CN114233332A CN202210020670.4A CN202210020670A CN114233332A CN 114233332 A CN114233332 A CN 114233332A CN 202210020670 A CN202210020670 A CN 202210020670A CN 114233332 A CN114233332 A CN 114233332A
Authority
CN
China
Prior art keywords
template
assembly
gantry
oil cylinder
adjusting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202210020670.4A
Other languages
Chinese (zh)
Inventor
王旭峰
林荷节
高超
徐礼付
张舒竹
彭莉
何勇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hangzhou Reservoir Management Service Center
Original Assignee
Hangzhou Reservoir Management Service Center
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hangzhou Reservoir Management Service Center filed Critical Hangzhou Reservoir Management Service Center
Priority to CN202210020670.4A priority Critical patent/CN114233332A/en
Publication of CN114233332A publication Critical patent/CN114233332A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/102Removable shuttering; Bearing or supporting devices therefor

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Civil Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The invention discloses a tunnel secondary lining trolley which comprises a template assembly, a bracket assembly, a translation mechanism, a portal assembly, a walking mechanism, a lateral hydraulic oil cylinder, a lateral support jack, a portal support jack and a control console, wherein the template assembly comprises an arc top template, a top side template and side templates which are symmetrically arranged at two sides of a trolley body; the walking mechanism comprises a motor and a speed reducer, and the walking structure is hinged with the longitudinal beam of the door frame.

Description

Tunnel secondary lining trolley
Technical Field
The invention relates to the field of tunnel lining construction, in particular to a tunnel secondary lining trolley.
Background
Along with the development of economy in China, the construction of railways and highways in China is accelerated continuously, the number of railways, highway tunnels and water conservancy culverts is increased continuously, in the construction process of the tunnels, tunnel concrete is a secondary lining process which is a very important process, the tunnels are mostly arranged in rock masses, after the excavation is finished, concrete is adopted to line the rock surfaces so as to ensure the operation safety of the tunnels, the whole tunnel construction procedure comprises the steps of tunnel excavation, primary support, concrete lining and grouting, a steel form trolley is mostly adopted in the concrete lining process, the process comprises the steps of leveling a bottom plate, installing a steel form trolley (the conventional subsection length is 9m), concrete pouring, demoulding and moving the steel form trolley, and concrete pouring until the lining of the tunnels is finished;
however, the change of the tunnel height brings disadvantages to lining, the conventional method is to customize or reform a steel mould trolley and a transition section according to different heights by adopting conventional mounting and supporting frames, formwork supporting, concrete pouring and formwork stripping, the top templates of the traditional tunnel secondary lining trolley are usually integrated, the top templates move integrally in the process of formwork erection and demoulding, the expansion amount is small, and the use effectiveness of the tunnel secondary lining trolley is limited.
Disclosure of Invention
The invention aims to overcome the defects of the prior art and provides a tunnel secondary lining trolley.
In order to solve the technical problems, the technical scheme provided by the invention is a tunnel secondary lining trolley which comprises a template assembly, a bracket assembly, a translation mechanism, a portal assembly, a walking mechanism, a lateral hydraulic oil cylinder, a lateral supporting jack, a portal supporting jack and a control platform, wherein the template assembly comprises an arc top template, a top side template and side templates, the arc top template, the top side template and the side templates are symmetrically arranged at two sides of a trolley body, the arc top template is positioned at the top of the trolley body, the two arc top templates are fixedly connected through bolts, the arc top template is hinged with the top side template, and the top side template is hinged with the side templates;
the gantry assembly comprises an adjusting cross beam, an adjusting upright post and a gantry longitudinal beam, the bracket assembly comprises a cross beam, a longitudinal main beam, upright posts, gantry brackets and cross braces, a plurality of uniformly distributed gantry brackets are arranged between the cross beam and the longitudinal main beam, the cross braces are arranged between every two adjacent gantry brackets, the upright post is arranged at the upper part of the cross beam, and the other end of the upright post is connected with the arc top template;
the translation mechanism comprises a longitudinal adjusting oil cylinder and a transverse adjusting oil cylinder, the longitudinal adjusting oil cylinder is respectively and fixedly connected with the gantry bracket and the longitudinal main beam, and the transverse adjusting oil cylinder is positioned at the upper part of the cross beam;
the walking mechanism comprises a motor and a speed reducer, and is hinged with the longitudinal beam of the door frame;
and a lateral hydraulic oil cylinder and a lateral supporting jack are arranged between the bracket assembly and the template assembly, and a lateral hydraulic oil cylinder and a lateral supporting jack are arranged between the portal assembly and the template assembly.
Furthermore, the adjusting cross beam and the adjusting upright post are connected through a diagonal draw bar.
Furthermore, a plurality of portal support jacks are arranged at the lower part of the adjusting beam.
Further, a control console is arranged on the upper portion of the cross beam.
Furthermore, crawling ladders are symmetrically arranged on two sides of the trolley body.
Compared with the prior art, the invention has the advantages that: the device has reasonable structural design and convenient use, and can complete vertical positioning and demoulding of the template assembly by longitudinally adjusting the oil cylinder; the transverse adjusting oil cylinder is used for adjusting the superposition of the lining central line of the template assembly and the tunnel central line, and meanwhile, the stability of the bracket assembly and the portal frame assembly during the operation of the device can be ensured through the lateral supporting jacks and the portal frame supporting jacks.
Drawings
Fig. 1 is a schematic structural diagram of a tunnel secondary lining trolley of the invention.
Fig. 2 is a schematic cross-sectional view of a tunnel secondary lining trolley according to the present invention.
As shown in the figure: 1. the template assembly comprises 101, arc top templates, 102, top side templates, 103, side templates, 2, a bracket assembly, 201, a cross beam, 202, a longitudinal main beam, 203, an upright post, 204, a gantry bracket, 205, a cross brace, 3, a translation mechanism, 301, a longitudinal adjusting oil cylinder, 302, a transverse adjusting oil cylinder, 4, a gantry assembly, 401, an adjusting cross beam, 402, an adjusting upright post, 403, a gantry longitudinal beam, 5, a traveling mechanism, 501, a motor, 502, a speed reducer, 6, a lateral hydraulic oil cylinder, 7, a lateral supporting jack, 8, a gantry supporting jack, 9 and a control console.
Detailed Description
The tunnel secondary lining trolley of the invention is further described in detail with reference to the accompanying drawings.
With reference to fig. 1-2, the tunnel secondary lining trolley comprises a template assembly 1, a bracket assembly 2, a translation mechanism 3, a gantry assembly 4, a walking mechanism 5, a lateral hydraulic oil cylinder 6, a lateral support jack 7, a gantry support jack 8 and a control console 9, wherein the template assembly 1 comprises an arc top template 101, a top side template 102 and a side template 103, the arc top template 101, the top side template 102 and the side template 103 are symmetrically arranged on two sides of a trolley body, the arc top template 101 is positioned on the top of the trolley body, the two arc top templates 101 are fixedly connected through bolts, the arc top template 101 is hinged with the top side template 102, and the top side template 102 is hinged with the side template 103;
the gantry assembly 4 comprises an adjusting cross beam 401, an adjusting upright post 402 and a gantry longitudinal beam 403, the bracket assembly 2 comprises a cross beam 201, a longitudinal main beam 202, upright posts 203, gantry brackets 204 and cross braces 205, a plurality of uniformly distributed gantry brackets 204 are arranged between the cross beam 201 and the longitudinal main beam 202, the cross braces 205 are arranged between every two adjacent gantry brackets 204, the upright posts 203 are arranged at the upper parts of the cross beams 201, and the other ends of the upright posts 203 are connected with the arc top template 101;
the translation mechanism 3 comprises a longitudinal adjusting oil cylinder 301 and a transverse adjusting oil cylinder 302, wherein the longitudinal adjusting oil cylinder 301 is fixedly connected with the gantry bracket 204 and the longitudinal main beam 202 respectively, and the transverse adjusting oil cylinder 302 is positioned at the upper part of the cross beam 201;
the walking mechanism 5 comprises a motor 501 and a speed reducer 502, and the walking mechanism 5 is hinged with the portal frame longitudinal beam 403;
a lateral hydraulic oil cylinder 6 and a lateral supporting jack 7 are arranged between the bracket assembly 2 and the template assembly 1, and a lateral hydraulic oil cylinder 6 and a lateral supporting jack 7 are arranged between the portal assembly 4 and the template assembly 1.
As a preferred embodiment of this embodiment, the adjusting beam 401 and the adjusting column 402 are connected by a diagonal draw bar.
As a preferred embodiment of the present embodiment, a plurality of gantry support jacks 8 are arranged at the lower part of the adjusting beam 401.
In the preferred embodiment of the present embodiment, a console 9 is disposed on the upper portion of the beam 201.
As a preferred embodiment of this embodiment, the ladder stands are symmetrically arranged on two sides of the trolley body.
When the device is used in specific implementation, an operator adjusts the appearance of the template assembly 1 through the control console 9, the lateral hydraulic oil cylinder 6 and the lateral support jack 7 to enable the template assembly to meet the construction requirements; the superposition of the lining central line of the template assembly 1 and the tunnel central line is adjusted by controlling the transverse adjusting oil cylinder 302; the longitudinal adjusting oil cylinder 301 can be used for completing vertical positioning and demoulding of the template assembly 1; the lateral hydraulic oil cylinder 6 is used for demoulding of the template assembly 1 and plays a role in supporting the template assembly 1; the lateral supporting jacks 7 are used for improving the stress adjustment of the gantry bracket 204 when concrete is poured, so that the reliability and stability of the bracket assembly 2 are ensured; the gantry support jack 8 is used for improving the stress condition of the gantry longitudinal beam 403 and ensuring the stability of the gantry assembly 4 when the whole trolley works; the traveling mechanism 5 can realize the function of forward and reverse traveling.
The present invention and its embodiments have been described above, and the description is not intended to be limiting, and the drawings are only one embodiment of the present invention, and the actual structure is not limited thereto. In summary, those skilled in the art should appreciate that they can readily use the disclosed conception and specific embodiments as a basis for designing or modifying other structures for carrying out the same purposes of the present invention without departing from the spirit and scope of the invention as defined by the appended claims.

Claims (5)

1. A two lining platform trucks in tunnel which characterized in that: the gantry type gantry crane comprises a template assembly (1), a bracket assembly (2), a translation mechanism (3), a gantry assembly (4), a walking mechanism (5), a lateral hydraulic oil cylinder (6), a lateral support jack (7), a gantry support jack (8) and a control console (9), wherein the template assembly (1) comprises an arc top template (101), a top side template (102) and a side template (103), the arc top template (101), the top side template (102) and the side template (103) are symmetrically arranged on two sides of a trolley body, the arc top template (101) is positioned at the top of the trolley body, the two arc top templates (101) are fixedly connected through bolts, the arc top template (101) is hinged with the top side template (102), and the top side template (102) is hinged with the side template (103);
the gantry assembly (4) comprises an adjusting cross beam (401), an adjusting upright post (402) and a gantry longitudinal beam (403), the bracket assembly (2) comprises a cross beam (201), a longitudinal main beam (202), upright posts (203), gantry brackets (204) and cross braces (205), a plurality of uniformly distributed gantry brackets (204) are arranged between the cross beam (201) and the longitudinal main beam (202), the cross braces (205) are arranged between every two adjacent gantry brackets (204), the upright posts (203) are arranged on the upper portion of the cross beam (201), and the other ends of the upright posts (203) are connected with the arc top template (101);
the translation mechanism (3) comprises a longitudinal adjusting oil cylinder (301) and a transverse adjusting oil cylinder (302), the longitudinal adjusting oil cylinder (301) is fixedly connected with the gantry bracket (204) and the longitudinal main beam (202) respectively, and the transverse adjusting oil cylinder (302) is positioned at the upper part of the cross beam (201);
the walking mechanism (5) comprises a motor (501) and a speed reducer (502), and the walking mechanism (5) is hinged with the portal longitudinal beam (403);
a lateral hydraulic oil cylinder (6) and a lateral supporting jack (7) are arranged between the bracket assembly (2) and the template assembly (1), and a lateral hydraulic oil cylinder (6) and a lateral supporting jack (7) are arranged between the portal assembly (4) and the template assembly (1).
2. A tunnel secondary lining trolley according to claim 1, characterized in that: the adjusting beam (401) and the adjusting upright post (402) are connected through a diagonal draw bar.
3. A tunnel secondary lining trolley according to claim 1, characterized in that: and a plurality of portal support jacks (8) are arranged at the lower part of the adjusting beam (401).
4. A tunnel secondary lining trolley according to claim 1, characterized in that: and a control console (9) is arranged at the upper part of the cross beam (201).
5. A tunnel secondary lining trolley according to claim 1, characterized in that: the ladder stand is symmetrically arranged on two sides of the trolley body.
CN202210020670.4A 2022-01-10 2022-01-10 Tunnel secondary lining trolley Pending CN114233332A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210020670.4A CN114233332A (en) 2022-01-10 2022-01-10 Tunnel secondary lining trolley

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210020670.4A CN114233332A (en) 2022-01-10 2022-01-10 Tunnel secondary lining trolley

Publications (1)

Publication Number Publication Date
CN114233332A true CN114233332A (en) 2022-03-25

Family

ID=80746203

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210020670.4A Pending CN114233332A (en) 2022-01-10 2022-01-10 Tunnel secondary lining trolley

Country Status (1)

Country Link
CN (1) CN114233332A (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102650211A (en) * 2012-05-22 2012-08-29 湖南五新重型装备有限公司 Universal type steel mould lining trolley for linear and curved sectional tunnel
CN202578714U (en) * 2012-05-22 2012-12-05 湖南五新重型装备有限公司 Universal steel die lining trolley for linear and curved section tunnel
CN204920986U (en) * 2015-09-09 2015-12-30 中国铁建大桥工程局集团有限公司 Light -duty top pushes away sliding tunnel lining platform truck
CN107130978A (en) * 2017-05-31 2017-09-05 中铁隧道集团四处有限公司 Combined type working jumbo for tunnel lining
CN207063995U (en) * 2017-08-02 2018-03-02 中铁二十二局集团第四工程有限公司 Can assembled detachable chassis
WO2021237402A1 (en) * 2020-05-25 2021-12-02 保利长大海外工程有限公司 Assembled lining trolley allowing for rapid turnover

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102650211A (en) * 2012-05-22 2012-08-29 湖南五新重型装备有限公司 Universal type steel mould lining trolley for linear and curved sectional tunnel
CN202578714U (en) * 2012-05-22 2012-12-05 湖南五新重型装备有限公司 Universal steel die lining trolley for linear and curved section tunnel
CN204920986U (en) * 2015-09-09 2015-12-30 中国铁建大桥工程局集团有限公司 Light -duty top pushes away sliding tunnel lining platform truck
CN107130978A (en) * 2017-05-31 2017-09-05 中铁隧道集团四处有限公司 Combined type working jumbo for tunnel lining
CN207063995U (en) * 2017-08-02 2018-03-02 中铁二十二局集团第四工程有限公司 Can assembled detachable chassis
WO2021237402A1 (en) * 2020-05-25 2021-12-02 保利长大海外工程有限公司 Assembled lining trolley allowing for rapid turnover

Similar Documents

Publication Publication Date Title
CN100406677C (en) Tunnel lining trolley
CN104594918B (en) Split integrated underground passage steel mold plate trolley and construction method thereof
CN113235472B (en) Concrete placement platform truck is contained to apron
CN107387122A (en) A kind of formwork jumbo and its construction method for the construction of piping lane tunneling boring
CN105155423A (en) Upward moving type movable formwork for continuous box girder construction
CN105673048B (en) A kind of self-propelled hydraulic box culvert chassis
CN109629439B (en) Construction method of single-tower cable-stayed bridge
CN214993219U (en) Concrete placement platform truck is contained to apron
CN210712594U (en) Culvert platform truck
CN109139050B (en) Self-propelled integrated tunnel inverted arch device
CN111042835B (en) Tunnel cable ditch and ditch construction trolley and construction method thereof
CN109371851B (en) Groove making machine with multiple bottom die head cover supporting frames
CN206636581U (en) A kind of shield tunnel Second Lining Construction chassis
CN212867563U (en) Tunnel super-large section two-lining trolley capable of being widened for multiple times
CN114233332A (en) Tunnel secondary lining trolley
CN212671805U (en) Split type hydraulic trolley
CN211973152U (en) Large-tonnage box girder erection construction system capable of realizing height control
CN212335790U (en) Large cantilever bent cap construction trolley
CN210317334U (en) A template platform truck for tunnel thin wall mid-board concrete placement
CN212835507U (en) Concrete reinforcement cage ligature and conversion equipment
CN211113223U (en) Four-leg structure of bridge girder erection machine capable of lifting height without limitation
CN111335185A (en) Large-tonnage box girder erection construction system for realizing height control and erection method thereof
CN205400755U (en) Disconnect -type platform truck
CN212272235U (en) Heavy lining trolley suitable for super large span tunnel
CN219638842U (en) A inside and outside mould platform truck combination for oversized section open cut tunnel major structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20220325

RJ01 Rejection of invention patent application after publication