CN113110243B - Construction operation site safety intelligent management and control platform - Google Patents

Construction operation site safety intelligent management and control platform Download PDF

Info

Publication number
CN113110243B
CN113110243B CN202110527944.4A CN202110527944A CN113110243B CN 113110243 B CN113110243 B CN 113110243B CN 202110527944 A CN202110527944 A CN 202110527944A CN 113110243 B CN113110243 B CN 113110243B
Authority
CN
China
Prior art keywords
center
control ball
mobile
violation
information
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202110527944.4A
Other languages
Chinese (zh)
Other versions
CN113110243A (en
Inventor
冯杰
徐越峰
游强
薛钊
方衍
符丁枫
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Shaanxi Electric Power Co Ltd
Original Assignee
State Grid Shaanxi Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Shaanxi Electric Power Co Ltd filed Critical State Grid Shaanxi Electric Power Co Ltd
Priority to CN202110527944.4A priority Critical patent/CN113110243B/en
Publication of CN113110243A publication Critical patent/CN113110243A/en
Application granted granted Critical
Publication of CN113110243B publication Critical patent/CN113110243B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G05CONTROLLING; REGULATING
    • G05BCONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS
    • G05B19/00Programme-control systems
    • G05B19/02Programme-control systems electric
    • G05B19/04Programme control other than numerical control, i.e. in sequence controllers or logic controllers
    • G05B19/042Programme control other than numerical control, i.e. in sequence controllers or logic controllers using digital processors
    • G05B19/0428Safety, monitoring
    • GPHYSICS
    • G05CONTROLLING; REGULATING
    • G05BCONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS
    • G05B2219/00Program-control systems
    • G05B2219/20Pc systems
    • G05B2219/24Pc safety
    • G05B2219/24024Safety, surveillance

Abstract

The application discloses a construction operation site safety intelligent management and control platform, which comprises an operation plan management center, a management center and a control platform, wherein the operation plan management center performs planning and arrangement on received operation projects and issues the operation projects to be executed; confirming the electric power operation site end and the movable distribution control ball through the movable external network end and starting operation; collecting video images of production behaviors of production personnel; the mobile control ball sends the rule-breaking judgment basis to a remote video control center, and the remote video control center carries out preliminary rule-breaking identification on the rule-breaking judgment basis; the anti-violation center carries out secondary identification on the suspected violation image according to the operation information; the operation plan management center checks the confirmed violation image and the operation information matched with the confirmed violation image. By arranging the system, the application realizes the real-time regulation violation monitoring of the electric operation, the monitoring result is convenient to inquire, the application is especially suitable for the field operation of the electric operation, and the monitoring cost of the regulation violation behavior is reduced.

Description

Construction operation site safety intelligent management and control platform
Technical Field
The application relates to the technical field of power systems, in particular to a safe and intelligent management and control platform for a construction operation site.
Background
With the continuous promotion of electric power construction work, a great amount of electric power business such as power grid construction, distribution network rush repair, equipment operation and maintenance and other field work load are increasingly increased, because the electric power system operation field points are wide and the three-level safety inspection team strength tracking and supervision of an electric power company are far from being enough, the field operation standardized overall process management and control business is necessary to be taken as a main line, the overall operation unified data center is taken as a support, the information such as outsourcing units, operators, violation conditions, on-duty conditions, operation behaviors, tool use, operation point positioning and the like is integrated, and meanwhile, the technical means such as video monitoring, mobile consultation and the like are mainly applied, and the whole-flow, intelligent, visual and trace-type field operation standardized management and control mode is formed at the mobile end and the large-screen end, so that the operation field all-dimensional supervision and control is realized.
In the prior art, although the technical scheme of carrying out the recognition of the illegal behaviors through the camera exists, in practical application, the power system often has field operation, so that each field point cannot be accurately distributed and controlled in the application of the prior art, and the illegal behaviors cannot be monitored in time.
Disclosure of Invention
The technical problem to be solved by the application is that the electric power system often has field operation, which causes that each field point cannot be accurately distributed and controlled in the application process in the prior art, so that the illegal behaviors cannot be monitored in time.
The application is realized by the following technical scheme:
the construction operation site safety intelligent management and control platform comprises an inner network and an outer network which are interacted through a safety gateway, and is characterized in that the outer network comprises a mobile outer network end; the intranet comprises an operation plan management center, a remote video management and control center, an anti-violation center, a safety access platform, a mobile distribution control ball and an electric power operation field terminal; the mobile control ball is interacted with the remote video center through the secure access platform, and the mobile control ball is distributed on a power production site;
the operation plan management center performs planning and arrangement on the received operation items and issues the operation items to be executed to the mobile external network end, the electric power operation field end, the anti-violation center and the remote video management and control center; the operation project comprises an operation place, operation time and operation content;
when a production person arrives at a working site according to a working project received by a mobile external network end, confirming the electric power working site end and the mobile control ball through the mobile external network end and starting the operation;
in operation, the mobile control ball collects video images of production behaviors of production personnel as rule violation judgment basis; the mobile control ball sends the rule-breaking judgment basis to the remote video control center, and the remote video control center performs preliminary rule-breaking identification on the rule-breaking judgment basis, performs screenshot on suspected rule-breaking behaviors to generate suspected rule-breaking images and sends the suspected rule-breaking images to the anti-rule-breaking center; the remote video management and control center also sends the operation information matched with the suspected violation image to the anti-violation center; the operation information comprises operation time, operation place, operation personnel, operation content and operation violation content;
the anti-violation center carries out secondary identification on the suspected violation image according to the operation information, and takes the identified suspected violation image as an identified violation image; the anti-violation center sends the confirmed violation image and the operation information matched with the confirmed violation image to the operation plan management center; and the operation plan management center checks the confirmation violation image and the operation information matched with the confirmation violation image according to the operation project, and records the confirmation violation image and the operation information matched with the confirmation violation image.
In the actual power production process, a large number of electrical devices are required to be overhauled and maintained, and the electrical devices are often in an outdoor environment and even far away from a main trunk, so that the violation monitoring cannot be performed through common fixedly installed devices in the existing design.
When the application is applied, all functions in field operation are realized through the movable control ball and the electric power operation field end, wherein the movable control ball can be carried by a supervisory personnel by itself, and the control ball installation of the operation field is completed; the operation personnel can carry out the operation site card punching confirmation through moving the control ball and the electric power operation site end, and the electric power operation site end is preferably a tablet personal computer used by site supervisory personnel. All communication processes of the mobile control ball are carried out on an internal network, so that data transmission is very convenient, monitoring of illegal behaviors can be realized in real time, and the electric power operation field end and the mobile external network end are carried out on an external network, thereby being beneficial to network security of an electric power system.
When the method is used for monitoring the violations, the monitoring image is identified twice, the first identification is carried out by an image identification technology, and because the transmission resources of the existing intranet are relatively limited, the video can be cut into suspected violations in the first identification, so that the second manual screening is facilitated. After manual screening, the confirmed violation images can be matched with the operation information, so that the violation information can be quickly acquired, and the violation behaviors of operators can be conveniently managed and controlled. By arranging the system, the application realizes the real-time regulation violation monitoring of the electric operation, the monitoring result is convenient to inquire, the application is especially suitable for the field operation of the electric operation, and the monitoring cost of the regulation violation behavior is reduced.
Further, when the production personnel confirms the electric power operation field end and the movable control ball through the movable external network end and starts operation;
and if the mobile control ball is not matched with the operation project, the mobile external network end sends the information of the mobile control ball to the operation plan management center, and the operation plan management center confirms the information of the mobile control ball and then records the information into the operation project or corrects the operation project.
When the mobile control ball is applied, in order to improve the universality of the mobile control ball, when the mobile control ball is arranged on different sites, the error correction and registration of the mobile control ball are realized by the site personnel through the mobile outer network end, so that the mobile control ball information in the whole system can be updated in time when the mobile control ball is changed.
Further, the information of the mobile control ball comprises the number information of the mobile control ball, the positioning information of the mobile control ball and the operation information of the mobile control ball;
when the positioning information of the mobile control ball is matched with the operation site in the operation project and the operation information of the mobile control ball is not matched with the operation project, correcting the operation information of the mobile control ball into the operation project; the operation information of the movable control ball is not matched with the operation project, and the operation information of the movable control ball is not identical with the operation project and comprises the absence of the operation information of the movable control ball;
when the positioning information of the mobile control ball is not matched with the operation location in the operation project, the operation plan management center sends warning signals to the mobile external network end and the electric operation site end.
Further, when the job site needs to modify the job content, a producer sends a temporary job plan to the job plan management center through the mobile external network terminal; the operation plan management center approves the temporary operation plan and sends the temporary operation plan to the electric power operation field terminal;
and the production personnel confirms the temporary operation on the electric power operation field end through the mobile external network end and then starts the temporary operation.
Further, the remote video management and control center adopts image recognition to capture the suspected illegal behaviors to generate suspected illegal images; and the anti-violation center adopts manual identification to carry out secondary identification on the suspected violation image according to the operation information.
Further, the camera also comprises a fixed camera; the fixed camera is arranged on a fixed power production site, and the movable control ball is movably arranged on an outdoor site of power production; the fixed cameras collect images and send the images to the remote video management and control center for daily production monitoring.
Further, the device also comprises an intranet input end; and the intranet input end inputs the operation items and sends the operation items to the operation plan management center.
Further, the system also comprises a unified data center; the unified data center is used for acquiring the planned and tidied operation items from the operation plan management center and carrying out overall management and control on the planned and tidied operation items.
Further, the mobile control ball interacts with the secure access platform through an APN private network channel.
Compared with the prior art, the application has the following advantages and beneficial effects:
by arranging the system, the real-time illegal monitoring of the electric operation is realized, the monitoring result is convenient to inquire, the intelligent control platform is particularly suitable for the field operation of the electric operation, and the monitoring cost of illegal behaviors is reduced.
Drawings
The accompanying drawings, which are included to provide a further understanding of embodiments of the application and are incorporated in and constitute a part of this specification, illustrate embodiments of the application and together with the description serve to explain the principles of the application. In the drawings:
FIG. 1 is a schematic diagram of a system according to the present application.
Detailed Description
For the purpose of making apparent the objects, technical solutions and advantages of the present application, the present application will be further described in detail with reference to the following examples and the accompanying drawings, wherein the exemplary embodiments of the present application and the descriptions thereof are for illustrating the present application only and are not to be construed as limiting the present application.
Examples
As shown in fig. 1, the safety intelligent management and control platform for a construction operation site comprises an inner network and an outer network which are interacted through a safety gateway, wherein the outer network comprises a mobile outer network end; the intranet comprises an operation plan management center, a remote video management and control center, an anti-violation center, a safety access platform, a mobile distribution control ball and an electric power operation field terminal; the mobile control ball is interacted with the remote video center through the secure access platform, and the mobile control ball is distributed on a power production site;
the operation plan management center performs planning and arrangement on the received operation items and issues the operation items to be executed to the mobile external network end, the electric power operation field end, the anti-violation center and the remote video management and control center; the operation project comprises an operation place, operation time and operation content;
when a production person arrives at a working site according to a working project received by a mobile external network end, confirming the electric power working site end and the mobile control ball through the mobile external network end and starting the operation;
in operation, the mobile control ball collects video images of production behaviors of production personnel as rule violation judgment basis; the mobile control ball sends the rule-breaking judgment basis to the remote video control center, and the remote video control center performs preliminary rule-breaking identification on the rule-breaking judgment basis, performs screenshot on suspected rule-breaking behaviors to generate suspected rule-breaking images and sends the suspected rule-breaking images to the anti-rule-breaking center; the remote video management and control center also sends the operation information matched with the suspected violation image to the anti-violation center; the operation information comprises operation time, operation place, operation personnel, operation content and operation violation content;
the anti-violation center carries out secondary identification on the suspected violation image according to the operation information, and takes the identified suspected violation image as an identified violation image; the anti-violation center sends the confirmed violation image and the operation information matched with the confirmed violation image to the operation plan management center; and the operation plan management center checks the confirmation violation image and the operation information matched with the confirmation violation image according to the operation project, and records the confirmation violation image and the operation information matched with the confirmation violation image.
In the actual power production process, a large number of electrical devices are required to be overhauled and maintained, and the electrical devices are often in an outdoor environment and even far away from a main trunk, so that the violation monitoring cannot be performed through common fixedly installed devices in the existing design.
When the embodiment is implemented, all functions in field operation are realized through the mobile control ball and the electric power operation field end, wherein the mobile control ball can be carried by a supervisory personnel by itself, and the control ball installation of the operation field is completed; the operator can carry out the operation site card punching confirmation action through moving the control ball and the electric power operation site end. All communication processes of the mobile control ball are carried out on an internal network, so that data transmission is very convenient, monitoring of illegal behaviors can be realized in real time, and the electric power operation field end and the mobile external network end are carried out on an external network, thereby being beneficial to network security of an electric power system.
When the method is used for monitoring the violations, the monitoring image is identified twice, the first identification is carried out by an image identification technology, and because the transmission resources of the existing intranet are relatively limited, the video can be cut into suspected violations in the first identification, so that the second manual screening is facilitated. After manual screening, the confirmed violation images can be matched with the operation information, so that the violation information can be quickly acquired, and the violation behaviors of operators can be conveniently managed and controlled. By arranging the system, the application realizes the real-time regulation violation monitoring of the electric operation, the monitoring result is convenient to inquire, the application is especially suitable for the field operation of the electric operation, and the monitoring cost of the regulation violation behavior is reduced.
In order to further explain the working process of the embodiment, when a producer confirms the electric power operation field end and the mobile control ball through the mobile external network end and starts operation;
and if the mobile control ball is not matched with the operation project, the mobile external network end sends the information of the mobile control ball to the operation plan management center, and the operation plan management center confirms the information of the mobile control ball and then records the information into the operation project or corrects the operation project.
In the implementation of the embodiment, in order to improve the universality of the mobile control ball, when the mobile control ball is arranged on different sites, the site personnel are required to realize the error correction and registration of the mobile control ball through the mobile external network end, so that the mobile control ball information in the whole system can be updated in time when the mobile control ball is changed.
In order to further illustrate the working process of the embodiment, the information of the mobile control ball includes the number information of the mobile control ball, the positioning information of the mobile control ball and the operation information of the mobile control ball;
when the positioning information of the mobile control ball is matched with the operation site in the operation project and the operation information of the mobile control ball is not matched with the operation project, correcting the operation information of the mobile control ball into the operation project; the operation information of the movable control ball is not matched with the operation project, and the operation information of the movable control ball is not identical with the operation project and comprises the absence of the operation information of the movable control ball;
when the positioning information of the mobile control ball is not matched with the operation location in the operation project, the operation plan management center sends warning signals to the mobile external network end and the electric operation site end.
In order to further explain the working process of the embodiment, when the job site needs to modify the job content, a producer sends a temporary job plan to the job plan management center through the mobile external network terminal; the operation plan management center approves the temporary operation plan and sends the temporary operation plan to the electric power operation field terminal;
and the production personnel confirms the temporary operation on the electric power operation field end through the mobile external network end and then starts the temporary operation.
In order to further explain the working process of the embodiment, the remote video management and control center uses image recognition to perform screenshot on the suspected illegal behaviors to generate suspected illegal images; and the anti-violation center adopts manual identification to carry out secondary identification on the suspected violation image according to the operation information.
To further illustrate the working process of the embodiment, the camera also comprises a fixed camera; the fixed camera is arranged on a fixed power production site, and the movable control ball is movably arranged on an outdoor site of power production; the fixed cameras collect images and send the images to the remote video management and control center for daily production monitoring.
In order to further illustrate the working process of the embodiment, the device further comprises an intranet input end; and the intranet input end inputs the operation items and sends the operation items to the operation plan management center.
To further illustrate the operation of the present embodiment, a unified data center is further included; the unified data center is used for acquiring the planned and tidied operation items from the operation plan management center and carrying out overall management and control on the planned and tidied operation items.
In order to further explain the working process of this embodiment, the mobile control ball interacts with the secure access platform through an APN private network channel.
In the embodiment, when the method is specifically applied to power grid operation, the method utilizes the ubiquitous Internet of things concept to interconnect the video devices of the internal and external networks for the first time, and the video devices of the internal and external networks are accessed into 11890 video resources of the internal and external networks altogether; firstly, realizing professional operation plan data fusion of production, capital construction and the like based on a unified data center of all services; by using a large screen visualization technology, an intelligent decision center for real-time display, panoramic visualization and intelligent early warning is constructed, and through a layered hierarchical joint supervision mode, full coverage monitoring of heavy point areas such as full-province high-operation risk level sites, transformer substations, power transmission lines (including three spans) and the like is realized, the inspection range is enlarged by 1468%, the average inspection efficiency is improved by 37 times, the violation rate is reduced by 26%, and the safety supervision efficiency is greatly improved.
The foregoing description of the embodiments has been provided for the purpose of illustrating the general principles of the application, and is not meant to limit the scope of the application, but to limit the application to the particular embodiments, and any modifications, equivalents, improvements, etc. that fall within the spirit and principles of the application are intended to be included within the scope of the application.

Claims (7)

1. The construction operation site safety intelligent management and control platform comprises an inner network and an outer network which are interacted through a safety gateway, and is characterized in that the outer network comprises a mobile outer network end; the intranet comprises an operation plan management center, a remote video management and control center, an anti-violation center, a safety access platform, a mobile distribution control ball and an electric power operation field terminal; the mobile control ball is interacted with the remote video center through the secure access platform, and the mobile control ball is distributed on a power production site;
the operation plan management center performs planning and arrangement on the received operation items and issues the operation items to be executed to the mobile external network end, the electric power operation field end, the anti-violation center and the remote video management and control center; the operation project comprises an operation place, operation time and operation content;
when a production person arrives at a working site according to a working project received by a mobile external network end, confirming the electric power working site end and the mobile control ball through the mobile external network end and starting the operation;
in operation, the mobile control ball collects video images of production behaviors of production personnel as rule violation judgment basis; the mobile control ball sends the rule-breaking judgment basis to the remote video control center, and the remote video control center performs preliminary rule-breaking identification on the rule-breaking judgment basis, performs screenshot on suspected rule-breaking behaviors to generate suspected rule-breaking images and sends the suspected rule-breaking images to the anti-rule-breaking center; the remote video management and control center also sends the operation information matched with the suspected violation image to the anti-violation center; the operation information comprises operation time, operation place, operation personnel, operation content and operation violation content;
the anti-violation center carries out secondary identification on the suspected violation image according to the operation information, and takes the identified suspected violation image as an identified violation image; the anti-violation center sends the confirmed violation image and the operation information matched with the confirmed violation image to the operation plan management center; the operation plan management center checks the confirmation violation image and the operation information matched with the confirmation violation image according to the operation project, and records the confirmation violation image and the operation information matched with the confirmation violation image;
when a producer confirms the electric power operation field end and the movable distribution control ball through the movable external network end and starts operation;
if the mobile control ball is not matched with the operation project, the mobile external network end sends the information of the mobile control ball to the operation plan management center, and the operation plan management center confirms the information of the mobile control ball and then records the information into the operation project or corrects the operation project;
the information of the mobile control ball comprises the number information of the mobile control ball, the positioning information of the mobile control ball and the operation information of the mobile control ball;
when the positioning information of the mobile control ball is matched with the operation site in the operation project and the operation information of the mobile control ball is not matched with the operation project, correcting the operation information of the mobile control ball into the operation project; the operation information of the movable control ball is not matched with the operation project, and the operation information of the movable control ball is not identical with the operation project and comprises the absence of the operation information of the movable control ball;
when the positioning information of the mobile control ball is not matched with the operation location in the operation project, the operation plan management center sends warning signals to the mobile external network end and the electric operation site end;
when the mobile control ball is arranged to different sites, the site personnel are required to realize the error correction and registration of the mobile control ball through the mobile external network terminal.
2. The construction operation site safety intelligent management and control platform according to claim 1, wherein when the operation site needs to modify the operation content, a producer sends a temporary operation plan to the operation plan management center through the mobile external network terminal; the operation plan management center approves the temporary operation plan and sends the temporary operation plan to the electric power operation field terminal;
and the production personnel confirms the temporary operation on the electric power operation field end through the mobile external network end and then starts the temporary operation.
3. The construction job site safety intelligent control platform according to claim 1, wherein the remote video control center uses image recognition to screen the suspected offence to generate a suspected offence image; and the anti-violation center adopts manual identification to carry out secondary identification on the suspected violation image according to the operation information.
4. The construction job site safety intelligent control platform according to claim 1, further comprising a fixed camera; the fixed camera is arranged on a fixed power production site, and the movable control ball is movably arranged on an outdoor site of power production; the fixed cameras collect images and send the images to the remote video management and control center for daily production monitoring.
5. The construction work site safety intelligent control platform according to claim 1, further comprising an intranet input end; and the intranet input end inputs the operation items and sends the operation items to the operation plan management center.
6. The construction job site safety intelligent management and control platform according to claim 1, further comprising a unified data center; the unified data center is used for acquiring the planned and tidied operation items from the operation plan management center and carrying out overall management and control on the planned and tidied operation items.
7. The construction job site safety intelligent management and control platform according to claim 1, wherein the mobile management and control ball interacts with the safety access platform through an APN private network channel.
CN202110527944.4A 2021-05-14 2021-05-14 Construction operation site safety intelligent management and control platform Active CN113110243B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110527944.4A CN113110243B (en) 2021-05-14 2021-05-14 Construction operation site safety intelligent management and control platform

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110527944.4A CN113110243B (en) 2021-05-14 2021-05-14 Construction operation site safety intelligent management and control platform

Publications (2)

Publication Number Publication Date
CN113110243A CN113110243A (en) 2021-07-13
CN113110243B true CN113110243B (en) 2023-10-17

Family

ID=76722182

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110527944.4A Active CN113110243B (en) 2021-05-14 2021-05-14 Construction operation site safety intelligent management and control platform

Country Status (1)

Country Link
CN (1) CN113110243B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113610011A (en) * 2021-09-22 2021-11-05 国网江苏省电力有限公司太仓市供电分公司 AI identification system for distribution network operation site personnel management and control

Citations (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103227811A (en) * 2012-12-27 2013-07-31 富阳市供电局 External network server-side management and control method for electric power working site management and control system
WO2015131462A1 (en) * 2014-03-07 2015-09-11 国家电网公司 Centralized monitoring system and monitoring method for unmanned aerial vehicle to patrol power transmission line
CN105812750A (en) * 2016-04-27 2016-07-27 国网安徽省电力公司六安市叶集供电公司 Mobile anti-violation of regulations individual equipment in power dispatching monitoring system
CN206932333U (en) * 2017-08-24 2018-01-26 北京融通智慧科技有限公司 Power grid visualization intelligent monitoring administration plateform system
CN110119656A (en) * 2018-02-07 2019-08-13 中国石油化工股份有限公司 Intelligent monitor system and the scene monitoring method violating the regulations of operation field personnel violating the regulations
CN110533317A (en) * 2019-08-26 2019-12-03 国网河北省电力有限公司保定供电分公司 One kind being based on Internet technology mobile job-oriented terminal system and method
CN209938622U (en) * 2018-12-28 2020-01-14 卡斯柯信号有限公司 Shunting operation plan transmission system
CN110852611A (en) * 2019-11-08 2020-02-28 国网上海市电力公司 Real-time management and control system for construction workers on capital construction project site
CN111147823A (en) * 2020-01-06 2020-05-12 国网上海市电力公司 Method for realizing remote monitoring and supporting for transformer substation emergency repair by adopting monitoring platform
CN111626707A (en) * 2020-05-28 2020-09-04 广东电力信息科技有限公司 Intelligent remote operation safety control method and device
CN112016803A (en) * 2020-07-23 2020-12-01 浙江图盛输变电工程有限公司温州科技分公司 Cross-professional power grid risk safety management and control system fusing operation big data
CN112131939A (en) * 2020-08-14 2020-12-25 广西电网有限责任公司来宾供电局 Image recognition system for habitual violation behaviors in power grid infrastructure engineering
CN112365223A (en) * 2020-10-23 2021-02-12 岭东核电有限公司 Job control method, apparatus, computer device, and storage medium

Patent Citations (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103227811A (en) * 2012-12-27 2013-07-31 富阳市供电局 External network server-side management and control method for electric power working site management and control system
WO2015131462A1 (en) * 2014-03-07 2015-09-11 国家电网公司 Centralized monitoring system and monitoring method for unmanned aerial vehicle to patrol power transmission line
CN105812750A (en) * 2016-04-27 2016-07-27 国网安徽省电力公司六安市叶集供电公司 Mobile anti-violation of regulations individual equipment in power dispatching monitoring system
CN206932333U (en) * 2017-08-24 2018-01-26 北京融通智慧科技有限公司 Power grid visualization intelligent monitoring administration plateform system
CN110119656A (en) * 2018-02-07 2019-08-13 中国石油化工股份有限公司 Intelligent monitor system and the scene monitoring method violating the regulations of operation field personnel violating the regulations
CN209938622U (en) * 2018-12-28 2020-01-14 卡斯柯信号有限公司 Shunting operation plan transmission system
CN110533317A (en) * 2019-08-26 2019-12-03 国网河北省电力有限公司保定供电分公司 One kind being based on Internet technology mobile job-oriented terminal system and method
CN110852611A (en) * 2019-11-08 2020-02-28 国网上海市电力公司 Real-time management and control system for construction workers on capital construction project site
CN111147823A (en) * 2020-01-06 2020-05-12 国网上海市电力公司 Method for realizing remote monitoring and supporting for transformer substation emergency repair by adopting monitoring platform
CN111626707A (en) * 2020-05-28 2020-09-04 广东电力信息科技有限公司 Intelligent remote operation safety control method and device
CN112016803A (en) * 2020-07-23 2020-12-01 浙江图盛输变电工程有限公司温州科技分公司 Cross-professional power grid risk safety management and control system fusing operation big data
CN112131939A (en) * 2020-08-14 2020-12-25 广西电网有限责任公司来宾供电局 Image recognition system for habitual violation behaviors in power grid infrastructure engineering
CN112365223A (en) * 2020-10-23 2021-02-12 岭东核电有限公司 Job control method, apparatus, computer device, and storage medium

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
布控球可接入电网安全接入平台及电网统一视频监控平台;搜狐;《布控球可接入电网安全接入平台及电网统一视频监控平台》;20210422;全文 *

Also Published As

Publication number Publication date
CN113110243A (en) 2021-07-13

Similar Documents

Publication Publication Date Title
CN103544739B (en) Based on the method for inspecting of the visual subway equipment routing inspection management system of B/S framework
CN104950855A (en) Town sewage plant and pump station operation monitoring management system and town sewage plant and pump station operation monitoring management method
CN104978692A (en) Handheld terminal collecting system
CN111062504A (en) AR technology-based intelligent power distribution station operation and maintenance system and method
CN111147823B (en) Method for realizing remote monitoring and supporting for transformer substation emergency repair by adopting monitoring platform
CN101458502A (en) Electrical power system standardized work intelligent control method and special equipment
CN112001310A (en) Transformer substation operation field safety control system based on visual perception and space positioning
CN105049223A (en) Electric power communication network defect and fault processing decision-aided analysis method
CN103177327A (en) Comprehensive management system for low-voltage power operations based on B/S (browser/server) and C/S (client/server) architectures
CN113110243B (en) Construction operation site safety intelligent management and control platform
CN107818449A (en) A kind of power transformation fortune inspection management system based on mobile solution platform
CN108574696A (en) A kind of command dispatching system and working method based on GIS map
CN111509840A (en) Wireless cluster visualization system and method based on power grid safety operation and maintenance
CN104966329A (en) System for intelligent scheduling and polling of photovoltaic power station
CN104076777A (en) Asphalt mixing plant wireless scheduling system and method based on terminals
KR100780450B1 (en) Management system for distribution system of power degradation in connection with new distribution information system and method thereof
CN107545519A (en) A kind of power grid enterprises' fortune inspection management-control method
CN111147822B (en) Monitoring system for transformer substation emergency repair
CN103559652A (en) Communication work-ticket management system based on unattended substation and operation method of communication work-ticket management system
CN103559665A (en) Preventing and disposing system for hospital emergencies
CN100547624C (en) The method of a kind of remote monitoring working-yard operation
CN106603965A (en) Remote real-time safety supervision method suitable for power construction site
CN104079871A (en) Video processing method
CN104009543B (en) The supervision method of transformer station's secondary equipment running status
CN112365017A (en) Remote intelligent inspection system for gas station

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant