CN114856259A - Shower room construction process - Google Patents

Shower room construction process Download PDF

Info

Publication number
CN114856259A
CN114856259A CN202210518649.7A CN202210518649A CN114856259A CN 114856259 A CN114856259 A CN 114856259A CN 202210518649 A CN202210518649 A CN 202210518649A CN 114856259 A CN114856259 A CN 114856259A
Authority
CN
China
Prior art keywords
wall surface
shower
ground
construction process
shower room
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202210518649.7A
Other languages
Chinese (zh)
Other versions
CN114856259B (en
Inventor
宣红卫
俞浩锋
徐小明
黄文兵
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hangzhou Lianggong Decoration Co ltd
Original Assignee
Hangzhou Lianggong Decoration Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hangzhou Lianggong Decoration Co ltd filed Critical Hangzhou Lianggong Decoration Co ltd
Priority to CN202210518649.7A priority Critical patent/CN114856259B/en
Publication of CN114856259A publication Critical patent/CN114856259A/en
Application granted granted Critical
Publication of CN114856259B publication Critical patent/CN114856259B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H1/00Buildings or groups of buildings for dwelling or office purposes; General layout, e.g. modular co-ordination or staggered storeys
    • E04H1/12Small buildings or other erections for limited occupation, erected in the open air or arranged in buildings, e.g. kiosks, waiting shelters for bus stops or for filling stations, roofs for railway platforms, watchmen's huts or dressing cubicles
    • E04H1/125Small buildings, arranged in other buildings
    • AHUMAN NECESSITIES
    • A47FURNITURE; DOMESTIC ARTICLES OR APPLIANCES; COFFEE MILLS; SPICE MILLS; SUCTION CLEANERS IN GENERAL
    • A47KSANITARY EQUIPMENT NOT OTHERWISE PROVIDED FOR; TOILET ACCESSORIES
    • A47K3/00Baths; Douches; Appurtenances therefor
    • A47K3/28Showers or bathing douches
    • A47K3/40Pans or trays
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C5/00Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
    • E04C5/07Reinforcing elements of material other than metal, e.g. of glass, of plastics, or not exclusively made of metal
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F13/00Coverings or linings, e.g. for walls or ceilings
    • E04F13/02Coverings or linings, e.g. for walls or ceilings of plastic materials hardening after applying, e.g. plaster
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F13/00Coverings or linings, e.g. for walls or ceilings
    • E04F13/07Coverings or linings, e.g. for walls or ceilings composed of covering or lining elements; Sub-structures therefor; Fastening means therefor
    • E04F13/08Coverings or linings, e.g. for walls or ceilings composed of covering or lining elements; Sub-structures therefor; Fastening means therefor composed of a plurality of similar covering or lining elements
    • E04F13/0875Coverings or linings, e.g. for walls or ceilings composed of covering or lining elements; Sub-structures therefor; Fastening means therefor composed of a plurality of similar covering or lining elements having a basic insulating layer and at least one covering layer
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F13/00Coverings or linings, e.g. for walls or ceilings
    • E04F13/07Coverings or linings, e.g. for walls or ceilings composed of covering or lining elements; Sub-structures therefor; Fastening means therefor
    • E04F13/08Coverings or linings, e.g. for walls or ceilings composed of covering or lining elements; Sub-structures therefor; Fastening means therefor composed of a plurality of similar covering or lining elements
    • E04F13/14Coverings or linings, e.g. for walls or ceilings composed of covering or lining elements; Sub-structures therefor; Fastening means therefor composed of a plurality of similar covering or lining elements stone or stone-like materials, e.g. ceramics concrete; of glass or with an outer layer of stone or stone-like materials or glass
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F15/00Flooring
    • E04F15/18Separately-laid insulating layers; Other additional insulating measures; Floating floors
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F15/00Flooring
    • E04F15/18Separately-laid insulating layers; Other additional insulating measures; Floating floors
    • E04F15/182Underlayers coated with adhesive or mortar to receive the flooring

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Health & Medical Sciences (AREA)
  • Public Health (AREA)
  • Chemical & Material Sciences (AREA)
  • Ceramic Engineering (AREA)
  • Epidemiology (AREA)
  • General Health & Medical Sciences (AREA)
  • Finishing Walls (AREA)

Abstract

The invention discloses a construction process of a shower room, which relates to the technical field of interior decoration and comprises the steps of installing support bars on the ground to form accommodating grooves by surrounding the ground, the wall surface and the support bars; the ground, the wall surface and the supporting strips are all subjected to waterproof treatment; mounting the shower base basin in the holding tank; sealing components are arranged at the joint of the shower bottom basin and the wall surface and the joint of the shower bottom basin and the supporting bar. Aiming at the technical problem of poor waterproof performance of the shower room, the invention has the technical effect that the shower room has good waterproof performance.

Description

Shower room construction process
Technical Field
The invention relates to the technical field of interior decoration, in particular to a construction process of a shower room.
Background
The shower room is a relatively independent bath space, is convenient for the dry-wet separation of a toilet, can be divided into a sliding door, a folding door, a vertical hinged door shower room and the like according to the door structure, and is widely applied to the toilet construction.
In the construction of a toilet, the requirement on water resistance is high, the wall surface and the ground are generally required to be coated with a plurality of waterproof layers, however, when the shower bottom basin is installed, the supporting bars of the shower bottom basin and the contact part of the shower bottom basin and the wall surface are easy to leak water, and therefore the shower room is poor in waterproof performance.
Disclosure of Invention
1. Technical problem to be solved by the invention
Aiming at the technical problem of poor waterproof performance of the shower room, the invention provides a construction process of the shower room, which enables the shower room to have good waterproof performance.
2. Technical scheme
In order to solve the problems, the technical scheme provided by the invention is as follows:
a construction process of a shower room comprises the following steps:
mounting support bars on the ground so that the ground, the wall surface and the support bars enclose to form an accommodating groove;
performing waterproof treatment on the ground, the wall surface and the supporting strips;
mounting a shower base basin within the receiving tank;
the shower end basin with the junction of wall, and, the shower end basin with the junction of support bar all installs seal assembly.
Optionally, the specific steps of installing the support bars on the ground are as follows:
snapping a line on the ground, and forming a groove;
presetting a plurality of steel I in the groove;
welding second steel materials on the tops of the first steel materials;
manufacturing a mould;
and (6) pouring and forming.
Optionally, one end of the supporting bar extends into the wall surface, and the extending range is 15-25 mm.
Optionally, after the casting molding, the supporting bar is chiseled.
Optionally, the distance between adjacent first steel materials is less than or equal to 300 mm.
Optionally, the width range of the supporting bars is 35-45mm, and the height range is 15-25 mm.
Optionally, the step of all doing water repellent to ground, wall and support bar includes:
coating and scraping the first-pass waterproof paint on the ground, the wall surface and the support bars;
and after the first-time waterproof coating is cured, coating and scraping the second-time waterproof coating on the ground, the wall surface and the support bars, wherein the coating and scraping direction of the second-time waterproof coating is perpendicular to that of the first-time waterproof coating.
Optionally, it is right all to do water repellent's step still includes ground, wall and support bar:
when the first-time waterproof coating is not cured, laying a first layer of glass fiber cloth on the first-time waterproof coating;
and when the waterproof coating for the second time is not cured, laying a second layer of glass fiber cloth on the waterproof coating for the second time.
Optionally, install the shower end basin back in the holding tank the tiling is gone up to wall and support bar, concrete step includes:
base layer treatment: the wall surface and the supporting strips are trimmed or roughened, and then are watered and moistened;
brushing the first adhesive: brushing a first adhesive on the wall surface and the support bars;
snapping line division: segmenting and dividing elastic lines according to the requirements of a drawing, and labeling alignment points on the wall surface and the supporting strips;
selecting bricks: rejecting unqualified bricks;
brick soaking: soaking the brick for 2-3 h;
tiling: brushing a second adhesive on the brick, and tiling the brick from bottom to top;
pointing and wiping;
wherein, shower end basin with the junction of the brick of wall, and, shower end basin with the junction of the brick of support bar all installs seal assembly.
Optionally, the first adhesive and the second adhesive are perpendicular to each other.
3. Advantageous effects
Compared with the prior art, the technical scheme provided by the invention has the following beneficial effects:
1. the specific method for performing the waterproof treatment on the ground, the wall surface and the supporting strips is to coat and scrape waterproof paint for multiple times, so that water splashed from the shower bottom basin is prevented from permeating into the ground, the wall surface and the supporting strips, water discharged from a water outlet of the shower bottom basin is prevented from permeating into the ground, and the waterproof performance is effectively improved; the sealing assembly can prevent water splashed from the shower bottom basin from permeating into the wall surface through the joint of the shower bottom basin and the wall surface, and can also prevent water splashed from the shower bottom basin from permeating into the accommodating groove through the joint of the shower bottom basin and the supporting bar, so that the waterproof performance is further improved; in conclusion, the shower room has good waterproof performance by performing waterproof treatment on the ground, the wall surface and the supporting bars and installing the sealing assembly at the joint for performing double waterproof;
2. the first steel is used for increasing the strength of the support bar 1, and the cross section of the first steel can be circular, so that the contact area between the first steel and the pouring material is increased conveniently, and the overall strength of the support bar is increased conveniently; the second steel is used for connecting the first steels, so that the connection firmness of the first steels is increased, and the first steels and the second steels are connected in a welding mode, so that the first steels and the second steels are good in connection performance and integrity;
3. when the waterproof coating is a resin waterproof coating, in order to strengthen the waterproofness, glass fiber cloth can be laid when the resin waterproof coating is not cured, wherein the specific times of the waterproof coating and the glass fiber cloth are not limited and can be determined according to the comprehensive consideration of cost, waterproof requirements and the like; when the waterproof coating is polyurethane waterproof coating, glass fiber cloth is not generally added, and the polyurethane waterproof coating can form an elastic protective film and has certain tensile resistance.
Drawings
FIG. 1 is a flow chart of a construction process of a shower room according to an embodiment of the invention;
FIG. 2 is a second schematic structural view of the shower room according to the embodiment of the present invention;
FIG. 3 is a second schematic structural view of the shower room according to the embodiment of the present invention;
in the figure: 1. a supporting strip; 2. a ground surface; 21. a groove; 3. a wall surface; 4. a seal assembly; 5. a shower bottom basin; 11. steel I; 12. and (5) steel II.
Detailed Description
For a further understanding of the present invention, reference will now be made in detail to the embodiments illustrated in the drawings.
The present application will be described in further detail with reference to the following drawings and examples. It is to be understood that the specific embodiments described herein are merely illustrative of the relevant invention and not restrictive of the invention. It should be noted that, for convenience of description, only the portions related to the present invention are shown in the drawings. The terms first, second, and the like in the present invention are provided for convenience of describing the technical solution of the present invention, and have no specific limiting effect, but are all generic terms, and do not limit the technical solution of the present invention. It should be noted that the embodiments and features of the embodiments in the present application may be combined with each other without conflict. In the description of the present invention, it should be noted that the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inner", "outer", etc., indicate orientations or positional relationships based on the orientations or positional relationships shown in the drawings, and are only for convenience of description and simplicity of description, but do not indicate or imply that the device or element being referred to must have a particular orientation, be constructed and operated in a particular orientation, and thus, should not be construed as limiting the present invention. Furthermore, the terms "first," "second," and "third" are used for descriptive purposes only and are not to be construed as indicating or implying relative importance. Unless expressly stated or limited otherwise, the terms "mounted," "connected," and "connected" are intended to be inclusive and mean, for example, that they may be fixedly connected, detachably connected, or integrally connected; can be mechanically or electrically connected; they may be connected directly or indirectly through intervening media, or they may be interconnected between two elements. The specific meanings of the above terms in the present invention can be understood in specific cases to those skilled in the art. The technical solutions in the same embodiment and the technical solutions in different embodiments can be arranged and combined to form a new technical solution without contradiction or conflict, and the technical solutions are within the scope of the present invention.
Example 1
With reference to fig. 1, this embodiment provides a construction process of a shower room, which includes:
the supporting strips 1 are arranged on the ground 2, so that the ground 2, the wall surface 3 and the supporting strips 1 form an accommodating groove in a surrounding mode;
the ground 2, the wall surface 3 and the supporting strips 1 are all subjected to waterproof treatment;
mounting the shower base tub 5 in the receiving tank;
seal assemblies 4 are mounted at the junction of the shower tray 5 and the wall surface 3, and at the junction of the shower tray 5 and the support bar 1.
Specifically, the supporting strips 1 are supported by the ground 2, are used for supporting the shower base basin 5, and are also used for retaining water, namely, preventing water in the accommodating tank from flowing to the outside and preventing water in the outside from flowing into the accommodating tank, and the accommodating tank formed by surrounding the ground 2, the wall surface 3 and the supporting strips 1 is used for accommodating the shower base basin 5, so that the stability of the shower base basin 5 is ensured, and when the shower base basin 5 is installed, the installation feet of the shower base basin 5 need to be in contact with the ground 2, so that the stability of the shower base basin 5 is further ensured; the specific method for performing the waterproof treatment on the ground 2, the wall surface 3 and the support bars 1 is to scrape waterproof paint for multiple times, so that water splashed from the shower bottom basin 5 is prevented from permeating into the ground 2, the wall surface 3 and the support bars 1, water discharged from a water outlet of the shower bottom basin 5 is prevented from permeating into the ground 2, and the waterproof performance is effectively improved; the sealing component 4 can prevent water splashed from the shower bottom basin 5 from permeating into the wall surface 3 through the joint of the shower bottom basin 5 and the wall surface 3 and can also prevent water splashed from the shower bottom basin 5 from permeating into the accommodating groove through the joint of the shower bottom basin 5 and the supporting bar 1, and the waterproof performance is further improved, wherein the sealing component 4 can be specifically a sealing strip, and the sealing strip can be made of modified PVC (polyvinyl chloride), thermoplastic ethylene propylene diene monomer rubber or vulcanized ethylene propylene diene monomer rubber and the like; in conclusion, the water-proof performance of the shower room is good by performing the water-proof treatment on the ground 2, the wall surface 3 and the supporting bars 1 and installing the sealing component 4 at the joint for performing double water-proof.
Further, the specific steps of installing the support bar 1 on the ground 2 are as follows:
snapping a line on the ground 2, and forming a groove 21;
a plurality of steel materials I11 are preset in the groove 21;
welding second steel materials 12 on the tops of the first steel materials 11;
manufacturing a mould;
and (6) pouring and forming.
Specifically, the snapping line is convenient to be provided with a groove 21; the groove 21 is used for accommodating a plurality of steel materials I11, one side of the support bar 1 extends into the ground 2, the support bar 1 is ensured to be fully contacted with the ground 2, and the connection strength of the support bar 1 and the ground 2 is further improved; the first steel 11 is used for increasing the strength of the support bar 1, and the cross section of the first steel 11 can be circular, so that the contact area between the first steel 11 and the casting material is increased conveniently, and the overall strength of the support bar 1 is increased conveniently; the second steel 12 is used for connecting the first steel 11, so that the connection firmness among the first steel 11 is increased, and the first steel 11 and the second steel 12 are connected in a welding manner, so that the connection performance of the first steel and the second steel is good, and the integrity of the first steel and the second steel is good; and manufacturing a mould, so that the first steel material 11 and the second steel material 12 are positioned in the mould, pouring materials into the mould, and removing the mould after 2-3 days to form a blank of the support bar 1, wherein the pouring materials can be heavy concrete, common concrete or light concrete and the like.
Furthermore, one end of the supporting strip 1 extends into the wall surface 3, and the extending range is 15-25 mm.
It is specific for support bar 1 and 3 abundant contacts of wall, thereby be favorable to joint support bar 1 and 3 joint strength of wall, wherein, stretch into the scope and can be for 15mm, 20mm or 25mm etc. if stretch into the scope undersize, will lead to support bar 1 and 3 joint strength of wall not enough, if stretch into the scope too big, will lead to the intensity of wall 3 itself to receive harmful effects.
Further, after the casting molding, the support bar 1 is roughened.
Specifically, be convenient for increase the surface roughness of support bar 1 to be convenient for support bar 1 and water proof coating combine, and then be convenient for carry out water repellent to support bar 1.
Further, the distance between the adjacent first steel products 11 is less than or equal to 300 mm.
Specifically, the distance between the adjacent first steel materials 11 may be 300mm, 280mm or 260mm, and if the distance between the adjacent first steel materials 11 is too large, the overall strength of the support bar 1 may be reduced.
Furthermore, the width range of the supporting strip 1 is 35-45mm, and the height range is 15-25 mm.
Specifically, the width of the support bar 1 can be 35mm, 40mm or 45mm, if the width of the support bar 1 is too small, the strength of the support bar 1 will be low, and if the width of the support bar 1 is too large, too much space of the shower room will be occupied; the height of support bar 1 specifically can be 15mm, 20mm or 25mm, if the high undersize of support bar 1, will lead to the high undersize of holding tank, and then lead to the holding tank can't hold shower end basin 5, if the height of support bar 1 is too big, will lead to shower end basin 5 too high, and then lead to the user not convenient to use.
Further, all do water repellent's step to ground 2, wall 3 and support bar 1 and include:
coating and scraping the first-time waterproof paint on the ground 2, the wall surface 3 and the support strips 1;
and after the first-time waterproof coating is cured, coating and scraping the second-time waterproof coating on the ground 2, the wall surface 3 and the support bars 1, wherein the coating and scraping directions of the second-time waterproof coating and the first-time waterproof coating are mutually vertical.
Specifically, the waterproof coating can effectively improve the waterproof performance of the ground 2, the wall surface 3 and the support bar 1 by coating and scraping for two times, and the waterproof coating can be specifically a polyurethane waterproof coating or a resin waterproof coating, wherein the specific coating and scraping number of the waterproof coating is not limited and is generally 2-3 times; and the coating and scraping directions of the adjacent waterproof coatings are mutually vertical, so that the connection firmness of the adjacent waterproof coatings can be effectively improved, and the waterproof performance of the ground 2, the wall surface 3 and the supporting strip 1 is further improved.
Further, all do water repellent's step to ground 2, wall 3 and support bar 1 and still include:
when the first-time waterproof coating is not cured, laying a first layer of glass fiber cloth on the first-time waterproof coating;
and when the waterproof coating for the second time is not cured, laying a second layer of glass fiber cloth on the waterproof coating for the second time.
Specifically, when the waterproof coating is a resin waterproof coating, in order to enhance the waterproofing, the glass fiber cloth can be laid when the resin waterproof coating is not cured, wherein the specific number of passes of the waterproof coating and the glass fiber cloth is not limited and can be determined according to the comprehensive consideration of the cost, the waterproofing requirement and the like; when the waterproof coating is polyurethane waterproof coating, glass fiber cloth is not generally added, and the polyurethane waterproof coating can form an elastic protective film and has certain tensile resistance.
Further, install back in the holding tank with shower end basin 5, tile on wall 3 and support bar 1, concrete step includes:
base layer treatment: the wall surface 3 and the supporting strips 1 are leveled or roughened, and then are watered and moistened;
brushing the first adhesive: brushing a first adhesive on the wall surface 3 and the support bars 1;
snapping line division: segmenting and dividing elastic lines according to the requirements of a drawing, and labeling alignment points on the wall surface 3 and the supporting strips 1;
selecting bricks: rejecting unqualified bricks;
brick soaking: soaking the brick for 2-3 h;
tiling: brushing a second adhesive on the brick, and tiling the brick from bottom to top;
pointing and wiping;
wherein, all install seal assembly 4 at the junction of the brick of shower end basin 5 and wall 3 to, at the junction of the brick of shower end basin 5 and support bar 1.
Specifically, when base layer processing is carried out, if the wall surface 3 and the supporting strips 1 are too rough, the wall surface 3 and the supporting strips 1 are properly trimmed, so that the wall surface 3 and the supporting strips 1 have certain smoothness, the smoothness of the bricks is further convenient to increase, if the wall surface 3 and the supporting strips 1 are too smooth, the wall surface 3 and the supporting strips 1 are properly roughened, the surface roughness of the wall surface 3 and the surface roughness of the supporting strips 1 are properly increased, the contact area between the wall surface 3 and the supporting strips 1 and the bricks is increased, the connection firmness between the wall surface 3 and the supporting strips 1 and the bricks is further increased, and the wall surface 3 and the supporting strips 1 can be prevented from cracking due to watering wetting; wherein, the adhesive can be cement mortar or mixed mortar, etc; the snapping line division is convenient for planning a tile area in advance, so that the accuracy of the tile is ensured, wherein the standard points can further ensure the accuracy of the tile; the unqualified bricks are removed, so that the qualified rate of the bricks can be improved, and the integral service life of the shower room is prolonged; the brick can be effectively prevented from cracking by brick soaking, so that the service life of the brick is prolonged; the second adhesive can be cement mortar or mixed mortar, and the like, and the bricks below can support the bricks above by tiling from bottom to top, so that the stability of the bricks above is ensured; the pointing and the wiping can effectively prevent dust from entering gaps between adjacent bricks; wherein, the brick can be a polished brick, a glazed brick or a mosaic brick, etc.
Furthermore, the direction of the first adhesive is perpendicular to the direction of the second adhesive.
The method is particularly beneficial to increasing the roughness of the joint of the first adhesive and the second adhesive, so that the friction force between the first adhesive and the second adhesive is increased, the friction force between the wall surface 3 and the brick and the friction force between the support bar 1 and the brick are increased, and the firmness of the brick is further ensured.
The present invention and its embodiments have been described above schematically, without limitation, and what is shown in the drawings is only one of the embodiments of the present invention, and the actual structure is not limited thereto. Therefore, if the person skilled in the art receives the teaching, without departing from the spirit of the invention, the person skilled in the art shall not inventively design the similar structural modes and embodiments to the technical solution, but shall fall within the scope of the invention.

Claims (10)

1. A construction process of a shower room is characterized by comprising the following steps:
mounting support bars on the ground to enable the ground, the wall surface and the support bars to form an accommodating groove in an enclosing mode;
performing waterproof treatment on the ground, the wall surface and the supporting strips;
mounting a shower base tub within the receiving tank;
the shower end basin with the junction of wall, and, the shower end basin with the junction of support bar all installs seal assembly.
2. The shower room construction process according to claim 1, wherein the specific steps of mounting the support bars on the ground are as follows:
snapping a line on the ground, and forming a groove;
presetting a plurality of steel I in the groove;
welding second steel materials on the tops of the first steel materials;
manufacturing a mould;
and (6) pouring and forming.
3. The shower room construction process according to claim 2, wherein one end of the supporting bar extends into the wall surface within a range of 15-25 mm.
4. The shower room construction process according to claim 2, wherein the support bars are chiseled after the casting molding.
5. The shower room construction process according to claim 2, wherein a spacing between adjacent steel products is less than or equal to 300 mm.
6. The shower room construction process according to claim 2, wherein the width range of the support bars is 35-45mm, and the height range is 15-25 mm.
7. The shower room construction process according to any one of claims 1 to 6, wherein the step of performing waterproof treatment on the ground, the wall surface and the supporting bars comprises:
coating and scraping the first-time waterproof paint on the ground, the wall surface and the support bars;
and after the first-time waterproof coating is cured, coating and scraping the second-time waterproof coating on the ground, the wall surface and the support bars, wherein the coating and scraping direction of the second-time waterproof coating is perpendicular to that of the first-time waterproof coating.
8. The shower room construction process according to claim 7, wherein the step of performing waterproof treatment on the ground, the wall surface and the support bars further comprises:
when the first-time waterproof coating is not cured, laying a first layer of glass fiber cloth on the first-time waterproof coating;
and when the waterproof coating for the second time is not cured, laying a second layer of glass fiber cloth on the waterproof coating for the second time.
9. A shower room construction process according to any one of claims 1 to 6, wherein after the shower tray is mounted in the receiving groove, the wall surface and the supporting bars are tiled, and the concrete steps include:
base layer treatment: the wall surface and the supporting strips are trimmed or roughened, and then are watered and moistened;
brushing the first adhesive: brushing a first adhesive on the wall surface and the support bars;
snapping line division: segmenting and dividing elastic lines according to the requirements of a drawing, and labeling alignment points on the wall surface and the supporting strips;
selecting bricks: rejecting unqualified bricks;
brick soaking: soaking the brick for 2-3 h;
tiling: brushing a second adhesive on the bricks, and tiling the bricks from bottom to top;
pointing and wiping;
wherein, shower end basin with the junction of the brick of wall, and, shower end basin with the junction of the brick of support bar all installs seal assembly.
10. The shower room construction process according to claim 9, wherein the direction of the first adhesive and the direction of the second adhesive are perpendicular to each other.
CN202210518649.7A 2022-05-12 2022-05-12 Shower room construction process Active CN114856259B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210518649.7A CN114856259B (en) 2022-05-12 2022-05-12 Shower room construction process

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210518649.7A CN114856259B (en) 2022-05-12 2022-05-12 Shower room construction process

Publications (2)

Publication Number Publication Date
CN114856259A true CN114856259A (en) 2022-08-05
CN114856259B CN114856259B (en) 2024-03-29

Family

ID=82637154

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210518649.7A Active CN114856259B (en) 2022-05-12 2022-05-12 Shower room construction process

Country Status (1)

Country Link
CN (1) CN114856259B (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6643863B1 (en) * 2002-10-30 2003-11-11 Lloyd Gerber Prefabricated shower pan with integrally molded curb reinforcements
CN112240108A (en) * 2020-09-17 2021-01-19 上海宝冶集团有限公司 Construction method of assembly type building integrated bathroom system
CN112401711A (en) * 2020-10-27 2021-02-26 河南德田卫浴有限公司 Assembled integrated shower room tray and construction method thereof
CN113180520A (en) * 2020-11-06 2021-07-30 深圳海智创科技有限公司 Toilet structure with integrated chassis combined with traditional process and construction process thereof
CN216221279U (en) * 2021-09-22 2022-04-08 平湖市佰斯德卫浴股份有限公司 Shower room bottom basin with high sealing performance and water leakage prevention

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6643863B1 (en) * 2002-10-30 2003-11-11 Lloyd Gerber Prefabricated shower pan with integrally molded curb reinforcements
CN112240108A (en) * 2020-09-17 2021-01-19 上海宝冶集团有限公司 Construction method of assembly type building integrated bathroom system
CN112401711A (en) * 2020-10-27 2021-02-26 河南德田卫浴有限公司 Assembled integrated shower room tray and construction method thereof
CN113180520A (en) * 2020-11-06 2021-07-30 深圳海智创科技有限公司 Toilet structure with integrated chassis combined with traditional process and construction process thereof
CN216221279U (en) * 2021-09-22 2022-04-08 平湖市佰斯德卫浴股份有限公司 Shower room bottom basin with high sealing performance and water leakage prevention

Also Published As

Publication number Publication date
CN114856259B (en) 2024-03-29

Similar Documents

Publication Publication Date Title
US7490371B2 (en) Shower receptor
CN205077752U (en) Roofing flashing waterproofing membrane of department brick wall protection architecture
EP3141670B1 (en) Shower floor sealing
KR101280879B1 (en) The complex water proofing construction method using a porous fabric sheet & non exposure urethane
KR102670612B1 (en) Field fabricated shower system
CN114856259A (en) Shower room construction process
CN105587137B (en) A kind of built-in integral vacuum toilet
CN212052176U (en) Novel plastic course
CN209924237U (en) Interior drainage daylighting top curtain wall construction
CN111519774B (en) Construction method of shower room water bar
CN110847639A (en) Mounting structure of assembled bathroom base plate
CN114753591B (en) Bathtub construction process
CN218881115U (en) Telescopic rail type long-strip-shaped floor drain
CN219118412U (en) Swimming pool waterproof construction
CN211873970U (en) Mounting structure of assembled bathroom base plate
CN204225324U (en) Wall thermal insulating integration point extension system
CN221118689U (en) Anti-leakage drainage system for house decoration and integral bathroom chassis
JP2006104741A (en) Opening structure of waterproof pan of bathroom
CN219431245U (en) Anti-drop wall ceramic tile
CN212358954U (en) Waterproof wall surface of toilet
CN212506668U (en) Telescopic rail type elongated shower room floor drain
CN215948785U (en) Regional waterproof construction in bathroom
CN109171521B (en) Bathroom chassis, manufacturing method thereof and waterproof frame
CN117179607A (en) Integral bathroom
CN208733992U (en) A kind of waterproof Dali stone ceramic tile

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant