CN113134587A - 一种通过塞棒开口度变化趋势判断水口堵塞和溶损的方法 - Google Patents

一种通过塞棒开口度变化趋势判断水口堵塞和溶损的方法 Download PDF

Info

Publication number
CN113134587A
CN113134587A CN202010052390.2A CN202010052390A CN113134587A CN 113134587 A CN113134587 A CN 113134587A CN 202010052390 A CN202010052390 A CN 202010052390A CN 113134587 A CN113134587 A CN 113134587A
Authority
CN
China
Prior art keywords
stopper rod
opening degree
crystallizer
value
tundish
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202010052390.2A
Other languages
English (en)
Other versions
CN113134587B (zh
Inventor
苏锦
郑建忠
职建军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Baoshan Iron and Steel Co Ltd
Original Assignee
Baoshan Iron and Steel Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Baoshan Iron and Steel Co Ltd filed Critical Baoshan Iron and Steel Co Ltd
Priority to CN202010052390.2A priority Critical patent/CN113134587B/zh
Publication of CN113134587A publication Critical patent/CN113134587A/zh
Application granted granted Critical
Publication of CN113134587B publication Critical patent/CN113134587B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B22CASTING; POWDER METALLURGY
    • B22DCASTING OF METALS; CASTING OF OTHER SUBSTANCES BY THE SAME PROCESSES OR DEVICES
    • B22D11/00Continuous casting of metals, i.e. casting in indefinite lengths
    • B22D11/16Controlling or regulating processes or operations
    • B22D11/18Controlling or regulating processes or operations for pouring

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Continuous Casting (AREA)

Abstract

本发明公开了一种通过塞棒开口度变化趋势判断水口堵塞和溶损的方法,通过研究塞棒(或者是滑板)开口度百分比的变化,同时考虑生产过程中拉速变化、中间包钢水重量变化,调整液面、调宽对塞棒(或者是滑板)开口度带来的影响,建立一个公式来计算塞棒(或者是滑板)开口度的变化,用其值来表征堵塞或溶损的程度。本发明为连铸过程中水口堵塞和溶损程度提出了一种定量计算方法,可以在生产过程中进行预警,并建立了其对应板坯的评级标准,为板坯的质量管理提供了有效手段,对堵塞或溶损严重的板坯采取降级、切废等措施,保证了最终产品的质量。

Description

一种通过塞棒开口度变化趋势判断水口堵塞和溶损的方法
技术领域
本发明涉及连铸生产工艺技术,更具体地说,涉及一种通过塞棒开口度变化趋势判断水口堵塞和溶损的方法。
背景技术
连铸技术是把液态的钢水通过浇注、冷凝、切割而得到铸坯的工艺。如图1所示,这个过程最主要的环节就是把利用盛钢水的钢包1,通过中间包2的过渡,连续地注入结晶器3,在四块铜板构成的结晶器3内通过水冷得到四周为固态的坯壳,坯壳的中间部分仍为液态钢水的铸坯。之后铸坯通过二次冷却4逐渐全部凝固,并通过拉矫装置5中辊子的支撑和转动作用被拉出连铸机主体,由切割装置切割成一定长度的板坯。这个过程可以不断更换钢包1来实现多炉连续浇铸。
如图2所示,连铸生产过程中,中间包2是关键的过渡设备,中间包2的形状决定了钢水的流动状态,同时其依靠塞棒(或者是滑板)机构6来控制钢水,通过浸入式水口流入结晶器3。一般用塞棒(或者是滑板)机构6打开的百分比来表征钢水进入结晶器3的流量。正常情况下,基于拉速和浇铸断面,塞棒(或者是滑板)机构6的开口度一般在50%~80%,并且在一次浇铸过程中由于浇铸断面变化不会很大,塞棒(或者是滑板)机构6的开口度变化幅度不会超过20%。
实际浇铸过程中,可以控制塞棒(或者是滑板)机构6的开口度百分比来调节进入结晶器3钢水的流量,以平衡浇铸过程的各种变化,如拉速提升或降低、中间包2钢水重量波动等,目的是保持钢水在结晶器3内的液位稳定,保证铸坯质量。
但是浇铸过程中存在两种异常情况会影响到塞棒(或者是滑板)机构6的开口度百分比实际值,一种是由于钢中Al2O3、MgO·Al2O3等夹杂物的产生和凝聚,会堵塞水口,从而影响实际钢水流入结晶器3的流量。堵塞物挡住钢水的正常流入,例如塞棒(或者是滑板)机构6的开口度百分比已经超过80%了,而由于堵塞物的存在,实际流入结晶器3的钢水量小于正常情况下开口度达到80%流入的量。极端情况是开口度开到100%,但水口全部被堵塞物挡住,钢水不能流入结晶器3而造成断浇。另一种是钢水中含Ca,其含量过高会与塞棒(或者是滑板)机构6、水口的本体发生化学反应,从而导致塞棒(或者是滑板)机构6、水口的本体溶损,使实际流入的钢水量大于塞棒(或者是滑板)机构6正常开口度应该流入的量,会造成流量失控,发生生产事故。
浇铸过程中水口堵塞和溶损这两种情况除了对浇铸生产过程造成影响,也会影响期间产出的铸坯质量。实际生产中,这两种情况发生时往往不是最极端的,即堵塞但没有完全堵死;溶损有时也不显著。这样相对应的铸坯也能产出,但其质量较正常浇铸的铸坯为差。
浇铸过程中塞棒(或者是滑板)开口度的百分比变化同时受到正常操作和异常情况的影响,目前没有建立一种方法,通过过程参数来判断出这两种异常情况,并根据严重程度进行评级,进而应用到板坯的质量管理中。
发明内容
针对现有技术中存在的上述缺陷,本发明的目的是提供一种通过塞棒开口度变化趋势判断水口堵塞和溶损的方法,结合生产过程中拉速变化、中间包钢水重量变化,调整液面、调宽对塞棒开口度带来的影响,从而计算塞棒开口度的变化,用其值来表征堵塞或溶损的程度。
为实现上述目的,本发明采用如下技术方案:
一种通过塞棒开口度变化趋势判断水口堵塞和溶损的方法,为了对连铸生产中水口堵塞和溶损的情况进行表征,并进一步对相应的板坯进行评级,评级需要将铸坯分段,考虑最短板坯为5m也要保证一定的分段数,分段为1min时间内浇铸的长度(如一般拉速为1m/min,此时浇铸的长度为1m/min×1min=1m)。对板坯上的每一段计算评估系数E值,根据评估表将E值超标的次数组合起来,就能得到最终的评级结果。为了计算每一段的E值,需要利用连铸高频数据采集系统每秒采集的数据,因为一段的时间为1分钟,在这段时间内还要选择一个合适的时间周期来计算各个参数的变化趋势。由于堵塞或溶损在较长的时间才能判断,这个周期不能太短;周期太长则1分钟内计算趋势的值太少,将这个周期定为10秒是比较合适的。计算每10秒塞棒(滑板)开口度的最大值,每10秒塞棒(滑板)开口度的平均值,每10秒拉速的平均值,每10秒中间包钢水重量的平均值,每10秒结晶器设定液位平均值,每10秒结晶器上口宽度平均值,作为基本运算数据。
定义:
塞棒开口度的最大值Stopper rod position(max),每10秒塞棒(滑板)开口度的最大值,单位%;
If stopper rod position(max)>=90%,判定为非常严重堵水口;
If stopper rod position(max)<90%,按以下步骤判断:
定义:
塞棒开口度的平均值Stopper rod position(avg),每10秒塞棒(滑板)开口度的平均值,单位%;
拉速的最大值v(max),每10秒拉速的最大值,单位m/min;
中间包钢水重量的平均值Tundish weight(avg),每10秒中间包钢水重量的平均值,单位kg;
结晶器设定液位平均值Mold Level Setpoint(avg),每10秒结晶器设定液位平均值,单位mm;
结晶器上口宽度平均值MoldWidthtop(avg),每10秒结晶器上口宽度平均值,单位mm;
Fv,拉速影响因子;
ftw,中间包钢水重量影响因子;
fmls,结晶器设定液位因子;
fw,结晶器上口宽度因子;
以1分钟为周期,有
Stopper rod position(avg)i,i=1~6;
Stopper rod position(max)i,i=1~6;
v(max)i,i=1~6;
Tundish weight(avg)i,i=1~6;
Mold Level Setpoint(avg)i,i=1~6;
Widthtop(avg)i,i=1~6;
fv(i),i=1~6;ftw(i),i=1~6;fmls(i),i=1~6;fw(i),i=1~6;
采用塞棒开口度变化Stopper rod Change来表征堵水口和塞棒溶损的程度,则
Figure BDA0002371643070000041
上述公式(1)中,fv(i)取值如下:(ABS为绝对值计算)
1)If ABS(v(max)i+1-v(max)i)<0.02m/min,fv(i)=0;
2)If ABS(v(max)i+1-v(max)i)≧0.02m/min;
若公式(1)中拉速影响因子fv(i)满足公式(1)中条件If ABS(v(max)i+1-v(max)i)≧0.02m/min时,选取相同连铸机之前浇铸的50~100条数据,数据满足以下要求:
(1)中间包钢水重量变化不大,即ABS(Tundish weight(avg)i+1-Tundish weight(avg)i)<=150kg;
(2)结晶器设定液位不变,即ABS(Mold Level Setpoint(avg)i+1-Mold LevelSetpoint(avg)i)<=2.5mm;
(3)没有调宽,即ABS(Mold Widthtop(avg)i+1-Mold Widthtop(avg)i)<=2mm;
(4)Stopper rod position(max)实际值范围在50%~80%之间;
(5)两两一组选取采集周期连续的拉速v(max)i+1和v(max)i,以及同时刻采集的塞棒开口度Stopper rod position(max)i+1和Stopper rod position(max)i,选取条件为ABS(v(max)i+1-v(max)i)>=0.02m/min,且(v(max)i+1-v(max)i)×(Stopper rod position(max)i+1-Stopper rod position(max)i)>0,计算:
Figure BDA0002371643070000051
Figure BDA0002371643070000052
最后计算得到:
Figure BDA0002371643070000053
n为选取的组数
对符合要求的组的计算结果取平均值,作为fv(i)当前计算公式(1)时满足条件的取值。
ftw(i)取值如下:
1)If ABS(Tundish weight(avg)i+1-Tundish weight(avg)i)<=150kg,ftw(i)=0;
2)If ABS(Tundish weight(avg)i+1-Tundish weight(avg)i)>150kg;
若公式(1)中中间包钢水重量影响因子ftw(i)满足公式(1)中条件ABS(Tundishweight(avg)i+1-Tundish weight(avg)i)>150kg时,选取浇铸过程50~100条数据,数据满足以下要求:
(1)拉速变化不大,即ABS(v(max)i+1-v(max)i)<0.02m/min;
(2)结晶器设定液位不变,即ABS(Mold Level Setpoint(avg)i+1-Mold LevelSetpoint(avg)i)<=2.5mm;
(3)没有调宽,即ABS(Mold Widthtop(avg)i+1-Mold Widthtop(avg)i)<=2mm;
(4)Stopper rod position(max)实际值范围在50%~80%之间;
(5)两两一组选取采集周期连续的中间包钢水重量Tundish weight(avg)i+1和Tundish weight(avg)i,以及同时刻采集的塞棒开口度Stopper rod position(avg)i+1和Stopper rod position(avg)i,选取条件为ABS(Tundish weight(avg)i+1-Tundish weight(avg)i)>150kg,且(Tundish weight(avg)i+1-Tundish weight(avg)i)×(Stopper rodposition(avg)i+1-Stopper rod position(avg)i)<0,计算:
Figure BDA0002371643070000054
Figure BDA0002371643070000055
最后计算得到:
Figure BDA0002371643070000061
n为选取的组数
对符合要求的组的计算结果取平均值,作为ftw(i)当前计算公式(1)时满足条件的取值。
fmls(i)和fw(i)的取值
浇铸过程中结晶器设定液位调整和调宽过程时间都比较短(小于2.5分钟),对塞棒(滑板)开口度的影响可以看成扰动因素来处理,因此
fmls(i)取值如下:
1)ABS(Mold Level Setpoint(avg)i+1-Mold Level Setpoint(avg)i)<=2.5mm,fmls(i)=1;
2)ABS(Mold Level Setpoint(avg)i+1-Mold Level Setpoint(avg)i)>2.5mm,fmls(i)=0;
fw(i)取值如下:
1)ABS(Mold Widthtop(avg)i+1-Mold Widthtop(avg)i)<=2mm,fw(i)=1;
2)ABS(Mold Widthtop(avg)i+1-Mold Widthtop(avg)i)>2mm,fw(i)=0;
将上述公式(1)为每1分钟计算一次,对应的铸坯约1m(按1m/min的拉速计算),得到一次Stopper rod Change的值,构造:
Stopper rod Change=E%
利用计算出的E值大小来判断对应铸坯产生时是否有水口堵塞或溶损情况,在浇铸过程中可以实时预警;而一块板坯一般长度从5.8m~12m不等,用E值大小结合一块板坯上发生水口堵塞或溶损的次数来表征其严重程度,从而进一步对板坯进行评级,达到质量管控的目的。
建立以下表1来判定每块板坯生产时水口堵塞或溶损的程度
表1
Figure BDA0002371643070000062
Figure BDA0002371643070000071
堵塞的夹杂物有可能掉落造成干扰,因此规定附加规则如下:
1、以上表格优先级为从上至下(特别指出:如一块板坯在堵塞中已经评级,溶损就不再评级);
2、如一块板坯在堵塞中已经评级,其后紧接着的一块板坯不在溶损中评级。
所述计算板坯分段E值及对板坯进行评级具体如下:
1)建立时间序列,10秒为一个周期,定义i=1,j=1,n=1,id=1;
2)获取i和i+1时的各个数据项;
3)定义E10(i)=(DeltaSTP-DeltaV×fv(i)-DeltaTW×ftw(i))×fmls(i)×fw(i);
4)计算1分钟的E值,1分钟的铸片长度l,1分钟开口度的最大值;
5)获取板坯长度L,累加铸片长度,得到板坯的分段数。
所述获取i和i+1时的各个数据项,有塞棒开口度平均值和最大值Stopper rodposition(avg)、Stopper rod position(max),最大和平均拉速v(max)、v(avg),中间包钢水重量平均值Tundish weight(avg),结晶器上口宽度平均值Mold Widthtop(avg),结晶器设定液位平均值Mold Level Setpoint(avg)。
所述DeltaSTP表示
Figure BDA0002371643070000081
DeltaV表示
Figure BDA0002371643070000082
DeltaTW表示
Figure BDA0002371643070000083
所述1分钟的E值为
Figure BDA0002371643070000084
所述1分钟的铸片长度l为
Figure BDA0002371643070000085
所述1分钟开口度的最大值为
Figure BDA0002371643070000086
使
Figure BDA0002371643070000087
得到x的解加1即为这块板坯分段数。
根据板坯内每段的E值和塞棒最大开口度,即E(id)和MAXSTP(id),按照表1获得相应的评级,其结果以板坯号为关键字记录在这块板坯的实绩数据中。
本发明所提供的一种通过塞棒开口度变化趋势判断水口堵塞和溶损的方法,为连铸过程中水口堵塞和溶损程度提出了一种定量计算方法,可以在生产过程中进行预警,并建立了其对应板坯的评级标准,为板坯的质量管理提供了有效手段,对堵塞或溶损严重的板坯采取降级、切废等措施,保证了最终产品的质量。
附图说明
图1是现有典型的直弧形连铸机的结构示意图;
图2是图1直弧形连铸机上中间包内部的结构示意图;
图3是本发明方法中拉速影响因子fv(i)满足公式(1)中条件ABS(v(max)i+1-v(max)i)≧0.02m/min时的流程图;
图4是本发明方法中中间包钢水重量影响因子ftw(i)满足公式(1)中条件ABS(Tundish weight(avg)i+1-Tundish weight(avg)i)>150kg时的流程图;
图5是本发明方法中计算板坯分段的E值及对板坯进行评级的流程图。
具体实施方式
下面结合具体实施例对本发明进行详细说明。以下实施例将有助于本领域的技术人员进一步理解本发明,但不以任何形式限制本发明。应当指出的是,对本领域的普通技术人员来说,在不脱离本发明构思的前提下,还可以做出若干变形和改进。这些都属于本发明的保护范围。
实施例
现以3号机生产的两块板坯计算E值并评级来进一步说明本发明方法。
根据公式(1)需要先确定fv和ftw,采集3号机某年某月浇铸过程的每10秒的数据项:拉速最大值v(max),中间包钢水重量平均值Tundish weight(avg),结晶器设定液位平均值Mold Level Setpoint(avg),结晶器上口宽度平均值Mold Widthtop(avg),塞棒(滑板)开口度最大值Stopper rod position(max),塞棒(滑板)开口度平均值Stopper rodposition(avg)。
1)按两两一组选取采集周期连续的拉速v(max)i+1和v(max)i,以及同时刻采集的塞棒开口度Stopper rod position(max)i+1和Stopper rod position(max)i,选取条件同时满足以下要求:
(1)ABS(v(max)i+1-v(max)i)>=0.02m/min(ABS为取绝对值,下同),且(v(max)i+1-v(max)i)×(Stopper rod position(max)i+1-Stopper rod position(max)i)>0;
(2)ABS(Tundish weight(avg)i+1-Tundish weight(avg)i)<=150kg;
(3)ABS(Mold Level Setpoint(avg)i+1-Mold Level Setpoint(avg)i)<=2.5mm;
(4)ABS(Mold Widthtop(avg)i+1-Mold Widthtop(avg)i)<=2mm;
(5)Stopper rod position(max)实际值范围在50%~80%之间。
选到3号机某年某月30组60条符合上述要求的数据,计算得到:
Figure BDA0002371643070000101
2)按两两一组选取采集周期连续的中间包钢水重量Tundish weight(avg)i+1和Tundish weight(avg)i,以及同时刻采集的塞棒开口度Stopper rod position(avg)i+1和Stopper rod position(avg)i,选取条件同时满足以下要求:
(1)ABS(Tundish weight(avg)i+1-Tundish weight(avg)i)>150kg,且(Tundishweight(avg)i+1-Tundish weight(avg)i)×(Stopper rod position(avg)i+1-Stopper rodposition(avg)i)<0;
(2)ABS(v(max)i+1-v(max)i)<0.02m/min;
(3)ABS(Mold Level Setpoint(avg)i+1-Mold Level Setpoint(avg)i)<=2.5mm;
(4)ABS(Mold Widthtop(avg)i+1-Mold Widthtop(avg)i)<=2mm;
(5)Stopper rod position(max)实际值范围在50%~80%之间。
选到3号机某年某月30组60条符合上述要求的数据,计算得到:
Figure BDA0002371643070000102
一块板坯号为27484630600长度5.8m,采集的数据见下表2:
表2, 27484630600板坯的过程数据
Figure BDA0002371643070000103
Figure BDA0002371643070000111
Figure BDA0002371643070000121
按公式(1)
Figure BDA0002371643070000122
用DeltaSTP表示
Figure BDA0002371643070000123
用DeltaV表示
Figure BDA0002371643070000124
用DeltaTW表示
Figure BDA0002371643070000125
fv(i)取值如下:
1)If ABS(v(max)i+1-v(max)i)<0.02m/min,fv(i)=0;
2)If ABS(v(max)i+1-v(max)i)>=0.02m/min,fv(i)=0.203;
ftw(i)取值如下:
1)If ABS(Tundish weight(avg)i+1-Tundish weight(avg)i)<=150kg,ftw(i)=0;
2)If ABS(Tundish weight(avg)i+1-Tundish weight(avg)i)>150kg,ftw(i)=-0.010;
fmls(i)取值如下:
1)ABS(Mold Level Setpoint(avg)i+1-Mold Level Setpoint(avg)i)<=2.5mm,fmls(i)=1;
2)ABS(Mold Level Setpoint(avg)i+1-Mold Level Setpoint(avg)i)>2.5mm,fmls(i)=0;
fw(i)取值如下:
1)ABS(Mold Widthtop(avg)i+1-Mold Widthtop(avg)i)<=2mm,fw(i)=1;
2)ABS(Mold Widthtop(avg)i+1-Mold Widthtop(avg)i)>2mm,fw(i)=0;
令Stopper rod Change=E%
结合表2和以上条件得到表3:
表3, 27484630600板坯得到的计算结果
Figure BDA0002371643070000131
Figure BDA0002371643070000141
Figure BDA0002371643070000151
根据表3,板坯27484630600计算得到的E值
8>E≥7,1次;
9>E≥8,2次;
再根据表2,板坯27484630600过程数据中
Stopper rod position(max)≥90%,发生4次
最后根据表1的评级标准及其优先级判定,
板坯27484630600为堵塞5级,即其生产过程中水口严重堵塞。
另一块板坯号为27552330600长度11.4m,采集的数据见表4:
表4, 27552330600板坯的过程数据
Figure BDA0002371643070000152
Figure BDA0002371643070000161
Figure BDA0002371643070000171
Figure BDA0002371643070000181
同前按公式(1)
Figure BDA0002371643070000182
用DeltaSTP表示
Figure BDA0002371643070000183
用DeltaV表示
Figure BDA0002371643070000184
用DeltaTW表示
Figure BDA0002371643070000185
fv(i)取值如下:
1)If ABS(v(max)i+1-v(max)i)<0.02m/min,fv(i)=0;
2)If ABS(v(max)i+1-v(max)i)>=0.02m/min,fv(i)=0.203;
ftw(i)取值如下:
1)If ABS(Tundish weight(avg)i+1-Tundish weight(avg)i)<=150kg,ftw(i)=0;
2)If ABS(Tundish weight(avg)i+1-Tundish weight(avg)i)>150kg,ftw(i)=-0.010;
fmls(i)取值如下:
1)ABS(Mold Level Setpoint(avg)i+1-Mold Level Setpoint(avg)i)<=2.5mm,fmls(i)=1;
2)ABS(Mold Level Setpoint(avg)i+1-Mold Level Setpoint(avg)i)>2.5mm,fmls(i)=0;
fw(i)取值如下:
1)ABS(Mold Widthtop(avg)i+1-Mold Widthtop(avg)i)<=2mm,fw(i)=1;
2)ABS(Mold Widthtop(avg)i+1-Mold Widthtop(avg)i)>2mm,fw(i)=0;
令Stopper rod Change=E%
结合表4和以上条件得到表5:
表5, 27552330600板坯得到的计算结果
Figure BDA0002371643070000191
Figure BDA0002371643070000201
Figure BDA0002371643070000211
Figure BDA0002371643070000221
根据表5,板坯27552330600计算得到的E值全部:
-5≤E<5,
再根据表1的评级标准及其优先级判定;
板坯27552330600为正常板坯。
本技术领域中的普通技术人员应当认识到,以上的实施例仅是用来说明本发明,而并非用作为对本发明的限定,只要在本发明的实质精神范围内,对以上所述实施例的变化、变型都将落在本发明的权利要求书范围内。

Claims (10)

1.一种通过塞棒开口度变化趋势判断水口堵塞和溶损的方法,其特征在于包括以下步骤:
选择计算参数变化趋势的时间周期,该时间周期设定为10秒;
计算每10秒的拉速的最大值v(max),单位m/min;塞棒开口度的最大值stopper rodposition(max),单位%;塞棒开口度的平均值Stopper rod position(avg),单位%;中间包钢水重量的平均值Tundish weight(avg),单位kg;结晶器设定液位的平均值Mold LevelSetpoint(avg),单位mm;结晶器上口宽度的平均值Mold Widthtop(avg),单位mm;利用连铸高频数据采集系统采集数据,所述数据包括上述的拉速最大值、塞棒开口度最大值、塞棒开口度平均值、中间包钢水重量平均值、结晶器设定液位平均值、结晶器上口宽度平均值,作为运算数据;
采用塞棒开口度变化参数Stopper rod Change来表征堵水口和塞棒溶损的程度,则
Figure FDA0002371643060000011
上述公式(1)中,
Fv为拉速影响因子;
ftw为中间包钢水重量影响因子;
fmls为结晶器设定液位因子;
fw,结晶器上口宽度因子;
i为自然数,以1分钟为周期,i取值为1、2、3、4、5、6,
将上述公式(1)定时计算一次,得到一次塞棒开口度变化,构造:
塞棒开口度变化=E%
利用计算出的板坯分段E值大小来判断对应铸坯产生时是否有水口堵塞或溶损情况,用E值大小结合一块板坯上发生水口堵塞或溶损的次数来表征其严重程度,从而进一步对板坯进行评级。
2.如权利要求1所述的通过塞棒开口度变化趋势判断水口堵塞和溶损的方法,其特征在于:
所述公式(1)中,拉速影响因子fv(i)满足条件∣(拉速的最大值i+1-拉速的最大值i)∣<0.02m/min时,fv(i)=0;拉速影响因子fv(i)满足条件∣(拉速的最大值i+1-拉速的最大值i)∣≧0.02m/min时,选取50~100条数据,将采集周期连续的两条数据作为一组,满足条件后,每组数据计算,公式如下:
Figure FDA0002371643060000021
对符合要求的组的计算结果取平均值,作为fv(i)当前计算公式(1)时满足条件的取值。
3.如权利要求2所述的通过塞棒开口度变化趋势判断水口堵塞和溶损的方法,其特征在于:所述两条数据满足条件为:
1)∣(拉速的最大值i+1-拉速的最大值i)∣≧0.02m/min,且(拉速的最大值i+1-拉速的最大值i)×(塞棒开口度的最大值i+1-塞棒开口度的最大值i)>0;
2)∣(中间包钢水重量的平均值i+1-中间包钢水重量的平均值i)∣<=150kg;
3)∣(结晶器设定液位平均值i+1-结晶器设定液位平均值i)∣<=2.5mm;
4)∣(结晶器上口宽度平均值i+1-结晶器上口宽度平均值i)∣<=2mm;
5)塞棒开口度的最大值在50%~80%之间。
4.如权利要求1所述的通过塞棒开口度变化趋势判断水口堵塞和溶损的方法,其特征在于:
所述公式(1)中,中间包钢水重量影响因子满足条件(中间包钢水重量的平均值i+1-中间包钢水重量的平均值i)∣<=150kg,ftw(i)=0;中间包钢水重量影响因子ftw(i)满足条件∣(中间包钢水重量的平均值i+1-中间包钢水重量的平均值i)∣>150kg时,选取50~100条数据,将采集周期连续的两条数据作为一组,满足条件后,每组数据计算,公式如下:
Figure FDA0002371643060000031
对符合要求的组的计算结果取平均值,作为ftw(i)当前计算公式(1)时满足条件的取值。
5.如权利要求4所述的通过塞棒开口度变化趋势判断水口堵塞和溶损的方法,其特征在于:所述两条数据满足条件为:
1)∣(中间包钢水重量的平均值i+1-中间包钢水重量的平均值i)∣>150kg,且(中间包钢水重量的平均值i+1-中间包钢水重量的平均值i)×(塞棒开口度的最大值i+1-塞棒开口度的最大值i)<0;
2)∣(结晶器设定液位平均值i+1-结晶器设定液位平均值i)∣<=2.5mm;
3)∣(结晶器上口宽度平均值i+1-结晶器上口宽度平均值i)∣<=2mm;
4)∣(拉速的最大值i+1-拉速的最大值i)∣<0.02m/min;
5)塞棒开口度的最大值在50%~80%之间。
6.如权利要求1所述的通过塞棒开口度变化趋势判断水口堵塞和溶损的方法,其特征在于:
所述公式(1)中,结晶器设定液位因子fmls(i)取值如下:
1)∣(结晶器设定液位平均值i+1-结晶器设定液位平均值i)∣<=2.5mm,fmls(i)=1;
2)∣(结晶器设定液位平均值i+1-结晶器设定液位平均值i)∣>2.5mm,fmls(i)=0。
7.如权利要求1所述的通过塞棒开口度变化趋势判断水口堵塞和溶损的方法,其特征在于:
所述公式(1)中,结晶器上口宽度因子fw(i)取值如下:
1)∣(结晶器上口宽度平均值i+1-结晶器上口宽度平均值i)∣<=2mm,fw(i)=1;
2)∣(结晶器上口宽度平均值i+1-结晶器上口宽度平均值i)∣>2mm,fw(i)=0。
8.如权利要求1所述的通过塞棒开口度变化趋势判断水口堵塞和溶损的方法,其特征在于:
所述计算板坯分段E值及对板坯进行评级具体如下:
1)建立时间序列,10秒为一个周期,定义i=1,j=1,n=1,id=1;
2)获取i和i+1时的各个数据项;
3)定义E10(i)=(DeltaSTP-DeltaV×fv(i)-DeltaTW×ftw(i))×fmls(i)×fw(i);
4)计算1分钟的E值,1分钟的铸片长度l,1分钟开口度的最大值;
5)获取板坯长度L,累加铸片长度,得到板坯的分段数。
9.如权利要求8所述的通过塞棒开口度变化趋势判断水口堵塞和溶损的方法,其特征在于:所述获取i和i+1时的各个数据项,有塞棒开口度的平均值和最大值、拉速最大和平均值、中间包钢水重量平均值、结晶器上口宽度平均值、结晶器设定液位平均值。
10.如权利要求8所述的通过塞棒开口度变化趋势判断水口堵塞和溶损的方法,其特征在于:所述1分钟的E值为
Figure FDA0002371643060000041
所述1分钟的铸片长度l为
Figure FDA0002371643060000042
所述1分钟开口度的最大值为
Figure FDA0002371643060000043
CN202010052390.2A 2020-01-17 2020-01-17 一种通过塞棒开口度变化趋势判断水口堵塞和溶损的方法 Active CN113134587B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010052390.2A CN113134587B (zh) 2020-01-17 2020-01-17 一种通过塞棒开口度变化趋势判断水口堵塞和溶损的方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010052390.2A CN113134587B (zh) 2020-01-17 2020-01-17 一种通过塞棒开口度变化趋势判断水口堵塞和溶损的方法

Publications (2)

Publication Number Publication Date
CN113134587A true CN113134587A (zh) 2021-07-20
CN113134587B CN113134587B (zh) 2022-11-18

Family

ID=76808277

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010052390.2A Active CN113134587B (zh) 2020-01-17 2020-01-17 一种通过塞棒开口度变化趋势判断水口堵塞和溶损的方法

Country Status (1)

Country Link
CN (1) CN113134587B (zh)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114264786A (zh) * 2021-11-29 2022-04-01 马鞍山钢铁股份有限公司 基于连铸中间包浸入式水口结脱落瘤物的铸坯质量评价方法及系统

Citations (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08281403A (ja) * 1995-04-17 1996-10-29 Sumitomo Metal Ind Ltd 鋳型内溶鋼面のレベル制御装置
JP2001129647A (ja) * 1999-08-25 2001-05-15 Sumitomo Metal Ind Ltd 連続鋳造機の湯面レベル制御方法及び湯面レベル制御装置
JP2005246466A (ja) * 2004-03-08 2005-09-15 Nippon Steel Corp 連続鋳造設備の鋳型内溶鋼レベル制御方法
JP2008540130A (ja) * 2005-05-03 2008-11-20 フォセコ インターナショナル リミテッド 溶融金属の連続鋳造のためのタンデッシュ棒栓
CN102233415A (zh) * 2010-04-20 2011-11-09 宝山钢铁股份有限公司 连铸生产中铁素体不锈钢板坯宽度的设定方法
KR20110130771A (ko) * 2010-05-28 2011-12-06 현대제철 주식회사 침지 노즐 막힘 경고 방법
CN102847901A (zh) * 2011-06-28 2013-01-02 宝山钢铁股份有限公司 一种连铸生产中控制铁素体不锈钢板坯宽度的方法
KR20130012451A (ko) * 2011-07-25 2013-02-04 주식회사 포스코 스토퍼 장치 및 스토퍼 장치 제어 방법
WO2013048083A2 (ko) * 2011-09-28 2013-04-04 현대제철 주식회사 연속주조시 연연주수 예측 방법
CN104999043A (zh) * 2014-04-17 2015-10-28 宝山钢铁股份有限公司 一种连铸钢包滑动水口开度在线测量装置及其测量方法
CN106180619A (zh) * 2016-08-12 2016-12-07 湖南千盟物联信息技术有限公司 一种连铸过程智能控制的系统方法
CN107891134A (zh) * 2017-12-12 2018-04-10 首钢集团有限公司 一种确定水口堵塞的方法及装置
CN108176844A (zh) * 2018-01-15 2018-06-19 山东钢铁股份有限公司 一种清理中间包上水口结瘤物的装置和方法
CN109332625A (zh) * 2018-11-08 2019-02-15 武汉钢铁有限公司 一种改善塞棒控流Al脱氧钢水口堵塞的浇铸方法
CN109848401A (zh) * 2017-11-30 2019-06-07 上海梅山钢铁股份有限公司 一种抑制中间包塞棒粘结堵塞效应的方法

Patent Citations (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08281403A (ja) * 1995-04-17 1996-10-29 Sumitomo Metal Ind Ltd 鋳型内溶鋼面のレベル制御装置
JP2001129647A (ja) * 1999-08-25 2001-05-15 Sumitomo Metal Ind Ltd 連続鋳造機の湯面レベル制御方法及び湯面レベル制御装置
JP2005246466A (ja) * 2004-03-08 2005-09-15 Nippon Steel Corp 連続鋳造設備の鋳型内溶鋼レベル制御方法
JP2008540130A (ja) * 2005-05-03 2008-11-20 フォセコ インターナショナル リミテッド 溶融金属の連続鋳造のためのタンデッシュ棒栓
CN102233415A (zh) * 2010-04-20 2011-11-09 宝山钢铁股份有限公司 连铸生产中铁素体不锈钢板坯宽度的设定方法
KR20110130771A (ko) * 2010-05-28 2011-12-06 현대제철 주식회사 침지 노즐 막힘 경고 방법
CN102847901A (zh) * 2011-06-28 2013-01-02 宝山钢铁股份有限公司 一种连铸生产中控制铁素体不锈钢板坯宽度的方法
KR20130012451A (ko) * 2011-07-25 2013-02-04 주식회사 포스코 스토퍼 장치 및 스토퍼 장치 제어 방법
WO2013048083A2 (ko) * 2011-09-28 2013-04-04 현대제철 주식회사 연속주조시 연연주수 예측 방법
CN104999043A (zh) * 2014-04-17 2015-10-28 宝山钢铁股份有限公司 一种连铸钢包滑动水口开度在线测量装置及其测量方法
CN106180619A (zh) * 2016-08-12 2016-12-07 湖南千盟物联信息技术有限公司 一种连铸过程智能控制的系统方法
CN109848401A (zh) * 2017-11-30 2019-06-07 上海梅山钢铁股份有限公司 一种抑制中间包塞棒粘结堵塞效应的方法
CN107891134A (zh) * 2017-12-12 2018-04-10 首钢集团有限公司 一种确定水口堵塞的方法及装置
CN108176844A (zh) * 2018-01-15 2018-06-19 山东钢铁股份有限公司 一种清理中间包上水口结瘤物的装置和方法
CN109332625A (zh) * 2018-11-08 2019-02-15 武汉钢铁有限公司 一种改善塞棒控流Al脱氧钢水口堵塞的浇铸方法

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114264786A (zh) * 2021-11-29 2022-04-01 马鞍山钢铁股份有限公司 基于连铸中间包浸入式水口结脱落瘤物的铸坯质量评价方法及系统
CN114264786B (zh) * 2021-11-29 2024-01-12 马鞍山钢铁股份有限公司 基于连铸中间包浸入式水口脱落结瘤物的铸坯质量评价方法及系统

Also Published As

Publication number Publication date
CN113134587B (zh) 2022-11-18

Similar Documents

Publication Publication Date Title
CN109261922A (zh) 一种凝固末端大压下连铸机的控制方法及生产工艺
CN107649657A (zh) 一种小方坯中间包停浇的方法
CN111250672B (zh) 一种基于通钢量对比的连铸钢包终浇方法
CN113134587B (zh) 一种通过塞棒开口度变化趋势判断水口堵塞和溶损的方法
CN107357953A (zh) 一种根据热流密度分析水口堵塞的方法
JP2008525200A (ja) 双ロール式薄板鋳造工程における湯面レベルのロバスト制御方法
CN114713784B (zh) 一种连铸尾坯定尺优化切割的方法
CN113634728A (zh) 连铸实际混浇定尺铸坯混合率实时确定方法及显示方法
CA1093271A (en) Method and apparatus for the continuous casting of steel
CN113275533B (zh) 一种连铸中间包钢水浇注温度的自动化控制装置
CN104646641B (zh) 连铸系统中降拉速控制方法以及换中间包控制方法
CN109047698A (zh) 一种连铸坯定重定尺在线预测方法
CA2375133A1 (en) Automation of a high-speed continuous casting plant
JP5825084B2 (ja) 高炭素鋼スラブの連続鋳造方法
CN110548847B (zh) 一种连铸机在中包快换期间扇形段自动躲接痕板坯的方法
CZ292822B6 (cs) Způsob plynulého odlévání roztaveného kovu, zejména oceli
KR101267341B1 (ko) 연주공정에서 응고쉘의 브레이크아웃 방지 장치 및 그 방법
CN114515825A (zh) 基于钢水成分的异钢种异断面混浇坯精准切割的控制方法
Thomas Continuous casting (metallurgy)
CN109759552A (zh) 板坯中心裂纹缺陷控制方法
CN114905015B (zh) 一种板坯连铸异常终浇轻压下模型控制方法
CN114535528B (zh) 一种板坯连铸终浇防冒涨的工艺方法
JP6160578B2 (ja) 連続鋳造片の表面割れ判定方法
KR101435115B1 (ko) 슬라브 표면 결함 예측 방법
CN116329511B (zh) 一种减少热轧低碳钢连铸板坯卷渣夹杂物含量的方法

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant