Real estate construction quality control method and system Download PDF

Info

Publication number
CN115147021B
CN115147021B CN202211071714.2A CN202211071714A CN115147021B CN 115147021 B CN115147021 B CN 115147021B CN 202211071714 A CN202211071714 A CN 202211071714A CN 115147021 B CN115147021 B CN 115147021B
Authority
CN
China
Prior art keywords
module
construction
acceptance
data
image data
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202211071714.2A
Other languages
Chinese (zh)
Other versions
CN115147021A (en
Inventor
蔡其旭
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenzhen Fangbangbang Internet Technology Co ltd
Original Assignee
Shenzhen Fangbangbang Internet Technology Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shenzhen Fangbangbang Internet Technology Co ltd filed Critical Shenzhen Fangbangbang Internet Technology Co ltd
Priority to CN202211071714.2A priority Critical patent/CN115147021B/en
Publication of CN115147021A publication Critical patent/CN115147021A/en
Application granted granted Critical
Publication of CN115147021B publication Critical patent/CN115147021B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0639Performance analysis of employees; Performance analysis of enterprise or organisation operations
    • G06Q10/06395Quality analysis or management
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction
    • HELECTRICITY
    • H04ELECTRIC COMMUNICATION TECHNIQUE
    • H04NPICTORIAL COMMUNICATION, e.g. TELEVISION
    • H04N7/00Television systems
    • H04N7/18Closed-circuit television [CCTV] systems, i.e. systems in which the video signal is not broadcast

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Economics (AREA)
  • Strategic Management (AREA)
  • General Physics & Mathematics (AREA)
  • General Business, Economics & Management (AREA)
  • Theoretical Computer Science (AREA)
  • Educational Administration (AREA)
  • Marketing (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Development Economics (AREA)
  • Tourism & Hospitality (AREA)
  • Physics & Mathematics (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Game Theory and Decision Science (AREA)
  • Health & Medical Sciences (AREA)
  • General Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Multimedia (AREA)
  • Signal Processing (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention relates to the technical field of data processing, in particular to a real estate construction quality control method and system, comprising the following steps: the control platform is a main control end of the system and is used for sending out an execution command; the storage module is used for storing the system operation transceiving data content; the modification module is used for modifying the content of the data stored in the storage module; the camera module is used for recording construction scene image data; the design module is used for designing a completion building acceptance scheme and synchronously transmitting the acceptance scheme to the transmitting end equipment; the invention can divide the construction site into areas, further acquire the image data of the construction site by matching with the camera, store the image data, synchronously configure the construction progress feedback, and achieve the aim of clear responsibility of construction quality in a construction progress feedback mode, thereby realizing the construction quality control of the construction site, having simple and stable overall operation logic of the system and greatly reducing the manual labor output in the construction quality control process.

Description

Real estate construction quality control method and system
Technical Field
The invention relates to the technical field of data processing, in particular to a real estate construction quality control method and system.
Background
In the construction projects developed by real estate, the construction quality of the building is always the most powerful evaluation standard for evaluating the comprehensive strength level of the real estate developer, but the real estate developer does not basically have building conditions, so that the developed land is outsourced to a building enterprise in a bidding mode.
However, this outsourcing action results in the outsourcing of construction management rights, and real estate developers cannot effectively manage the construction quality of the building, and reliable construction quality monitoring cannot be satisfied by only manual inspection or deployment of simple monitoring equipment, which further causes construction quality defects.
Disclosure of Invention
Technical problem to be solved
Aiming at the defects existing in the prior art, the invention provides a real estate construction quality control method and a real estate construction quality control system, and solves the technical problems in the background art.
Technical proposal
In order to achieve the above purpose, the invention is realized by the following technical scheme:
in a first aspect, an real estate agent management and control system comprising:
the control platform is a main control end of the system and is used for sending out an execution command;
the storage module is used for storing the system operation transceiving data content;
the modification module is used for modifying the content of the data stored in the storage module;
the camera module is used for recording construction scene image data;
the design module is used for designing a completion building acceptance scheme and synchronously transmitting the acceptance scheme to the transmitting end equipment;
the sampling module is used for extracting an acceptance target;
the uploading module is used for uploading the system acceptance target line acceptance result;
and the evaluation module is used for measuring and calculating the qualification rate of the finished building and making a decision of the acceptance result of the finished building by referring to the qualification rate.
Still further, the storage module is provided with a sub-module at a lower stage, including:
the editing unit is used for newly establishing a data folder in the storage module;
the memory unit is used for acquiring the equipment information of the data content transmitting end when the storage module stores the data content;
the editing unit operates the newly built data folders and generates the newly built data folders according to the input quantity of the user side, the user side manually edits the data folders to rename, the user side synchronously acquires the transmitting side information obtained by the operation of the memory unit when manually editing the renamed data folders, and the user side configures the data folders according to the transmitting side equipment information to grant the transmitting side equipment with permission to transmit data contents.
Still further, the storage module is provided with a sub-module at a lower stage, and further includes:
the cloning unit is used for copying the editing unit and the memory unit operation logic to operate again under the data folder newly built by the editing unit;
the number of the cloning units is not unique, and the number of the cloning units is even.
Furthermore, the storage module stores construction progress text information with text format as data content, the modification module operates to provide the transmitting end equipment with data content authority in the modification data folder on the editing unit in the storage module, and the number of transmitting end equipment with data content authority in the modification data folder is less than that of transmitting end equipment with data content transmission authority.
Still further, camera module lower level is provided with the submodule piece, includes:
the cloud database is used for storing the image data of the construction scene recorded by the operation of the camera module;
a marking unit for marking the image data as an image data file name;
the marking unit operates to mark the image data file marking logic according to the occurrence time and the position of the image data.
Still further, the as built building acceptance plan design includes: completion building acceptance projects and completion building acceptance time, and the sampling module operates to extract an acceptance target as an installation position of the camera module corresponding to image data stored in the cloud database corresponding to the newly built data folder of the editing unit;
and the system end user uploads the acceptance result through the uploading module, and the camera module is in a starting state before uploading the acceptance result after the operation of the sampling module is finished.
Further, the qualification rate of the completion building is calculated by the evaluation module according to the following formula:
wherein: n is the number of items;
is a predicted value (manually input for a system end user);
is a true value.
Furthermore, the control platform is electrically connected with a storage module through a medium, the storage module is electrically connected with an editing unit and a memory unit through the medium, the editing unit and the memory unit are all connected with a cloning unit through the medium, the storage module is electrically connected with a modification module, a design module, a sampling module and an uploading module through the medium, the sampling module is connected with a camera module through the medium, the camera module is connected with the control platform through the medium, the camera module is connected with a cloud database and a marking unit through the medium, and the uploading module is connected with an evaluation module through the medium.
In a second aspect, the real estate construction quality control method includes the following steps:
step1: dividing construction areas according to construction areas of a construction target building, deploying monitoring equipment to each construction area in the construction target building, setting a virtual storage cloud disk on an image data line, and uploading recorded image data of the monitoring equipment;
step2: creating a magnetic disk on a computer and configuring a data transmission channel to provide a construction target building construction site management end user to send an engineering progress message, setting a progress message feedback period, and sending the engineering progress message according to the feedback period by the management end user;
step3: reading engineering progress information on a computer, judging a construction state of a construction target building, and designing a completion acceptance scheme synchronously according to a construction project when the construction target building is completed as a judgment result;
step4: uploading data content of a checking result of a checking scheme, calling an engineering progress message in a computer for construction projects with unqualified checking results, and synchronously downloading construction project corresponding construction sheet area image data in a virtual storage cloud disk on an image data line;
step5: setting an engineering acceptance threshold value, and calculating the acceptance rate of the finished building according to the data content of the acceptance result of the acceptance scheme;
step6: and comparing the finished building qualification rate with a set engineering acceptance threshold value, and judging whether the finished building qualification rate is within the engineering acceptance threshold value range.
Further, the project progress message content sent by the management end user to the computer in Step2 includes the identity information of the corresponding project constructor.
Advantageous effects
Compared with the known public technology, the technical scheme provided by the invention has the following beneficial effects:
1. the invention provides a real estate construction work management and control system, which can divide areas of a construction site, further acquire construction site image data for storage by matching with a camera, synchronously configure construction progress feedback, and achieve the aim of clear construction quality responsibility in a construction progress feedback mode, so that the construction quality management and control of the construction site are realized, the overall operation logic of the system is simple and stable, the manual labor output in the construction quality management and control process is greatly reduced, the construction work management and control cost is saved, and meanwhile, corresponding construction data is stored, so that the follow-up adjustment of required construction data is facilitated.
2. The system of the invention can be used for checking the qualification rate of the finished building at the same time of running, and further can be used for determining whether the whole finished building is qualified or not according to the qualification rate, thereby the data can be used for more accurately evaluating the finished building.
3. The invention provides a real estate construction quality control method, which can further maintain the stability of system operation in the method through the execution of steps in the method, can orderly store data content generated in the execution step, and carry out qualification judgment on finished buildings, and if the judgment result is negative, can timely carry out responsibility judgment and tracing on unqualified places of the finished buildings, thereby bringing more convenience for users in specific use.
Drawings
In order to more clearly illustrate the technical solutions of the present invention or the prior art, the drawings used in the description of the embodiments or the prior art will be briefly described below. It is evident that the drawings in the following description are only some embodiments of the present invention and that other drawings may be obtained from these drawings without inventive effort for a person of ordinary skill in the art.
FIG. 1 is a schematic diagram of a construction of an real estate agent management and control system;
FIG. 2 is a schematic flow chart of a real estate construction quality control method;
reference numerals in the drawings represent respectively: 1. a control platform; 2. a storage module; 21. an editing unit; 22. a memory unit; 23. a cloning unit; 3. modifying the module; 4. a camera module; 41. a cloud database; 42. a marking unit; 5. designing a module; 6. a sampling module; 7. an uploading module; 8. and an evaluation module.
Detailed Description
In order to make the objects, technical solutions and advantages of the present invention more apparent, the technical solutions of the present invention will be clearly and completely described below with reference to the accompanying drawings. It will be apparent that the described embodiments are some, but not all, embodiments of the invention. All other embodiments, which can be made by those skilled in the art based on the embodiments of the invention without making any inventive effort, are intended to be within the scope of the invention.
The invention is further described below with reference to examples.
Example 1
The real estate agent management and control system of the present embodiment, as shown in fig. 1, includes:
the control platform 1 is a main control end of the system and is used for sending out an execution command;
a storage module 2 for storing the system operation transceiving data content;
a modifying module 3, configured to modify the content of the data stored in the storage module 2;
the camera module 4 is used for recording construction scene image data;
a design module 5 for designing a completion building acceptance plan and synchronously transmitting the acceptance plan to the transmitting end equipment;
the sampling module 6 is used for extracting an acceptance target;
the uploading module 7 is used for uploading the system acceptance target line lower acceptance result;
and the evaluation module 8 is used for measuring and calculating the qualification rate of the finished building and making a decision of the acceptance result of the finished building by referring to the qualification rate.
In this embodiment, the control platform 1 controls the camera module 4 to run and record the construction scene image data in real time, the synchronous storage system of the storage module 2 runs and receives data content, the management end user can remotely modify the data content stored in the storage module 2 through the modification module 3, after the building is completed, the user designs the completion building acceptance scheme through the design module 5, synchronously sends the acceptance scheme to the sending end equipment, then the sampling module 6 extracts the acceptance target, the uploading module 7 uploads the acceptance result of the system acceptance target line to the storage module 2, and finally the evaluation module 8 measures and calculates the qualification rate of the completion building, and makes a decision of the completion building acceptance result with reference to the qualification rate.
Example 2
On the aspect of the specific implementation, on the basis of the embodiment 1, the embodiment further specifically describes the real estate agent management and control system in the embodiment 1 with reference to fig. 1:
as shown in fig. 1, the storage module 2 is provided with a sub-module at a lower stage, including:
an editing unit 21 for newly creating a data folder in the storage module 2;
a memory unit 22, configured to obtain data content sender device information when the storage module 2 stores data content;
the editing unit 21 operates the newly created data folder according to the input number of the user terminal, the user terminal manually edits the data folder to rename, and synchronously obtains the sending terminal information obtained by the operation of the memory unit 22 when the user terminal manually edits the renamed data folder, and the user terminal configures the data folder according to the sending terminal device information to grant the sending terminal device permission to send the data content.
By configuring an independent credit data transmission channel for the transmitting terminal device for matching with the newly built data folder in the editing unit 21, the data content transmitted by the transmitting terminal device can be directly transmitted to the corresponding data folder for storage.
As shown in fig. 1, the storage module 2 is provided with a sub-module at a lower stage, and further includes:
a cloning unit 23 for copying the operation logic of the editing unit 21 and the memory unit 22 to be operated again under the data folder newly created by the editing unit 21;
the number of cloning units 23 is not unique, and the number of cloning units 23 is even.
As shown in fig. 1, the storage module 2 stores construction progress text information with text format as data content, and the modification module 3 operates to provide transmitting end devices to modify data content rights in the data folder on the editing unit 21 in the storage module 2, and the number of transmitting end devices provided with the data content rights in the modification folder is smaller than that of transmitting end devices provided with the data content rights.
Through the arrangement, the editing unit 21 and the memory unit 22 can be repeatedly deployed at the lower stage of the data folder established in the editing unit 21 in the system operation process, so that the data content stored in the storage module 2 is more refined under the system operation, a system end user can know the condition and progress of a construction site in more detail, and meanwhile, the data browsing amount of the system end user is reduced through the stepped data feedback and real-time modification update, and the purpose that the system application is faster and more convenient is achieved.
As shown in fig. 1, the camera module 4 is provided with a sub-module at a lower stage, including:
the cloud database 41 is used for storing image data of the construction scene recorded by the operation of the camera module 4;
a marking unit 42 for marking the image data as an image data file name;
wherein the marking unit 42 operates to mark the image data file marking logic according to the time and the position of the image data.
Through the arrangement, the image data recorded by the operation of the camera module 4 can be logically and reasonably stored, so that the image data corresponding to the required construction area can be conveniently fetched and used later.
As shown in fig. 1, the as-built building acceptance plan design includes: completion building acceptance project and completion building acceptance time, the sampling module 6 operates to extract an acceptance target to be the installation position of the camera module 4 corresponding to the image data stored in the cloud database 41 for the newly built data folder of the editing unit 21;
the system end user uploads the acceptance result through the uploading module 7, and before the acceptance result is uploaded after the operation of the sampling module 6 is finished, the camera module 4 is in a starting state.
Through this setting, further applied camera module 4 to the monitoring management that the acceptance link of completion building carries out to the effectual reliability that has promoted the acceptance link of completion building.
As shown in fig. 1, the qualification rate of the finished building is calculated by the evaluation module 8 according to the following formula:
wherein: n is the number of items;
is a predicted value (manually input for a system end user);
is a true value.
As shown in fig. 1, the control platform 1 is electrically connected with a storage module 2 through a medium, the storage module 2 is electrically connected with an editing unit 21 and a memory unit 22 through a medium, the editing unit 21 and the memory unit 22 are both connected with a cloning unit 23 through a medium, the storage module 2 is electrically connected with a modification module 3, a design module 5, a sampling module 6 and an uploading module 7 through a medium, the sampling module 6 is connected with the uploading module 7 through a medium, the camera module 4 is connected with the control platform 1 through a medium, the camera module 4 is connected with a cloud database 41 and a marking unit 42 through a medium, and the uploading module 7 is connected with an evaluation module 8 through a medium.
Example 3
On the aspect of the specific implementation, on the basis of the embodiment 1, the embodiment further specifically describes the real estate agent management and control system in the embodiment 1 with reference to fig. 2:
the real estate construction quality control method comprises the following steps:
step1: dividing construction areas according to construction areas of a construction target building, deploying monitoring equipment to each construction area in the construction target building, setting a virtual storage cloud disk on an image data line, and uploading recorded image data of the monitoring equipment;
step2: creating a magnetic disk on a computer and configuring a data transmission channel to provide a construction target building construction site management end user to send an engineering progress message, setting a progress message feedback period, and sending the engineering progress message according to the feedback period by the management end user;
step3: reading engineering progress information on a computer, judging a construction state of a construction target building, and designing a completion acceptance scheme synchronously according to a construction project when the construction target building is completed as a judgment result;
step4: uploading data content of a checking result of a checking scheme, calling an engineering progress message in a computer for construction projects with unqualified checking results, and synchronously downloading construction project corresponding construction sheet area image data in a virtual storage cloud disk on an image data line;
step5: setting an engineering acceptance threshold value, and calculating the acceptance rate of the finished building according to the data content of the acceptance result of the acceptance scheme;
step6: and comparing the finished building qualification rate with a set engineering acceptance threshold value, and judging whether the finished building qualification rate is within the engineering acceptance threshold value range.
The project progress message content sent by the management end user to the computer in Step2 comprises corresponding project constructor identity information.
In summary, through the above embodiment, the construction site can be divided into areas, the image data of the construction site can be further obtained by matching with the camera to be stored, and the construction progress feedback is synchronously configured, so that the purpose of clear responsibility of construction quality is achieved in a construction progress feedback mode, thereby realizing the construction quality control of the construction site, the overall operation logic of the system is simple and stable, the manual labor output in the construction quality control process is greatly reduced, the construction quality control cost is saved, and meanwhile, the corresponding construction data is stored, so that the follow-up acquisition of the required construction data is facilitated; meanwhile, the qualification rate of the finished building can be checked, and whether the whole finished building is qualified or not is further determined according to the qualification rate, so that the finished building can be accurately assessed according to the data; in addition, by executing the steps in the method, the system operation stability can be recorded in the embodiment of maintenance, meanwhile, the data content generated in the execution step can be orderly stored, the completion building is subjected to qualification judgment, the judgment result is no, and the responsibility judgment and tracing can be timely carried out on unqualified completion building positions, so that more convenience is brought to a user in specific use.
The above embodiments are only for illustrating the technical solution of the present invention, and are not limiting; although the invention has been described in detail with reference to the foregoing embodiments, it will be understood by those of ordinary skill in the art that: the technical scheme described in the foregoing embodiments can be modified or some technical features thereof can be replaced by equivalents; such modifications and substitutions do not depart from the spirit and scope of the technical solutions of the embodiments of the present invention.

Claims (1)

1. Real estate construction work medium management and control system, characterized by comprising:
the control platform (1) is a main control end of the system and is used for sending out an execution command;
a storage module (2) for storing the system operation transceiving data content;
a modifying module (3) for modifying the content of the stored data in the storing module (2);
the camera module (4) is used for recording construction scene image data;
a design module (5) for designing an acceptance plan of the finished building and synchronously transmitting the acceptance plan to the transmitting end equipment;
a sampling module (6) for extracting an acceptance target;
the uploading module (7) is used for uploading the system acceptance target line lower acceptance result;
the evaluation module (8) is used for measuring and calculating the qualification rate of the finished building and making a decision of the acceptance result of the finished building by referring to the qualification rate;
the storage module (2) is provided with a sub-module at the lower stage, and comprises:
an editing unit (21) for newly creating a data folder in the storage module (2);
a memory unit (22) for acquiring the device information of the data content transmitting end when the storage module (2) stores the data content;
the editing unit (21) operates the newly built data folder to generate according to the input quantity of the user side, the user side manually edits the data folder to rename, the user side synchronously acquires the transmitting side information obtained by the operation of the memory unit (22) when manually editing the renamed data folder, and the user side configures the data folder to grant the transmitting side device with permission to transmit data content according to the transmitting side device information;
the lower level of the storage module (2) is provided with a sub-module, and the storage module further comprises:
the cloning unit (23) is used for copying the operation logic of the editing unit (21) and the memory unit (22) to be operated again under the newly built data folder of the editing unit (21);
the number of the clone units (23) is not unique, and the number of the clone units (23) is even;
the storage module (2) stores construction progress text information with text format of data content, the modification module (3) operates and provides transmitting terminal equipment to modify data content authority in a data folder on an editing unit (21) in the storage module (2), and the number of transmitting terminal equipment provided with the data content authority in the modification folder is less than that of transmitting terminal equipment provided with the data content transmission authority;
the camera module (4) is provided with the submodule in the lower level, includes:
the cloud database (41) is used for storing the image data of the construction scene recorded by the operation of the camera module (4);
a marking unit (42) for marking the image data as an image data file name;
wherein the marking unit (42) is used for marking the image data file marking logic according to the occurrence time and the position of the image data;
the as built building acceptance plan design content includes: completion building acceptance project and completion building acceptance time, a sampling module (6) operates to extract acceptance targets for the installation positions of the camera modules (4) corresponding to image data in the cloud database (41) and corresponding to newly built data folders of the editing unit (21);
the system end user uploads the acceptance result through the uploading module (7), and the camera module (4) is in a starting state before uploading the acceptance result after the operation of the sampling module (6) is finished;
the qualification rate of the completion building is calculated by the evaluation module (8) according to the following formula:
wherein: n is the number of the items and is the number of the items,for the predicted value, the predicted value is manually input by the user at the system end>Is a true value;
the control platform (1) is electrically connected with the storage module (2) through a medium, the storage module (2) is electrically connected with the editing unit (21) and the memory unit (22) through the medium, the editing unit (21) and the memory unit (22) are both electrically connected with the cloning unit (23) through the medium, the storage module (2) is electrically connected with the modification module (3), the design module (5), the sampling module (6) and the uploading module (7) through the medium, the sampling module (6) is electrically connected with the uploading module (7) through the medium, the camera module (4) is electrically connected with the control platform (1) through the medium, the camera module (4) is electrically connected with the cloud database (41) and the marking unit (42) through the medium, and the uploading module (7) is electrically connected with the evaluation module (8) through the medium.
The real estate construction work management and control system is used for providing real estate construction work management and control for real estate developers, and comprises the following steps:
step1: dividing construction areas according to construction areas of a construction target building, deploying monitoring equipment to each construction area in the construction target building, setting a virtual storage cloud disk on an image data line, and uploading recorded image data of the monitoring equipment;
step2: creating a magnetic disk on a computer and configuring a data transmission channel to provide a construction target building construction site management end user to send an engineering progress message, setting a progress message feedback period, and sending the engineering progress message by the management end user according to the feedback period, wherein the engineering progress message content comprises corresponding engineering constructor identity information;
step3: reading engineering progress information on a computer, judging a construction state of a construction target building, and designing a completion acceptance scheme synchronously according to a construction project when the construction target building is completed as a judgment result;
step4: uploading data content of a checking result of a checking scheme, calling an engineering progress message in a computer for construction projects with unqualified checking results, and synchronously downloading construction project corresponding construction sheet area image data in a virtual storage cloud disk on an image data line;
step5: setting an engineering acceptance threshold value, and calculating the acceptance rate of the finished building according to the data content of the acceptance result of the acceptance scheme;
step6: and comparing the finished building qualification rate with a set engineering acceptance threshold value, and judging whether the finished building qualification rate is within the engineering acceptance threshold value range.
CN202211071714.2A 2022-09-02 2022-09-02 Real estate construction quality control method and system Active CN115147021B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202211071714.2A CN115147021B (en) 2022-09-02 2022-09-02 Real estate construction quality control method and system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202211071714.2A CN115147021B (en) 2022-09-02 2022-09-02 Real estate construction quality control method and system

Publications (2)

Publication Number Publication Date
CN115147021A CN115147021A (en) 2022-10-04
CN115147021B true CN115147021B (en) 2024-03-19

Family

ID=83415367

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202211071714.2A Active CN115147021B (en) 2022-09-02 2022-09-02 Real estate construction quality control method and system

Country Status (1)

Country Link
CN (1) CN115147021B (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115474027A (en) * 2022-11-14 2022-12-13 深圳市睿拓新科技有限公司 Method and device for processing project progress state data
CN116192947B (en) * 2023-04-25 2023-07-11 单县不动产登记中心 Real estate data safety storage management system
CN116592950B (en) * 2023-07-14 2023-11-28 南通祥峰电子有限公司 Electrical component design sample system based on intelligent model

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20020041390A (en) * 2002-05-15 2002-06-01 주식회사 인터빌드노아 Method for construction project management using internet and system therefor
JP2003150671A (en) * 2001-11-16 2003-05-23 Itochu Corp Construction acceptance inspection system and construction acceptance inspection method
JP2004280545A (en) * 2003-03-17 2004-10-07 Tsubasa System Co Ltd Method for confirming quality of dwelling house
CN106056347A (en) * 2016-05-16 2016-10-26 北京诺士诚国际工程项目管理有限公司 Engineering project management cloud platform system based on video monitoring
CN107423895A (en) * 2017-07-20 2017-12-01 浙江之江工程项目管理有限公司 A kind of quality control system of house fine fitment
CN111598379A (en) * 2020-03-31 2020-08-28 中铁建华南建设有限公司 Project management method, platform, device, computer equipment and storage medium
JP2020155127A (en) * 2019-03-18 2020-09-24 フリーダムアーキテクツデザイン株式会社 Real estate server and real estate search system
WO2022094934A1 (en) * 2020-11-06 2022-05-12 深圳市深能环保东部有限公司 Site location-based system and method for management of engineering quality acceptance
KR20220074309A (en) * 2020-11-27 2022-06-03 조원석 Real estate development consulting system
CN114662919A (en) * 2022-03-23 2022-06-24 张俊 Building engineering quality control system based on BIM

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003150671A (en) * 2001-11-16 2003-05-23 Itochu Corp Construction acceptance inspection system and construction acceptance inspection method
KR20020041390A (en) * 2002-05-15 2002-06-01 주식회사 인터빌드노아 Method for construction project management using internet and system therefor
JP2004280545A (en) * 2003-03-17 2004-10-07 Tsubasa System Co Ltd Method for confirming quality of dwelling house
CN106056347A (en) * 2016-05-16 2016-10-26 北京诺士诚国际工程项目管理有限公司 Engineering project management cloud platform system based on video monitoring
CN107423895A (en) * 2017-07-20 2017-12-01 浙江之江工程项目管理有限公司 A kind of quality control system of house fine fitment
JP2020155127A (en) * 2019-03-18 2020-09-24 フリーダムアーキテクツデザイン株式会社 Real estate server and real estate search system
CN111598379A (en) * 2020-03-31 2020-08-28 中铁建华南建设有限公司 Project management method, platform, device, computer equipment and storage medium
WO2022094934A1 (en) * 2020-11-06 2022-05-12 深圳市深能环保东部有限公司 Site location-based system and method for management of engineering quality acceptance
KR20220074309A (en) * 2020-11-27 2022-06-03 조원석 Real estate development consulting system
CN114662919A (en) * 2022-03-23 2022-06-24 张俊 Building engineering quality control system based on BIM

Also Published As

Publication number Publication date
CN115147021A (en) 2022-10-04

Similar Documents

Publication Publication Date Title
CN115147021B (en) Real estate construction quality control method and system
US20190333169A1 (en) Blockchain enabled quality control in construction projects
US10216840B2 (en) Asset tag template creation from readable elements
CN110969719A (en) Automatic inspection method, system, terminal equipment and storage medium
CN108023955B (en) Processing method and device for three-dimensional animation production process
CN113485881B (en) Test method and device of temporary speed limiting server, electronic equipment and medium
CN113360144B (en) Auxiliary processing method, device, storage medium and program product for software development
CN108848337A (en) Long-range auditing method, device, terminal and the computer storage medium of line project
US11593538B2 (en) Verification, modification, and/or validation of an infrastructure design document via improved collaboration between on site devices and remote devices
CN104090948A (en) Method, device and system for processing mass data of nuclear power station
CN110866738A (en) BIM technology-based construction site progress analysis method and system
KR102307874B1 (en) Facility maintenance and management system
CN113094251A (en) Embedded system testing method and device, computer equipment and storage medium
CN113626170B (en) Control method and device for full life cycle of communication engineering task
CN102270126B (en) Method and equipment for quickly determining interface code and test script parameter value
CN111124321B (en) Debugging method and system of laser printer
CN112163832A (en) Online security quality management method and device, mobile terminal and storage medium
CN111105499B (en) System and method for recording building status
CN207867479U (en) A kind of man-machine interactive system based on NFC
CN108628979A (en) Power cut record dissemination method, system, computer equipment and storage medium
US20230186775A1 (en) Structural inspection using feedback from artificial intelligence services
Mokhlis et al. Implementation Challenges in Automation of Gas Lift Optimization Workflow: A Case Study for Digital Fields Journey
CN115061999B (en) Data center data management method and system based on artificial intelligence
Miyazaki et al. Construction of a Skill Evaluation System Based on database‐driven Approach for a Hydraulic Excavator
CN117648198B (en) Application adaptation method, device, equipment and storage medium

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant