CN113137247A - Method for improving concrete pouring efficiency and compactness of tunnel secondary lining arch wall - Google Patents

Method for improving concrete pouring efficiency and compactness of tunnel secondary lining arch wall Download PDF

Info

Publication number
CN113137247A
CN113137247A CN202110339961.5A CN202110339961A CN113137247A CN 113137247 A CN113137247 A CN 113137247A CN 202110339961 A CN202110339961 A CN 202110339961A CN 113137247 A CN113137247 A CN 113137247A
Authority
CN
China
Prior art keywords
pouring
mould
pour
concrete
arch wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202110339961.5A
Other languages
Chinese (zh)
Other versions
CN113137247B (en
Inventor
戴小松
刘开扬
余南山
贾瑞华
叶亦盛
谷海华
陈伟
许剑波
鲁文博
彭文韬
刘康宇
鲁翔翔
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Ccteb Infrastructure Construction Investment Co ltd
China State Construction Engineering Corp Ltd CSCEC
China Construction Third Engineering Bureau Co Ltd
Original Assignee
Ccteb Infrastructure Construction Investment Co ltd
China State Construction Engineering Corp Ltd CSCEC
China Construction Third Engineering Bureau Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Ccteb Infrastructure Construction Investment Co ltd, China State Construction Engineering Corp Ltd CSCEC, China Construction Third Engineering Bureau Co Ltd filed Critical Ccteb Infrastructure Construction Investment Co ltd
Priority to CN202110339961.5A priority Critical patent/CN113137247B/en
Publication of CN113137247A publication Critical patent/CN113137247A/en
Application granted granted Critical
Publication of CN113137247B publication Critical patent/CN113137247B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/102Removable shuttering; Bearing or supporting devices therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/105Transport or application of concrete specially adapted for the lining of tunnels or galleries ; Backfilling the space between main building element and the surrounding rock, e.g. with concrete

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Architecture (AREA)
  • Mining & Mineral Resources (AREA)
  • Civil Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The invention discloses a method for improving the concrete pouring efficiency and compactness of a tunnel secondary lining arch wall, which comprises the following steps of utilizing a steel mould trolley as a template during the construction of the arch wall, wherein the steel mould trolley is provided with a plurality of pouring ports and mould-carrying pouring holes, and adopting a small steel mould to plug an end mould; when pouring, insert the tip with the pump line and pour the mouth, open all and pour a mouthful flashboard and pour high performance micro-expansion self-compaction concrete, it need not to switch and pours the mouth to pour the in-process, utilize single mouthful of pouring to push away the concrete crowded distal end and pour and combine area mould slip casting hole, the dense condition judgement is pour to the excessive thick liquid condition of end mould, pour and carry out area mould slip casting immediately after accomplishing, promoted pouring efficiency and two lining arch walls by a wide margin and pour closely knit degree, effectively guaranteed tunnel construction quality.

Description

Method for improving concrete pouring efficiency and compactness of tunnel secondary lining arch wall
Technical Field
The invention relates to the technical field of tunnel secondary lining construction, in particular to a method for improving the concrete pouring efficiency and compactness of a tunnel secondary lining arch wall.
Background
In two lining construction fields in the tunnel, more or less all can have the vault to pour the quality general fault that is not closely knit and cavity in the arch wall construction, and pour efficiency extremely low, it has to do its reason: firstly, air at the vault is not discharged, and a cavity is formed to cause that concrete at the vault position is not full; secondly, the reliability of end mold plugging is poor, and the end mold plugging cannot bear large pump pressure, so that proper over-irrigation cannot be realized; thirdly, the vault is hollowed due to the shrinkage phenomenon in the concrete curing process; fourthly, the dense vibrating effect of the second lining steel bar arrangement is not good; fifthly, the pouring opening needs to be replaced frequently, the pump is stopped frequently, a cold joint is easy to form, and the pouring time is prolonged. Therefore, how to improve the concrete pouring compactness and pouring efficiency of the second-lining arch wall is the key for determining the success or failure of the second-lining construction.
Disclosure of Invention
In order to overcome the technical defects in the prior art, the invention provides a method for improving the pouring efficiency and the compactness of the tunnel double-lined arch wall concrete.
The invention realizes the aim through the following technical scheme, and provides a method for improving the concrete pouring efficiency and the compactness of a tunnel secondary lining arch wall.
The steel mould trolley is provided with a plurality of pouring openings and mould-carrying grouting holes, the mould-carrying grouting holes are arranged on two sides of each pouring opening, each pouring opening is provided with a movable gate plate, the steel mould trolley is configured with a small shaping steel mould for end mould plugging, the small shaping steel mould is connected with a steel mould trolley end flange through bolts, bolt holes are all long round holes, an angle steel back edge is arranged to reinforce the small shaping steel mould, the bearing capacity of an end mould is improved, the long round holes in the small shaping steel mould are radial long round holes, the long round holes in the steel mould trolley flange are annular long round holes, high-performance micro-expansion self-compacting concrete is poured into the mould with the slump expansion degree not less than 600mm, and the limited expansion rate is greater than 0.015%.
The annular adjustment can ensure that the small blocks of the sizing steel dies are tightly installed, and the radial adjustment can ensure that the small blocks of the sizing steel dies are tightly attached to the primary support surface.
The method for improving the concrete pouring efficiency and compactness of the tunnel secondary lining arch wall comprises the following construction steps:
s1: installing the injection pipe with the mold in place, and opening all pouring port flashboards;
s2: connecting the pump pipe to the end pouring opening for pouring;
s3: when pouring to the side mold observation window, stopping the pump properly, and starting the flat plate vibrator for vibrating;
s4: and closing the gate plates of the other pouring openings when the slurry overflows, and continuously pouring until all the grouting pipes with the molds and the highest ends of the end molds overflow the slurry, so that pouring can be finished.
According to the method for improving the concrete pouring efficiency and the compactness of the tunnel secondary lining arch wall, the single-opening pouring is carried out only by using end pouring in the whole pouring process, and a pouring opening is not replaced.
According to the method for improving the concrete pouring efficiency and compactness of the tunnel secondary lining arch wall, the mould-carrying grouting is carried out immediately after the pouring is finished
Generally, compared with the prior art, the technical scheme of the invention can achieve the following beneficial effects: according to the method for improving the pouring efficiency and the compactness of the concrete of the tunnel secondary lining arch wall, frequent switching of pouring ports is not needed in the pouring process of the arch wall, the pouring efficiency and the pouring compactness of the secondary lining arch wall are greatly improved, and the construction quality of the tunnel is effectively guaranteed.
Drawings
The following detailed description of embodiments of the invention is provided in conjunction with the appended drawings, in which:
FIG. 1 is a layout view of a steel form trolley pouring opening and a molded grouting hole according to the present invention;
FIG. 2 is a schematic structural view of a small block sizing steel die used for end die plugging of the present invention;
in the figure: 1-pouring opening, 2-pouring hole with mold, 3-observation window, 4-small shaping steel mold, 5-angle steel and 6-long round hole.
Detailed Description
The invention relates to a method for improving the concrete pouring efficiency and compactness of a tunnel secondary lining arch wall.
The steel mould trolley is provided with a plurality of pouring ports 1 and mould-carrying grouting holes 2, the arrangement of the pouring ports 1 and the mould-carrying grouting holes 2 on the steel mould trolley is as shown in figure 1, the mould-carrying grouting holes 2 are arranged on two sides of the pouring ports 1, the pouring ports 1 are provided with movable gate plates, and the side end face of the steel mould trolley is provided with a small block sizing steel mould 4 for end mould plugging.
The small block shaping steel die 4 adopted by end die plugging is shown in fig. 2, the small block shaping steel die 4 is in bolted connection with a steel die trolley end flange, bolt holes are all long round holes 6, an angle steel 5 back edge is arranged to reinforce the small block shaping steel die 4, the long round holes 6 in the small block shaping steel die 4 are radial long round holes, the long round holes 6 in the steel die trolley flange are circumferential long round holes, the high-performance micro-expansion self-compaction concrete in-die slump expansion degree is not less than 600mm, and the expansion limiting rate is greater than 0.015%.
The pouring method comprises the following construction steps:
the method comprises the following steps: installing the injection pipe with the mold in place, and opening the flashboards of all the pouring openings 1;
step two: connecting a pump pipe to the end pouring opening 1 for pouring;
step three: when pouring to the side mold observation window, stopping the pump properly, and starting the flat plate vibrator for vibrating;
step four: and closing the gate plates of the other pouring openings 1 when the slurry overflows, and continuously pouring until all the grouting pipes with the molds and the highest ends of the end molds overflow the slurry, thus finishing pouring.
In the whole pouring process, single-port pouring is carried out only by using the end pouring port 1, the pouring port is not replaced, and the pouring with the mold is immediately carried out after the concrete pouring is finished.
The method has simple process, does not need to frequently switch pouring ports in the pouring process of the arch wall, greatly improves the pouring efficiency and the pouring compactness of the secondary lining arch wall, and effectively ensures the tunnel construction quality.
It will be understood by those skilled in the art that the foregoing is only a preferred embodiment of the present invention, and is not intended to limit the invention, and that any modification, equivalent replacement, or improvement made within the spirit and principle of the present invention should be included in the scope of the present invention.

Claims (3)

1. A method for improving the concrete pouring efficiency and compactness of a tunnel secondary lining arch wall is characterized in that an arch wall pouring template used in the method is a steel mould trolley, the concrete adopts high-performance micro-expansion self-compaction concrete, and the pouring is performed with mould grouting;
the steel mould trolley is provided with a plurality of pouring openings (1) and mould-carrying grouting holes (2), the mould-carrying grouting holes (2) are formed in two sides of each pouring opening (1), each pouring opening (1) is provided with a movable gate plate, the steel mould trolley is configured with a small shaping steel mould (4) for end mould plugging, the small shaping steel mould (4) is connected with a flange at the end of the steel mould trolley through bolts, bolt holes are all long round holes (6), an angle steel (5) back edge is arranged to reinforce the small shaping steel mould (4), the long round holes (6) in the small shaping steel mould (4) are radial long round holes, the long round holes (6) in the flange of the steel mould trolley are circumferential long round holes, the slump expansion degree of the high-performance micro-expansion self-compaction concrete in the mould is not less than 600mm, and the expansion limiting rate is more than 0.015%;
the pouring method comprises the following construction steps:
s1: installing the injection pipe with the mould in place, and opening the flashboards of all pouring openings (1);
s2: connecting the pump pipe to the end pouring opening (1) for pouring;
s3: when pouring to the side mold observation window, stopping the pump properly, and starting the flat plate vibrator for vibrating;
s4: and closing the gate plates of the other pouring openings (1) when the slurry overflows, and continuing pouring until all the grouting pipes with the molds and the highest ends of the end molds overflow the slurry, thus finishing pouring.
2. The method for improving the pouring efficiency and the compactness of the tunnel secondary lining arch wall concrete according to claim 1, characterized in that the whole pouring process only uses the end pouring opening (1) to carry out single-opening pouring without replacing the pouring opening.
3. The method for improving the pouring efficiency and compactness of the tunnel secondary lining arch wall concrete according to claim 1, wherein the tape casting is performed immediately after the pouring is completed.
CN202110339961.5A 2021-03-30 2021-03-30 Method for improving concrete pouring efficiency and compactness of tunnel secondary lining arch wall Active CN113137247B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110339961.5A CN113137247B (en) 2021-03-30 2021-03-30 Method for improving concrete pouring efficiency and compactness of tunnel secondary lining arch wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110339961.5A CN113137247B (en) 2021-03-30 2021-03-30 Method for improving concrete pouring efficiency and compactness of tunnel secondary lining arch wall

Publications (2)

Publication Number Publication Date
CN113137247A true CN113137247A (en) 2021-07-20
CN113137247B CN113137247B (en) 2023-10-20

Family

ID=76811632

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110339961.5A Active CN113137247B (en) 2021-03-30 2021-03-30 Method for improving concrete pouring efficiency and compactness of tunnel secondary lining arch wall

Country Status (1)

Country Link
CN (1) CN113137247B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113847063A (en) * 2021-09-26 2021-12-28 兰州理工大学 Tunnel secondary lining concrete construction simulation system and simulation method

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004190286A (en) * 2002-12-10 2004-07-08 Gifu Kogyo Co Ltd Concrete placing method and its apparatus for tunnel
JP2015094167A (en) * 2013-11-13 2015-05-18 鹿島建設株式会社 Concrete placing method
CN207634088U (en) * 2017-11-01 2018-07-20 中铁隧道勘察设计研究院有限公司 A kind of grouped controls for lining trolley and tamping equipment
CN109026065A (en) * 2018-07-25 2018-12-18 中铁十六局集团有限公司 A kind of Tunnel Second Lining zero-fault construction method
CN110410106A (en) * 2019-07-30 2019-11-05 中铁十二局集团有限公司 Tunnel vault band film grouting construction method
CN111335922A (en) * 2020-03-25 2020-06-26 陕西公路交通科技开发咨询公司 Lining trolley and tunnel secondary lining construction method using lining trolley
CN211258625U (en) * 2019-08-30 2020-08-14 中铁五局集团第五工程有限责任公司 Tunnel secondary lining platform truck end template

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004190286A (en) * 2002-12-10 2004-07-08 Gifu Kogyo Co Ltd Concrete placing method and its apparatus for tunnel
JP2015094167A (en) * 2013-11-13 2015-05-18 鹿島建設株式会社 Concrete placing method
CN207634088U (en) * 2017-11-01 2018-07-20 中铁隧道勘察设计研究院有限公司 A kind of grouped controls for lining trolley and tamping equipment
CN109026065A (en) * 2018-07-25 2018-12-18 中铁十六局集团有限公司 A kind of Tunnel Second Lining zero-fault construction method
CN110410106A (en) * 2019-07-30 2019-11-05 中铁十二局集团有限公司 Tunnel vault band film grouting construction method
CN211258625U (en) * 2019-08-30 2020-08-14 中铁五局集团第五工程有限责任公司 Tunnel secondary lining platform truck end template
CN111335922A (en) * 2020-03-25 2020-06-26 陕西公路交通科技开发咨询公司 Lining trolley and tunnel secondary lining construction method using lining trolley

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113847063A (en) * 2021-09-26 2021-12-28 兰州理工大学 Tunnel secondary lining concrete construction simulation system and simulation method
CN113847063B (en) * 2021-09-26 2024-01-26 兰州理工大学 Tunnel secondary lining concrete construction simulation method

Also Published As

Publication number Publication date
CN113137247B (en) 2023-10-20

Similar Documents

Publication Publication Date Title
CN113137247A (en) Method for improving concrete pouring efficiency and compactness of tunnel secondary lining arch wall
CN110978404A (en) Injection mold with temperature control function
CN102900201B (en) Manufacture mold and manufacture method of grouting anchor reinforced bar connection sleeve
CN105562610A (en) Casting all-ceramic pouring mechanism
CN216372671U (en) Solid brick embryo mould of concrete
CN106493308B (en) A kind of gate valve casting of the low cost without riser
CN109465396B (en) Pouring shunting device for pig casting machine
CN210857297U (en) Be used for construction joint structure between hydraulic engineering bottom plate and pier wall
CN210498264U (en) Sand core assembly cast through drainage hole of multi-cylinder large-scale cylinder block
CN220185123U (en) Tunnel roof arch concrete placement hole packer
CN111705565A (en) Post-cast strip pouring support system and post-cast strip pouring construction method
CN209794078U (en) Assembled inspection shaft flowing water groove template
CN218314202U (en) Pouring mold for building prefabricated wall
CN210065817U (en) Improved main ditch casting body
CN219158219U (en) One-time pouring forming fixing device for roof exhaust pipe
CN214353159U (en) Leak protection thick liquid PC component mould
CN103912287A (en) Method for pouring compound pipe piece
CN114454310B (en) Segment beam prefabricated end die panel matching manufacturing method based on unmatched beam
CN110625746A (en) Two cabin utility tunnel casting mold
CN210880154U (en) Assembled building forming die
CN209851177U (en) Square precast concrete assembled inspection shaft mould
CN213563408U (en) Autoclaved aerated concrete slab ferry vehicle
CN209959262U (en) Two lining concrete placement switching device
CN219902600U (en) Prefabricated mould of water conservancy diversion mound
CN203409216U (en) Die-casting system for electromagnetic valve body

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant