CN113279423B - Prefabricated column pier and post-cast strip foundation beam assembly integral construction method - Google Patents
Prefabricated column pier and post-cast strip foundation beam assembly integral construction method Download PDFInfo
- Publication number
- CN113279423B CN113279423B CN202110724808.4A CN202110724808A CN113279423B CN 113279423 B CN113279423 B CN 113279423B CN 202110724808 A CN202110724808 A CN 202110724808A CN 113279423 B CN113279423 B CN 113279423B
- Authority
- CN
- China
- Prior art keywords
- post
- cast strip
- prefabricated column
- column pier
- foundation beam
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 238000010276 construction Methods 0.000 title claims abstract description 79
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 28
- 239000010959 steel Substances 0.000 claims abstract description 28
- 239000004567 concrete Substances 0.000 claims abstract description 21
- 238000009826 distribution Methods 0.000 claims abstract description 12
- 238000005266 casting Methods 0.000 claims abstract description 6
- 230000002787 reinforcement Effects 0.000 claims description 64
- 238000000034 method Methods 0.000 claims description 6
- 230000003014 reinforcing effect Effects 0.000 claims description 6
- 238000003466 welding Methods 0.000 claims description 3
- 239000011150 reinforced concrete Substances 0.000 description 8
- 238000005452 bending Methods 0.000 description 5
- 238000010586 diagram Methods 0.000 description 5
- 230000000694 effects Effects 0.000 description 4
- 230000005540 biological transmission Effects 0.000 description 2
- 230000003111 delayed effect Effects 0.000 description 2
- 238000009415 formwork Methods 0.000 description 2
- 238000012423 maintenance Methods 0.000 description 2
- 238000004904 shortening Methods 0.000 description 2
- 230000003044 adaptive effect Effects 0.000 description 1
- 238000009435 building construction Methods 0.000 description 1
- 230000006835 compression Effects 0.000 description 1
- 238000007906 compression Methods 0.000 description 1
- 238000005260 corrosion Methods 0.000 description 1
- 238000000280 densification Methods 0.000 description 1
- 230000002708 enhancing effect Effects 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 238000004080 punching Methods 0.000 description 1
- 239000002689 soil Substances 0.000 description 1
- 239000002023 wood Substances 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D27/00—Foundations as substructures
- E02D27/01—Flat foundations
- E02D27/016—Flat foundations made mainly from prefabricated concrete elements
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D27/00—Foundations as substructures
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D27/00—Foundations as substructures
- E02D27/01—Flat foundations
- E02D27/02—Flat foundations without substantial excavation
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Bridges Or Land Bridges (AREA)
Abstract
本发明公开了一种预制柱墩及后浇条形基础梁装配整体施工方法,包括预制柱墩及后浇条形基础梁,所述预制柱墩顶部向上延伸出用于连接上部框架柱纵向受力钢筋的第一接头钢筋,所述预制柱墩侧面延伸出用于连接后浇条形基础梁肋梁纵向受力钢筋和翼板分布钢筋的第二接头钢筋和第三接头钢筋;施工时将所述预制柱墩安放在预定柱位,进行第一钢筋接头的延长及第一结构层的框架结构施工,在上部结构施工的同时适时同步进行预制柱墩第二接头钢筋和第三接头钢筋的延长并浇筑混凝土完成后浇条形基础梁并进一步向上延伸结构;本发明通过后浇条形基础梁以形成空间刚度较大的交叉条形基础并承受不断向上延伸的结构自重及施工荷载,从而达到节约工期的目的。
The invention discloses an integral construction method for assembling a prefabricated column pier and a post-cast strip foundation beam, comprising a prefabricated column pier and a post-cast strip foundation beam. The first joint steel bar of the force steel bar, the side of the prefabricated column pier extends out the second joint steel bar and the third joint steel bar used to connect the longitudinal stress steel bar of the post-cast strip-shaped foundation beam rib beam and the wing plate distribution steel bar; The prefabricated column piers are placed at the predetermined column positions, and the extension of the first steel bar joint and the construction of the frame structure of the first structural layer are carried out, and the second joint steel bar and the third joint steel bar of the prefabricated column pier are timely and synchronously carried out during the construction of the upper structure. After the extension and pouring of concrete is completed, the strip-shaped foundation beam is poured and the structure is further extended upward; the present invention forms a cross-stripe foundation with relatively large spatial rigidity by post-casting the strip-shaped foundation beam and bears the self-weight and construction load of the structure extending upward continuously, thereby To achieve the purpose of saving time.
Description
技术领域technical field
本发明涉及建筑施工领域,特别适用于无附建式地下室的一种预制柱墩及后浇条形基础梁装配整体施工方法。The invention relates to the field of building construction, and is particularly suitable for an integral construction method for assembling a prefabricated column pier and a post-cast strip foundation beam for a basement without an attached building.
背景技术Background technique
柱下条形基础是指布置成单向或双向的钢筋混凝土条形基础,也称梁式基础或基础梁。其横断面由一根肋梁及横向向外伸出的翼板所组成。由于肋梁梁高相对较大且配置一定数量的纵向受力钢筋和箍筋,且翼板底部设置有横向受弯钢筋及翼板分布钢钢筋,因而具有较大的抗剪、抗弯及抗冲切能力,所以常用于荷载较大而地基承载力较小的情况,如软弱地基上的框架或排架结构。柱下条形基础具有刚度大、调整不均匀沉降能力强等诸多优点。The strip foundation under the column refers to the reinforced concrete strip foundation arranged in one or two directions, also known as the beam foundation or the foundation beam. Its cross section is composed of a rib beam and laterally protruding wings. Because the height of the rib beam is relatively large, a certain number of longitudinal stress steel bars and stirrups are arranged, and the lateral bending steel bars and the wing plate distribution steel bars are arranged at the bottom of the wing plate, so it has greater shear, bending and anti-corrosion resistance. Punching capacity, so it is often used in situations where the load is large and the bearing capacity of the foundation is small, such as a frame or bent structure on a weak foundation. The strip foundation under the column has many advantages, such as high rigidity and strong ability to adjust uneven settlement.
对于荷载较大的高层建筑,当地基软弱,且地基土的压缩均匀性较差或者柱荷载沿纵横两个方向大小相差悬殊,需要条形基础在纵、横两个方向上都有一定的抗弯刚度,以减少地基变形,避免过大不均匀沉降,通常在纵、横两个方向上均设置成钢筋混凝土梁的十字交叉条形基础。作为空间承载结构的十字交叉条形基础整体刚度较大,能有效地减小柱基之间的沉降差,满足地基承载力和地基变形的要求,从而保证建筑物的可靠性。For high-rise buildings with large loads, the foundation is weak, the compression uniformity of the foundation soil is poor, or the column load is very different in the vertical and horizontal directions, so the strip foundation needs to have certain resistance in the vertical and horizontal directions In order to reduce the deformation of the foundation and avoid excessive uneven settlement, it is usually set as a crisscross strip foundation of reinforced concrete beams in both the longitudinal and transverse directions. As a space bearing structure, the overall stiffness of the crisscross strip foundation is relatively large, which can effectively reduce the settlement difference between the column foundations and meet the requirements of the bearing capacity of the foundation and the deformation of the foundation, thereby ensuring the reliability of the building.
为保证基础工程及上部结构的可靠性,目前除部分桩基础(含预制木桩、钢管桩、预制混凝土管桩及预制混凝土方桩等)及预制杯口基础在PC构件厂生产养护完成后运至施工现场进行施工外,绝大多数钢筋混凝土基础均在施工现场进行钢筋绑扎及现浇混凝土的施工,待基础混凝土强度达到预定强度后方可进行上部结构的施工,由于钢筋混凝土基础工程的施工及养护时间较长,因此不利于达到缩短工期的目的。In order to ensure the reliability of the foundation engineering and the superstructure, at present, except for some pile foundations (including prefabricated wood piles, steel pipe piles, prefabricated concrete pipe piles and prefabricated concrete square piles, etc.) In addition to being transported to the construction site for construction, most of the reinforced concrete foundations are reinforced with reinforcement and cast-in-place concrete construction at the construction site. The construction of the superstructure can only be carried out after the strength of the foundation concrete reaches the predetermined strength. Due to the construction of the reinforced concrete foundation project And the maintenance time is long, so it is not conducive to the purpose of shortening the construction period.
鉴于目前国外内常用的现浇钢筋混凝土基础(尤其是条形基础)存在以下缺点:①施工现场钢筋混凝土基础施工需要较长时间的养护,不利于缩短工期,现浇钢筋混凝土基础施工完成后不能立即承受不断向上延伸的建筑物结构自重及施工荷载,因而不能与上部结构的施工平行作业;②现场基础工程施工时需要较多的模板和大量施工人员,不利于实现快速安装的建筑工业化;③基础工程的施工在露天进行,受天气及自然环境影响较大,容易因天气原因延长工期;如公开号为CN210946872U的柱下条形基础以及公开号为CN110080264A的一种条形基础局部加固的方法中均存在上述问题。为了解决上述问题,本发明提供一种预制柱墩及后浇条形基础梁装配整体施工方法,来解决施工进度缓慢工期冗长的问题。In view of the fact that the cast-in-place reinforced concrete foundation (especially the strip foundation) commonly used in foreign countries has the following shortcomings: ① The construction of the reinforced concrete foundation on the construction site requires a long time of maintenance, which is not conducive to shortening the construction period. Immediately bear the self-weight and construction load of the building structure that continues to extend upward, so it cannot be operated in parallel with the construction of the superstructure; ② The construction of the on-site foundation project requires more formwork and a large number of construction personnel, which is not conducive to the realization of rapid installation of building industrialization; ③ The construction of the foundation project is carried out in the open air, which is greatly affected by the weather and the natural environment, and the construction period is easily extended due to weather reasons; for example, the bar foundation under the column with the publication number CN210946872U and a method for local reinforcement of the bar foundation with the publication number CN110080264A All of the above problems exist. In order to solve the above problems, the present invention provides an integrated construction method for the assembly of prefabricated column piers and post-cast strip foundation beams, so as to solve the problem of slow construction progress and long construction period.
发明内容SUMMARY OF THE INVENTION
本发明的目的是提供一种预制柱墩及后浇条形基础梁装配整体施工方法,来达到节约工期,加快施工进度的目的。The purpose of the present invention is to provide a prefabricated column pier and post-cast strip foundation beam assembly integral construction method to achieve the purpose of saving construction period and speeding up construction progress.
为实现上述目的,本发明提供了如下方案:For achieving the above object, the present invention provides the following scheme:
一种预制柱墩及后浇条形基础梁装配整体施工方法,包括预制柱墩及后浇条形基础梁,两者共同构成交叉条形基础梁:An integral construction method for assembling a prefabricated column pier and a post-cast strip foundation beam, comprising a prefabricated column pier and a post-cast strip foundation beam, which together form a cross strip foundation beam:
所述预制柱墩顶部向上延伸出用于连接上部结构框架柱纵向受力筋的第一接头钢筋,所述预制柱墩侧面延伸出用于连接后浇条形基础梁肋梁纵向受力钢筋与翼板分布钢筋的第二接头钢筋和第三接头钢筋;The top of the prefabricated column pier extends upwards with the first joint reinforcement for connecting the longitudinal reinforcement of the upper structure frame column, and the side of the prefabricated column pier extends out for connecting the longitudinal reinforcement reinforcement of the post-cast strip foundation beam rib beam with the longitudinal reinforcement reinforcement. The second joint reinforcement and the third joint reinforcement of the wing plate distribution reinforcement;
将所述预制柱墩安放在预定柱位;进行第一结构层框架柱钢筋与预制柱墩第一钢筋接头的连接并浇捣混凝土形成第一结构层框架,在第一结构层至第三结构层施工期间适时同步进行后浇条形基础梁肋梁纵向受力钢筋和翼板分布钢筋分别与第二接头钢筋和第三接头钢筋的连接,浇捣混凝土形成后浇条形基础梁连接相互独立的预制柱墩形成空间刚度较大的交叉条形基础,通过后浇条形基础梁增大基础与地基的接触面积以承受不断向上延伸的结构自重及施工荷载,直至完成整栋建筑物的施工。The prefabricated column pier is placed at the predetermined column position; the connection between the frame column reinforcement of the first structural layer and the first reinforcement joint of the prefabricated column pier is performed, and the concrete is poured to form the first structural layer frame. During the layer construction, the post-cast strip foundation beams, the longitudinal stress reinforcement of the rib beam, and the wing plate distribution reinforcement are connected to the second joint reinforcement and the third joint reinforcement respectively, and the post-cast strip foundation beams are connected independently by pouring and tamping the concrete. The prefabricated column piers form a cross-strip foundation with high spatial rigidity, and the contact area between the foundation and the foundation is increased by post-casting strip foundation beams to bear the self-weight and construction load of the structure extending upwards until the construction of the entire building is completed. .
优选的,在安放所述预制柱墩之前开挖基坑或基槽并设置混凝土垫层,并将所述预制柱墩安放在所述混凝土垫层上预定柱位。Preferably, before placing the prefabricated piers, excavate a foundation pit or a foundation groove and set up a concrete cushion, and place the prefabricated piers on the concrete cushion at a predetermined column position.
优选的,所述预制柱墩包括承载部以及安装在所述承载部周向上的连接部,所述承载部顶部向上延伸出所述第一接头钢筋,所述连接部远离所述承载部的一端延伸出所述第二接头钢筋和第三接头钢筋。Preferably, the prefabricated pier includes a bearing portion and a connecting portion installed in the circumferential direction of the bearing portion, the first joint steel bar extends upward from the top of the bearing portion, and the connecting portion is away from one end of the bearing portion The second and third joint reinforcing bars are extended.
优选的,所述预制柱墩外形为短十字柱体,其底面积应能满足第一结构层至第三结构层的结构自重及施工荷载对地基承载力及变形控制的要求。Preferably, the shape of the prefabricated pier is a short cross cylinder, and its bottom area should meet the requirements of the structural self-weight and construction load of the first structural layer to the third structural layer on the bearing capacity and deformation control of the foundation.
优选的,所述连接部在远离所述承载部端面设置粗糙面,所述粗糙面的面积不小于所述预制柱墩与所述后浇条形基础梁结合面面积的80%。Preferably, the connecting part is provided with a rough surface away from the end face of the bearing part, and the area of the rough surface is not less than 80% of the area of the joint surface between the prefabricated pier and the post-cast strip foundation beam.
优选的,所述连接部远离所述承载部端面设置凹槽,所述凹槽横向贯通所述连接部端面。Preferably, the connecting portion is provided with a groove away from the end face of the bearing portion, and the groove transversely penetrates the end face of the connecting portion.
优选的,所述凹槽的深度不小于30mm,宽度不小于所述凹槽深度的3倍不大于所述凹槽深度的10倍。Preferably, the depth of the groove is not less than 30 mm, and the width is not less than 3 times the depth of the groove and not more than 10 times the depth of the groove.
优选的,所述预制柱墩上安装有用于吊装的吊环。Preferably, a lifting ring for hoisting is installed on the prefabricated pier.
优选的,所述后浇条形基础梁包括肋梁和翼板两部分,所述肋梁设置在所述翼板的中部并保持所述肋梁与所述翼板的端部在同一端面,所述翼板的端面与所述肋梁端面形成倒T形横截面并构成所述连接部。Preferably, the post-casting strip-shaped foundation beam includes two parts: a rib beam and a wing plate, the rib beam is arranged in the middle of the wing plate and keeps the rib beam and the end of the wing plate on the same end surface, the The end face of the wing plate and the end face of the rib beam form an inverted T-shaped cross section and constitute the connecting portion.
优选的,所述后浇条形基础梁肋梁纵向受力钢筋及翼板分布钢筋分别与所述第二接头钢筋和第三接头钢筋采用机械或焊接的方法连接,所述后浇条形基础梁肋梁的箍筋在靠近所述第二接头钢筋和第三接头钢筋的位置设置加密区。Preferably, the post-cast strip-shaped foundation beam rib-beam longitudinal stress reinforcement and the wing plate distribution reinforcement are respectively connected with the second joint reinforcement and the third joint reinforcement by mechanical or welding methods, and the post-cast strip foundation The stirrups of the beam rib beam are provided with densified areas at positions close to the second joint reinforcement and the third joint reinforcement.
本发明相对于现有技术取得了以下技术效果:The present invention has achieved the following technical effects with respect to the prior art:
1、本发明通过提前安放预制柱墩的方式,使预制柱墩承受上部建筑低层结构(第一结构层至第三结构层)自重及施工荷载的同时,在进行上部建筑低层结构框架施工期间适时同步进行后浇条形基础梁的施工,从而达到节约工期的目的,避免了以往条形基础施工时,只能待条形基础梁施工完成后才能进行第一结构层框架柱的施工,在等待条形基础强度达标的过程中,延误工期,影响施工进度。1. The present invention makes the prefabricated column piers bear the self-weight and construction load of the upper building low-rise structure (the first structural layer to the third structural layer) by placing the prefabricated column piers in advance, and at the same time, it is timely during the construction of the upper building low-rise structure frame. Simultaneously carry out the construction of the post-cast strip foundation beams, so as to save the construction period and avoid the construction of the first structural layer frame columns only after the strip foundation beam construction is completed in the previous strip foundation construction. When the strength of the strip foundation reaches the standard, the construction period is delayed and the construction progress is affected.
2、本发明在安放所述预制柱墩之前开挖基坑或基槽并设置混凝土垫层,并将预制柱墩安放在所述混凝土垫层上预定柱位,混凝土垫层的设置保证所有预制柱墩在安放后处于一个稳定水平的状态,预制柱墩顶底面标高与后浇条形基础梁的顶底面标高一致。2. The present invention excavates foundation pits or foundation trenches and sets up a concrete cushion before placing the prefabricated piers, and places the prefabricated piers on the concrete cushions at predetermined column positions. The setting of the concrete cushions ensures that all prefabricated The column pier is in a stable horizontal state after being placed, and the elevation of the top and bottom surfaces of the prefabricated column pier is the same as that of the post-cast strip foundation beam.
3、本发明中预制柱墩包括承载部以及安装在所述承载部周向上的连接部,承载部顶部向上延伸出第一接头钢筋,连接部远离承载部的一端延伸出第二接头钢筋和第三接头钢筋,即上部框架结构柱、后浇条形基础梁与预制柱墩的连接均是钢筋混凝土连接,增强了彼此之间的连接强度及刚度,进而加强交叉条形基础梁结构整体强度及刚度。3. In the present invention, the prefabricated pier includes a bearing portion and a connecting portion installed in the circumferential direction of the bearing portion. The top of the bearing portion extends upward with a first joint steel bar, and the end of the connecting portion away from the bearing portion extends out a second joint steel bar and a first joint steel bar. The three-joint steel bars, that is, the connection between the upper frame structure column, the post-cast strip foundation beam and the prefabricated column pier are all connected by reinforced concrete, which enhances the connection strength and rigidity between each other, and further strengthens the overall strength and strength of the cross strip foundation beam structure. stiffness.
4.本发明预制柱墩上安装有用于吊装的吊环,便于预制柱墩的转运及安放。4. The prefabricated pier of the present invention is provided with a hoisting ring for hoisting, which facilitates the transport and placement of the prefabricated pier.
附图说明Description of drawings
为了更清楚地说明本发明或现有技术中的技术方案,下面将对实施例中所需要使用的附图作简单地介绍,显而易见地,下面描述中的附图仅仅是本发明的一些实施例,对于本领域普通技术人员来讲,在不付出创造性劳动性的前提下,还可以根据这些附图获得其他的附图。In order to more clearly illustrate the present invention or the technical solutions in the prior art, the accompanying drawings required in the embodiments will be briefly introduced below. Obviously, the drawings in the following description are only some embodiments of the present invention. , for those of ordinary skill in the art, other drawings can also be obtained from these drawings without creative labor.
附图1为预制柱墩的结构示意图;
附图2为预制柱墩凹槽的结构示意图;Accompanying
附图3为后浇条形基础梁钢筋笼示意图;Accompanying
附图4为预制柱墩及后浇条形基础梁与上部结构平行作业示意图;
附图5为后浇条形基础梁示意图Accompanying
其中,1、预制柱墩;2、承载部;201、第一接头钢筋;3、连接部;301、第二接头钢筋;302、第三接头钢筋;303、凹槽;4、后浇条形基础梁钢筋笼;401、后浇条形基础梁肋梁纵向受力钢筋;402、后浇条形基础梁翼板分布钢筋;403、后浇条形基础梁翼板横向受弯钢筋;404、后浇条形基础梁肋梁箍筋;5、后浇条形基础梁;501、后浇条形基础梁肋梁;502、后浇条形基础梁翼板;6、第一结构层框架柱;7、第一结构层梁板;Among them, 1. prefabricated column pier; 2. bearing part; 201, first joint steel bar; 3. connecting part; 301, second joint steel bar; 302, third joint steel bar; 303, groove; 4, post-cast bar Reinforcement cage of foundation beam; 401. Longitudinal stress reinforcement of post-cast strip-shaped base beam rib beam; 402. Post-cast strip-shaped base beam wing plate distribution reinforcement; 403. Post-cast strip-shaped base beam and wing plate transverse bending reinforcement; 404, Post-cast strip foundation beam rib beam stirrup; 5. Post-cast strip base beam; 501. Post-cast strip base beam rib beam; 502. Post-cast strip base beam wing plate; 6. Frame column on the first
具体实施方式Detailed ways
下面将结合本发明实施例中的附图,对本发明实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例仅仅是本发明一部分实施例,而不是全部的实施例。基于本发明中的实施例,本领域普通技术人员在没有做出创造性劳动前提下所获得的所有其他实施例,都属于本发明保护的范围。The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings in the embodiments of the present invention. Obviously, the described embodiments are only a part of the embodiments of the present invention, but not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those of ordinary skill in the art without creative efforts shall fall within the protection scope of the present invention.
本发明的目的在于提供一种预制柱墩及后浇条形基础梁装配整体施工方法,来达到节约工期,加快施工进度的目的。The purpose of the present invention is to provide an integral construction method for assembling a prefabricated column pier and a post-cast strip foundation beam, so as to achieve the purpose of saving the construction period and speeding up the construction progress.
为使本发明的上述目的、特征和优点能够更加明显易懂,下面结合附图和具体实施方式对本发明作进一步详细的说明。In order to make the above objects, features and advantages of the present invention more clearly understood, the present invention will be described in further detail below with reference to the accompanying drawings and specific embodiments.
请参考图1~4,一种预制柱墩及后浇条形基础梁装配整体施工方法,包括以下内容:预制柱墩1及后浇条形基础梁5,两者共同构成交叉条形基础梁,所述预制柱墩1顶部向上延伸出用于连接上部结构框架柱纵向受力钢筋的第一接头钢筋201,所述预制柱墩1侧面延伸出用于连接后浇条形基础梁钢筋笼4的第二接头钢筋301和第三接头钢筋302;将所述预制柱墩1安放在预定柱位;进行第一结构层框架柱6受力纵向钢筋和第一接头钢筋201的绑扎并进行第一结构层框架的施工,然后在第一结构层至第三结构层施工期间适时同步进行后浇条形基础梁钢筋笼4肋梁纵向受力钢筋401与第二接头钢筋301连接、翼板分布钢筋402与第三接头钢筋302的连接,在后浇条形基础梁钢筋笼4的翼板分布钢筋402下方绑扎翼板横向受弯钢筋403并为肋梁设置箍筋404,后浇条形基础梁5混凝土,从而完成柱下后浇条形基础梁5的施工;本发明通过提前安放预制柱墩1的方式,在预制柱墩1承受上部建筑低层(第一结构层至第三结构层)结构自重及施工荷载的同时适时同步进行后浇条形基础梁5并完成上部结构的不断延伸施工,从而达到节约工期的目的,避免了以往条形基础施工时只能完成条形基础的施工以后才可以进行第一结构层框架柱6的施工,在等待条形基础强度达标的过程中,延误工期,影响施工进度;进一步的,在预制柱墩1对地基的承载力及变形控制满足上部建筑物低层结构(第一结构层至第三结构层)施工的同时,适时同步进行后浇条形基础梁5,同时进行建筑物上部结构如楼板和框架柱的施工,如此以来,进一步加快了建筑物的施工进度,对于整个建筑物结构的施工进度起到重要影响。Please refer to Figures 1 to 4, an overall construction method for assembling a prefabricated column pier and a post-cast strip foundation beam, including the following contents: a
进一步的,在安放所述预制柱墩1之前开挖基坑或基槽并设置混凝土垫层,并将预制柱墩1安放在所述混凝土垫层上预定柱位,混凝土垫层的设置保证所有预制柱墩1在安放后处于一个稳定水平的状态,预制柱墩1顶底面标高与后浇条形基础梁的顶底面处于同一标高。Further, before placing the
参考图1,预制柱墩1包括承载部2以及安装在所述承载部2周向上的连接部3,承载部2顶部向上延伸出第一接头钢筋201,连接部3远离承载部2的一端延伸出第二接头钢筋301和第三接头钢筋302,即第一结构层框架柱6与预制柱墩1的连接以及后浇条形基础梁5与预制柱墩1的连接均是钢筋混凝土的连接,增强了彼此之间的连接强度及刚度,进而加强后浇交叉条形基础梁5结构整体强度及刚度。Referring to FIG. 1 , the
进一步的,预制柱墩外形为短十字柱体,满足常规条形基础梁横、纵向90°交叉的施工习惯,对于模板的选择具有普遍性,同时,第一结构层框架柱6结构位于短十字柱体预制柱墩1顶部的中心部位,因此,短十字预制柱墩1的四条短臂对于低层框架结构(第一结构层至第三结构层)自重及施工荷载具有分散作用,从而提高了该预制柱墩1的承载能力并满足变形控制;进一步的,预制柱墩1外形整体上也可以为立方体、长方体、圆柱体或锥台体等。Further, the shape of the prefabricated column and pier is a short cross column, which satisfies the construction habit of the conventional strip foundation beams crossing horizontally and vertically at 90°, and the choice of formwork is universal. The central part of the top of the column prefabricated
进一步的,连接部3远离承载部2的一端设置粗糙面,粗糙面的面积不小于预制柱墩1与后浇条形基础梁5结合面积的80%,以增大连接部3与后浇条形基础梁5的连接强度及传力效果。Further, the end of the connecting
参考图2,连接部3远离承载部2的端面设置凹槽303,凹槽303横向贯通承载部2的端面,在后续的施工中,条形基础梁5在浇筑混凝土的过程中会与预制柱墩1上的凹槽303进行连接,而进入到凹槽303内的条形基础梁5的混凝土有利于对预制柱墩1的竖向荷载向后浇条形基础梁5进行可靠传力,同时达到增强彼此连接强度的目的。Referring to FIG. 2 , a
进一步的,凹槽303的深度不小于30mm,宽度不小于所述凹槽303深度的3倍不大于所述凹槽303深度的10倍,达到条形基础梁5与预制柱墩1的最佳连接效果。Further, the depth of the
进一步的,预制柱墩1上安装有用于吊装的吊环,便于预制柱墩1的安放、移动和运输。Further, the
参考图5,条形基础梁5包括肋梁501和翼板502,肋梁501设置在翼板502中部并保持肋梁501与翼板502的端部在同一截面,翼板502端部与肋梁501端部形成倒T形截面并与连接部3连接,倒T形端部会形成稳定的结构基础,翼板的设置增大后浇条形基础梁5与地基的接触面积,从而达到满足地基承载力及变形控制的目的。5, the strip-shaped
进一步的,后浇条形基础梁钢筋笼4中肋梁纵向受力纲筋401与第二接头钢筋301连接,后浇条形基础梁钢筋笼4的翼板分布钢筋402与第三接头钢筋302连接,连接方式可采用机械连接或焊接,后浇条形基础梁钢筋笼4的翼板分布钢筋402下方绑扎翼板横向受弯钢筋403,并为肋梁纵向受力钢筋401设置箍筋404,后浇条形基础梁钢筋笼4肋梁箍筋404在靠近第二接头钢筋301和第三接头钢筋302的位置设置加密区。同时,加密区的设置,加强了后浇条形基础梁5与预制柱墩1的连接强度及刚度。Further, the
根据实际需求而进行的适应性改变均在本发明的保护范围内。Adaptive changes made according to actual needs are all within the protection scope of the present invention.
需要说明的是,对于本领域技术人员而言,显然本发明不限于上述示范性实施例的细节,而且在不背离本发明的精神或基本特征的情况下,能够以其他的具体形式实现本发明。因此,无论从哪一点来看,均应将实施例看作是示范性的,而且是非限制性的,本发明的范围由所附权利要求而不是上述说明限定,因此旨在将落在权利要求的等同要件的含义和范围内的所有变化囊括在发明内。不应将权利要求中的任何附图标记视为限制所涉及的权利要求。It should be noted that it is obvious to those skilled in the art that the present invention is not limited to the details of the above-mentioned exemplary embodiments, and the present invention can be implemented in other specific forms without departing from the spirit or essential characteristics of the present invention. . Therefore, the embodiments are to be regarded in all respects as illustrative and not restrictive, and the scope of the invention is to be defined by the appended claims rather than the foregoing description, which are therefore intended to fall within the scope of the claims. All changes within the meaning and scope of the equivalents of , are included in the invention. Any reference signs in the claims shall not be construed as limiting the involved claim.
Claims (10)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202110724808.4A CN113279423B (en) | 2021-06-29 | 2021-06-29 | Prefabricated column pier and post-cast strip foundation beam assembly integral construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202110724808.4A CN113279423B (en) | 2021-06-29 | 2021-06-29 | Prefabricated column pier and post-cast strip foundation beam assembly integral construction method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN113279423A CN113279423A (en) | 2021-08-20 |
CN113279423B true CN113279423B (en) | 2022-05-24 |
Family
ID=77286077
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202110724808.4A Active CN113279423B (en) | 2021-06-29 | 2021-06-29 | Prefabricated column pier and post-cast strip foundation beam assembly integral construction method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN113279423B (en) |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN115404899A (en) * | 2022-10-14 | 2022-11-29 | 中国十七冶集团有限公司 | A beam-type raft structure and its construction method |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106223463A (en) * | 2016-08-30 | 2016-12-14 | 赵挺生 | A kind of prefabricated node and the prefabricated assembled frame structure of one and construction method thereof |
CN111287206A (en) * | 2020-03-26 | 2020-06-16 | 常州工程职业技术学院 | Assembly type concrete strip foundation module system and construction method |
CN213062068U (en) * | 2020-06-17 | 2021-04-27 | 湘潭大学 | Assembled bar foundation structure |
-
2021
- 2021-06-29 CN CN202110724808.4A patent/CN113279423B/en active Active
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106223463A (en) * | 2016-08-30 | 2016-12-14 | 赵挺生 | A kind of prefabricated node and the prefabricated assembled frame structure of one and construction method thereof |
CN111287206A (en) * | 2020-03-26 | 2020-06-16 | 常州工程职业技术学院 | Assembly type concrete strip foundation module system and construction method |
CN213062068U (en) * | 2020-06-17 | 2021-04-27 | 湘潭大学 | Assembled bar foundation structure |
Also Published As
Publication number | Publication date |
---|---|
CN113279423A (en) | 2021-08-20 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105067211B (en) | Detachable recycling shear wall Experimental Study on Seismic Behavior loading frame and test method | |
CN101775844A (en) | Connecting joint of ring beam of steel core concrete column used for topdown construction method foundation pit engineering | |
CN108005401A (en) | A kind of support and change method of the column of existing frame structure base isolation reinforcement | |
CN108104284B (en) | Wall panel connection structure and assembly method with steel arm of shear wall embedded in floor slab | |
CN102864796B (en) | Construction spreading foundation adaptive to filled ground settlement and construction method | |
CN110080244A (en) | A kind of super-sized foundation pit support replacement backfill structure and construction method | |
CN113216409A (en) | Connecting structure of precast concrete tubular pile column with diagonal bracing and hollow floor or flat floor | |
CN108412100A (en) | Fully assembled sunken floor and connection structure thereof | |
CN207660132U (en) | A kind of wallboard connecting structure of shear wall overhanging steel arm insertion floor end | |
CN105952044A (en) | Fully-prefabricated prestressed concrete floor structure and prestressed assembly method | |
CN113279423B (en) | Prefabricated column pier and post-cast strip foundation beam assembly integral construction method | |
CN101839063B (en) | Movable steel base for constructing prefabricated beam and standard joint thereof | |
CN104032855B (en) | Assembled cross mixing coupled wall and construction method thereof | |
CN201671063U (en) | Movable steel base for construction precast beams and standard knot thereof | |
CN110206020B (en) | Prefabricated snowflake type concrete steel sheet pile and construction method thereof | |
CN116771182B (en) | Building structure of electronic factory building and construction method thereof | |
CN209339171U (en) | Transmission line assembled sheet pile composite foundation | |
CN104032859B (en) | Assembled L-shaped mixing coupled wall and construction method thereof | |
CN104032862B (en) | Assembled girder steel seam line L shape mixing coupled wall and construction method thereof | |
CN201598734U (en) | A Connecting Node of Concrete Steel Tube Column and Ring Beam Used in Foundation Pit Engineering of Upside-Down Method | |
CN217758906U (en) | Assembled anti-settlement beam slab foundation structure | |
CN217299956U (en) | Hollow floor supporting mechanism | |
CN108265883A (en) | A kind of wine cup shape Section of Steel-concrete Composite Beam and its construction method | |
CN208009729U (en) | Assembled horse tooth trough overlap edge-punching sheet metal floorslab with bars | |
CN112854603A (en) | Connecting structure of precast concrete tubular pile column and hollow floor or flat floor |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant | ||
EE01 | Entry into force of recordation of patent licensing contract | ||
EE01 | Entry into force of recordation of patent licensing contract |
Application publication date: 20210820 Assignee: Hunan Yihui Construction Co.,Ltd. Assignor: University OF SOUTH CHINA Contract record no.: X2024980011419 Denomination of invention: A method for overall construction of prefabricated column piers and post cast strip foundation beams assembly Granted publication date: 20220524 License type: Common License Record date: 20240809 |