CN113137247B - Method for improving concrete pouring efficiency and compactness of tunnel secondary lining arch wall - Google Patents
Method for improving concrete pouring efficiency and compactness of tunnel secondary lining arch wall Download PDFInfo
- Publication number
- CN113137247B CN113137247B CN202110339961.5A CN202110339961A CN113137247B CN 113137247 B CN113137247 B CN 113137247B CN 202110339961 A CN202110339961 A CN 202110339961A CN 113137247 B CN113137247 B CN 113137247B
- Authority
- CN
- China
- Prior art keywords
- pouring
- concrete
- arch wall
- grouting
- moulds
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/04—Lining with building materials
- E21D11/10—Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
- E21D11/102—Removable shuttering; Bearing or supporting devices therefor
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/04—Lining with building materials
- E21D11/10—Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
- E21D11/105—Transport or application of concrete specially adapted for the lining of tunnels or galleries ; Backfilling the space between main building element and the surrounding rock, e.g. with concrete
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Architecture (AREA)
- Mining & Mineral Resources (AREA)
- Civil Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Geology (AREA)
- Lining And Supports For Tunnels (AREA)
Abstract
本发明公开了一种提高隧道二衬拱墙混凝土浇筑效率及密实度的方法,在拱墙施工时,利用钢模台车作为模板,钢模台车设置有多个浇筑口及带模注浆孔,并采用小块钢模封堵端模;浇筑时,将泵管接入端部浇筑口,开启所有浇筑口闸板并浇筑高性能微膨胀自密实混凝土,浇筑过程中无需切换浇筑口,利用单浇筑口将混凝土挤推至远端进行浇筑并结合带模注浆孔、端模溢浆情况进行浇筑密实情况判断,浇筑完成后立即进行带模注浆,大幅提升了浇筑效率及二衬拱墙浇筑密实度,有效保证了隧道施工质量。
The invention discloses a method for improving the concrete pouring efficiency and density of the second lining arch wall of a tunnel. During the construction of the arch wall, a steel formwork trolley is used as a template. The steel formwork trolley is equipped with multiple pouring openings and belt mold grouting. hole, and use a small piece of steel form to seal the end mold; when pouring, connect the pump pipe to the end pouring port, open all the pouring port gates and pour high-performance micro-expansion self-compacting concrete. There is no need to switch the pouring port during the pouring process. The single pouring port is used to push the concrete to the far end for pouring, and the pouring density is judged based on the mold grouting holes and end mold overflow conditions. After the pouring is completed, the molded grouting is performed immediately, which greatly improves the pouring efficiency and the secondary lining. The density of the arch wall pouring effectively ensures the quality of tunnel construction.
Description
技术领域Technical field
本发明涉及隧道二衬施工技术领域,具体为一种提高隧道二衬拱墙混凝土浇筑效率及密实度的方法。The invention relates to the technical field of tunnel secondary lining construction, specifically a method for improving the concrete pouring efficiency and compactness of the tunnel secondary lining arch wall.
背景技术Background technique
在隧道二衬施工领域,拱墙施工或多或少都会存在拱顶浇筑不密实和空洞的质量通病,且浇筑效率极低,究其原因有:一是拱顶空气未排出,形成空腔造成拱顶位置混凝土不饱满;二是端模封堵可靠性差,无法承受较大泵压,导致无法适当超灌;三是混凝土养护过程中存在收缩现象,造成拱顶脱空;四是二衬钢筋布置密集振捣效果不佳;五是需频繁更换浇筑口,停泵频繁,易形成冷缝,且增加浇筑时间。故如何提高二衬拱墙混凝土浇筑密实度及浇筑效率是决定二衬施工成败的关键。In the field of tunnel secondary lining construction, arch wall construction will more or less have the common quality problem of poor pouring and cavities in the vault, and the pouring efficiency is extremely low. The reasons are as follows: First, the air in the vault is not discharged, forming a cavity and causing The concrete at the vault is not full; secondly, the end form sealing has poor reliability and cannot withstand large pump pressure, resulting in the inability to properly overfill; thirdly, there is shrinkage during the concrete curing process, causing the vault to become hollow; fourthly, the secondary lining of steel bars The effect of intensive vibration arrangement is not good; fifthly, the pouring port needs to be replaced frequently, the pump is stopped frequently, cold joints are easily formed, and the pouring time is increased. Therefore, how to improve the concrete pouring density and pouring efficiency of the secondary lining arch wall is the key to determining the success or failure of the secondary lining construction.
发明内容Contents of the invention
为了克服现有技术中的上述技术缺陷,本发明提供了一种提高隧道二衬拱墙混凝土浇筑效率及密实度的方法,在拱墙浇筑过程中无需频繁切换浇筑口,大幅提升了浇筑效率及二衬拱墙浇筑密实度,有效保证了隧道施工质量,解决了上述技术问题。In order to overcome the above-mentioned technical defects in the prior art, the present invention provides a method for improving the concrete pouring efficiency and compactness of the second lining arch wall of a tunnel. During the arch wall pouring process, there is no need to frequently switch pouring ports, which greatly improves the pouring efficiency and density. The pouring density of the secondary lining arch wall effectively ensures the quality of tunnel construction and solves the above technical problems.
本发明通过以下技术方案来实现上述目的,一种提高隧道二衬拱墙混凝土浇筑效率及密实度的方法,该方法中使用的拱墙浇筑模板为钢模台车,混凝土采用高性能微膨胀自密实混凝土,浇筑完成后需进行带模注浆。The present invention achieves the above object through the following technical solution: a method for improving the concrete pouring efficiency and compactness of the second lining arch wall of a tunnel. The arch wall pouring formwork used in this method is a steel formwork trolley, and the concrete adopts high-performance micro-expansion automatic For dense concrete, formwork grouting is required after the pouring is completed.
钢模台车设置有多个浇筑口及带模注浆孔,带模注浆孔设置在浇筑口两侧,浇筑口设置有活动闸板,钢模台车配置有小块定型钢模进行端模封堵,小块定型钢模与钢模台车端部法兰采用螺栓连接,螺栓孔均为长圆孔,并设置角钢背楞对小块定型钢模进行加强,提高端模的承压能力,小块定型钢模上的长圆孔为径向长圆孔,钢模台车法兰上的长圆孔为环向长圆孔,高性能微膨胀自密实混凝土入模坍落扩展度不小于600mm,限制膨胀率大于0.015%。The steel formwork trolley is equipped with multiple pouring openings and molded grouting holes. The molded grouting holes are set on both sides of the pouring opening. The pouring opening is equipped with movable gates. The steel formwork trolley is equipped with a small shaped steel mold for end The mold is sealed, and the small shaped steel mold is connected to the end flange of the steel mold trolley using bolts. The bolt holes are all oblong holes, and angle steel back ribs are set up to strengthen the small shaped steel mold and improve the pressure bearing capacity of the end mold. , the oblong hole on the small shaped steel mold is a radial oblong hole, the oblong hole on the steel formwork trolley flange is a circumferential oblong hole, the slump expansion of high-performance micro-expansion self-compacting concrete into the mold is not less than 600mm, the limit The expansion rate is greater than 0.015%.
环向调节可确保小块定型钢模之间安装紧密,径向调节可确保小块定型钢模之间紧贴初支面。The circumferential adjustment can ensure that the small pieces of shaped steel molds are installed tightly, and the radial adjustment can ensure that the small pieces of shaped steel molds are closely connected to the initial support surface.
一种提高隧道二衬拱墙混凝土浇筑效率及密实度的方法包括以下施工步骤:A method to improve the concrete pouring efficiency and density of the secondary lining arch wall of a tunnel includes the following construction steps:
S1:将带模注浆管安装到位,并将所有浇筑口闸板打开;S1: Install the molded grouting pipe in place and open all pouring gates;
S2:将泵管连接至端部浇筑口进行浇筑;S2: Connect the pump pipe to the end pouring port for pouring;
S3:浇筑至至侧模观察窗时,适当停泵,开启平板振捣器进行振捣;S3: When pouring reaches the observation window of the side mold, stop the pump appropriately and turn on the flat vibrator for vibration;
S4:当其他浇筑口溢浆时关闭其闸板继续浇筑,直到所有带模注浆管及端模最高端均溢浆,即可完成浇筑。S4: When other pouring openings overflow with grout, close their gates and continue pouring until all grouting pipes with molds and the highest ends of the end molds overflow with grout, then the pouring can be completed.
上述的一种提高隧道二衬拱墙混凝土浇筑效率及密实度的方法,整个浇筑过程只利用端部浇筑进行单口浇筑,不更换浇筑口。The above-mentioned method to improve the concrete pouring efficiency and compactness of the secondary lining arch wall of the tunnel is to use only the end pouring for single-port pouring during the entire pouring process without changing the pouring port.
上述的一种提高隧道二衬拱墙混凝土浇筑效率及密实度的方法,所述的带模注浆在浇筑完成后立即实施The above-mentioned method of improving the concrete pouring efficiency and compactness of the secondary lining arch wall of a tunnel, the described grouting with formwork is implemented immediately after the pouring is completed.
总体而言,通过本发明所构思的以上技术方案与现有技术相比,可以达到以下有益效果:本发明一种提高隧道二衬拱墙混凝土浇筑效率及密实度的方法,在拱墙浇筑过程中无需频繁切换浇筑口,大幅提升了浇筑效率及二衬拱墙浇筑密实度,有效保证了隧道施工质量。Generally speaking, compared with the prior art, the above technical solutions conceived by the present invention can achieve the following beneficial effects: The present invention is a method for improving the concrete pouring efficiency and compactness of the secondary lining arch wall of a tunnel. During the arch wall pouring process, There is no need to frequently switch pouring openings, which greatly improves the pouring efficiency and the pouring density of the secondary lining arch wall, effectively ensuring the quality of tunnel construction.
附图说明Description of the drawings
下面结合附图对本发明的具体实施方式做进一步详细的说明,其中:The specific embodiments of the present invention will be described in further detail below with reference to the accompanying drawings, wherein:
图1为本发明所述的钢模台车浇筑口及带模注浆孔布置图;Figure 1 is a layout diagram of the pouring opening of the steel formwork trolley and the grouting hole with the mold according to the present invention;
图2为本发明的端模封堵所采用的小块定型钢模结构示意图;Figure 2 is a schematic structural diagram of a small shaped steel mold used in the end mold sealing of the present invention;
图中:1-浇筑口,2-带模注浆孔,3-观察窗,4-小块定型钢模,5-角钢,6-长圆孔。In the picture: 1-pouring port, 2-grouting hole with mold, 3-observation window, 4-small shaped steel mold, 5-angle steel, 6-oblong hole.
具体实施方式Detailed ways
本发明一种提高隧道二衬拱墙混凝土浇筑效率及密实度的方法,该方法中使用的拱墙浇筑模板为钢模台车,混凝土采用高性能微膨胀自密实混凝土,浇筑完成后需进行带模注浆。The invention is a method for improving the concrete pouring efficiency and compactness of the secondary lining arch wall of a tunnel. The arch wall pouring template used in the method is a steel formwork trolley, and the concrete is made of high-performance micro-expansion self-compacting concrete. After the pouring is completed, it needs to be belted. Mold grouting.
钢模台车设置有多个浇筑口1及带模注浆孔2,钢模台车上浇筑口1及带模注浆孔2的布置如图1所示,带模注浆孔2设置在浇筑口1两侧,浇筑口1设置有活动闸板,钢模台车的侧端面配置有小块定型钢模4进行端模封堵。The steel formwork trolley is provided with multiple pouring openings 1 and molded grouting holes 2. The layout of the pouring openings 1 and molded grouting holes 2 on the steel formwork trolley is shown in Figure 1. The molded grouting holes 2 are arranged on On both sides of the pouring port 1, the pouring port 1 is provided with movable gates, and the side end face of the steel mold trolley is equipped with a small shaped steel mold 4 for end mold sealing.
端模封堵采用的小块定型钢模4如图2所示,小块定型钢模4与钢模台车端部法兰采用螺栓连接,螺栓孔均为长圆孔6,并设置角钢5背楞对小块定型钢模4进行加强,小块定型钢模4上的长圆孔6为径向长圆孔,钢模台车法兰上的长圆孔6为环向长圆孔,高性能微膨胀自密实混凝土入模坍落扩展度不小于600mm,限制膨胀率大于0.015%。The small shaped steel mold 4 used for end mold sealing is shown in Figure 2. The small shaped steel mold 4 is connected to the end flange of the steel mold trolley by bolts. The bolt holes are all oblong holes 6, and angle steel 5 is provided on the back. The small shaped steel mold 4 is reinforced. The oblong holes 6 on the small shaped steel mold 4 are radial oblong holes, and the oblong holes 6 on the flange of the steel mold trolley are circumferential oblong holes. High-performance micro-expansion automatic The slump expansion of dense concrete into the mold is not less than 600mm, and the limited expansion rate is greater than 0.015%.
所述的浇筑方法包括以下施工步骤:The pouring method includes the following construction steps:
步骤一:将带模注浆管安装到位,并将所有浇筑口1闸板打开;Step 1: Install the molded grouting pipe in place and open all pouring port 1 gates;
步骤二:将泵管连接至端部浇筑口1进行浇筑;Step 2: Connect the pump pipe to the end pouring port 1 for pouring;
步骤三:浇筑至至侧模观察窗时,适当停泵,开启平板振捣器进行振捣;Step 3: When pouring reaches the observation window of the side mold, stop the pump appropriately and turn on the flat vibrator for vibration;
步骤四:当其他浇筑口1溢浆时关闭其闸板继续浇筑,直到所有带模注浆管及端模最高端均溢浆,即可完成浇筑。Step 4: When the other pouring port 1 overflows with grout, close its gate and continue pouring until all the molded grouting pipes and the highest end of the end mold overflow with grout, then the pouring can be completed.
整个浇筑过程只利用端部浇筑口1进行单口浇筑,不更换浇筑口,在混凝土浇筑完毕后立即实施带模注浆。During the entire pouring process, only the end pouring port 1 is used for single pouring without changing the pouring port. Grouting with formwork is performed immediately after the concrete pouring is completed.
本发明工序简单,在拱墙浇筑过程中无需频繁切换浇筑口,大幅提升了浇筑效率及二衬拱墙浇筑密实度,有效保证了隧道施工质量。The process of the invention is simple, and there is no need to frequently switch the pouring opening during the arch wall pouring process, which greatly improves the pouring efficiency and the pouring density of the secondary lining arch wall, and effectively ensures the quality of tunnel construction.
本领域的技术人员容易理解,以上所述仅为本发明的较佳实施例而已,并不用于限制本发明,凡在本发明的精神和原则之内所作的任何修改、等同替换和改进等,均应包含在本发明的保护范围之内。It is easy for those skilled in the art to understand that the above descriptions are only preferred embodiments of the present invention and are not intended to limit the present invention. Any modifications, equivalent substitutions and improvements, etc., made within the spirit and principles of the present invention, All should be included in the protection scope of the present invention.
Claims (3)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202110339961.5A CN113137247B (en) | 2021-03-30 | 2021-03-30 | Method for improving concrete pouring efficiency and compactness of tunnel secondary lining arch wall |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202110339961.5A CN113137247B (en) | 2021-03-30 | 2021-03-30 | Method for improving concrete pouring efficiency and compactness of tunnel secondary lining arch wall |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN113137247A CN113137247A (en) | 2021-07-20 |
| CN113137247B true CN113137247B (en) | 2023-10-20 |
Family
ID=76811632
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202110339961.5A Active CN113137247B (en) | 2021-03-30 | 2021-03-30 | Method for improving concrete pouring efficiency and compactness of tunnel secondary lining arch wall |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN113137247B (en) |
Families Citing this family (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN113847063B (en) * | 2021-09-26 | 2024-01-26 | 兰州理工大学 | Tunnel secondary lining concrete construction simulation method |
Citations (7)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2004190286A (en) * | 2002-12-10 | 2004-07-08 | Gifu Kogyo Co Ltd | Concrete placing method and its apparatus for tunnel |
| JP2015094167A (en) * | 2013-11-13 | 2015-05-18 | 鹿島建設株式会社 | Concrete placement method |
| CN207634088U (en) * | 2017-11-01 | 2018-07-20 | 中铁隧道勘察设计研究院有限公司 | A kind of grouped controls for lining trolley and tamping equipment |
| CN109026065A (en) * | 2018-07-25 | 2018-12-18 | 中铁十六局集团有限公司 | A kind of Tunnel Second Lining zero-fault construction method |
| CN110410106A (en) * | 2019-07-30 | 2019-11-05 | 中铁十二局集团有限公司 | Tunnel vault band film grouting construction method |
| CN111335922A (en) * | 2020-03-25 | 2020-06-26 | 陕西公路交通科技开发咨询公司 | Lining trolley and tunnel secondary lining construction method using lining trolley |
| CN211258625U (en) * | 2019-08-30 | 2020-08-14 | 中铁五局集团第五工程有限责任公司 | Tunnel secondary lining platform truck end template |
-
2021
- 2021-03-30 CN CN202110339961.5A patent/CN113137247B/en active Active
Patent Citations (7)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2004190286A (en) * | 2002-12-10 | 2004-07-08 | Gifu Kogyo Co Ltd | Concrete placing method and its apparatus for tunnel |
| JP2015094167A (en) * | 2013-11-13 | 2015-05-18 | 鹿島建設株式会社 | Concrete placement method |
| CN207634088U (en) * | 2017-11-01 | 2018-07-20 | 中铁隧道勘察设计研究院有限公司 | A kind of grouped controls for lining trolley and tamping equipment |
| CN109026065A (en) * | 2018-07-25 | 2018-12-18 | 中铁十六局集团有限公司 | A kind of Tunnel Second Lining zero-fault construction method |
| CN110410106A (en) * | 2019-07-30 | 2019-11-05 | 中铁十二局集团有限公司 | Tunnel vault band film grouting construction method |
| CN211258625U (en) * | 2019-08-30 | 2020-08-14 | 中铁五局集团第五工程有限责任公司 | Tunnel secondary lining platform truck end template |
| CN111335922A (en) * | 2020-03-25 | 2020-06-26 | 陕西公路交通科技开发咨询公司 | Lining trolley and tunnel secondary lining construction method using lining trolley |
Also Published As
| Publication number | Publication date |
|---|---|
| CN113137247A (en) | 2021-07-20 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN113137247B (en) | Method for improving concrete pouring efficiency and compactness of tunnel secondary lining arch wall | |
| CN112302685B (en) | Formwork grouting system and construction method for tunnel lining vault | |
| CN210910496U (en) | Prefabricated wallboard horizontally connect with pore-forming mould to drawing bolt hole | |
| CN219686033U (en) | Prefabricated bridge overhauls ladder template device of marking time | |
| CN202727092U (en) | Plugging device for position of straight rib of side mold of precast concrete component of wall | |
| CN201030418Y (en) | Blast Furnace Main Ditch Integrated Casting Mold | |
| CN211941362U (en) | Butt-joint type elastic grout-blocking clamp of sleeper mould | |
| CN219343472U (en) | A kind of sewage well with built-in flange structure sealing connection | |
| CN209478433U (en) | An autoclaved lightweight sand aerated concrete slab pouring device | |
| CN210679085U (en) | A kind of cement slurry filling plastic mold rainwater gully | |
| CN218844317U (en) | A concrete steam curing structure | |
| CN220699956U (en) | A polymer mortar forming auxiliary device | |
| CN105113783B (en) | A kind of construction formwork and its construction method of gypsum cast-in-situ wall | |
| CN202556558U (en) | Precast concrete sewage inspection shaft steel die | |
| CN223849540U (en) | A pneumatic backflushing precast template | |
| CN219445474U (en) | Adjusting device for gap of diaphragm wall | |
| CN120516821B (en) | A production mold for prefabricated concrete box culverts | |
| CN219464695U (en) | A steel mold for inspection well | |
| CN220621886U (en) | Template structure suitable for tunnel cast-in-place concrete lining | |
| CN111705565A (en) | Post-pouring zone pouring support system and post-pouring zone pouring construction method | |
| CN220725777U (en) | Pump pipe shunt for pouring cast-in-situ shear wall with built-in EPS plates | |
| CN222701497U (en) | Prefabricated inspection shaft pipeline interface closing die | |
| CN209851177U (en) | Square precast concrete assembled inspection shaft mould | |
| CN204414349U (en) | The vertical integrally forming mould of Novel precast concrete pipe sheet | |
| CN217977950U (en) | An underground temporary sealing structure for water supply and drainage engineering |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| GR01 | Patent grant | ||
| GR01 | Patent grant |