CN114876236A CN202210674552.5A CN202210674552A CN114876236A CN 114876236 A CN114876236 A CN 114876236A CN 202210674552 A CN202210674552 A CN 202210674552A CN 114876236 A CN114876236 A CN 114876236A
Authority
CN
China
Prior art keywords
lifting platform
paint
repair
ancestral
ancient
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202210674552.5A
Other languages
Chinese (zh)
Inventor
房晓峰
曾超
刘欣妍
龚艳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangzhou Garden Construction Co ltd
Original Assignee
Guangzhou Garden Construction Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangzhou Garden Construction Co ltd filed Critical Guangzhou Garden Construction Co ltd
Priority to CN202210674552.5A priority Critical patent/CN114876236A/en
Publication of CN114876236A publication Critical patent/CN114876236A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/24Safety or protective measures preventing damage to building parts or finishing work during construction
    • E04G21/246Safety or protective measures preventing damage to building parts or finishing work during construction specially adapted for curing concrete in situ, e.g. by covering it with protective sheets
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F21/00Implements for finishing work on buildings
    • E04F21/02Implements for finishing work on buildings for applying plasticised masses to surfaces, e.g. plastering walls
    • E04F21/06Implements for applying plaster, insulating material, or the like
    • E04F21/08Mechanical implements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G1/00Scaffolds primarily resting on the ground
    • E04G1/18Scaffolds primarily resting on the ground adjustable in height
    • E04G1/22Scaffolds having a platform on an extensible substructure, e.g. of telescopic type or with lazy-tongs mechanism
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G1/00Scaffolds primarily resting on the ground
    • E04G1/24Scaffolds primarily resting on the ground comprising essentially special base constructions; comprising essentially special ground-engaging parts, e.g. inclined struts, wheels
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G23/00Working measures on existing buildings
    • E04G23/02Repairing, e.g. filling cracks; Restoring; Altering; Enlarging
    • E04G23/0218Increasing or restoring the load-bearing capacity of building construction elements
    • E04G23/0225Increasing or restoring the load-bearing capacity of building construction elements of circular building elements, e.g. by circular bracing
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G23/00Working measures on existing buildings
    • E04G23/02Repairing, e.g. filling cracks; Restoring; Altering; Enlarging
    • E04G23/0296Repairing or restoring facades
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G5/00Component parts or accessories for scaffolds
    • E04G5/14Railings
    • E04G5/141Railings with an access door or the like therefor
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G1/00Scaffolds primarily resting on the ground
    • E04G1/24Scaffolds primarily resting on the ground comprising essentially special base constructions; comprising essentially special ground-engaging parts, e.g. inclined struts, wheels
    • E04G2001/242Scaffolds movable on wheels or tracks
    • E04G2001/244Scaffolds movable on wheels or tracks mechanically operated
    • E04G2001/246Scaffolds movable on wheels or tracks mechanically operated human powered
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G23/00Working measures on existing buildings
    • E04G23/02Repairing, e.g. filling cracks; Restoring; Altering; Enlarging
    • E04G23/0218Increasing or restoring the load-bearing capacity of building construction elements
    • E04G2023/0248Increasing or restoring the load-bearing capacity of building construction elements of elements made of wood

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Chemical & Material Sciences (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • Electrochemistry (AREA)
  • Working Measures On Existing Buildindgs (AREA)

Abstract

The application relates to a construction method for repairing ancient ruins in an ancestral hall, which relates to the field of house repair and aims to solve the problems that the existing workers repair wooden pillars and the paint spraying efficiency are low, and the construction method comprises the following steps: the method comprises the following steps: the movable base is driven to move, the lifting platform is driven to move to a position close to the wood column, and then the position of the movable base is fixed; step two: driving the lifting platform to further move towards one side close to the wooden column so that the lifting platform forms a semi-surrounding state on the wooden column; step three: placing tools required for repair and paint spraying on the lifting platform, and simultaneously placing a paint bucket on the lifting platform; step four: repairing personnel enter the lifting platform, the height position of the lifting platform is manually controlled, and the lifting platform stirs the paint in the paint bucket in the lifting process; step five: the drilling machine or the paint spray gun is manually arranged on the lifting platform to repair and paint the wooden column. The application has the effect of improving the repairing and paint spraying efficiency of the wood columns.

Description

Ancient writing repair construction method for temple hall
Technical Field
The application relates to the field of house repair, in particular to a construction method for repairing ancient ruins in a temple hall.
Background
The temple is commonly used in ancestors of sacrifice, and wood members such as wood columns, beams, purlins, rafters and the like form a skeleton of the temple and bear vertical, horizontal and earthquake loads. Since the ancient temple has been repaired for a long time, under the circumstances of old age, poor protection, exposure to sunlight, rain, weathering, damage, worm-eating, bacterial decay and the like, the ancient temple must be repaired.
After the existing building house repairs the wood columns, a herringbone ladder is generally needed to be erected, repair personnel carry tools for repair to climb to a certain height, then the wood columns are drilled through a drilling machine, then reinforcing devices are installed on the wood columns, the bearing capacity of the wood columns is enhanced, after the wood columns are repaired, the surfaces of the wood columns are sprayed with paint through a paint spray gun, and the attractiveness of the wood columns is improved.
In view of the above-mentioned related art, the inventors found that the following drawbacks exist: the wooden column usually has certain height, and when repairing the wooden column, the repairment personnel need carry the instrument and climb to the eminence, repairs the wooden column, need the instrument of change to climb to the eminence again after repairing, sprays paint to the wooden column, and operating procedure is complicated, reduces the repair and the paint spraying efficiency of wooden column.
Disclosure of Invention
In order to improve the repairing and paint spraying efficiency of wood columns, the application provides a repairing construction method for ancient classic of temple.
The application provides an ancestral ancient painting repair construction method which adopts the following technical scheme:
a construction method for repairing ancient ruins of an ancestral hall comprises the following steps:
the method comprises the following steps: the movable base is driven to move, the lifting platform is driven to move to a position close to the wood column, and then the position of the movable base is fixed;
step two: driving the lifting platform to further move towards one side close to the wooden column so that the lifting platform forms a semi-surrounding state on the wooden column;
step three: placing tools required for repair and paint spraying on the lifting platform, and simultaneously placing a paint bucket on the lifting platform;
step four: repairing personnel enter the lifting platform, the height position of the lifting platform is manually controlled, and the lifting platform stirs the paint in the paint bucket in the lifting process;
step five: the drilling machine or the paint spray gun is manually arranged on the lifting platform to repair and paint the wooden column.
Optionally, a first driving part for driving the mounting plate to move in the horizontal direction and a mounting plate are arranged on the moving base in the first step, the lifting platform is arranged on the mounting plate, and a height adjusting assembly for driving the lifting platform to move in the vertical direction is arranged on the mounting plate.
Through adopting above-mentioned technical scheme, when moving the base and removing suitable position, remove through first driving piece drive mounting panel, further be close to the post, height adjusting part drive lift platform removes in the vertical direction to the workman of being convenient for repairs and sprays paint the post.
Optionally, an opening for the timber column to be embedded is formed in one side of the lifting platform, a mounting frame for the drilling machine and the spray gun to be detachably mounted is arranged on the lifting platform, the mounting frame is arranged at the opening, and the periphery of the timber column is sleeved with the mounting frame movably.
Through adopting above-mentioned technical scheme, the mounting panel drives lift platform and is removing the back, makes the stake get into the opening part on the lift platform, and lift platform plays the state of semi-encirclement to the stake to the week side to the stake that the workman can be better is handled, and drilling machine and spray gun when using, make the mounting bracket cover locate the week side of stake earlier, install drilling machine and spray gun on the mounting bracket again, reduce the time of workman's handheld operation, thereby practice thrift the manpower.
Optionally, be provided with the centre gripping subassembly on the mounting bracket, the centre gripping subassembly includes sliding block, two sets of grip blocks and screw rod, set up the spout with the sliding adaptation of sliding block along length direction on the mounting bracket, screw rod threaded connection is on the sliding block, the axis direction of screw rod is on a parallel with the upper surface of sliding block, the grip block sets up in two sets of the one end that the screw rod is close to each other.
Through adopting above-mentioned technical scheme, rotate the screw rod and can remove on realizing the sliding block to two sets of grip blocks of drive are close to each other and carry out the centre gripping to drilling machine or spray gun, when ordering about the sliding block and remove in the spout on the mounting bracket, can adjust the position angle of drilling machine or spray gun, thereby can be convenient for drill and spray paint to the position of difference on the post, and along with lift platform's lift, can drill and spray paint to the height of difference on the post.
Optionally, the height adjusting assembly comprises a telescopic frame and a second driving piece used for driving the telescopic frame to stretch, the bottom end of the telescopic frame is arranged on the mounting plate, the top end of the telescopic frame is arranged on the lifting platform, the telescopic frame comprises a plurality of groups of connecting units connected end to end in the vertical direction, each connecting unit comprises two groups of connecting rods which are arranged in a crossed mode, and the two groups of connecting rods are connected in a rotating mode.
Through adopting above-mentioned technical scheme, the linkage unit comprises two sets of alternately arranged's connecting rod, constitutes the expansion bracket by multiunit linkage unit again for the connecting rod can make the whole extension of expansion bracket or shorten when rotating, thereby is convenient for adjust lift platform's height, and lift platform is more stable when rising or descending, so that when the workman is on lift platform, can operate the position of co-altitude not on the stake.
Optionally, the second driving piece includes sliding sleeve, two-way threaded rod and rotating electrical machines, the sliding sleeve set up in the tip of connecting rod, all set up on mounting panel and the lift platform with the spacing groove of sliding sleeve slip adaptation, the rotating electrical machines level sets up on the mounting panel, two-way threaded rod is coaxial to be set up on the output shaft of rotating electrical machines, and is two sets of sliding sleeve is threaded connection both ends on two-way threaded rod respectively.
Through adopting above-mentioned technical scheme, the two-way threaded rod of rotating electrical machines drive rotates to can drive two sets of sliding sleeves on the two-way threaded rod and be close to each other or keep away from each other, and then drive the connecting rod and take place to rotate, realize elevating platform's rising and reduction, need not manual operation, and elevating platform is more stable in the motion process, and the workman of being convenient for operates on elevating platform.
Optionally, a placing groove for placing a paint bucket is formed in the lifting platform, a placing plate is connected to the bottom end of the placing groove in a rotating mode, a stirring piece inserted into the paint bucket is detachably connected to the placing groove, and a driving connecting assembly used for driving the placing plate to rotate is arranged on the mounting plate.
Through adopting above-mentioned technical scheme, spray paint to the post for the realization, place the paint kettle on placing the board, the standing groove makes the paint kettle place more stably, installs the stirring piece on the standing groove back, can make the stirring piece insert the inside of paint kettle, the board rotation is placed in the rethread drive coupling assembling drive, and then drives the paint kettle and rotate, makes the stirring piece that inserts the inside of paint kettle can stir paint, avoids paint to take place to solidify after one section, influences its spraying effect.
Optionally, the drive coupling assembling includes telescopic link and belt, the coaxial fixed connection of one end of telescopic link in place on the board, the other end fixed connection of telescopic link in on the mounting panel, the belt cover locate the telescopic link with between the two-way threaded rod.
Through adopting above-mentioned technical scheme, when the two-way threaded rod of rotating electrical machines drive rotated, drive lift platform moved in vertical direction, drove belt and telescopic link simultaneously and rotate, and the telescopic link rotates and places board and paint kettle rotation in order to drive, need not to set up additionally and is used for driving telescopic link pivoted power unit, practices thrift the manufacturing cost of this equipment.
Equal coaxial cover is equipped with the position sleeve on telescopic link and the two-way threaded rod, the confession has been seted up to the periphery wall of position sleeve the belt inlays the constant head tank of establishing.
Through adopting above-mentioned technical scheme, the belt cover is located on the locating sleeve on telescopic link and the two-way threaded rod and is sheathe in, realizes that drive telescopic link and two-way threaded rod rotate in step, and in the constant head tank on the belt embedding locating sleeve, makes setting up of belt more stable, and the result of use is better.
Optionally, guardrails are arranged on the periphery of the lifting platform, a channel is arranged on one side of each guardrail, and a baffle is arranged at the position of each channel.
Through adopting above-mentioned technical scheme, the guardrail encloses the fender to the week side of lift platform, and operating personnel gets into lift platform from the passageway on to close the passageway through the baffle, it is safer when making the staff operate on lift platform.
In summary, the present application includes at least the following advantageous technical effects:
when the moving base is moved to a proper position during repairing the wood column, the mounting plate is driven to move through the first driving piece and further approach the wood column, the lifting platform is driven to move in the vertical direction by the height adjusting assembly, and tools for repairing and painting are carried by an operator to be synchronously lifted or lowered along with the lifting platform, so that the operator can repair and paint the wood column on the lifting platform conveniently, and the repairing and painting efficiency of the wood column is improved;
by arranging the mounting frame, the screw rod can move on the sliding block by rotating, so that two groups of clamping plates are driven to approach each other to clamp the drilling machine or the spray gun, the sliding block is arranged in the sliding groove on the mounting frame in a sliding manner, the drilling machine and the spray gun are mounted on the mounting frame, the time of hand-held operation of workers is reduced, and when the sliding block is driven to move in the sliding groove on the mounting frame, the position angle of the drilling machine or the spray gun can be adjusted, so that different positions on a wood column can be conveniently drilled and painted, and the operation of the workers is more convenient;
paint kettle places on placing the board, will stir the piece and install the back on the standing groove, can make the stirring piece insert paint kettle's inside, and lift platform places the board rotation at the in-process rethread drive coupling assembling drive that reciprocates, and then drives paint kettle and rotates, makes the stirring piece that inserts paint kettle inside can stir paint, avoids paint to take place to solidify after one section, influences its spraying effect.
Drawings
FIG. 1 is a schematic view of an overall structure at a first viewing angle according to an embodiment of the present application;
FIG. 2 is an enlarged view of portion A of FIG. 1;
fig. 3 is a schematic diagram of an overall structure at a second viewing angle in the embodiment of the present application.
Reference numerals: 1. moving the base; 11. mounting a plate; 111. a limiting groove; 12. a first driving member; 2. a lifting platform; 21. an opening; 22. a mounting frame; 221. a chute; 23. a placement groove; 24. placing the plate; 25. a stirring member; 26. a guardrail; 27. a baffle plate; 3. a height adjustment assembly; 31. a telescopic frame; 311. a connection unit; 3111. a connecting rod; 32. a second driving member; 321. a sliding sleeve; 322. a bidirectional threaded rod; 323. a rotating electric machine; 4. a clamping assembly; 41. a slider; 42. a clamping plate; 43. a screw; 5. a drive connection assembly; 51. a telescopic rod; 52. a belt; 53. a positioning sleeve; 531. and (6) positioning a groove.
Detailed Description
The present application is described in further detail below with reference to figures 1-3.
The embodiment of the application discloses an ancestral hall ancient painting repair construction method.
Referring to fig. 1, a construction method for repairing ancient temple comprises the following steps:
the method comprises the following steps: the movable base 1 is driven to move, the lifting platform 2 is driven to move to a position close to the wooden pillar, and then the position of the movable base 1 is fixed;
step two: driving the lifting platform 2 to further move towards one side close to the wooden column, so that the lifting platform 2 forms a semi-surrounding state on the wooden column;
step three: tools needed for repairing and painting are placed on the lifting platform 2, and meanwhile, a paint bucket is also placed on the lifting platform 2;
step four: repairing personnel enter the lifting platform 2, the height position of the lifting platform 2 is manually controlled, and the lifting platform 2 stirs the paint in the paint bucket in the lifting process;
step five: the wood columns are repaired and painted by manually installing a drilling machine or a paint spray gun on the lifting platform 2.
Referring to fig. 1, in order to fix the position of the mobile base 1 after moving, brake wheels are fixedly mounted at four corners of the bottom end of the mobile base 1, and when the mobile base 1 moves to a position close to a timber pile, the position of the mobile base 1 is fixed through the brake wheels;
in order to further facilitate the operation of a worker on a wood column, the moving base 1 is connected with a mounting plate 11 and a first driving part 12 for driving the mounting plate 11 to slide in the horizontal direction in a sliding manner, the first driving part 12 is an air cylinder in the embodiment, one end of the mounting plate 11 is fixedly connected with a piston rod of the air cylinder, the lifting platform 2 is movably arranged on the mounting plate 11 in the vertical direction, one side of the lifting platform 2 is provided with an opening 21, the air cylinder pushes the mounting plate 11 to move so as to drive the lifting platform 2 to further approach the wood column, the wood column is embedded in the opening 21 of the lifting platform 2, the lifting platform 2 plays a half-surrounding state on the wood column, a height adjusting component 3 is arranged between the mounting plate 11 and the lifting platform 2, the lifting platform 2 is driven to move in the vertical direction through the height adjusting component 3, and thus an operator and a construction tool are lifted;
in order to improve the safety of the operating worker on the lifting platform 2, the side of the lifting platform 2 is fixedly provided with a guardrail 26, one side of the guardrail 26 is provided with a channel, and a baffle plate 27 is rotatably connected to the channel, so that the operating worker can conveniently move onto the lifting platform 2 from the channel.
Referring to fig. 1 and 3, in order to make the lifting platform 2 move stably in the vertical direction, the height adjusting assembly 3 includes an expansion bracket 31 and a second driving member 32, the bottom end of the expansion bracket 31 is disposed on the mounting plate 11, the lifting platform 2 is disposed at the top end of the expansion bracket 31, the expansion bracket 31 is driven to expand and contract by the second driving member 32 so as to make the lifting platform 2 lift, in this embodiment, the expansion bracket 31 includes a plurality of groups of connecting units 311 connected end to end in the vertical direction, the connecting units 311 are composed of two groups of connecting rods 3111 crossed at the middle parts, the crossing positions of the two groups of connecting rods 3111 are mutually rotatably connected, and the whole extension or shortening of the expansion bracket 31 is realized by the rotation of the connecting rods 3111;
in order to drive the connecting rod 3111 to rotate, the second driving member 32 includes a sliding sleeve 321, a bidirectional threaded rod 322 and a rotating motor 323, the sliding sleeve 321 is provided with four sets, which are respectively rotatably connected to the end of the topmost connecting rod 3111 and the end of the lowest connecting rod 3111, the mounting plate 11 and the lifting platform 2 are both provided with a limiting groove 111 adapted to the sliding sleeve 321 in a sliding manner, the rotating motor 323 is horizontally and fixedly mounted on the mounting plate 11, the opening and closing of the rotating motor 323 are controlled by remote control, the output axial direction of the rotating motor 323 is the same as the sliding direction of the sliding sleeve 321, the bidirectional threaded rod 322 is coaxially connected to the output shaft of the rotating motor 323, the bidirectional threaded rod 322 penetrates through the two sets of sliding sleeves 321 slidably connected to the mounting plate 11 and is in threaded connection with the two sets of sliding sleeves 321 on the mounting plate 11, the rotating motor 323 drives the bidirectional threaded rod 322 to rotate so as to enable the two sets of sliding sleeves 321 to be close to each other or far away from each other at the same time, the driving link 3111 is rotated to raise or lower the lifting platform 2.
Referring to fig. 2, in order to facilitate an operator to use tools such as a drilling machine and a spray gun on the lifting platform 2, a mounting frame 22 for detachably mounting the drilling machine and the spray gun is disposed on the lifting platform 2, the mounting frame 22 is slidably disposed on a guardrail 26 at an opening 21, the mounting frame 22 is movably sleeved on the periphery of a wooden column, both sides of the mounting frame 22 are in threaded connection with a jackscrew, when the mounting frame 22 is in a proper position during sliding, the jackscrew is abutted against the guardrail 26 by rotating the jackscrew, so that the mounting frame 22 is fixed in position, a clamping assembly 4 is disposed on the mounting frame 22, the clamping assembly 4 comprises a sliding block 41, two groups of clamping plates 42 and a screw 43, a projection of the mounting frame 22 in the vertical direction is in a U shape, a sliding chute 221 which is in sliding fit with the sliding block 41 is disposed on the mounting frame 22 along the length direction, the screw 43 is in threaded connection with the sliding block 41, and the axial direction of the screw 43 is parallel to the upper surface of the sliding block 41, the clamping plates 42 are rotatably connected to one ends, close to each other, of the two sets of screw rods 43, the sliding blocks 41 can move through rotation of the screw rods 43, the two sets of clamping plates 42 are made to be close to each other to clamp the drilling machine or the spray gun, and when the sliding blocks 41 are driven to move in the sliding grooves 221 in the mounting frame 22, the position angles of the drilling machine or the spray gun can be adjusted, so that drilling and painting can be conducted on different positions on a wood column conveniently.
Referring to fig. 1, in order to facilitate paint spraying on a wooden pillar, a placing groove 23 for placing a paint bucket is fixedly connected to one side of a lifting platform 2, a placing plate 24 is rotatably connected to the bottom end of the placing groove 23, a rotating axis of the placing plate 24 is vertically arranged, a stirring part 25 inserted into the paint bucket is detachably connected to the placing groove 23, the stirring part 25 comprises an insertion rod and a stirring rod, the placing groove 23 is provided with an insertion hole in insertion fit with the insertion rod, the insertion rod is inserted into the insertion hole to enable the stirring rod to be inserted into the paint bucket, a driving connection assembly 5 for driving the placing plate 24 to rotate is arranged on a mounting plate 11, the driving connection assembly 5 comprises a telescopic rod 51, a belt 52 and two groups of positioning sleeves 53, one end of the telescopic rod 51 is coaxially and fixedly connected to the bottom end of the placing plate 24, the other end of the telescopic rod 51 is rotatably connected to the mounting plate 11, and the two groups of positioning sleeves 53 are respectively sleeved on the telescopic rod 51 and a bidirectional threaded rod 322, locating sleeve 53's periphery wall is seted up and is supplied belt 52 to inlay constant head tank 531 of establishing, belt 52 cover is located on two sets of constant head tanks 531, when rotating electrical machines 323 drive two-way threaded rod 322 rotates, drive lift platform 2 moves in vertical direction, drive belt 52 and telescopic link 51 simultaneously and rotate, telescopic link 51 rotates and places board 24 and paint kettle rotation in order to drive, insert the inside stirring piece 25 of paint kettle and can stir paint, avoid paint to take place after one section and solidify.
The above embodiments are preferred embodiments of the present application, and the protection scope of the present application is not limited by the above embodiments, so: all equivalent changes made according to the structure, shape and principle of the present application shall be covered by the protection scope of the present application.

Claims (10)

1. A construction method for repairing ancient ruins of temple is characterized by comprising the following steps: the method comprises the following steps:
the method comprises the following steps: the movable base (1) is driven to move, the lifting platform (2) is driven to move to a position close to the wood column, and then the position of the movable base (1) is fixed;
step two: the lifting platform (2) is driven to further move towards one side close to the wooden column, so that the lifting platform (2) forms a semi-surrounding state on the wooden column;
step three: tools needed for repairing and paint spraying are placed on the lifting platform (2), and meanwhile, a paint bucket is also placed on the lifting platform (2);
step four: repairing personnel enter the lifting platform (2), the height position of the lifting platform (2) is manually controlled, and the lifting platform (2) stirs the paint in the paint bucket in the lifting process;
step five: a drilling machine or a paint spray gun is manually arranged on the lifting platform (2) to repair and paint the wood columns.
2. The method of constructing ancestral ancient repair of ancestral hall according to claim 1, wherein: move in step one and be provided with mounting panel (11) and drive mounting panel (11) on base (1) and move first driving piece (12) on the horizontal direction, lift platform (2) set up on mounting panel (11), be provided with on mounting panel (11) and be used for driving height control assembly (3) that lift platform (2) moved in vertical direction.
3. The method of ancestral ancient repair construction of claim 2, wherein: opening (21) that confession post inlayed and establish are seted up to one side of lift platform (2), be provided with on lift platform (2) and supply drilling machine and spray gun demountable installation's mounting bracket (22), mounting bracket (22) set up in opening (21) department, just the week side of post is located to mounting bracket (22) movable sleeve.
4. The method of ancestral ancient repair of claim 3, wherein: be provided with centre gripping subassembly (4) on mounting bracket (22), centre gripping subassembly (4) include sliding block (41), two sets of grip block (42) and screw rod (43), offer spout (221) with sliding block (41) slip adaptation along length direction on mounting bracket (22), screw rod (43) threaded connection is on sliding block (41), the axis direction of screw rod (43) is on a parallel with the upper surface of sliding block (41), grip block (42) set up in two sets of the one end that screw rod (43) are close to each other.
5. The method of repairing ancient classic in temple, according to claim 2, wherein: altitude mixture control subassembly (3) include expansion bracket (31) and be used for driving second driving piece (32) that expansion bracket (31) are flexible, the bottom of expansion bracket (31) set up in on mounting panel (11), the top of expansion bracket (31) set up in on lift platform (2), expansion bracket (31) include multiunit end to end connection's linkage unit (311) in vertical direction, linkage unit (311) comprise two sets of alternately arranged connecting rod (3111), and the rotation is connected between two sets of connecting rod (3111).
6. The method of constructing ancestral ancient repair of ancestral hall according to claim 5, wherein: second driving piece (32) include sliding sleeve (321), two-way threaded rod (322) and rotating electrical machines (323), sliding sleeve (321) set up in the tip of connecting rod (3111), all set up spacing groove (111) with sliding sleeve (321) slip adaptation on mounting panel (11) and lift platform (2), rotating electrical machines (323) level sets up on mounting panel (11), two-way threaded rod (322) coaxial setting is on the output shaft of rotating electrical machines (323), and is two sets of sliding sleeve (321) is both ends on two-way threaded rod (322) respectively threaded connection.
7. The method of constructing ancestral ancient repair of ancestral hall according to claim 6, wherein: be provided with standing groove (23) that are used for placing the paint kettle on lift platform (2), the bottom of standing groove (23) is rotated and is connected with and places board (24), can dismantle on standing groove (23) and be connected with stirring piece (25) that insert the inside paint kettle, be provided with on mounting panel (11) and be used for the drive to place board (24) pivoted drive coupling assembling (5).
8. The method of ancestral ancient repair of claim 7, wherein: drive coupling assembling (5) include telescopic link (51) and belt (52), the coaxial fixed connection in of one end of telescopic link (51) place on board (24), the other end of telescopic link (51) rotate connect in on mounting panel (11), telescopic link (51) and between two-way threaded rod (322) are located to belt (52) cover.
9. The method of ancestral ancient repair of claim 8, wherein: equal coaxial cover is equipped with position sleeve (53) on telescopic link (51) and two-way threaded rod (322), the confession has been seted up to the periphery wall of position sleeve (53) belt (52) inlays constant head tank (531) of establishing.
10. The method of ancestral ancient repair construction of claim 2, wherein: the periphery of the lifting platform (2) is provided with a guardrail (26), one side of the guardrail (26) is provided with a channel, and a baffle (27) is arranged at the channel.
CN202210674552.5A 2022-06-15 2022-06-15 Construction method for repairing ancient trails of temple hall Pending CN114876236A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210674552.5A CN114876236A (en) 2022-06-15 2022-06-15 Construction method for repairing ancient trails of temple hall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210674552.5A CN114876236A (en) 2022-06-15 2022-06-15 Construction method for repairing ancient trails of temple hall

Publications (1)

Publication Number Publication Date
CN114876236A true CN114876236A (en) 2022-08-09

Family

ID=82682488

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210674552.5A Pending CN114876236A (en) 2022-06-15 2022-06-15 Construction method for repairing ancient trails of temple hall

Country Status (1)

Country Link
CN (1) CN114876236A (en)

Citations (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107905508A (en) * 2017-11-20 2018-04-13 刘世荣 A kind of finishing paint spraying equipment
CN209452139U (en) * 2018-11-20 2019-10-01 苏州诚盟电子科技有限公司 A kind of spray equipment for water paint
WO2021004009A1 (en) * 2019-07-10 2021-01-14 上海建为历保科技股份有限公司 Scaffold used for restoration of large old structures
CN212428172U (en) * 2020-05-21 2021-01-29 深圳铭泰达建设有限公司 Energy-saving and environment-friendly brick wall repairing structure
CN112474130A (en) * 2020-12-09 2021-03-12 蒋先云 Paint spraying device for branched trees
CN113000259A (en) * 2021-04-29 2021-06-22 中国华能集团清洁能源技术研究院有限公司 Automatic painting device for wind power tower cylinder
CN213972685U (en) * 2020-12-02 2021-08-17 南京红复玻璃钢有限公司 Glass steel is from handing over post maintenance device
CN214272997U (en) * 2020-10-30 2021-09-24 刘秀娥 Cement that civil engineering construction was used sprays curing means
CN214330028U (en) * 2020-12-29 2021-10-01 深圳鹏润建设工程有限公司 Surface paint spraying equipment for repairing ancient architecture
CN215212229U (en) * 2021-03-23 2021-12-17 浙江可久建筑工程有限公司 House building construction platform
CN215317804U (en) * 2021-06-24 2021-12-28 南通江勤美金属制品有限公司 Efficient is grinding machanism for belted steel production
CN215907341U (en) * 2021-08-02 2022-02-25 昆明冶金高等专科学校 Interior decoration construction platform
CN114130561A (en) * 2021-10-11 2022-03-04 西安智能再制造研究院有限公司 Laser spraying composite fixture and laser spraying composite system
CN216025641U (en) * 2021-07-27 2022-03-15 彭泽县三峡水环境综合治理有限责任公司 Highway warning stake paint spraying apparatus for road environmental maintenance

Patent Citations (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107905508A (en) * 2017-11-20 2018-04-13 刘世荣 A kind of finishing paint spraying equipment
CN209452139U (en) * 2018-11-20 2019-10-01 苏州诚盟电子科技有限公司 A kind of spray equipment for water paint
WO2021004009A1 (en) * 2019-07-10 2021-01-14 上海建为历保科技股份有限公司 Scaffold used for restoration of large old structures
CN212428172U (en) * 2020-05-21 2021-01-29 深圳铭泰达建设有限公司 Energy-saving and environment-friendly brick wall repairing structure
CN214272997U (en) * 2020-10-30 2021-09-24 刘秀娥 Cement that civil engineering construction was used sprays curing means
CN213972685U (en) * 2020-12-02 2021-08-17 南京红复玻璃钢有限公司 Glass steel is from handing over post maintenance device
CN112474130A (en) * 2020-12-09 2021-03-12 蒋先云 Paint spraying device for branched trees
CN214330028U (en) * 2020-12-29 2021-10-01 深圳鹏润建设工程有限公司 Surface paint spraying equipment for repairing ancient architecture
CN215212229U (en) * 2021-03-23 2021-12-17 浙江可久建筑工程有限公司 House building construction platform
CN113000259A (en) * 2021-04-29 2021-06-22 中国华能集团清洁能源技术研究院有限公司 Automatic painting device for wind power tower cylinder
CN215317804U (en) * 2021-06-24 2021-12-28 南通江勤美金属制品有限公司 Efficient is grinding machanism for belted steel production
CN216025641U (en) * 2021-07-27 2022-03-15 彭泽县三峡水环境综合治理有限责任公司 Highway warning stake paint spraying apparatus for road environmental maintenance
CN215907341U (en) * 2021-08-02 2022-02-25 昆明冶金高等专科学校 Interior decoration construction platform
CN114130561A (en) * 2021-10-11 2022-03-04 西安智能再制造研究院有限公司 Laser spraying composite fixture and laser spraying composite system

Similar Documents

Publication Publication Date Title
CN109773242B (en) Be suitable for drilling equipment of accurate environmental protection of building multi-angle wall
CN109877977B (en) Drilling method for realizing accurate environment-friendly building multi-angle wall surface
CN109610844A (en) Ground concrete levelling machine
CN111287460B (en) Sectional type elevated column grouting device
CN114876236A (en) Construction method for repairing ancient trails of temple hall
CN111005383B (en) Subway steel pipe pile position correcting assembly
CN111319011A (en) Operation device for concrete structure bar planting and bar planting drilling method
CN112405891A (en) Adjustable multifunctional wall drilling device for building
CN209509528U (en) Ground concrete levelling machine
CN115095269B (en) Novel insulating operation platform
CN114961241B (en) Clear water concrete V-shaped column formwork support system and construction method thereof
CN212153377U (en) Adjustable pile cutting equipment
CN220058319U (en) Quick construction type site construction safety shed
CN115450440B (en) Concrete firewall construction device and working method thereof
CN219672034U (en) Scaffold with automatic discharging function for building construction
CN221321677U (en) Support for building engineering
CN212954222U (en) Building construction is with lift that has safety structure
CN219993049U (en) Construction platform for house building engineering construction
CN214942517U (en) Concrete pouring workbench for house construction
CN215167801U (en) Scaffold for industrial and civil buildings
CN215468288U (en) Rotatable electric punching tool
CN220566952U (en) Portable overhead operation auxiliary device
CN219158359U (en) Assembled building construction scaffold
CN218912813U (en) Bridge construction drilling platform
CN220006087U (en) Auxiliary device for reinforcing bar planting hole drilling of constructional column

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information
CB02 Change of applicant information

Address after: Units 301-303, Building (1) - (3), No. 8 Lujing Road, Yuexiu District, Guangzhou City, Guangdong Province, 510030

Applicant after: Guangzhou Landscape Construction Group Co.,Ltd.

Address before: 510000 No.1, Lingyuan West Road, Yuexiu District, Guangzhou City, Guangdong Province

Applicant before: Guangzhou Garden Construction Co.,Ltd.