CN113393212A - Outer wall spraying engineering project management platform and management method - Google Patents

Outer wall spraying engineering project management platform and management method Download PDF

Info

Publication number
CN113393212A
CN113393212A CN202110664633.2A CN202110664633A CN113393212A CN 113393212 A CN113393212 A CN 113393212A CN 202110664633 A CN202110664633 A CN 202110664633A CN 113393212 A CN113393212 A CN 113393212A
Authority
CN
China
Prior art keywords
project
robot
labor
budget
task execution
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202110664633.2A
Other languages
Chinese (zh)
Inventor
路可可
正端
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhucheng Technology Shenzhen Co ltd
Original Assignee
Zhucheng Technology Shenzhen Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhucheng Technology Shenzhen Co ltd filed Critical Zhucheng Technology Shenzhen Co ltd
Priority to CN202110664633.2A priority Critical patent/CN113393212A/en
Publication of CN113393212A publication Critical patent/CN113393212A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0639Performance analysis of employees; Performance analysis of enterprise or organisation operations
    • G06Q10/06398Performance of employee with respect to a job function

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Strategic Management (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Economics (AREA)
  • Physics & Mathematics (AREA)
  • Development Economics (AREA)
  • Marketing (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Tourism & Hospitality (AREA)
  • Educational Administration (AREA)
  • General Business, Economics & Management (AREA)
  • General Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Game Theory and Decision Science (AREA)
  • Data Mining & Analysis (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention provides an outer wall spraying project management platform and a management method, wherein the outer wall spraying project management platform comprises a project management module and a service management module, wherein the project management module is used for decomposing project engineering quantity into a plurality of tasks and setting associated project members for each task; and the service management module sends the task requirements to the project members, and sends corresponding task execution records to the project management module after the project members upload the task execution records. The invention has the beneficial effects that: the utility model provides an outer wall engineering project management platform can conveniently realize the construction project management to the outer wall engineering through this platform, can be according to specific conditions for every task rational distribution project member's constitution, can be applicable to pure robot, pure manual work, the project management of artifical and robot mixed construction, through the evaluation system, can find more suitable labor worker fast to the reason of the robot that analysis efficiency is low, can know the construction progress of project more clearly through the decomposition to the project engineering volume.

Description

Outer wall spraying engineering project management platform and management method
Technical Field
The invention relates to the technical field of computers, in particular to an outer wall spraying engineering project management platform and a management method.
Background
Most of the existing building engineering project management adopts a traditional and extensive management mode, and depends on manual on-site investigation, manual recording and manual collection modes, so that the management is time-consuming and labor-consuming, the problems of file loss, calculation errors and the like easily occur, the problems of the material purchase, personnel allocation, equipment allocation, labor management and the like exist at the bottom of the working efficiency, the overall informatization degree of the industry is low, and the engineering project is difficult to realize accurate management.
Disclosure of Invention
The technical problem to be solved by the invention is as follows: an outer wall spraying project management platform and a management method based on coating robot construction are provided.
In order to solve the technical problems, the invention adopts the technical scheme that: an outer wall spraying project management platform comprises a project management module and a service management module,
the project management module is used for realizing information maintenance of project contracts, project basic information and project engineering quantities, decomposing the project engineering quantities into a plurality of tasks according to the project basic information and setting associated project members for each task;
the service management module is used for registering and recording basic information of project members, sending task requirements to the project members according to task setting of the project management module, and sending corresponding task execution records to the project management module after the project members upload the task execution records.
Further, the method comprises the following steps: the service management module specifically comprises a robot management submodule and a labor worker management submodule,
the robot management submodule is used for inputting basic information of the robot, receiving a robot task execution record uploaded by the robot and sending the corresponding robot task execution record to the project management module;
the labor worker management submodule is used for inputting basic information of labor workers, performing team assignment on the labor workers, assigning designated responsible persons, receiving task execution records uploaded by the responsible persons and sending corresponding task execution records of the labor workers to the project management module.
And further, the robot management submodule is also used for analyzing the construction efficiency of the robot according to the execution record of the robot task, judging whether the construction efficiency of the robot is normal or not, if not, generating a maintenance list and sending the maintenance list to a robot manufacturer.
The system further comprises a budget management module, wherein the budget management module is used for calculating the total budget of the project according to the material budget and the labor budget of each task, and the labor budget is the robot construction budget or the labor worker budget or the combined construction budget of the robot construction and the labor worker construction.
The evaluation module is used for carrying out statistical analysis according to the robot task execution records or the labor worker task execution records and assessing project members according to the statistical analysis result.
Furthermore, the labor worker management submodule is also used for managing and recording the attendance checking condition of the labor worker.
The invention also relates to an outer wall engineering project management method, which comprises the following steps:
decomposing project engineering quantity into a plurality of tasks according to the project basic information, and setting a related project member for each task;
and sending a task requirement to the project member according to the task setting of the project management module, and sending a corresponding task execution record to the project management module after the project member uploads the task execution record.
Further, the task execution records comprise robot task execution records, and the method further comprises analyzing the robot construction efficiency according to the robot task execution records, judging whether the robot construction efficiency is normal, if not, generating a maintenance list, and sending the maintenance list to a robot manufacturer.
Further, the method comprises the step of calculating the total budget of the project according to the material budget and the labor budget of each task, wherein the labor budget is the robot construction budget or the labor worker budget or the combined construction budget of the robot construction and the labor worker construction.
Further, the method further comprises the steps of carrying out statistical analysis according to the robot task execution records or the labor worker task execution records, and examining project members according to the statistical analysis results.
The invention has the beneficial effects that: the utility model provides an outer wall spraying engineering project management platform and management method, can conveniently realize the construction project management to the outer wall engineering through this platform, can be according to the constitution of each task rational allocation project member of particular case, can be applicable to the project management of pure robot, pure manual work, manual work and robot mixed construction, through the evaluation system, can find more suitable labor worker fast, and the reason of the robot of analysis inefficiency, can know the construction progress of project more clearly through the decomposition to the project engineering volume.
Drawings
The specific structure and process of the present invention are detailed below with reference to the accompanying drawings:
FIG. 1 is a system architecture diagram of the present invention;
FIG. 2 is a schematic flow chart of the present invention.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
In the description of the present invention, it is to be understood that the terms "center", "longitudinal", "lateral", "length", "width", "thickness", "upper", "lower", "front", "rear", "left", "right", "vertical", "horizontal", "top", "bottom", "inner", "outer", "clockwise", "counterclockwise", and the like, indicate orientations and positional relationships based on those shown in the drawings, and are used only for convenience of description and simplicity of description, and do not indicate or imply that the device or element being referred to must have a particular orientation, be constructed and operated in a particular orientation, and thus, should not be considered as limiting the present invention.
Furthermore, the terms "first", "second" and "first" are used for descriptive purposes only and are not to be construed as indicating or implying relative importance or implicitly indicating the number of technical features indicated. Thus, a feature defined as "first" or "second" may explicitly or implicitly include one or more features. In the description of the present invention, "a plurality" means two or more unless specifically defined otherwise.
In the present invention, unless otherwise expressly stated or limited, the terms "mounted," "connected," "secured," and the like are to be construed broadly and can, for example, be connected or detachably connected or integrated; can be mechanically or electrically connected; either directly or indirectly through intervening media, either internally or in any other relationship. The specific meanings of the above terms in the present invention can be understood by those skilled in the art according to specific situations.
In the present invention, unless otherwise expressly stated or limited, "above" or "below" a first feature means that the first and second features are in direct contact, or that the first and second features are not in direct contact but are in contact with each other via another feature therebetween. Also, the first feature being "on," "above" and "over" the second feature includes the first feature being directly on and obliquely above the second feature, or merely indicating that the first feature is at a higher level than the second feature. A first feature being "under," "below," and "beneath" a second feature includes the first feature being directly under and obliquely below the second feature, or simply meaning that the first feature is at a lesser elevation than the second feature.
In the description herein, references to the description of the term "one embodiment," "some embodiments," "an example," "a specific example," or "some examples," etc., mean that a particular feature, structure, material, or characteristic described in connection with the embodiment or example is included in at least one embodiment or example of the invention. In this specification, the schematic representations of the terms used above should not be understood to necessarily refer to the same embodiment or example. Furthermore, the particular features, structures, materials, or characteristics described may be combined in any suitable manner in any one or more embodiments or examples. Furthermore, various embodiments or examples described in this specification can be combined and combined by those skilled in the art.
Example 1
Referring to fig. 1, a project management platform for exterior wall painting projects includes a project management module and a service management module,
the project management module is used for realizing information maintenance of project contracts, project basic information and project engineering quantities, inputting the project contracts into an outer wall spraying project management platform through the project management module to generate corresponding projects, and inputting the project basic information into the corresponding projects.
The project management module decomposes project engineering quantity into a plurality of tasks according to project basic information, sets related project members for each task, specifically, records projects according to operation surfaces according to actual field conditions of the project engineering quantity, groups the operation surfaces according to buildings to form a multi-level structure of project-building-operation surfaces, facilitates subsequent construction management, records operation surface names and construction areas simultaneously, distributes the project members for each operation surface, and marks the project members as manual construction or robot construction or combined construction of manual and robot.
And the service management module sends task requirements to the project members according to the task setting of the project management module, and sends corresponding task execution records to the project management module after the project members upload the task execution records.
Specifically, the service management module is used for registering basic information of the input project members, the service management module specifically comprises a robot management submodule and a labor worker management submodule,
and the robot management submodule is used for inputting basic information of the robot.
After the robot is produced, the robot is numbered according to rules, and relevant basic information of the robot is input into the platform through the robot management submodule, so that the registration of the robot is completed.
And in the construction process or after the construction is finished, the robot management submodule is responsible for receiving the robot task execution record uploaded by the robot and sending the corresponding robot task execution record to the project management module, and the project management platform can display the current construction condition to a project chief responsible person according to the robot task execution record, acquire project progress information and facilitate command and decision. The robot carries out uploading of robot task execution records through wifi or a mobile communication network, wherein the robot task execution records include robot working data and external environment data, and the external environment data include but are not limited to temperature data acquired through a temperature sensor, humidity data acquired through a humidity sensor, wind speed and direction data acquired through a wind direction sensor and video data provided when necessary.
After the robot construction is completed, a project manager or project manager can grade the working face of the robot.
The labor worker management submodule is used for inputting basic information of labor workers, performing team distribution on the labor workers, designating team managers, uploading task execution records of the labor workers by receiving the managers and sending corresponding task execution records of the labor workers to the project management module.
The labor worker management submodule can realize the roster management of labor workers, the identity card photos of the labor workers are uploaded through the WeChat applet terminal, the basic information of the labor workers is identified by using an OCR technology, and the registration management of the labor workers is completed.
And (4) performing team distribution on labor workers, and designating a team leader to realize team in-out management.
The labor worker management submodule is also used for managing and recording the work worker attendance conditions and recording the attendance conditions into the evaluation of the labor workers.
After the labor workers finish the work, the crew leader can report the task execution record of the labor workers through the WeChat applet.
The engineering project management platform further comprises an evaluation module, wherein the evaluation module is used for carrying out statistical analysis according to the robot task execution record or the labor worker task execution record and assessing project members according to the statistical analysis result.
Specifically, the robot management submodule is further used for analyzing the robot construction efficiency according to the robot task execution record, judging whether the robot construction efficiency is normal or not by combining the working environment of the robot and scoring after construction is completed, if the robot construction efficiency is abnormal, the scoring is too low, the robot management submodule generates a maintenance list and sends the maintenance list to a robot manufacturer, and an engineer is arranged by the manufacturer to intervene to search for reasons or return to the manufacturer for maintenance.
After the construction of the labor workers is completed, the project manager or the project manager can grade the working face of the labor workers, and in the subsequent assignment of the construction tasks, the labor workers or the teams with high grades can be preferentially selected.
The project management platform further comprises a budget management module, wherein the budget management module is used for calculating the total budget of the project according to the material budget and the labor budget of each task, and the labor budget is the robot construction budget or the labor worker budget or the combined construction budget of the robot construction and the labor worker construction.
According to different characteristics of manual construction and robot construction, the labor budget of each task is calculated, the total budget of the project can be obtained by combining the material budget of each task, and project management personnel and company leaders can more conveniently know whether the total budget and actual expenditure are in or out.
And the project management module is also used for judging whether the tasks related to the current project engineering quantity are completely finished according to the task execution records, and archiving the task execution records of all the tasks related to the current project engineering quantity if the tasks related to the current project engineering quantity are completely finished.
From the above description, the beneficial effects of the present invention are: the utility model provides an outer wall engineering project management platform can conveniently realize the construction project management to the outer wall engineering through this platform, can be according to specific conditions for every task rational distribution project member's constitution, can be applicable to pure robot, pure manual work, the project management of artifical and robot mixed construction, through the evaluation system, can find more suitable labor worker fast to the reason of the robot that analysis efficiency is low, can know the construction progress of project more clearly through the decomposition to the project engineering volume.
Example 2
Referring to fig. 2, the present invention further relates to an exterior wall engineering project management method, including:
decomposing project engineering quantity into a plurality of tasks according to the project basic information, and setting a related project member for each task;
the project management module decomposes project engineering quantity into a plurality of tasks according to project basic information, sets related project members for each task, specifically, records projects according to operation surfaces according to actual field conditions of the project engineering quantity, groups the operation surfaces according to buildings to form a multi-level structure of project-building-operation surfaces, facilitates subsequent construction management, records operation surface names and construction areas simultaneously, distributes the project members for each operation surface, and marks the project members as manual construction or robot construction or combined construction of manual and robot.
Sending task requirements to project members according to task setting of a project management module, and sending corresponding task execution records to the project management module after the project members upload the task execution records;
the service management module specifically comprises a robot management submodule and a labor worker management submodule, wherein the robot management submodule is used for inputting basic information of the robot, receiving a robot task execution record uploaded by the robot and sending a corresponding robot task execution record to the project management module; the labor worker management submodule is used for inputting basic information of labor workers, performing team distribution on the labor workers, designating team managers, uploading task execution records of the labor workers by receiving the managers and sending corresponding task execution records of the labor workers to the project management module.
And judging whether the tasks associated with the current project engineering quantity are completely finished or not according to the task execution records, and archiving the task execution records of all the tasks associated with the current project engineering quantity if the tasks associated with the current project engineering quantity are completely finished.
When a plurality of tasks related to the current project engineering quantity are completely finished, filing the task execution records of all tasks related to the current project engineering quantity and timely informing project management personnel and company leaders.
And the task execution records comprise robot task execution records, the robot construction efficiency is analyzed according to the robot task execution records, whether the robot construction efficiency is normal or not is judged, if not, a maintenance list is generated, and the maintenance list is sent to a robot manufacturer.
And calculating the total budget of the project according to the material budget and the labor budget of each task, wherein the labor budget is the robot construction budget or the labor worker budget or the combined construction budget of the robot construction and the labor worker construction.
According to different characteristics of manual construction and robot construction, the labor budget of each task is calculated, the total budget of the project can be obtained by combining the material budget of each task, and project management personnel and company leaders can more conveniently know whether the total budget and actual expenditure are in or out.
And carrying out statistical analysis according to the robot task execution record or the labor worker task execution record, and assessing the project members according to the statistical analysis result.
After the construction of the labor workers is completed, the project manager or the project manager can grade the working face of the labor workers, and in the subsequent assignment of the construction tasks, the labor workers or the teams with high grades can be preferentially selected.
After the robot construction is completed, the robot construction efficiency is analyzed according to the robot task execution record, whether the robot construction efficiency is normal or not is judged by combining the working environment of the robot and the score after the construction is completed, and if the robot construction efficiency is not normal, the robot can be timely maintained to ensure the smooth completion of the construction work.
The above description is only an embodiment of the present invention, and not intended to limit the scope of the present invention, and all modifications of equivalent structures and equivalent processes performed by the present specification and drawings, or directly or indirectly applied to other related technical fields, are included in the scope of the present invention.

Claims (10)

1. The utility model provides an outer wall spraying engineering project management platform which characterized in that: comprises an item management module and a service management module,
the project management module is used for realizing information maintenance of project contracts, project basic information and project engineering quantities, decomposing the project engineering quantities into a plurality of tasks according to the project basic information and setting associated project members for each task;
the service management module is used for registering and recording basic information of project members, sending task requirements to the project members according to task setting of the project management module, and sending corresponding task execution records to the project management module after the project members upload the task execution records.
2. The exterior wall painting project management platform of claim 1, wherein: the service management module specifically comprises a robot management submodule and a labor worker management submodule,
the robot management submodule is used for inputting basic information of the robot, receiving a robot task execution record uploaded by the robot and sending the corresponding robot task execution record to the project management module;
the labor worker management submodule is used for inputting basic information of labor workers, performing team assignment on the labor workers, assigning designated responsible persons, receiving task execution records uploaded by the responsible persons and sending corresponding task execution records of the labor workers to the project management module.
3. The exterior wall painting project management platform of claim 2, wherein: and the robot management submodule is also used for analyzing the robot construction efficiency according to the robot task execution record, judging whether the robot construction efficiency is normal or not, if not, generating a maintenance list and sending the maintenance list to a robot manufacturer.
4. The exterior wall painting project management platform of claim 3, wherein: the system further comprises a budget management module, wherein the budget management module is used for calculating the total budget of the project according to the material budget and the labor budget of each task, and the labor budget is the robot construction budget or the labor worker budget or the combined construction budget of the robot construction and the labor worker construction.
5. The exterior wall painting project management platform of claim 4, wherein: the evaluation module is used for carrying out statistical analysis according to the robot task execution records or the labor worker task execution records and assessing project members according to the statistical analysis result.
6. The exterior wall painting project management platform of claim 5, wherein: the labor management submodule is also used for managing and recording the attendance checking condition of labor workers.
7. A management method for an outer wall spraying project comprises the following steps:
decomposing project engineering quantity into a plurality of tasks according to the project basic information, and setting a related project member for each task;
and sending a task requirement to the project member according to the task setting of the project management module, and sending a corresponding task execution record to the project management module after the project member uploads the task execution record.
8. The exterior wall painting project management method of claim 7, wherein: the task execution records comprise robot task execution records, and the method further comprises the steps of analyzing the robot construction efficiency according to the robot task execution records, judging whether the robot construction efficiency is normal or not, generating a maintenance list if the robot construction efficiency is not normal, and sending the maintenance list to a robot manufacturer.
9. The exterior wall painting project management method of claim 8, wherein: and calculating the total budget of the project according to the material budget and the labor budget of each task, wherein the labor budget is the robot construction budget or the labor worker budget or the combined construction budget of the robot construction and the labor worker construction.
10. The exterior wall painting project management method of claim 9, wherein: and performing statistical analysis according to the robot task execution record or the labor worker task execution record, and assessing project members according to the statistical analysis result.
CN202110664633.2A 2021-06-16 2021-06-16 Outer wall spraying engineering project management platform and management method Pending CN113393212A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110664633.2A CN113393212A (en) 2021-06-16 2021-06-16 Outer wall spraying engineering project management platform and management method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110664633.2A CN113393212A (en) 2021-06-16 2021-06-16 Outer wall spraying engineering project management platform and management method

Publications (1)

Publication Number Publication Date
CN113393212A true CN113393212A (en) 2021-09-14

Family

ID=77621353

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110664633.2A Pending CN113393212A (en) 2021-06-16 2021-06-16 Outer wall spraying engineering project management platform and management method

Country Status (1)

Country Link
CN (1) CN113393212A (en)

Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20130211866A1 (en) * 2011-07-20 2013-08-15 Bank Of America Corporation Project checklist and table of changes for project management
CN107220741A (en) * 2016-03-22 2017-09-29 赫克斯冈技术中心 Method and system for job site management and support system using marking robot
CN107437167A (en) * 2017-07-19 2017-12-05 中诚工程建设管理(苏州)股份有限公司 Construction-engineering project data handling system
CN108537511A (en) * 2018-04-10 2018-09-14 万翼科技有限公司 The method, apparatus and computer readable storage medium of project process displaying
CN109165841A (en) * 2018-08-21 2019-01-08 麦格创科技(深圳)有限公司 A kind of project management platform and project management method based on cloud service
CN111461570A (en) * 2020-04-20 2020-07-28 成都一智科技有限公司 Building construction evaluation system based on mobile internet and related intelligent equipment
CN111563805A (en) * 2020-07-15 2020-08-21 炬星科技(深圳)有限公司 Work information acquisition method, robot, device, and storage medium
CN111921733A (en) * 2020-10-14 2020-11-13 广东博嘉拓建筑科技有限公司 Spraying operation method and system
CN112036688A (en) * 2020-07-22 2020-12-04 深圳中冶管廊建设投资有限公司 Economic evaluation method and device for working robot and storage medium
CN112464494A (en) * 2020-12-14 2021-03-09 北京城建集团有限责任公司 Construction system is built to wisdom
CN112621752A (en) * 2019-08-20 2021-04-09 广东博智林机器人有限公司 Robot construction method and device and industrial personal computer
CN112950162A (en) * 2020-07-09 2021-06-11 北京中百信信息技术股份有限公司 Information system engineering supervision work distribution management information system

Patent Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20130211866A1 (en) * 2011-07-20 2013-08-15 Bank Of America Corporation Project checklist and table of changes for project management
CN107220741A (en) * 2016-03-22 2017-09-29 赫克斯冈技术中心 Method and system for job site management and support system using marking robot
CN107437167A (en) * 2017-07-19 2017-12-05 中诚工程建设管理(苏州)股份有限公司 Construction-engineering project data handling system
CN108537511A (en) * 2018-04-10 2018-09-14 万翼科技有限公司 The method, apparatus and computer readable storage medium of project process displaying
CN109165841A (en) * 2018-08-21 2019-01-08 麦格创科技(深圳)有限公司 A kind of project management platform and project management method based on cloud service
CN112621752A (en) * 2019-08-20 2021-04-09 广东博智林机器人有限公司 Robot construction method and device and industrial personal computer
CN111461570A (en) * 2020-04-20 2020-07-28 成都一智科技有限公司 Building construction evaluation system based on mobile internet and related intelligent equipment
CN112950162A (en) * 2020-07-09 2021-06-11 北京中百信信息技术股份有限公司 Information system engineering supervision work distribution management information system
CN111563805A (en) * 2020-07-15 2020-08-21 炬星科技(深圳)有限公司 Work information acquisition method, robot, device, and storage medium
CN112036688A (en) * 2020-07-22 2020-12-04 深圳中冶管廊建设投资有限公司 Economic evaluation method and device for working robot and storage medium
CN111921733A (en) * 2020-10-14 2020-11-13 广东博嘉拓建筑科技有限公司 Spraying operation method and system
CN112464494A (en) * 2020-12-14 2021-03-09 北京城建集团有限责任公司 Construction system is built to wisdom

Similar Documents

Publication Publication Date Title
CN111861358A (en) Building information integration platform based on BIM technology
US20210349476A1 (en) Method and apparatus for controlling cruise of unmanned air vehicle based on prefabricated construction platform
JP5688533B1 (en) Concrete structure maintenance management system
CN111260325A (en) Bridge construction progress management system based on BIM
US20120221379A1 (en) Facility control system (fcs) to manage assets and products
CN109086895A (en) A kind of operation management system and method for heating ventilation air-conditioning system
CN109377034A (en) Risk profiles appraisal procedure based on smart grid information communication system
CN107680194A (en) A kind of information system for power enterprise automates cruising inspection system
CN116090634B (en) Engineering fine-packaging and repairing intelligent management platform and method based on Internet of things
CN114282824B (en) Building engineering informatization management system
CN115994641A (en) Comprehensive management system for construction engineering progress
CN110334942A (en) Construction Supervision Work procedure information management system
CN117114619B (en) Project security management system based on big data analysis
CN118246103A (en) Construction method of assembled steel-concrete combined structure
KR20030068661A (en) Integrated construction management system and method using portable terminal
CN112184945A (en) Mobile terminal inspection management method and system
CN117649207A (en) Building construction management system
CN116934180B (en) Whole process consultation information management method, system, device and storage medium
CN117114386A (en) Workflow management system for designer and industrial worker
CN113393212A (en) Outer wall spraying engineering project management platform and management method
CN113793117A (en) BIM-based remote supervision method for building construction
CN116542469A (en) Building engineering supervision intelligent integrated cloud platform based on BIM technology and supervision method
Zhang Complexity of cellular manufacturing systems based on entropy models
CN116051063A (en) Project creation system and method
CN115906349A (en) Wireless positioning system based on data processing

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information

Address after: 3A17, Building U2, Junxiang U8 Intelligent Manufacturing Industrial Park, Guxing Community, Xixiang Street, Bao'an District, Shenzhen, Guangdong 518000

Applicant after: ZHUCHENG TECHNOLOGY (SHENZHEN) Co.,Ltd.

Address before: 518000 601, Huichuang space 2018 Creative Park, 93a, Gushu 1st Road, Gushu community, Xixiang street, Bao'an District, Shenzhen City, Guangdong Province

Applicant before: ZHUCHENG TECHNOLOGY (SHENZHEN) Co.,Ltd.

CB02 Change of applicant information