214738854U (en) * 2020-11-20 2021-11-16 青岛中建联合集团有限公司 Wallboard sealing connection mechanism for assembly type building

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH10266439A (en) * 1997-03-27 1998-10-06 Onoda Autoclaved Light Weight Concrete Co Ltd Structure for attaching autoclaved lightweight concrete wall panel to concrete surface
CN104746772A (en) * 2015-04-16 2015-07-01 重庆建工第三建设有限责任公司 Ash concrete hollow partition board anti-cracking construction method
CN106223516A (en) * 2016-09-08 2016-12-14 北京城建深港建筑装饰工程有限公司 ALC steam-pressing aero-concrete batten tilts curtain wall structure and construction method
CN106499091A (en) * 2016-11-22 2017-03-15 中国建筑第七工程局有限公司 A kind of assembling type partition wall construction method based on ALC plates
CN206815590U (en) * 2017-03-31 2017-12-29 中民筑友科技投资有限公司 A kind of wallboard installation node based on frame system
CN106869502A (en) * 2017-04-20 2017-06-20 中铁七局集团第四工程有限公司 The accurate building block method for controlling crack of steam pressure sand aerated concrete
CN111549932A (en) * 2020-04-30 2020-08-18 中国一冶集团有限公司 Connecting structure of lightweight concrete wallboard and foundation structure and construction method
CN212224297U (en) * 2020-05-13 2020-12-25 中建八局天津建设工程有限公司 Prefabricated autoclaved aerated concrete outer wall plate structure system
CN111576890A (en) * 2020-05-28 2020-08-25 重庆市中科大业建筑科技有限公司 Construction method of assembled ALC partition wall
CN214738854U (en) * 2020-11-20 2021-11-16 青岛中建联合集团有限公司 Wallboard sealing connection mechanism for assembly type building

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
张智强;: "ALC墙板综合性能分析及施工工艺探讨", 安装, no. 08 *

Similar Documents

Publication Publication Date Title
CN209817249U (en) A compound wallboard of prefabricated foam concrete for building infilled wall
CN109138227A (en) Without exterior sheathing exterior-wall heat insulation and structure-integrated pouring molding construction technology
CN102140841A (en) Construction method of building superstructure in high-rise steel-concrete mixed structure with few supporting formworks
CN103835505A (en) Outer wall compound heat preservation board construction method
CN102644382A (en) Mounting technology of large-module wall
CN110630011A (en) Template reinforcing system for double shear walls at deformation joint and construction method thereof
CN215888729U (en) Assembled building interior wall baffle
CN117661844A (en) Light energy-saving wall partition board installation construction method
CN112459307A (en) Construction method of prefabricated heat-preservation-structure integrated wall external formwork
CN218374567U (en) Can fix a position ALC wallboard reinforced structure that can exempt from to plaster
CN115199052A (en) Anti-cracking ALC wallboard fixed installation construction method
CN116104224A (en) External wall heat insulation integrated gap spliced construction node and construction method
CN215671018U (en) Shear force wall layer connects a stubble department reinforced structure
CN102296827A (en) Mounting method of light-weight partition wall board
KR20190078792A (en) Multi system bracket
CN111379337B (en) Secondary structure anti-seepage and anti-leakage construction method
CN111535578A (en) Mounting process of template of cast-in-place structure
CN112127501A (en) Combined wall structure and construction method thereof
CN106639099A (en) Control method for flatness of surface of formwork bracing system of plant fiber type heat-preservation non-dismantling formwork
CN111576681A (en) FS composite heat-preservation construction integrated technology construction process
CN109707152A (en) Aluminum alloy mould plate system and its construction method
CN114575491B (en) Composite construction method for special-shaped complex secondary structure
CN218758706U (en) A template system of consolidating for superimposed sheet post-cast strip construction
CN217982797U (en) Reusable flag platform
CN209837379U (en) Wallboard connecting joint

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination