CN113333981A - Large-size pi-shaped pipeline installation method - Google Patents

Large-size pi-shaped pipeline installation method Download PDF

Info

Publication number
CN113333981A
CN113333981A CN202110620530.6A CN202110620530A CN113333981A CN 113333981 A CN113333981 A CN 113333981A CN 202110620530 A CN202110620530 A CN 202110620530A CN 113333981 A CN113333981 A CN 113333981A
Authority
CN
China
Prior art keywords
component
pipeline
equal
crane
welding
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202110620530.6A
Other languages
Chinese (zh)
Inventor
丁旭
邓彦双
陈伟
蒲小龙
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PowerChina Sichuan Engineering Corp Ltd
Original Assignee
PowerChina Sichuan Engineering Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PowerChina Sichuan Engineering Corp Ltd filed Critical PowerChina Sichuan Engineering Corp Ltd
Priority to CN202110620530.6A priority Critical patent/CN113333981A/en
Publication of CN113333981A publication Critical patent/CN113333981A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B23MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
    • B23KSOLDERING OR UNSOLDERING; WELDING; CLADDING OR PLATING BY SOLDERING OR WELDING; CUTTING BY APPLYING HEAT LOCALLY, e.g. FLAME CUTTING; WORKING BY LASER BEAM
    • B23K31/00Processes relevant to this subclass, specially adapted for particular articles or purposes, but not covered by only one of the preceding main groups
    • B23K31/02Processes relevant to this subclass, specially adapted for particular articles or purposes, but not covered by only one of the preceding main groups relating to soldering or welding
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B23MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
    • B23KSOLDERING OR UNSOLDERING; WELDING; CLADDING OR PLATING BY SOLDERING OR WELDING; CUTTING BY APPLYING HEAT LOCALLY, e.g. FLAME CUTTING; WORKING BY LASER BEAM
    • B23K31/00Processes relevant to this subclass, specially adapted for particular articles or purposes, but not covered by only one of the preceding main groups
    • B23K31/02Processes relevant to this subclass, specially adapted for particular articles or purposes, but not covered by only one of the preceding main groups relating to soldering or welding
    • B23K31/027Making tubes with soldering or welding

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention provides a method for installing a large-size pi-shaped pipeline, which comprises the steps of horizontally placing the pipeline below a cross-road steel structure on site, dividing the pipeline into a component 1 and a component 2, combining the components into 2 factory-shaped structures, respectively finishing the work of aligning, welding and RT (reverse transcription) detection of the pipeline in the components, and passing the inspection and acceptance of a general packet party and an owner party. The invention provides a method for installing a large-size pi-shaped pipeline, which has the advantages that only one crane is needed, primary hoisting command is not needed, and the cost of machines is reduced. And multiple cranes are prevented from being matched for construction in the construction process, so that the safety risk is reduced.

Description

Large-size pi-shaped pipeline installation method
Technical Field
The invention belongs to the technical field of pipeline installation, and particularly relates to a large-size pi-shaped pipeline installation method.
Background
The cross-road pipeline is common in various industrial factories, and the large-size cross-road pipeline mainly has the characteristics of heavy weight and large overall dimension. In the construction process, different difficulties are brought to construction due to factors such as construction sites, construction environments, construction cost and the like, so that different construction methods can be adopted.
In the prior art, hoisting is relatively complex and strict. The safety specification requires: when a single crane works, if the working load is greater than 85% of the rated load, a special hoisting operation plan issued by a first-level hoisting command is required or a first-level crane worker commands on site. If the hoisted objects of 40t or more are hoisted or two or more cranes are operated cooperatively, a 'first-level hoisting command' is needed for commanding.
The hoisting command is divided into 3 grades of 'first-grade hoisting command', 'second-grade hoisting command' and 'third-grade hoisting command'. The first-level hoisting command has the highest level, the third-level hoisting command has the lowest level, the third-level hoisting command can only command hoisted objects below 10t, the second-level hoisting command can command hoisted objects of 10t-39t, the first-level hoisting command can command hoisted objects of 40t or more, and can command hoisting work of more than two vehicles which are matched with each other, and other hoisting work with special requirements such as night construction and the like. Particularly, in the 'first-level hoisting command' of the project work of the America oil company, the America oil company needs to be approved and issue a work certificate to work, so the expense is higher, the temporary labor work is 400 Riyaer/hour, and because the America oil company has strict control and control, the number of issued work permission is less, and the 'first-level hoisting command' is difficult to be hired in ideal time in short-term use.
Disclosure of Invention
The invention aims to solve the defects in the prior art and provides a method for installing a large-size pi-shaped pipeline. And multiple cranes are prevented from being matched for construction in the construction process, so that the safety risk is reduced.
The invention adopts the following technical scheme:
the invention relates to a method for installing a large-size pi-shaped pipeline, which comprises the following steps
(1) Assembly combination
Horizontally placing the pipeline below the cross-road steel structure on site, dividing the pipeline into a component 1 and a component 2, combining the components into 2 shapes in a shape like a Chinese character 'factory', respectively finishing the work of pipeline alignment, welding, welded junction RT (reverse transcription) detection and the like in the components, and passing the acceptance of a general packet party and an owner party;
(2) component body turning over
The maximum length of the assembly 1 after combination is more than or equal to 18m, the maximum length of the assembly 2 after combination is more than or equal to 17.6m, the height of the assembly 1 after combination is more than or equal to 9m, the height of the assembly 2 after combination is more than or equal to 8.6m, the overall weight of the assembly 1 after combination is more than or equal to 26.06t, the weight of the assembly 2 after combination is more than or equal to 24.62t, and the total weight of a lifting appliance and a lifting hook is more than or equal to 5 t. The component can be turned over and put in place by using a crane, the working range of the crane is determined to be 20m according to the weight calculation of the component 1, the load rate is less than 85 percent according to safety specifications, the rated load of the crane 20m is not less than (26.06+5)/0.85 t which is 36.5t, and the component can be turned over from the horizontal state to the vertical state according to the calculation that a 300t truck crane can meet the hoisting requirement.
(3) With the components in place
Taking the sequence of firstly hoisting the component 1 and then hoisting the component 2 as an example, after the component 1 is turned over and leveled, the component 1 is hoisted to a position where the component is positioned by a 300t truck crane. According to the design, only one formal support is arranged on the main beam at each end of the steel structure, and the components 1 and 2 cannot be balanced after being independently placed in place, so that the crane cannot be hooked loosely after the components 1 are placed in place to keep the stability of the pipeline. And then stably reinforcing the assembly, wherein the reinforcing work comprises the following steps:
firstly, after the welded junction A is in place, the pipeline butt welding work is immediately carried out, and at least argon arc welding bottoming and one layer of manual welding cover surface of the welded junction are finished.
And secondly, the pipe clamp for aligning the pipeline is retained on the weld opening, and the limiting bolt is tightened, so that the stress of the weld opening is reduced.
And thirdly, below the horizontal section of the component 1, a batten is used for being filled between the pipeline and the secondary beam, and the levelness of the horizontal section of the component is ensured.
Fourthly, temporarily supporting and strengthening the stability below the 90-degree elbow at the welding opening A.
After the reinforcement work is completed, the crane can be unhooked. After the crane of the component 1 looses the hook, the hoisting work of the component 2 is carried out, the hoisting procedure of the component 2 is the same as that of the component 1, and after the component 2 is in place, the opening aligning, welding and reinforcing work is carried out on the welding opening B and the welding opening C at the same time.
The large-size pi-shaped pipeline is as follows: the outer diameter of the pipeline is larger than or equal to 1422.4mm, the wall thickness is larger than or equal to 28.58mm, the center elevation of the pipeline is larger than or equal to 9361mm, the center distance of two vertical pipes is larger than or equal to 30000mm, the lengths of the vertical pipes are larger than or equal to 7600mm and larger than or equal to 8000mm respectively, a single pipeline is provided with A, B formal supports on a steel frame, the unit weight of a straight pipe is larger than or equal to 0.98t/m, the unit weight of a 90-degree elbow is larger than or equal to 4.5 t/piece, and the combined weight of the pipeline is larger than or equal to 50.22 t.
The invention has the beneficial effects that:
the method has the advantages that only one crane is needed, and primary hoisting command is not needed, so that the cost of machines and tools is reduced. And multiple cranes are prevented from being matched for construction in the construction process, so that the safety risk is reduced.
Drawings
FIG. 1 is a schematic structural view of the present invention;
FIG. 2 is a schematic diagram of the sectional assembly of the present invention.
Priming by argon arc welding: argon arc welding is a non-melting electrode welding method protected by argon gas, and is characterized by that it uses a special welding handle, uses tungsten bar as electrode, and uses argon gas to protect the periphery of the electrode, when the short circuit is used to ignite electric arc, the base material is melted, and the argon gas protects molten pool, then the welding wire is used to melt and form welding seam. Argon is an inert gas that does not undergo oxidation reactions with molten metal. Priming means first layer soldering. I.e. the closed welding of the pipes. The main purpose is that the bottom layer does not form welding slag and keeps the interior of the pipeline clean.
One layer of welding rod is filled in an arc welding mode: the filling refers to the number of welding layers between the argon arc welding priming coat and the outermost layer (cover coat) of the crater, and the number of filling layers is different according to the wall thickness of the pipeline.
Detailed Description
In order to make the objects, technical solutions and advantages of the present invention more apparent, the technical solutions of the present invention are described below clearly and completely, and it is obvious that the described embodiments are some, not all embodiments of the present invention. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
Examples
The Saudi MGS second-stage project is a new project of a gas booster station, the owner is Saudi America oil company, the specification of a main pipeline of a plant area is 56 inches, the total length is 10762m, and 5 pipelines are designed to cross roads to match with the road of the plant area. The 6 pipelines are arranged side by side on the pipeline gallery, the outer diameter of the pipeline is 1422mm, and the wall thickness has two specifications of 25.4mm and 28.58 mm. This example compares the advantages and disadvantages of the two schemes by comparing the overall combination with the installation scheme of the present invention.
Parameters associated with the pipe
The field large size pipeline has 5 positions, and 56 inches 28.58mm pipelines in a U30 area PB01 are taken as an example for illustration. The outer diameter of the pipeline is 1422.4mm, the wall thickness is 28.58mm, as shown in figure 1, the central elevation of the pipeline is 9361mm, the central distance between two vertical pipes is 30000mm, and the lengths of the vertical pipes are 7600mm and 8000mm respectively. The single pipeline has A, B two formal supports on the steel frame. The unit weight of the straight pipe is 0.98t/m, the unit weight of the 90-degree elbow is about 4.5 t/pipe, and the combined weight of the pipeline is about 50.22 t.
Pi-shaped pipeline construction method and analysis
Integral combined hoisting method
According to the common practice, the pipelines are combined on the ground into pi-shaped structures as shown in figure 2, the high-altitude work is reduced as much as possible, and the construction steps are as follows:
(1) assembly combination
The pipeline is horizontally placed on the spot below the cross-road steel structure for combination, the work of pipeline alignment, welding, welded junction RT detection and the like is completed, and the inspection and acceptance of a general packet side and an owner side are passed.
(2) Component body turning over
The maximum length of the assembly is 35m, the maximum height is 9m, the weight reaches 50.22t, and the weight of a lifting appliance, a crane lifting hook and a steel wire rope is considered to be 5 t. The assembled assembly is turned over using 1 main crane and 2 auxiliary cranes and then put into place by the main crane. According to the field situation, the working range of the main crane needs 20m, the working load is less than 85% of the rated load according to the American safety standard, so that the rated load is not less than (52.22+ 5)/0.85-67.31 t when the main crane works at 20m, and the main crane selects a truck crane of 450t to meet the construction requirement because the construction field is not suitable for arranging the crawler cranes. The working amplitude of the auxiliary crane is considered as 8m, the working load is considered as 50% of the weight of the whole assembly, 2 75t truck cranes are determined to be used as the auxiliary cranes, a first-level hoisting command is required to be commanded on site during hoisting, and the assembly is turned from the horizontal state to the vertical state.
(3) With the components in place
After the assembly is turned over to be in a vertical state, a lifting appliance of the auxiliary crane is taken down, the assembly is placed on supports at A, B by a truck crane of 450t, the lifting appliance is taken down after the relative size is adjusted, and the crane is unhooked.
The method has the advantages that the high-altitude operation is less, all assembly work is completed on the ground, and other auxiliary or reinforcing measures are not needed after the components are in place. But the area of the required combined field is large and the combination is not flexible enough. When the assembly is turned over, a plurality of cranes are required to be matched and the 'first-level hoisting command' is required, so that the assembly has certain risk and high cost. Special weather such as strong wind, sand storm and the like is foreseen, and great economic loss is caused if workers are lost.
The invention discloses a method for installing a large-size pi-shaped pipeline, which comprises the following steps:
(1) assembly combination
Horizontally placing the pipeline below the cross-road steel structure on site, dividing the pipeline into a component 1 and a component 2 as shown in figure 2, combining the components into 2 'factory' -shaped structures, respectively finishing the work of pipeline alignment, welding, welded junction RT (reverse transcription) detection and the like in the components, and passing the inspection and acceptance of a general packet side and an owner side;
(2) component body turning over
The combined maximum length of the two modules is about 18m (module 1) and 17.6m (module 2), the height is 9m (module 1) and 8.6m (module 2), and the total weight is about 26.06t (module 1) and 24.62t (module 2), and the total weight of the hanger and the lifting hook is 5 t. The component can be turned over and put in place by using a crane, the working range of the crane is determined to be 20m according to the weight calculation of the component 1, the load rate is less than 85 percent according to safety specifications, the rated load of the crane 20m is not less than (26.06+5)/0.85 t which is 36.5t, and the component can be turned over from the horizontal state to the vertical state according to the calculation that a 300t truck crane can meet the hoisting requirement.
(3) With the components in place
Taking the sequence of firstly hoisting the component 1 and then hoisting the component 2 as an example, after the component 1 is turned over and leveled, the component 1 is hoisted to a position where the component is positioned by a 300t truck crane. According to the design, only one formal support is arranged on the main beam at each end of the steel structure, and the components 1 and 2 cannot be balanced after being independently placed in place, so that the crane cannot be hooked loosely after the components 1 are placed in place to keep the stability of the pipeline. And then stably reinforcing the assembly, wherein the reinforcing work comprises the following steps:
firstly, after the welded junction A is in place, the pipeline butt welding work is immediately carried out, and at least argon arc welding bottoming and one layer of manual welding cover surface of the welded junction are finished.
And secondly, the pipe clamp for aligning the pipeline is retained on the weld opening, and the limiting bolt is tightened, so that the stress of the weld opening is reduced.
And thirdly, below the horizontal section of the component 1, a batten is used for being filled between the pipeline and the secondary beam, and the levelness of the horizontal section of the component is ensured.
Fourthly, temporarily supporting and strengthening the stability below the 90-degree elbow at the welding opening A.
After the reinforcement work is completed, the crane can be unhooked. After the crane of the component 1 looses the hook, the hoisting work of the component 2 is carried out, the hoisting procedure of the component 2 is the same as that of the component 1, and after the component 2 is in place, the opening aligning, welding and reinforcing work is carried out on the welding opening B and the welding opening C at the same time.
The construction method for selecting the Saudi MGS second-stage project is 'sectional combined hoisting', the coordination of a plurality of machines and tools and the use of 'first-stage hoisting command' are avoided in the construction process, the construction continuity is good, the utilization rate of the machines and tools is high, and certain effect is achieved in the aspect of economy.
When the components are combined, the components need to be combined below a road-crossing steel structure, a road at the position is occupied, pipelines can be placed compactly through sectional combination, the basic passing condition of the road at the position is guaranteed, and the passing influence on site construction vehicles is reduced. The field implementation proves that the method for sectional combined hoisting of the large-size pi-shaped pipeline has strong operability.
Through comparison, a series of actions such as turning over and hoisting of the assembly are completed by a single crane, the method has the advantages of small combined occupied area, small using amount of machines and tools and the like, and the installation work of the wide pipeline at the 5-position on site is smoothly completed.
Finally, it should be noted that: the above examples are only intended to illustrate the technical solution of the present invention, but not to limit it; although the present invention has been described in detail with reference to the foregoing embodiments, it will be understood by those of ordinary skill in the art that: the technical solutions described in the foregoing embodiments may still be modified, or some technical features may be equivalently replaced; and such modifications or substitutions do not depart from the spirit and scope of the corresponding technical solutions of the embodiments of the present invention.

Claims (3)

1. The method for installing the large-size pi-shaped pipeline is characterized by comprising the following steps
Step 1. Assembly combination
Horizontally placing the pipeline below the cross-road steel structure on site, dividing the pipeline into a component 1 and a component 2, combining the components into 2 shapes in a shape like a Chinese character 'factory', respectively finishing the work of aligning, welding and welding port RT (reverse transcription) detection of the pipeline in the components, and passing the acceptance of a general packet party and an owner party;
step 2, turning over the assembly
The maximum length of the combined component 1 is more than or equal to 18m, the maximum length of the combined component 2 is more than or equal to 17.6m, the height of the combined component 1 is more than or equal to 9m, the height of the combined component 2 is more than or equal to 8.6m, the overall weight of the combined component 1 is more than or equal to 26.06t, the combined weight of the combined component 2 is more than or equal to 24.62t, and the total weight of a lifting appliance and a lifting hook is more than or equal to 5t, wherein the component is turned over and positioned by using a crane, the working amplitude of the crane is determined to be 20m according to the weight calculation of the component 1, the load rate is less than 85% according to the safety specification, the 20m rated load of the crane is not less than 36.5t, and the component is turned over from the horizontal state to the vertical state according to the calculation that 300t of the truck crane meets the lifting requirement;
step 3, positioning the assembly
According to the sequence of firstly hoisting the component 1 and then hoisting the component 2, after the component 1 is turned over and leveled, the component 1 is hoisted to the in-position by a 300t truck crane, according to the design, only one formal support is respectively arranged on the main beams at two ends of a steel structure, the component 1 and the component 2 cannot be balanced after being independently in position, and after the component 1 is in position, a crane cannot loosen a hook, and then the component is stably reinforced;
after the reinforcement work is finished, the crane is unhooked, the component 1 is hoisted by the crane, the component 2 is hoisted, the hoisting procedure of the component 2 is the same as that of the component 1, and after the component 2 is in place, the weld joint B and the weld joint C are subjected to butt joint, welding and reinforcement work at the same time.
2. The method for installing a large-sized pi-shaped pipe as claimed in claim 1, wherein the reinforcement work in step 3 comprises:
after the welded junction A is in place, immediately performing pipeline butt welding work, and at least completing argon arc welding bottoming and one-layer welding rod arc welding filling of the welded junction;
secondly, the pipe clamp for aligning the pipeline is retained on the weld crater and the limiting bolt is tightened, so that the stress of the weld crater is reduced;
thirdly, a batten is arranged between the pipeline and the secondary beam below the horizontal section of the component 1 in a cushioning mode, and the levelness of the horizontal section of the component is guaranteed;
fourthly, temporarily supporting and strengthening the stability below the 90-degree elbow at the welding opening A.
3. The method for installing a large-size pi-shaped pipeline according to claim 1, wherein the large-size pi-shaped pipeline is: the outer diameter of the pipeline is larger than or equal to 1422.4mm, the wall thickness is larger than or equal to 28.58mm, the center elevation of the pipeline is larger than or equal to 9361mm, the center distance of two vertical pipes is larger than or equal to 30000mm, the lengths of the vertical pipes are larger than or equal to 7600mm and larger than or equal to 8000mm respectively, a single pipeline is provided with A, B formal supports on a steel frame, the unit weight of a straight pipe is larger than or equal to 0.98t/m, the unit weight of a 90-degree elbow is larger than or equal to 4.5 t/piece, and the combined weight of the pipeline is larger than or equal to 50.22 t.
CN202110620530.6A 2021-06-03 2021-06-03 Large-size pi-shaped pipeline installation method Pending CN113333981A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110620530.6A CN113333981A (en) 2021-06-03 2021-06-03 Large-size pi-shaped pipeline installation method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110620530.6A CN113333981A (en) 2021-06-03 2021-06-03 Large-size pi-shaped pipeline installation method

Publications (1)

Publication Number Publication Date
CN113333981A true CN113333981A (en) 2021-09-03

Family

ID=77473376

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110620530.6A Pending CN113333981A (en) 2021-06-03 2021-06-03 Large-size pi-shaped pipeline installation method

Country Status (1)

Country Link
CN (1) CN113333981A (en)

Citations (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6032851A (en) * 1996-10-21 2000-03-07 Premiere, Inc. Vertical pipe column assembly method
CN101487232A (en) * 2009-01-05 2009-07-22 广州市市政集团有限公司 Steel box girder assembling construction method
CN102003074A (en) * 2010-10-15 2011-04-06 中国建筑第八工程局有限公司 Construction method for indoor long-span steel connecting bridge
CN102192368A (en) * 2010-03-03 2011-09-21 五冶集团上海有限公司 Large-span overhead pipeline sliding installation method
CA2709563A1 (en) * 2010-07-22 2012-01-22 Larry Bertelsen Automated construction system
CN103692195A (en) * 2013-12-20 2014-04-02 中国五冶集团有限公司 Pipe installation method
CN105090613A (en) * 2015-08-03 2015-11-25 上海申能能源服务有限公司 Hoisting method of gas pipeline in external wall of super high-rise building
CN105345288A (en) * 2015-11-20 2016-02-24 天津二十冶建设有限公司 Power-driven chain block combination device for installing desulfurizing tower and installation method
CN105397351A (en) * 2015-12-02 2016-03-16 中国化学工程第十四建设有限公司 Onsite vertical mounting method for segmentally-prefabricated tower body
CN106121237A (en) * 2016-08-31 2016-11-16 中建四局第建筑工程有限公司 Large-span steel arch without outer construction method for supporting and assembled welding positioner
CN109610920A (en) * 2018-12-10 2019-04-12 中国电建集团河南工程有限公司 Transmission line of electricity single-column steel tube column construction method for hanging
CN110259145A (en) * 2019-06-28 2019-09-20 中冶建工集团有限公司 A kind of arch tubular truss rapid constructing method
CN110307395A (en) * 2019-05-10 2019-10-08 中国二十二冶集团有限公司 Across roofing great diameter and long duct segments construction method of installation

Patent Citations (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6032851A (en) * 1996-10-21 2000-03-07 Premiere, Inc. Vertical pipe column assembly method
CN101487232A (en) * 2009-01-05 2009-07-22 广州市市政集团有限公司 Steel box girder assembling construction method
CN102192368A (en) * 2010-03-03 2011-09-21 五冶集团上海有限公司 Large-span overhead pipeline sliding installation method
CA2709563A1 (en) * 2010-07-22 2012-01-22 Larry Bertelsen Automated construction system
CN102003074A (en) * 2010-10-15 2011-04-06 中国建筑第八工程局有限公司 Construction method for indoor long-span steel connecting bridge
CN103692195A (en) * 2013-12-20 2014-04-02 中国五冶集团有限公司 Pipe installation method
CN105090613A (en) * 2015-08-03 2015-11-25 上海申能能源服务有限公司 Hoisting method of gas pipeline in external wall of super high-rise building
CN105345288A (en) * 2015-11-20 2016-02-24 天津二十冶建设有限公司 Power-driven chain block combination device for installing desulfurizing tower and installation method
CN105397351A (en) * 2015-12-02 2016-03-16 中国化学工程第十四建设有限公司 Onsite vertical mounting method for segmentally-prefabricated tower body
CN106121237A (en) * 2016-08-31 2016-11-16 中建四局第建筑工程有限公司 Large-span steel arch without outer construction method for supporting and assembled welding positioner
CN109610920A (en) * 2018-12-10 2019-04-12 中国电建集团河南工程有限公司 Transmission line of electricity single-column steel tube column construction method for hanging
CN110307395A (en) * 2019-05-10 2019-10-08 中国二十二冶集团有限公司 Across roofing great diameter and long duct segments construction method of installation
CN110259145A (en) * 2019-06-28 2019-09-20 中冶建工集团有限公司 A kind of arch tubular truss rapid constructing method

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
李淑华: "《焊接技术经验》", 30 June 2014, 中国铁道出版社 *
王磊等: "武汉中心超长超重钢梁非对称提升技术", 《钢结构》 *
电力工业部建设协调司: "《焊工技术问答》", 31 October 1997, 中国电力出版社 *

Similar Documents

Publication Publication Date Title
CN111561048A (en) Method for mounting high-altitude hoisting type steel beam and beam column node
CN102296858A (en) Cement production line clinker storage warehouse roof steel structure and construction method thereof
CN109958065A (en) The construction method that a kind of bridge steel box girder segmental hoisting high-altitude closes up
CN105692468A (en) Large latticed shell type arch crown integral elevation hoisting mechanism and using method thereof
CN112211103A (en) Special safe construction process for assembling and installing coal conveying trestle steel truss
CN206513098U (en) A kind of apparatus for work for being used to remove towering structure
CN115075398A (en) Reverse-order socket construction method for installing Y-shaped steel column
CN118207957A (en) Steel mesh frame installation construction method
CN106087698B (en) Portable construction operation platform of bored pile
CN111622125A (en) Method for mounting through-type inverted triangular comb-shaped steel pipe arch rib
CN113333981A (en) Large-size pi-shaped pipeline installation method
CN107419907B (en) A kind of steel-making tower steel structure platform is staggered installation of welding method
CN103495793A (en) Improved construction method for hoisting and welding large-tonnage cast steel component complex joints
CN111790995B (en) Construction process for welding steel beam
CN110512910B (en) Integral heightening and mounting method for high-span steel structure of steel-making main plant
CN104563512A (en) Construction method of tall building steel structure
CN217071087U (en) Bridge crane girder fracture is in line welding set
CN215254455U (en) Fireproof hanging basket for high-altitude welding of steel structure
CN216471740U (en) Interim fixing device during welding of outer hanging tower crane foundation girder steel
CN215626195U (en) Adjustable steel pipe truss lifting appliance
CN211621962U (en) Node connection structure of multicavity L shape steel pipe concrete special-shaped column
CN111776937A (en) Assembled lifting device for lifting I-beam and combined module thereof and use method
CN106285017B (en) Thermal control boiler steel vertical shaft installation method
CN111519910A (en) Multi-angle large-slope steel column hoisting method and protection frame body assembly used in cooperation with same
CN110004831B (en) Reinforcing steel bar installation auxiliary tool and using method thereof

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20210903

RJ01 Rejection of invention patent application after publication