CN104594918B - Split integrated underground passage steel mold plate trolley and construction method thereof - Google Patents
Split integrated underground passage steel mold plate trolley and construction method thereof Download PDFInfo
- Publication number
- CN104594918B CN104594918B CN201410852859.5A CN201410852859A CN104594918B CN 104594918 B CN104594918 B CN 104594918B CN 201410852859 A CN201410852859 A CN 201410852859A CN 104594918 B CN104594918 B CN 104594918B
- Authority
- CN
- China
- Prior art keywords
- plate supporting
- supporting device
- frame
- underpass
- mould plate
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 238000010276 construction Methods 0.000 title claims abstract description 118
- 229910000831 Steel Inorganic materials 0.000 title claims abstract description 88
- 239000010959 steel Substances 0.000 title claims abstract description 88
- 239000010720 hydraulic oil Substances 0.000 claims abstract description 22
- 230000007246 mechanism Effects 0.000 claims abstract description 14
- 238000009415 formwork Methods 0.000 claims description 75
- 239000000178 monomer Substances 0.000 claims description 30
- 230000007306 turnover Effects 0.000 claims description 6
- 230000007423 decrease Effects 0.000 claims description 5
- 238000004080 punching Methods 0.000 claims description 5
- 239000003921 oil Substances 0.000 claims 1
- 239000007787 solid Substances 0.000 claims 1
- 238000009416 shuttering Methods 0.000 description 6
- 230000008602 contraction Effects 0.000 description 5
- 238000005516 engineering process Methods 0.000 description 5
- 238000000465 moulding Methods 0.000 description 4
- 238000004140 cleaning Methods 0.000 description 3
- 238000000034 method Methods 0.000 description 3
- 239000000203 mixture Substances 0.000 description 3
- 230000008859 change Effects 0.000 description 2
- 239000003795 chemical substances by application Substances 0.000 description 2
- 238000005345 coagulation Methods 0.000 description 2
- 230000015271 coagulation Effects 0.000 description 2
- 239000011248 coating agent Substances 0.000 description 2
- 238000000576 coating method Methods 0.000 description 2
- 230000007547 defect Effects 0.000 description 2
- 230000000694 effects Effects 0.000 description 2
- 239000007788 liquid Substances 0.000 description 2
- 239000000463 material Substances 0.000 description 2
- 238000000926 separation method Methods 0.000 description 2
- 239000002689 soil Substances 0.000 description 2
- 230000033228 biological regulation Effects 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 230000005611 electricity Effects 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000008450 motivation Effects 0.000 description 1
- 238000003466 welding Methods 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/04—Lining with building materials
- E21D11/10—Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
- E21D11/102—Removable shuttering; Bearing or supporting devices therefor
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Structural Engineering (AREA)
- Mining & Mineral Resources (AREA)
- Civil Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Geology (AREA)
- Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
Abstract
The invention discloses a slit integrated underground passage steel mold plate trolley and a construction method thereof, relates to the technical field of underground passage building concrete construction, and aims at the problems that the existing underground passage construction equipment is large in occupied area, the construction method is long in curing time, and continuous pouring construction cannot be realized. The steel mold plate trolley comprises at least three frame-type mold plate supporting devices which are connected integrally through detachable box-shaped cross beams, and at least two groups of posterior disassembly top mold plate supporting devices; a traveling mechanism at the lower part of the steel mold plate trolley can drive the frame-type mold plate supporting devices to move along longitudinal tracks; the two frame-type mold plate supporting devices positioned on the outer side can move in the horizontal direction under the operational control of a horizontal hydraulic oil cylinder group; each frame-type mold plate supporting device can lift in the vertical direction under the operational control of a vertical hydraulic oil cylinder group which is mounted on the corresponding frame-type mold plate supporting device; the at least two groups of posterior disassembly top mold plate supporting devices are respectively connected between the two adjacent frame-type mold plate supporting devices by bolts; universal wheels used for travelling are mounted at the bottom parts of the posterior disassembly top mold plate supporting devices.
Description
Technical field
The present invention relates to underpass building concrete technical field of construction, particularly to one kind and early-dismantling technology phase
In conjunction with split integrated underpass steel formwork trolley and its construction method.
Background technology
With the fast development of urban construction, traffic above-ground increasingly congestion, and developing underpass is to solve surface road
One of effective means of congestion.For reducing the construction cost of underpass, part underpass adopts open-cut, will entirely
Lower channel is divided into the construction cell of several certain lengths, and iterative method is constructed, to reduce the holding time of construction site, and
Avoid hindering traffic above-ground.
At present, the construction equipment of employing be a set of gathered monoblock type formwork jumbo and steel pipe type mould plate supporting device be
System, the defect of this system is: 1, steel pipe type mould plate supporting device is so that steel pipe and template occupied ground area are greatly and it needs to hang
Car is lifted with the cooperation of other big machineries;2nd, two side template cleaning difficulty of monoblock type formwork jumbo are big.It is accordingly applied
The defect of work method is: 1, wait concrete reach design strength time longer, the concrete of the next construction cell of impact
Pouring construction;2 it cannot be guaranteed that each construction cell continues uninterrupted pouring construction it is impossible to meet rapid construction requirement.
Therefore, how to provide one kind can improve efficiency of construction, shorten the construction period, and realize underpass concrete even
The formwork jumbo of continuous pouring construction and its construction method are those skilled in the art's technical problems urgently to be resolved hurrily.
Content of the invention
For existing underpass construction equipment floor space greatly, side template not easy cleaning, and construction method etc. is strong
Time length is it is impossible to realize the problem of continuous concreting construction, it is an object of the invention to provide a kind of integrated underground of split
Passage steel formwork trolley and its construction method, steel formwork trolley floor space is little and easy to operate, is capable of concrete continuous
Pour operation, improve efficiency of construction, shorten the construction period, and ensure that construction quality.
The present invention solves the split integrated underpass steel formwork trolley that its technical problem is adopted, and pours for installing
The template group of described underpass concrete, including at least three frame-types being arranged in order along described underpass transverse section
Mould plate supporting device, described frame-type mould plate supporting device is connected as one by some detachable box-shaped beams, and described frame
The bottom of posture mould plate supporting device is provided with walking mechanism, and described walking mechanism can drive described frame-type shuttering supporting dress
Put and move along the long rails parallel to described underpass axis, positioned at the two of the described frame-type mould plate supporting device at middle part
Side is provided with transverse hydraulic oil cylinder group, and two described frame-type mould plate supporting devices positioned at outside are in described transverse hydraulic oil cylinder
Under the operational control of group, horizontal direction can be made along described underpass transverse section and move, and described frame-type shuttering supporting
Device vertically can lift under the operational control of the vertical hydraulic jack group being mounted thereon;Top is torn open after at least two groups
Mould plate supporting device, described after tear backform plate supporting device open and be bolted to two neighboring described frame-type shuttering supporting dress respectively
Between putting, described after tear open backform plate supporting device bottom be provided with for walking universal wheel.
Preferably, described template group includes top template and the side template that can be closely connected, described top template and side template
Can be adapted with the profile of described underpass, described top template is to be spliced by some monomer top templates, described framework
Formula mould plate supporting device and described after tear the top of backform plate supporting device open and be respectively fixed with one piece of monomer top template, positioned at both sides
The outside of two described frame-type mould plate supporting devices be respectively articulated with one piece of side template.
Preferably, the described frame-type mould plate supporting device positioned at described steel formwork trolley both sides includes:
One framework type base, the outside of described framework type base is provided with the demoulding hydraulic oil being connected respectively with described side template
Cylinder group and support screw group;
One π shape bearing support, described π shape bearing support is bolted in described framework type base, described π shape bearing support
It is provided with two parallel longerons, described monomer top template is arranged on described longeron, is installed in described framework type base
Vertical hydraulic jack group can control described π shape bearing support vertically to lift;
Described longeron is hinged with described side template by side template turnover hinge bearing, and described side template is in described liquid parting
Shunk centered on described side template turnover hinge bearing under the control of compressing cylinder group and launch, and adjusted by described support screw group
Solidating is fixed.
Preferably, the bottom positioned at the described frame-type mould plate supporting device of described steel formwork trolley both sides is provided with and leads
Wheel, is mounted on transverse hydraulic oil cylinder group, the described frame of both sides positioned at the both sides of the described frame-type mould plate supporting device at middle part
Posture mould plate supporting device under the control of described transverse hydraulic oil cylinder group, and under the guiding of described guide wheel, can be along hanging down
Directly it is arranged at the cross track above described long rails to move to the direction closer or far from described steel formwork trolley axis.
Preferably, tearing backform plate supporting device open after described is the frame structure being formed by connecting by some steel pipe, described after
The top tearing backform plate supporting device open is connected with described monomer top template by screw mandrel group one, described after tear backform plate supporting device open
Base supported by screw mandrel group two, and the bottom of described base be provided with for walking universal wheel.
Preferably, described walking mechanism includes wheel, motor, decelerator and brake gear, and described wheel is disposed along institute
State on the described long rails of underpass axis direction laying, described walking mechanism is by described motor-driven, described electronic
Machine is through described decelerator speed governing, and passes through vehicle wheel rotation described in chain-driving so that described wheel can be along described longitudinal rail
Road moves.
Preferably, the width of described steel formwork trolley is equal to the width of the described underpass of pre- construction, and can pass through
The length changing described box-shaped beam is adjusted, and the height of described steel formwork trolley can be by the liter of described π shape bearing support
Fall is adjusted, and described steel formwork trolley is divided into structure identical at least two steel form along the axis direction of described underpass
Trolley unit, and bolt connection is integrated, each described steel formwork trolley element length is 12.5m~15m.
In addition, present invention also offers a kind of construction method of split integrated underpass steel formwork trolley, step is such as
Under:
Step one: described template group is arranged on described steel formwork trolley, arranges successively along described underpass transverse section
Arrange described frame-type mould plate supporting device, and connected by described box-shaped beam, described frame-type mould plate supporting device passes through described
After vertical hydraulic jack group is adjusted to calibrated altitude, bolt connection between two adjacent described frame-type mould plate supporting devices
Tear backform plate supporting device after described open, make described frame-type mould plate supporting device and described after tear open on backform plate supporting device fixing
Described monomer top template be located at same level, and progressively carry out concreting in the construction cell of described underpass
Construction;
Step 2: when the concrete of current construction cell reaches some strength, in described transverse hydraulic oil cylinder group and institute
State under the control of vertical hydraulic jack group, so that the described monomer top template on described frame-type mould plate supporting device is declined, described
Side template shrinks, and the company tearing open between backform plate supporting device and described frame-type mould plate supporting device after unclamping described in two groups
Connect, the outer profile size after described frame-type mould plate supporting device shrinks is less than the overall size of described underpass so that institute
State frame-type mould plate supporting device and can enter next construction cell through described underpass;
Step 3: after the concrete strength of described current construction cell reaches design requirement, then will be described after tear backform open
Plate supporting device moves to next construction cell, is connected with described frame-type mould plate supporting device, forms described steel form again
Chassis, carry out next construction cell pours operation.
Preferably, in described step 2, want when the concrete strength of the current construction cell of described underpass reaches design
Ask 60%~70% when, so that monomer top template on described frame-type mould plate supporting device and side template is shunk, and pass through institute
State underpass and enter next construction cell.
Preferably, when described underpass has bend segmental arc, it is 12.5m that described steel formwork trolley is resolved into length
The steel formwork trolley unit of~15m, each described steel formwork trolley unit is by direct for described frame-type mould plate supporting device spiral shell
Bolt is formed by connecting.
Effect of the invention is that:
First, the split of the present invention integrated underpass steel formwork trolley, is that one kind is combined with early-dismantling technology, energy
Enough make the construction equipment of underpass continuous concreting molding.It includes decomposing and the three frame-type templates combining
Backform plate supporting device is torn open, each frame-type mould plate supporting device can be vertical be mounted thereon after support meanss and two groups
Vertically lift under the operational control of hydraulic jack group, two frame-type mould plate supporting devices positioned at outside can be in peace
It is loaded under the operational control of the transverse hydraulic oil cylinder group on middle frame formula mould plate supporting device, along underpass transverse section side
To moving left and right, realize the separation of three frame-type mould plate supporting devices and combination so that being installed on frame-type shuttering supporting
The monomer top template of device upper end can vertically lift, and is installed on the side template energy of frame-type mould plate supporting device side
Enough make the movement of horizontal direction.Outer profile size after the contraction of frame-type mould plate supporting device is less than the profile chi of underpass
Very little, therefore so that segment template group can pass through with frame-type mould plate supporting device pours the underpass unit completing and enter
Enter next construction cell.The frame-type mould plate supporting device of the present invention and after tear open backform plate supporting device all can slidably,
Floor space is little, and scene dismounting is simple and convenient, participates in construction without hanging device, saves a large amount of manpower and materials;Punching block pallet
Car split moves laterally, and can provide working place for side template, be easy in long narrow underpass, side template be carried out
Cleaning and coating release agent.
After the reach of frame-type mould plate supporting device, pour to complete to retain two groups in construction cell monomer top template is installed
After tear backform plate supporting device open, reach to tear open again after design requirement intensity after concrete and move to next construction cell, in view of coagulation
Soil pours 3~5 days its intensity up to 50% about, and later strength rise slow characteristic, after tear backform plate supporting device open
Setting can make the monomer top template above it be in short across stress, can make frame-type mould plate supporting device underground lead to
When road concrete strength reaches some strength, you can move to next construction cell and continue construction, realize early form removal construction, reduce
Construction cost, shortens the construction period.
2nd, the construction method of the split of the present invention integrated underpass steel formwork trolley, first, tears backform open by after two groups
Plate supporting device is bolted between adjacent two frame-type mould plate supporting device respectively, forms steel formwork trolley, meets
The pouring construction of underpass concrete, whne concrete strength reach necessarily require when, frame-type mould plate supporting device is in hydraulic pressure
Shrink in the presence of system so that its can before move up into next construction cell, and recover original extended configuration, after reservation
Tear backform plate supporting device open then after underpass concrete reaches design requirement, then remove next construction cell of entrance, with frame
Posture mould plate supporting device is assembled into the pouring construction that steel formwork trolley carries out concrete again.By the construction party of the present invention
Method, not only can make underpass continuous concreting molding, and due to after tear the presence of backform plate supporting device open, can make
Frame-type mould plate supporting device is when underpass concrete strength reaches some strength, you can moves to next construction cell and continues
Continuous construction so that steel formwork trolley can do sth. in advance 10~15 heaven-made vertically move, realize morning form removal and construct, decrease construction cost,
Shorten the construction period, and ensure that construction quality and improve efficiency of construction.
Brief description
Fig. 1 is the structural representation of split integrated underpass steel formwork trolley in one embodiment of the invention;
Fig. 2 is the structural representation of the frame-type mould plate supporting device being located at right side in one embodiment of the invention;
Fig. 3 is the structural representation being located at middle frame-type mould plate supporting device in one embodiment of the invention;
Fig. 4 is the side view of Fig. 2;
Fig. 5 is the side view of Fig. 3;
Fig. 6 and Fig. 7 be in one embodiment of the invention after tear the structural representation of backform plate supporting device open;
The signal of construction method one embodiment for split of the present invention integrated underpass steel formwork trolley for the Fig. 8 to Figure 10
Figure;
Figure 11 is the schematic diagram of another embodiment of construction method of split of the present invention integrated underpass steel formwork trolley.
Specific embodiment
Below in conjunction with the drawings and specific embodiments to split proposed by the present invention integrated underpass steel formwork trolley and
Its construction method is described in further detail.According to description below and claims, advantages and features of the invention will more
Clear.Hereinafter accompanying drawing will be combined by cited embodiment, describe technology contents and the feature of the present invention in detail.For narration side
Just, described below " on ", D score, "left", "right" consistent with the direction of the upper and lower, left and right of accompanying drawing, but this can not become
The restriction of technical solution of the present invention.Need in addition illustrate, accompanying drawing all in the form of very simplification and all using non-accurately
Ratio, only in order to purpose that is convenient, lucidly aiding in illustrating the embodiment of the present invention.
Embodiment one: with reference to Fig. 1 to Fig. 8, the split of the present invention integrated underpass steel formwork trolley is described, for pacifying
Dress pours the template group of underpass concrete, as shown in figure 1, the steel formwork trolley of the present embodiment includes three along underpass
The frame-type mould plate supporting device that transverse section is arranged in order, is followed successively by frame-type mould plate supporting device 1, framework from right to left
Formula mould plate supporting device 2 200 and frame-type mould plate supporting device 3 300, three frame-type mould plate supporting devices 100,200,
Connected as one by the detachable box-shaped beam 20 of some horizontally sets between 300, and frame-type mould plate supporting device 1
It is mounted on walking mechanism with the bottom of frame-type mould plate supporting device 3 300, above-mentioned walking mechanism being capable of driver framework formula mould
Plate supporting device 100,200,300 is mobile along a pair of the long rails 10 parallel to underpass axis.Specifically, frame-type
The bottom of mould plate supporting device 100,200,300 is respectively provided with eight wheels, and wherein, the frame-type template positioned at outside is propped up
The wheel of support arrangement 1 and frame-type mould plate supporting device 3 300 bottom can slide along long rails 10, the framework of centre
The wheel of formula mould plate supporting device 2 200 bottom is contacted with underpass ground, when improving steel formwork trolley forward movement with this
Stability.The both sides of frame-type mould plate supporting device 2 200 are provided with transverse hydraulic oil cylinder group 204, frame-type shuttering supporting
Device 1 and frame-type mould plate supporting device 3 300, can be along landing under the operational control of transverse hydraulic oil cylinder group 204
Lower channel transverse section is made horizontal direction and is moved, and frame-type mould plate supporting device 100,200,300 can be mounted thereon
Vertically lift under the operational control of vertical hydraulic jack group 105,205,305;
As shown in figure 8, the steel formwork trolley of the present embodiment tears backform plate supporting device 400,500 open after also including two groups, from
Right-to-left tear open after being followed successively by backform plate supporting device 1 and after tear backform plate supporting device 2 500 open, after tear top template open and support dress
Put 1 to be bolted between adjacent frame-type mould plate supporting device 1 and frame-type mould plate supporting device 2 200,
Tear that backform plate supporting device 2 500 is bolted to adjacent frame-type mould plate supporting device 2 200 and frame-type template is propped up afterwards open
Between support arrangement 3 300, after tear the bottom of backform plate supporting device 400,500 open and be provided with and contact with the ground of underpass 50
Universal wheel 402 for walking.
The split integrated underpass steel formwork trolley of the present invention, is that one kind is combined with early-dismantling technology, can
Make the construction equipment of underpass continuous concreting molding.It includes decomposing is propped up with the three frame-type templates combining
Backform plate supporting device is torn open, each frame-type mould plate supporting device can be in the vertical liquid being mounted thereon after support arrangement and two groups
Vertically lift under the operational control of compressing cylinder group, two frame-type mould plate supporting devices positioned at outside can installed
Under the operational control of the transverse hydraulic oil cylinder group on middle frame formula mould plate supporting device, along underpass cross-sectional direction
Move left and right, realize the separation of three frame-type mould plate supporting devices and combination fills so that being installed on frame-type shuttering supporting
The monomer top template putting upper end can vertically lift, and the side template being installed on frame-type mould plate supporting device side can
Make the movement of horizontal direction.Outer profile size after the contraction of frame-type mould plate supporting device is less than the overall size of underpass,
Therefore so that segment template group can pass through with frame-type mould plate supporting device pours under the underpass unit that completes enters
One construction cell.The frame-type mould plate supporting device of the present invention and after tear open backform plate supporting device all can slidably, take up an area
Area is little, and scene dismounting is simple and convenient, participates in construction without hanging device, saves a large amount of manpower and materials;Steel formwork trolley divides
Body moves laterally, and can provide working place for side template, be easy in long narrow underpass, side template is carried out
And coating release agent.
After the reach of frame-type mould plate supporting device, pour to complete to retain two groups in construction cell monomer top template is installed
After tear backform plate supporting device open, reach to tear open again after design requirement intensity after concrete and move to next construction cell, in view of coagulation
Soil pours 3~5 days its intensity up to 50% about, and later strength rise slow characteristic, after tear backform plate supporting device open
Setting can make the monomer top template above it be in short across stress, can make frame-type mould plate supporting device underground lead to
When road concrete strength reaches some strength, you can move to next construction cell and continue construction, realize early form removal construction, reduce
Construction cost, shortens the construction period.
Refer to Fig. 1 and Fig. 8, above-mentioned template group includes top template and side template, top template and side template and underpass
50 profile is adapted, and in the present embodiment, the top template of whole underpass divides from right to left along underpass cross-sectional direction
For five pieces of monomer top templates 110,410,210,510,310, wherein, on three frame-type mould plate supporting devices 100,200,300
It is separately installed with one piece of monomer top template 110,210,310, tear open after two groups and be separately installed with backform plate supporting device 400,500
One piece of monomer top template 410,510.As shown in figure 1, frame-type mould plate supporting device 100,200,300 is provided with vertical hydraulic oil
Cylinder group 105,205,305, can control the monomer top template 110,210,310 of its upper end vertically to lift, frame-type mould
The outside of plate supporting device 1 and frame-type mould plate supporting device 3 300 is respectively provided with one piece of side template 111,311, side form
Plate 111,311 can be installed on taking off outside frame-type mould plate supporting device 1 and frame-type mould plate supporting device 3 300
Stretching, extension and the contraction of horizontal direction, above-mentioned top template are made in the control lower edge underpass transverse section of mould hydraulic jack group 103,303
Tight with side template 111,311 be connected to constitute pour the template group of underpass 50 concrete.The shape of above-mentioned template group and chi
Very little should be determined according to the profile of underpass 50, be not construed as limiting herein.
As shown in Figure 2 and Figure 4, explanation taking the frame-type mould plate supporting device 1 on the right side of steel formwork trolley as a example
Its concrete composition and structure, it includes a framework type base 101, and is connected to the π shape bearing support in framework type base 101
Two parallel longerons 107 are connected with 102, π shape bearing supports 102, monomer top template 110 is assembled on longeron 107.This reality
Apply in example, longeron 107 is made up of H type steel, the connected mode of above-mentioned each component is bolt connection.Vertical hydraulic jack group 105
Monomer top template 110 is driven vertically to lift by π shape bearing support 102.The upper end of side template 111 be fixed on longeron
Turnover hinge bearing 108 pin connection on 107, the right side of frame-type mould plate supporting device 1 be provided with respectively with side template 111
The demoulding hydraulic jack group 103 connecting and support screw group 104.Side template 111 can be in the control of demoulding hydraulic jack group 103
Under make stretching, extension and the contraction of horizontal direction for fulcrum along underpass cross-sectional direction with turnover hinge bearing 108, and by
Support wire bar group 104 fixed bearing.In the present embodiment, the lifting of monomer top template 110 is by positioned at frame-type mould plate supporting device one
Vertical hydraulic jack group 105 operational control at 100 two ends, and by adjustable screw group 109 fixed bearing.In the present embodiment, vertically
Hydraulic jack group 105 is made up of 5 vertical hydraulic jacks, and demoulding hydraulic jack group 103 is made up of 36 hydraulic jacks, supporting wire
Bar group 104 is made up of each 22 laterally adjustable support leading screws up and down, and adjustable screw group 109 is made up of 60 adjustable screws.Similar
, frame-type mould plate supporting device on the left of steel formwork trolley 3 300 and frame-type mould plate supporting device one described previously
100 composition and structure are identical, and here is omitted.
As shown in Figure 3 and Figure 5, and refer to Fig. 1, the both sides of centrally located frame-type mould plate supporting device 2 200
It is mounted on transverse hydraulic oil cylinder group 204, on frame-type mould plate supporting device 1 and frame-type mould plate supporting device 3 300
Bottom near frame-type mould plate supporting device 2 200 side is provided with guide wheel 106, frame-type mould plate supporting device 1 He
Frame-type mould plate supporting device 3 300 can be under the control of transverse hydraulic oil cylinder group 204, and under the guiding of guide wheel 106, edge
The cross track being vertically installed in long rails 10 top to the direction closer or far from frame-type mould plate supporting device 2 200
Mobile.Above-mentioned cross track only moves horizontally frame-type mould plate supporting device 1 and frame-type mould plate supporting device three in need
Lay when 300 temporarily, remove after the completion of moving horizontally.
Tear backform plate supporting device 400,500 composition after two groups open and structure is identical, tear backform plate supporting device open herein later
Describe in detail as a example 400, as shown in Figure 6 and Figure 7, after to tear backform plate supporting device 400 open be by 6 vertical steel pipes and some horizontal strokes
To the steel pipe of steel-pipe welding, its cross section is rectangle.Leading screw group one is passed through in the upper end tearing backform plate supporting device 400 afterwards open
404 are connected with monomer top template 410, after tear the base of backform plate supporting device 400 open and supported by screw mandrel group 2 403, and base
Bottom is provided with the universal wheel 402 for walking.Leading screw group 1 and leading screw group 2 403 are made up of 6 adjustable screws respectively.
When after tear backform plate supporting device 400 open and be bolted to frame-type mould plate supporting device 1 and frame-type mould plate supporting device
After between 2 200, after tear backform plate supporting device 400,500 and adjacent π shape bearing support 102,202 open and adopt steel pipe to make laterally
Connect.In view of 3~5 days its intensity of concreting is up to 50% about, and later strength rise slow characteristic, after tear backform open
The setting of plate supporting device 400,500 can make the monomer top template 410,510 above it be in short across stress, can make
Frame-type mould plate supporting device 100,200,300 is when underpass 50 concrete strength reaches some strength, you can move to down
One construction cell continue construction so that steel formwork trolley can do sth. in advance 10~15 heaven-made vertically move, realize morning form removal and construct.
Above-mentioned walking mechanism includes wheel, motor, decelerator and brake gear (not shown), and wheel is disposed along ground
On the long rails 10 of lower channel 50 axis direction laying, long rails 10 play the effect of load-bearing and guiding.Walking mechanism is by electricity
Motivation drives, and motor is through planet pendulum pin type decelerator speed governing, and passes through chain-driving vehicle wheel rotation so that wheel is along longitudinal direction
Track 10 is advanced, and brake gear is capable of the direction of effective control wheel advance.
The width of steel formwork trolley is equal to the width of pre- underpass 50 of constructing, and is 25m~30m, and its width can basis
The length that job requirements change box-shaped beam 20 carries out appropriate folding and unfolding adjustment.The height of steel formwork trolley can pass through π shape bearing support
102nd, 202,302 lifting is vertically adjusted, and the height of steel formwork trolley reaches as high as 8m.The length of steel formwork trolley is permissible
It is adjusted according to job requirements, structure identical at least two steel formwork trolley unit can be divided into, and bolt at the construction field (site)
Link into an integrated entity, each steel formwork trolley element length is 12.5m~15m, and whole steel formwork trolley is the longest to reach 30m.
Embodiment two: with reference to Fig. 8 to Figure 10, and referring to figs. 1 to Fig. 7, the split of the present invention integrated underpass steel is described
The construction method of formwork jumbo, specifically comprises the following steps that
Step one: template group is arranged on steel formwork trolley, and is arranged in order three frames along underpass 50 transverse section
Posture mould plate supporting device 100,200,300, three frame-type mould plate supporting devices 100,200,300 reach assignment position
Afterwards, its lengthwise position is connected using detachable box-shaped beam 20 up and down, and is stably and firmly located in underpass 50, framework
Formula mould plate supporting device 100,200,300 after vertical hydraulic jack group 105,205,305 is adjusted to calibrated altitude, adjacent
Two frame-type mould plate supporting devices 100,200,300 between tear backform plate supporting device 400,500 open after bolt connection, make frame
Posture mould plate supporting device 100,200,300 and after tear on backform plate supporting device 400,500 5 pieces of fixing monomer top templates open
110th, 410,210,510,310 it is located at same level, then, progressively carry out concrete in the construction cell of underpass 50
Pouring construction;
Step 2: when the concrete of current construction cell reaches some strength, as shown in figure 9, in transverse hydraulic oil cylinder
Under the control of group 204 and vertical hydraulic jack group 105,205,305, make on frame-type mould plate supporting device 100,200,300
Three pieces of monomer top templates 110,210,310 decline, and the side template 111,311 of both sides shrinks, and tear top template open after unclamping two groups and prop up
The connection of support arrangement 400,500 and frame-type mould plate supporting device 100,200,300, as shown in Figure 10, frame-type after contraction
The outer profile size of mould plate supporting device 100,200,300 is less than the overall size of underpass 50 so that it can be in walking
The underpass 50 that is driven through of mechanism enters next construction cell;Now, frame-type mould plate supporting device 100,200,300
Front end leave upper and lower two box-shaped beams 20, to ensure the globality of frame-type mould plate supporting device 100,200,300, and tear open
Except the box-shaped beam 20 of other positions is so that when frame-type mould plate supporting device 100,200,300 moves forward, can tear top open after getting around
Mould plate supporting device 400,500 is smooth to enter next construction cell.
Step 3: after the concrete strength of current construction cell reaches design requirement, then by after tear open top template support dress
Put 400,500 and move to next construction cell, be connected with frame-type mould plate supporting device 100,200,300, form punching block again
Pallet car, carry out next construction cell pours operation.Above-mentioned concrete strength design requirement refers to that concrete strength meets
The regulation of " concrete structure engineering construction quality accident specification ".
The construction method of the split integrated underpass steel formwork trolley of the present invention, first, tears top template open by after two groups
Support meanss are bolted between adjacent two frame-type mould plate supporting device respectively, form steel formwork trolley, contentedly
The pouring construction of lower channel concrete, whne concrete strength reach necessarily require when, frame-type mould plate supporting device is in hydraulic pressure system
Shrink in the presence of system so that its can before move up into next construction cell, and recover original extended configuration, tear open after reservation
Backform plate supporting device is then after underpass concrete reaches design requirement, then removes next construction cell of entrance, with framework
Formula mould plate supporting device is assembled into the pouring construction that steel formwork trolley carries out concrete again.By the construction method of the present invention,
Not only can make underpass continuous concreting molding, and due to after tear the presence of backform plate supporting device open, frame can be made
Posture mould plate supporting device is when underpass concrete strength reaches some strength, you can moves to next construction cell and continues
Construction so that steel formwork trolley can do sth. in advance 10~15 heaven-made vertically move, realize early form removal and construct, decrease construction cost, contract
The short construction period, and ensure that construction quality and improve efficiency of construction.
Preferably, in above-mentioned steps two, when underpass 50 concrete strength reaches the 60%~70% of design requirement,
The top template 110,210,310 on frame-type mould plate supporting device 100,200,300 is made to decline, the side template 111,311 of both sides
Shrink, and pass through underpass 50 to enter next construction cell.
Embodiment three: combine Figure 11, and refering to Fig. 1 to Figure 10, the split of the present invention integrated underpass steel form is described
The construction method of chassis, from unlike embodiment two, the present embodiment is that have some bend segmental arc situations in underpass 50
Under pouring construction operation, as shown in figure 11, when the bend segmental arc having radius r to reach 400m in underpass, by punching block pallet
Car resolves into the steel formwork trolley unit 1 that length l is 12.5m length, and the box-shaped beam 20 on steel formwork trolley is removed, and directly will
Three frame-type mould plate supporting device 100,200,300 bolt connections become an entirety so that steel formwork trolley narrowed width, just
In moving forward along bend segmental arc in underpass 50, because steel formwork trolley shortens so that underground after concreting
The profile of the bend segmental arc of passage 50 can be closer to the arc shape of design requirement.The construction method of the present embodiment, by three frames
The direct bolt connection of posture mould plate supporting device, its narrowed width, to meet, there is pouring of bend segmental arc underpass concrete
Build construction, flexible operation, can treatment in accordance with local conditions so that the suitability of steel formwork trolley of the present invention is higher.
Foregoing description is only the description to present pre-ferred embodiments, not any restriction to the scope of the invention, this
Any change that the those of ordinary skill in bright field does according to the disclosure above content, modification, belong to the protection of claims
Scope.
Claims (10)
1. split integrated underpass steel formwork trolley, for installing the template group pouring described underpass concrete, its
It is characterised by, comprising:
At least three frame-type mould plate supporting devices being arranged in order along described underpass transverse section, described frame-type template is propped up
Support arrangement is connected as one by some detachable box-shaped beams, and the bottom of described frame-type mould plate supporting device is provided with row
Walk mechanism, described walking mechanism can drive described frame-type mould plate supporting device along indulging parallel to described underpass axis
Move to track, positioned at the both sides of the described frame-type mould plate supporting device at middle part, transverse hydraulic oil cylinder group is installed, positioned at outer
Two described frame-type mould plate supporting devices of side, can be along described under the operational control of described transverse hydraulic oil cylinder group
Lower channel transverse section is made horizontal direction and is moved, and described frame-type mould plate supporting device can be in the vertical hydraulic pressure being mounted thereon
Vertically lift under the operational control of oil cylinder group;
Tear backform plate supporting device after at least two groups open, described after tear backform plate supporting device open and be bolted to two neighboring institute respectively
State between frame-type mould plate supporting device, described after tear open backform plate supporting device bottom be provided with for walking universal wheel.
2. the integrated underpass steel formwork trolley of split according to claim 1 it is characterised in that: described template group bag
Include the top template that can be closely connected and side template, described top template mutually can be fitted with the profile of described underpass with side template
Should, described top template is to be spliced by some monomer top templates, described frame-type mould plate supporting device and described after tear backform open
The top of plate supporting device is respectively fixed with one piece of monomer top template, positioned at two described frame-type mould plate supporting devices of both sides
Outside be respectively articulated with one piece of side template.
3. the integrated underpass steel formwork trolley of split according to claim 2 is it is characterised in that be located at described punching block
The described frame-type mould plate supporting device of pallet car both sides includes:
One framework type base, the outside of described framework type base is provided with the demoulding hydraulic jack group being connected respectively with described side template
With support screw group;
One π shape bearing support, described π shape bearing support is bolted in described framework type base, and described π shape bearing support sets
There are two parallel longerons, described monomer top template is arranged on described longeron, is installed on vertical in described framework type base
Hydraulic jack group can control described π shape bearing support vertically to lift;
Described longeron is hinged with described side template by side template turnover hinge bearing, and described side template is in described demoulding hydraulic oil
Shunk centered on described side template turnover hinge bearing under the control of cylinder group and launch, and solid by the adjustment of described support screw group
Fixed.
4. the integrated underpass steel formwork trolley of the split according to any one of claims 1 to 3 it is characterised in that: position
In the bottom of the described frame-type mould plate supporting device of described steel formwork trolley both sides, guide wheel is installed, positioned at the described frame at middle part
The both sides of posture mould plate supporting device are mounted on transverse hydraulic oil cylinder group, and the described frame-type mould plate supporting device of both sides is in institute
State under the control of transverse hydraulic oil cylinder group, and under the guiding of described guide wheel, can be along being vertically installed in described long rails
The cross track of top moves to the direction closer or far from described steel formwork trolley axis.
5. the integrated underpass steel formwork trolley of the split according to any one of claim 2 to 3 it is characterised in that: institute
Tearing backform plate supporting device after stating open is the frame structure being formed by connecting by some steel pipe, described after tear backform plate supporting device open
Top is connected with described monomer top template by screw mandrel group one, described after tear the base of backform plate supporting device open by screw mandrel group two
Hold, and the bottom of described base is provided with the universal wheel for walking.
6. the integrated underpass steel formwork trolley of the split according to any one of claims 1 to 3 it is characterised in that: institute
State walking mechanism and include wheel, motor, decelerator and brake gear, described wheel is disposed along described underpass axis direction
Laying described long rails on, described walking mechanism by described motor-driven, described motor through described decelerator speed governing,
And by vehicle wheel rotation described in chain-driving so that described wheel can move along described long rails.
7. the integrated underpass steel formwork trolley of split according to claim 3 it is characterised in that: described punching block pallet
The width of car is equal to the width of the described underpass of pre- construction, and can be adjusted by changing the length of described box-shaped beam
Whole, the height of described steel formwork trolley can be adjusted by the lifting of described π shape bearing support, described steel formwork trolley edge
The axis direction of described underpass is divided into structure identical at least two steel formwork trolley unit, and bolt connection is integrated,
Each described steel formwork trolley element length is 12.5m~15m.
8. the construction method of the integrated underpass of the split as described in any one of claim 2 to 7 steel formwork trolley, step is such as
Under:
Step one: described template group is arranged on described steel formwork trolley, is arranged in order institute along described underpass transverse section
State frame-type mould plate supporting device, and connected by described box-shaped beam, described frame-type mould plate supporting device passes through described vertical
After hydraulic jack group is adjusted to calibrated altitude, described in bolt connection between two adjacent described frame-type mould plate supporting devices
After tear backform plate supporting device open, make described frame-type mould plate supporting device and described after tear on backform plate supporting device fixing institute open
State monomer top template and be located at same level, and progressively carry out concreting in the construction cell of described underpass and apply
Work;
Step 2: when the concrete of current construction cell reaches some strength, in described transverse hydraulic oil cylinder group and described perpendicular
To under the control of hydraulic jack group, the described monomer top template on described frame-type mould plate supporting device is made to decline, described side form
Plate shrinks, and the connection tearing open between backform plate supporting device and described frame-type mould plate supporting device after unclamping described in two groups, institute
State the outer profile size after frame-type mould plate supporting device shrinks and be less than the overall size of described underpass so that described framework
Formula mould plate supporting device can enter next construction cell through described underpass;
Step 3: after the concrete strength of described current construction cell reaches design requirement, then will be described after tear top template open and prop up
Support arrangement moves to next construction cell, is connected with described frame-type mould plate supporting device, forms described steel formwork trolley again,
Carry out next construction cell pours operation.
9. construction method according to claim 8 it is characterised in that: in described step 2, when described underpass is current
When the concrete strength of construction cell reaches the 60%~70% of design requirement, make the list on described frame-type mould plate supporting device
Body top template and side template shrink, and enter next construction cell through described underpass.
10. construction method according to claim 8 it is characterised in that: when described underpass has bend segmental arc, will
Described steel formwork trolley resolves into the steel formwork trolley unit that length is 12.5m~15m, and each described steel formwork trolley unit is
Direct for described frame-type mould plate supporting device bolt connection is formed.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201410852859.5A CN104594918B (en) | 2014-12-31 | 2014-12-31 | Split integrated underground passage steel mold plate trolley and construction method thereof |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201410852859.5A CN104594918B (en) | 2014-12-31 | 2014-12-31 | Split integrated underground passage steel mold plate trolley and construction method thereof |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN104594918A CN104594918A (en) | 2015-05-06 |
| CN104594918B true CN104594918B (en) | 2017-01-18 |
Family
ID=53120927
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201410852859.5A Active CN104594918B (en) | 2014-12-31 | 2014-12-31 | Split integrated underground passage steel mold plate trolley and construction method thereof |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN104594918B (en) |
Families Citing this family (15)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN105041339B (en) * | 2015-07-28 | 2017-12-26 | 上海市机械施工集团有限公司 | Disengaging type formwork jumbo, chassis component and underpass concrete construction method |
| CN105216101B (en) * | 2015-10-10 | 2018-08-21 | 山东铁鹰建设工程有限公司 | A kind of self-propelled hydraulic T-type beam prefabricated form device and its release method |
| CN105401960B (en) * | 2015-10-12 | 2018-03-20 | 中铁十九局集团第六工程有限公司 | A kind of mould bases and its construction method for the construction of railway tunnel inverted arch |
| CN106437769B (en) * | 2016-11-09 | 2018-06-01 | 辽宁工程技术大学 | The self-propelled hydraulic formwork jumbo poured for Deep Foundation Pit of Metro Stations engineering top plate |
| CN107165193A (en) * | 2017-07-17 | 2017-09-15 | 中建三局第三建设工程有限责任公司 | A kind of fabricated construction mobile formwork |
| CN107630463A (en) * | 2017-09-19 | 2018-01-26 | 洛阳高飞桥隧机械有限公司 | A kind of construction technology of underground pipe gallery construction mobile jumbo device |
| CN107761583A (en) * | 2017-10-18 | 2018-03-06 | 宁夏宁博通模板有限责任公司 | A kind of adjustable box culvert internal model branch tears system open |
| CN107905818B (en) * | 2017-12-11 | 2019-12-27 | 李信斌 | Tunnel concrete lining construction auxiliary equipment and construction process |
| CN110682417A (en) * | 2018-07-04 | 2020-01-14 | 任丘市永基建筑安装工程有限公司 | Vertical combined stair board mould equipment |
| CN109356616A (en) * | 2018-11-02 | 2019-02-19 | 广州市高速公路有限公司 | Subsidence-style tunnel roof plate template trolley device |
| CN110065148B (en) * | 2019-05-31 | 2024-03-22 | 中交武汉港湾工程设计研究院有限公司 | Novel immersed tube tunnel pipe section prefabricated traffic lane centre form platform truck is walked device |
| CN110242330B (en) * | 2019-07-18 | 2024-10-01 | 中铁隧道局集团有限公司 | Movable type can Adjustable grouting template |
| CN112171865A (en) * | 2020-09-25 | 2021-01-05 | 广东欣龙隧道装备股份有限公司 | Trolley convenient for mold erecting and demolding and use method |
| CN114412516A (en) * | 2022-03-11 | 2022-04-29 | 中建三局集团有限公司 | A kind of equipment and construction method for steel formwork trolley for low headroom air duct plate in underground passage |
| CN117108005A (en) * | 2023-09-08 | 2023-11-24 | 巢势科技(上海)有限公司 | An intelligent construction trolley for platform canopies |
Citations (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US2139078A (en) * | 1935-10-18 | 1938-12-06 | William A Gurtler | Concrete form |
| CN202810870U (en) * | 2012-09-06 | 2013-03-20 | 成都市新筑路桥机械股份有限公司 | Combined type template trolley for box culvert lining |
| CN103806926A (en) * | 2014-03-07 | 2014-05-21 | 陕西理工学院 | Span-changing and height-changing device of concrete lining steel bench vehicle |
| CN104234723A (en) * | 2014-07-23 | 2014-12-24 | 中建三局集团有限公司 | Self-propelled mobile template support trolley for open trench tunnel with rectangular cross section |
Family Cites Families (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP3316136B2 (en) * | 1996-07-02 | 2002-08-19 | 株式会社栗本鐵工所 | Repair units for existing waterways and their repair methods |
| JP5619646B2 (en) * | 2011-02-04 | 2014-11-05 | 大成建設株式会社 | Construction method of underground structure and underground structure |
-
2014
- 2014-12-31 CN CN201410852859.5A patent/CN104594918B/en active Active
Patent Citations (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US2139078A (en) * | 1935-10-18 | 1938-12-06 | William A Gurtler | Concrete form |
| CN202810870U (en) * | 2012-09-06 | 2013-03-20 | 成都市新筑路桥机械股份有限公司 | Combined type template trolley for box culvert lining |
| CN103806926A (en) * | 2014-03-07 | 2014-05-21 | 陕西理工学院 | Span-changing and height-changing device of concrete lining steel bench vehicle |
| CN104234723A (en) * | 2014-07-23 | 2014-12-24 | 中建三局集团有限公司 | Self-propelled mobile template support trolley for open trench tunnel with rectangular cross section |
Also Published As
| Publication number | Publication date |
|---|---|
| CN104594918A (en) | 2015-05-06 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN104594918B (en) | Split integrated underground passage steel mold plate trolley and construction method thereof | |
| CN103015325B (en) | Construction method of cast-in-place concrete crash barrier with eaves | |
| CN103452052B (en) | Movable mold hanging equipment for closing swivel bridges and closure section construction method | |
| CN106089253B (en) | A kind of all-hydraulic template system poured for culvert | |
| CN107338727B (en) | Integrally-disassembled and assembled anti-collision wall template and walking type rail hanging and moving system thereof | |
| CN102296971B (en) | A lining method for a tunnel emergency avoidance zone and a tunnel lining trolley | |
| CN113235472B (en) | A trolley for pouring concrete for slab culvert | |
| CN105155423A (en) | Upward moving type movable formwork for continuous box girder construction | |
| CN106120563A (en) | Cast-in-situ box girder Combined movable mould bases and construction method thereof | |
| CN107060823B (en) | Non-dismantling trolley for tunnel anchor section secondary lining concrete construction | |
| CN105952482A (en) | Self-propelled tunnel invert lining trolley | |
| CN207944955U (en) | Tunnel widening section second lining trolley | |
| CN109629439B (en) | Construction method of single-tower cable-stayed bridge | |
| CN106593469A (en) | Trolley for construction of inverted arch | |
| CN103982200B (en) | Slide rail Mobile steel mould trolley in tunneling boring | |
| CN212867563U (en) | A double-lined trolley with a super large section of a tunnel that can be widened multiple times | |
| CN113882286A (en) | Bridge dismantling and building all-in-one machine and spanning method thereof, bridge dismantling method and new building method | |
| CN114575892B (en) | Off-wall vault lining trolley and construction method thereof | |
| CN206035507U (en) | Rectangle box culvert and for tunnel construction platform truck | |
| CN102660925A (en) | Moveable formwork for variable-width curved bridge | |
| CN105970822A (en) | A 50m double-width upward mobile formwork and its corresponding beam-making construction method | |
| CN103388305A (en) | Railway T-beam cast-in-site bridge deck forming machine | |
| CN104453951B (en) | Combined type subway station lining template trolley for baffle | |
| CN105133497B (en) | A kind of construction method being inclined cross low clearance active service highway multi-azimuth adjustable cast-in-place box beam bracket system | |
| CN208844612U (en) | A kind of stalk vaulted type open trench tunnel main body construction mobile formwork |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C06 | Publication | ||
| PB01 | Publication | ||