CN112854251A - Multistage construction platform for critical stable slope and construction method thereof - Google Patents

Multistage construction platform for critical stable slope and construction method thereof Download PDF

Info

Publication number
CN112854251A
CN112854251A CN202011633616.4A CN202011633616A CN112854251A CN 112854251 A CN112854251 A CN 112854251A CN 202011633616 A CN202011633616 A CN 202011633616A CN 112854251 A CN112854251 A CN 112854251A
Authority
CN
China
Prior art keywords
construction platform
construction
slope
slope body
platform
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202011633616.4A
Other languages
Chinese (zh)
Inventor
刘超
郭小红
晁峰
郭建涛
姚再峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China State Construction Engineering Corp Ltd CSCEC
China State Construction Engineering Industry Technology Research Institute
Original Assignee
China State Construction Engineering Corp Ltd CSCEC
China State Construction Engineering Industry Technology Research Institute
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China State Construction Engineering Corp Ltd CSCEC, China State Construction Engineering Industry Technology Research Institute filed Critical China State Construction Engineering Corp Ltd CSCEC
Priority to CN202011633616.4A priority Critical patent/CN112854251A/en
Publication of CN112854251A publication Critical patent/CN112854251A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/20Securing of slopes or inclines
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/20Securing of slopes or inclines
    • E02D17/207Securing of slopes or inclines with means incorporating sheet piles or piles
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/10Deep foundations
    • E02D27/12Pile foundations
    • E02D27/14Pile framings, i.e. piles assembled to form the substructure

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)

Abstract

The application discloses a multistage construction platform for a critical stable slope and a construction method thereof, wherein the construction platform (6) is used for implementing construction engineering on the slope. The method for constructing the construction platform (6) on the slope body (100) comprises the following steps: at least one stage of auxiliary construction platform (2) is built along the slope body from the bottom to top from the slope toe of the slope body, wherein the last stage of auxiliary construction platform (4) in the auxiliary construction platforms is used for building the construction platform (6); and building the construction platform (6) on the last-stage auxiliary construction platform (4).

Description

Multistage construction platform for critical stable slope and construction method thereof
Technical Field
The application relates to the field of engineering construction, in particular to a multistage construction platform for a critical stable slope and a construction method thereof.
Background
The critical stable slope body is a slope body in a critical stable state, and when the slope body of the type is disturbed by excavation, the slope is easy to slide to cause safety accidents. With the accelerated development of the basic construction of China and the implementation of the western major development strategy, the engineering construction of railways, roads, water conservancy, energy resources and the like is more and more greatly influenced by the landform conditions. Excavation of the mountain is inevitably required in the construction of these infrastructures. Due to the influence of special geological conditions, climatic conditions and the like on a steep hillside, the slope rock-soil body is weathered and degraded by wind and the terrain cutting effect is strong to form a critical stable slope body, so that the phenomena of geological disasters such as collapse, landslide, debris flow and the like are very easy to occur, the critical stable slope body becomes a main risk source for engineering construction in mountain areas, the construction difficulty is greatly increased, the national property is endangered, more serious persons endanger the safety of constructors, and the engineering construction is troublesome.
The construction of the steep slope mainly comprises two aspects: firstly, the excavation construction of side slope. For a steep side slope, excavation of rock and soil mass often has no footing, construction period for temporarily building a road with a large slope is long, influence on the environment is caused, and road building such as unfavorable geological conditions and the like becomes extremely difficult. In addition, the side slope instability caused by side slope excavation is very serious. And secondly, protection construction of a steep side slope. The protection construction difficulty is high, the geological conditions are complex, and the terrains are dangerous, so that various difficulties are brought to the protection construction. Excavation disturbances can also adversely affect slope protection.
Regarding the technical method and the device of the prior slope construction platform, the method and the device are mainly characterized in that a first-level movable construction platform is built on a slope. However, the movable construction platform is generally only suitable for small slopes with low terrain or low gradient, but has great limitation for steep hillside slopes with large height, and cannot meet the construction requirements of large-scale machinery. The slope faced in construction cannot be adapted by the known method. Therefore, a novel slope construction platform scheme needs to be provided for the engineering environment.
Aiming at the technical problems that the engineering construction is difficult and the construction platform is difficult to build in the steep and critical stable side slope terrain in the prior art, an effective solution is not provided at present.
Disclosure of Invention
The utility model provides a multistage construction and construction platform for a critical stable slope body and a construction method thereof, which at least solve the technical problems that the engineering construction and construction are difficult and the construction platform is difficult to build in the steep and critical stable slope terrain in the prior art.
According to one aspect of the embodiment of the application, a method for constructing a construction platform on a slope body is provided, and the construction platform is used for implementing construction engineering on the slope body. The method comprises the following steps: and at least one stage of auxiliary construction platform is built along the slope body from the bottom to the top from the slope toe of the slope body, wherein the last stage of auxiliary construction platform in the auxiliary construction platforms is used for building a construction platform, and the construction platform is built on the last stage of auxiliary construction platform.
According to another aspect of the embodiments of the present application, a method of performing construction work on a slope body is provided. The method comprises the following steps: according to the method, a construction platform for constructing the construction project is built; and carrying out construction engineering on the construction engineering platform.
According to another aspect of the embodiment of the application, a multistage construction platform built on a slope body is provided. The multistage construction platform includes: at least one stage of auxiliary construction platform; and a construction platform for implementing construction engineering on the slope. Wherein at least one stage of auxiliary construction platform is built along the slope body from the toe of the slope body in the sequence from bottom to top; and the construction platform is built on the last-stage auxiliary construction platform.
Thereby through the technical scheme of this embodiment, the above-mentioned technical problem who exists among the prior art has been solved to this embodiment is applicable to the constructive construction on the steep side slope topography of full type under the effect of multistage auxiliary construction platform, has following advantage:
1. aiming at the construction and excavation work on steep slope terrain, a safe and stable construction platform can be provided, and the operation of construction equipment and the material transfer are facilitated;
2. the fragile side slope can be permanently reinforced, and the side slope geological disaster can be prevented;
3. the method can be suitable for the construction of railway, highway, water conservancy, bridge and other projects in steep slope terrain, and has wide application range; and
4. the method has better anti-interference capability on complex geological conditions, climate and the like in steep slope terrain, can effectively reduce the construction period, reduces the influence on the ecological environment and improves the construction safety.
The above and other objects, advantages and features of the present application will become more apparent to those skilled in the art from the following detailed description of specific embodiments thereof, taken in conjunction with the accompanying drawings.
Drawings
Some specific embodiments of the present application will be described in detail hereinafter by way of illustration and not limitation with reference to the accompanying drawings. The same reference numbers in the drawings identify the same or similar elements or components. Those skilled in the art will appreciate that the drawings are not necessarily drawn to scale. In the drawings:
fig. 1 is a flow chart of a method for constructing a construction platform on a slope body according to an embodiment of the application;
FIG. 2 is a side view of the overall arrangement for constructing a construction platform on a slope and constructing a tunnel according to the embodiment of the application;
fig. 3 is a top view of the overall arrangement for constructing a construction platform on a slope and constructing a tunnel according to the embodiment of the application;
FIG. 4 is a side view of the overall arrangement for constructing a construction platform on a slope body and constructing a bridge according to the embodiment of the application;
Detailed Description
It should be noted that, in the present disclosure, the embodiments and features of the embodiments may be combined with each other without conflict. The present disclosure will be described in detail below with reference to the accompanying drawings in conjunction with embodiments.
In order to make the technical solutions of the present disclosure better understood by those skilled in the art, the technical solutions of the embodiments of the present disclosure will be clearly and completely described below with reference to the drawings in the embodiments of the present disclosure, and it is obvious that the described embodiments are only some embodiments of the present disclosure, not all embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments disclosed herein without making any creative effort, shall fall within the protection scope of the present disclosure.
It should be noted that the terms "first," "second," and the like in the description and claims of the present disclosure and in the above-described drawings are used for distinguishing between similar elements and not necessarily for describing a particular sequential or chronological order. It is to be understood that the terms so used are interchangeable under appropriate circumstances for describing the embodiments of the disclosure herein. Furthermore, the terms "comprises," "comprising," and "having," and any variations thereof, are intended to cover a non-exclusive inclusion, such that a process, method, system, article, or apparatus that comprises a list of steps or elements is not necessarily limited to those steps or elements expressly listed, but may include other steps or elements not expressly listed or inherent to such process, method, article, or apparatus.
It is noted that the terminology used herein is for the purpose of describing particular embodiments only and is not intended to be limiting of example embodiments according to the present application. As used herein, the singular forms "a", "an" and "the" are intended to include the plural forms as well, and it should be understood that when the terms "comprises" and/or "comprising" are used in this specification, they specify the presence of stated features, steps, operations, devices, components, and/or combinations thereof, unless the context clearly indicates otherwise.
Fig. 1 is a flowchart of a method for constructing a construction platform 6 on a slope 100 according to an embodiment of the present application. The construction platform 6 is used for implementing construction engineering on a slope body 100, and as shown in fig. 1, the method comprises the following steps:
s102: at least one stage of auxiliary construction platforms 2 and 4 are built along the slope body 100 from the bottom to the top from the toe of the slope body 100, wherein the last stage of auxiliary construction platform 4 in the auxiliary construction platforms 2 and 4 is used for building a construction platform 6; and
s104: and (4) building a construction platform 6 on the last-stage auxiliary construction platform 4.
Specifically, fig. 2 shows an overall arrangement side view of constructing a construction platform on a slope and constructing a tunnel according to the embodiment of the application. Referring to fig. 2, according to the method of the present embodiment, before the tunnel 8 is excavated, a construction platform 6 required for excavating the tunnel 8 needs to be built. In order to build the construction platform 6, at least one stage of auxiliary construction platforms 2 and 4 are built from the toe in sequence from bottom to top, and then the construction platform 6 is built on the last stage of auxiliary construction platform 4, so that the building of the construction platform 6 is completed, and then the construction of the tunnel 8 can be carried out on the construction platform 6.
As described in the background art, a critical stable slope body is a slope body in a critical stable state, and when the slope body of the type is disturbed by excavation, a slope is easy to occur to cause a safety accident. The mountain is inevitably required to be excavated in the construction of foundation engineering. And the critical stable slope body formed on the steep hillside is easy to have geological disasters such as collapse, landslide, debris flow and the like, thereby greatly increasing the construction difficulty, endangering the national property, endangering the safety of constructors by more serious persons and bringing troubles to engineering construction. The existing construction platform cannot meet the constructive construction under a steep slope body, the construction condition under a critical stable state is not considered at the beginning of design, equipment is only limited to a low terrain or a small slope with a low gradient, and the construction platform cannot be applied to the constructive construction under the condition of the steep terrain.
For the technical problem, the method of the embodiment builds the auxiliary construction platform 2 and the auxiliary construction platform 4 in the process of building the construction platform 6. For example, the method of the embodiment builds the auxiliary construction platforms 2 and 4 step by step along the slope body 100 from the bottom to the top in sequence starting from the toe of the slope body 100. Then, the method of this embodiment performs construction on the last-stage auxiliary construction platform 4 of the auxiliary construction platforms and builds the construction platform 6. Therefore, the method of the embodiment starts from the toe of the slope body, and builds the construction platform upwards step by step until the construction platform 6 suitable for construction is built finally.
Therefore, by the mode of building the auxiliary construction platform step by step and finally building the construction platform, the construction platform meeting construction conditions can be built on a slope body with steep terrain. And moreover, a multi-stage auxiliary construction platform is built during construction, and a critical stable slope body is stably reinforced, so that the technical problems that engineering construction on steep and critical stable slope terrain is difficult and a construction platform is difficult to build in the prior art are solved.
Optionally, the operation of building at least one level of auxiliary construction platform 2 and 4 comprises: and a next-stage auxiliary construction platform 4 is built on the previous-stage auxiliary construction platform 2. Wherein the scale of the next-stage auxiliary construction platform 4 is larger than that of the previous-stage auxiliary construction platform 2.
Specifically, referring to fig. 2, according to the method of the present embodiment, a small auxiliary construction platform 2 may be built on a slope toe by manual and small mechanical construction, and then a mechanical construction may be performed on the small construction platform 2 to build an auxiliary construction platform 4 on a slope body 100, which is larger than the small construction platform 2. And then, a construction platform 6 is built on the auxiliary construction platform 4 in a large mechanical construction mode.
As described in the background art, construction on a steep hill with a large height needs to meet the construction requirements of large-scale mechanical construction. But limited by the limitation of terrain, a platform suitable for the construction requirement of large-scale machinery is difficult to build on a steep hillside. In view of this, the method described in this embodiment may be implemented, starting from the toe of the hillside, by first building an auxiliary construction platform (e.g., the small construction platform 2) with low difficulty and small scale, and then building a next-stage auxiliary construction platform (e.g., the medium construction platform 4) with larger scale on the auxiliary construction platform with small scale. Therefore, by the mode, the scale of the auxiliary construction platform can be enlarged step by step, and finally, the construction platform suitable for large-scale mechanized construction is built on the auxiliary construction platform.
Optionally, referring to fig. 2 and 3, the operation of building at least one auxiliary construction platform includes building each of the auxiliary construction platforms 2 and 4 of the at least one auxiliary construction platform by: inserting a plurality of fixed piles 1 and 3 on the slope body 100 according to the boundaries corresponding to the auxiliary construction platforms 2 and 4, wherein the fixed piles 1 and 3 penetrate through the critical stable slope rock-soil mass 9 of the slope body 100 and are inserted into the stable slope rock-soil mass 10 of the slope body; and forming the auxiliary construction platforms 2 and 4 within the boundaries.
Specifically, referring to fig. 2 and 3, according to the method of the present embodiment, when the auxiliary construction platform 2 is constructed, the fixed pile 1 is inserted according to a preset boundary (e.g., "concave" boundary) corresponding to the auxiliary construction platform 2, wherein the fixed pile 1 is inserted into the stable slope rock soil mass 10 of the slope body through the critical stable slope rock soil mass 9 of the slope body 100. And then forming an auxiliary construction platform 2 within the boundary range defined by the fixing piles 1. And then constructing on the auxiliary construction platform 2, and inserting the fixed piles 3 into the boundary corresponding to the auxiliary construction platform 4, wherein the fixed piles 3 penetrate through the critical stable slope rock-soil mass 9 of the slope body 100 and are inserted into the stable slope rock-soil mass 10 of the slope body 100.
Therefore, when the auxiliary construction platforms 2 and 4 are built, the corresponding fixed piles 1 and 3 penetrate through the critical stable slope rock-soil mass 9 and are inserted into the stable slope rock-soil mass 10, so that the stability of the auxiliary construction platform 2 and the auxiliary construction platform 4 is guaranteed. And, by means of the fixing piles 1 and 3 of the auxiliary construction platforms at all levels, the critical stable slope rock-soil mass 9 can be better fixed on the stable slope rock-soil mass 10. Therefore, when the later-stage auxiliary construction platform is built or the construction platform is built, the scale of the later-stage auxiliary construction platform or the construction platform can be further enlarged, and the requirement of large-scale mechanized construction can be gradually met on the basis of ensuring safety and stability.
Optionally, the operation of building the construction platform 6 includes: inserting a plurality of fixed piles 5 into the slope body 100 according to the boundary corresponding to the construction platform 10, wherein the fixed piles 5 penetrate through the critical stable slope rock-soil mass 9 of the slope body 100 and are inserted into the stable slope rock-soil mass 10 of the slope body; and forming a construction platform 6 within the confines of the boundary.
Specifically, referring to fig. 2 and 3, in the method of the present embodiment, when the construction platform 6 is built, a plurality of fixing piles 5 may be inserted into the slope 100 according to the boundary corresponding to the construction platform 10. And wherein the spud pile 5 is inserted into the stable slope rock-soil mass 10 of the slope body through the critical stable slope rock-soil mass 9 of the slope body 100. Then, the construction platform 6 is formed within the boundary.
Therefore, the fixed pile 5 penetrates through the critical stable slope rock-soil mass 9 and is inserted into the stable slope rock-soil mass 10, and the stability of the construction platform 6 is guaranteed. And rely on the spud pile 5, can fix critical stable side slope rock-soil body 9 on stable side slope rock-soil body 10 better to guarantee the slope body is stable, finally satisfy the demand of large-scale mechanized construction.
In particular, as mentioned above, in the case of steep terrain, the operation of building at least one auxiliary construction platform comprises: a small construction platform 2 is built at the toe of the slope body 100, wherein the width of the small construction platform 2 is 2.5-3.5 m; and constructing on the small construction platform 2, and building a medium construction platform 4 on the slope body 100, wherein the width of the medium construction platform 4 is 4.5-5.5 m. And the operation of building the construction platform 6 includes: and constructing on the medium-sized construction platform 4, and building a large-sized construction platform 6 serving as a construction platform 6 on the slope body 100, wherein the width of the large-sized construction platform 6 is 10-15 m.
When the large construction platform 6 for construction is built on the slope body 100, the small construction platform 2 can be built on the slope toe manually and in a small mechanical mode (wherein the width of the small construction platform 2 can be 2.5-3.5 m, for example). And then, constructing a medium-sized construction platform 4 on the small-sized construction platform 2 by adopting mechanical construction (wherein the width of the medium-sized construction platform 4 can be 4.5-5.5 m, for example). And then, a large construction platform 6 for construction is constructed on the medium construction platform 4 through large mechanical operation (wherein the width of the large construction platform 6 can be 10-15 m, for example). Therefore, by the mode, the scales of all levels of construction platforms can be gradually enlarged from the toe of the slope body 100, and finally the large construction platform 6 suitable for construction requirements is built.
Alternatively, referring to fig. 2 and 3, the operation of building the small construction platform 2 on the toe of the slope body 100 includes: inserting a plurality of small-sized fixed piles 1 into the slope toe according to the boundary of the small-sized construction platform 2 corresponding to the small-sized construction platform 2, wherein the diameter of each small-sized fixed pile 1 is 60-80 cm, and the small-sized fixed piles penetrate through the critical stable slope rock-soil mass 9 of the slope body 100 and are inserted into the stable slope rock-soil mass 10 of the slope body 100; and forming the small construction platform 2 within the range of the boundary of the small construction platform 2.
Specifically, referring to fig. 3, according to the method of the present embodiment, for example, small steel pipe piles 1 (i.e., small fixed piles with a diameter of 60-80 cm) can be constructed in a "concave" arrangement at the toe of a slope by using manpower and small machinery, and a small construction platform with a width of 2.5-3.5 m can be constructed in a flat site. Preferably, the small construction platform has a width of 3 m. And, referring to fig. 2, the small steel pipe pile 1 is inserted into the stabilized slope rock-soil mass 10 of the slope body 100 through the critical stabilized slope rock-soil mass 9 of the slope body 100. Therefore, the small steel pipe pile 1 penetrates through the critical stable slope rock-soil mass 9 and is inserted into the stable slope rock-soil mass 10, and the stability of the small construction platform 2 is guaranteed. And rely on small-size steel-pipe pile 1, can fix critical stability side slope rock-soil body 9 on stability side slope rock-soil body 10 better to guarantee that the slope body is stable, finally satisfy the demand of large-scale mechanized construction.
Alternatively, referring to fig. 3, the operation of building the medium construction platform 4 on the slope body 100 includes: inserting a plurality of medium-sized fixed piles 3 into the slope body 100 according to the boundary of the medium-sized construction platform 4 corresponding to the medium-sized construction platform 4, wherein the diameter of each medium-sized fixed pile 3 is 100-120 cm, and the critical stable slope rock-soil mass 9 penetrating through the slope body 100 is inserted into the stable slope rock-soil mass 10 of the slope body 100; and forming the middle-sized construction platform 4 within the range of the boundary of the middle-sized construction platform 4.
Specifically, referring to fig. 3, according to the method of this embodiment, after the structure of the small construction platform 1 is stabilized, for example, a small concrete pile 3 (i.e., a medium-sized fixed pile with a diameter of 100-120 cm) may be constructed on the small construction platform in a "concave" manner by using a machine, and a medium-sized construction platform with a construction width of 4.5-5.5 m may be set up on a leveling field. Preferably, the small construction platform has a width of 3 m. And, referring to fig. 2, the small concrete pile 3 is inserted into the stabilized slope rock soil mass 10 of the slope body 100 through the critical stabilized slope rock soil mass 9 of the slope body 100. Therefore, the small concrete pile 3 penetrates through the critical stable slope rock-soil body 9 and is inserted into the stable slope rock-soil body 10, and the stability of the medium-sized construction platform 4 is guaranteed. And rely on small-size concrete pile 3, can fix critical stable side slope rock-soil mass 9 on stable side slope rock-soil mass 10 better to guarantee the slope body stable, finally satisfy the demand of large-scale mechanized construction.
Optionally, referring to fig. 2 and 3, the operation of building the construction platform 6 includes: inserting a plurality of large-scale fixed piles 5 into the slope body 100 according to the large-scale construction platform boundary corresponding to the large-scale construction platform 6 serving as the construction platform 6, wherein the diameter of each large-scale fixed pile 5 is 180-250 cm, and the critical stable slope rock-soil mass 9 penetrating through the slope body 100 is inserted into the stable slope rock-soil mass 10 of the slope body 100; and forming the large construction platform 6 within the range of the boundary of the large construction platform 6.
Specifically, referring to fig. 3, after the medium-sized construction platform 4 is structurally stable, a large-sized machine may be used to construct a large-sized pier pile or an anti-slide pile 5 (i.e., a large-sized fixed pile, with a diameter of 180-250 cm) in a "concave" manner on the medium-sized construction platform, and a large-sized construction platform 6 (i.e., a construction platform) with a width of 10-15 m is formed in a flat site. And, referring to fig. 2, the large pier pile or the anti-slide pile 5 is inserted into the stabilized slope rock soil mass 10 of the slope body 100 through the critical stabilized slope rock soil mass 9 of the slope body 100. Therefore, the large pier piles or the anti-slide piles 5 penetrate through the critical stable slope rock-soil mass 9 and are inserted into the stable slope rock-soil mass 10, and the stability of the large construction platform 6 is guaranteed. And rely on large-scale pier stud or friction pile 5, can fix critical stable slope rock-soil body 9 on stable slope rock-soil body 10 better to guarantee that the slope body is stable, finally satisfy the demand of large-scale mechanized construction.
And, optionally, the method further comprises providing access roads on the at least one auxiliary construction platform 2 and 4 and the construction platform 6. So that materials and large construction machinery can be transported to the construction platform 6 through the sidewalk.
Further, according to another aspect of the present embodiment, there is provided a method of performing construction work on a slope body 100, comprising:
s202: according to any one of the methods, a construction platform 6 for construction engineering is built; and
s204: and (5) carrying out construction engineering on the construction engineering platform 6.
Specifically, referring to fig. 2 and 4, the present embodiment also provides a method for performing construction work on a slope body 100. According to this method, first, according to the above-described contents of the present embodiment, the construction platform 6 suitable for construction work is constructed. And then carrying out construction engineering on the construction engineering platform 6.
Optionally, the performing of the construction work on the construction work platform 6 includes performing tunnel boring construction on the construction work platform 6. Specifically, referring to fig. 2, after the large construction platform 6 is stabilized, a tunnel portal excavation protection 7 may be built on the large construction platform 6, and then a tunnel 8 may be excavated.
Optionally, the performing of the construction work on the construction work platform 6 includes performing the bridge construction on the construction work platform 6. Specifically, referring to fig. 4, after the large construction platform 6 is constructed stably, the bridge pile foundation 11 and the bearing platform 12 may be constructed on the large construction platform 6, and after the large construction platform is stabilized, the bridge 13 may be constructed.
And further optionally, the method further comprises performing slope protection construction on the slope body 100 while performing the construction work.
In addition, according to another aspect of the present embodiment, a multi-stage construction platform built on the slope body 100 is provided. Referring to fig. 2 and 3, the multistage construction platform includes: at least one level of auxiliary construction platform 2 and 4; and a construction platform 6 for performing construction works on the slope body 100, wherein at least one stage of auxiliary construction platforms 2 and 4 are built along the slope body 100 from the toe of the slope body 100 in the order from bottom to top; and the construction platform 6 is built on the last-stage auxiliary construction platform 4.
In addition, for more contents of the multi-stage construction platform, refer to the foregoing description of the present embodiment, and no further description is provided herein.
Thereby through the technical scheme of this embodiment, the above-mentioned technical problem who exists among the prior art has been solved to this embodiment is applicable to the construction of steep slope topography under the multistage auxiliary construction platform, has following advantage:
1. aiming at the construction and excavation work on steep terrain, a safe and stable construction platform can be provided, and the operation of construction equipment and the material transfer are convenient;
2. the fragile side slope can be permanently reinforced, and the side slope geological disaster can be prevented;
3. the method can be suitable for the construction of railway, highway, water conservancy, bridge and other projects in steep terrain, and has wide application range; and
4. the method has better anti-interference capability on complex geological conditions, climate and the like in steep terrain, can effectively reduce the construction period, reduces the influence on ecological environment and improves the construction safety.
The relative arrangement of the components and steps, the numerical expressions, and numerical values set forth in these embodiments do not limit the scope of the present disclosure unless specifically stated otherwise. Meanwhile, it should be understood that the sizes of the respective portions shown in the drawings are not drawn in an actual proportional relationship for the convenience of description. Techniques, methods, and apparatus known to those of ordinary skill in the relevant art may not be discussed in detail but are intended to be part of the specification where appropriate. In all examples shown and discussed herein, any particular value should be construed as merely illustrative, and not limiting. Thus, other examples of the exemplary embodiments may have different values. It should be noted that: like reference numbers and letters refer to like items in the following figures, and thus, once an item is defined in one figure, further discussion thereof is not required in subsequent figures.
Spatially relative terms, such as "above … …," "above … …," "above … …," "above," and the like, may be used herein for ease of description to describe one device or feature's spatial relationship to another device or feature as illustrated in the figures. It will be understood that the spatially relative terms are intended to encompass different orientations of the device in use or operation in addition to the orientation depicted in the figures. For example, if a device in the figures is turned over, devices described as "above" or "on" other devices or configurations would then be oriented "below" or "under" the other devices or configurations. Thus, the exemplary term "above … …" can include both an orientation of "above … …" and "below … …". The device may be otherwise variously oriented (rotated 90 degrees or at other orientations) and the spatially relative descriptors used herein interpreted accordingly.
In the description of the present disclosure, it is to be understood that the orientation or positional relationship indicated by the directional terms such as "front, rear, upper, lower, left, right", "lateral, vertical, horizontal" and "top, bottom", etc., are generally based on the orientation or positional relationship shown in the drawings, and are presented only for the convenience of describing and simplifying the disclosure, and in the absence of a contrary indication, these directional terms are not intended to indicate and imply that the device or element being referred to must have a particular orientation or be constructed and operated in a particular orientation, and therefore, should not be taken as limiting the scope of the disclosure; the terms "inner and outer" refer to the inner and outer relative to the profile of the respective component itself.
The above description is only for the preferred embodiment of the present application, but the scope of the present application is not limited thereto, and any changes or substitutions that can be easily conceived by those skilled in the art within the technical scope of the present application should be covered within the scope of the present application. Therefore, the protection scope of the present application shall be subject to the protection scope of the claims.

Claims (10)

1. A method of constructing a construction platform (6) on a slope body (100), the construction platform (6) being for performing construction work on the slope body (100), characterized in that the method comprises:
at least one stage of auxiliary construction platform (2, 4) is built along the slope body (100) from bottom to top from the toe of the slope body (100), wherein the last stage of auxiliary construction platform (4) in the auxiliary construction platforms (2, 4) is used for building the construction platform (6); and
and building the construction platform (6) on the last-stage auxiliary construction platform (4).
2. Method according to claim 1, characterized in that the operation of building up said at least one auxiliary construction platform (2, 4) comprises: and (2) building a next-stage auxiliary construction platform (4) on the previous-stage auxiliary construction platform (2), wherein the scale of the next-stage auxiliary construction platform (4) is larger than that of the previous-stage auxiliary construction platform (2).
3. The method according to claim 1, characterized in that the operation of building up the at least one level of auxiliary construction platform comprises building up each level of auxiliary construction platform (2, 4) of the at least one level of auxiliary construction platform by:
inserting a plurality of fixed piles (1, 3) on the slope body (100) according to the boundary corresponding to the auxiliary construction platforms (2, 4), wherein the fixed piles (1, 3) penetrate through the critical stable slope rock-soil body (9) of the slope body (100) and are inserted into the stable slope rock-soil body (10) of the slope body (100); and
auxiliary construction platforms (2, 4) are formed within the boundaries.
4. The method according to claim 1, wherein the operation of building the construction platform (6) comprises:
inserting a plurality of fixed piles (5) into the slope body (100) according to the boundary corresponding to the construction platform (10), wherein the fixed piles (5) penetrate through the critical stable slope rock-soil mass (9) of the slope body (100) and are inserted into the stable slope rock-soil mass (10) of the slope body (100); and
forming the construction platform (6) within the boundaries.
5. The method according to claim 1, characterized in that the operation of building up said at least one auxiliary construction platform comprises:
a small construction platform (2) is built on a slope toe of the slope body (100), wherein the width of the small construction platform (2) is 2.5-3.5 m; and
constructing on the small construction platform (2), and constructing a medium construction platform (4) on the slope body (100), wherein the width of the medium construction platform (4) is 4.5-5.5 m, and wherein
-operation of building said construction platform (6), comprising: and constructing the medium-sized construction platform (4), and constructing a large-sized construction platform (6) serving as the construction platform (6) on the slope body (100), wherein the width of the large-sized construction platform (6) is 10-15 m.
6. The method according to claim 5, characterized in that the operation of building a small construction platform (2) at the toe of the slope body (100) comprises:
inserting a plurality of small-sized fixed piles (1) into the slope toe according to the boundary of a small-sized construction platform corresponding to the small-sized construction platform (2), wherein the diameter of each small-sized fixed pile (1) is 60-80 cm, and critical stable slope rock-soil mass (9) penetrating through the slope body (100) is inserted into the stable slope rock-soil mass (10) of the slope body (100); and
forming the small construction platform (2) within the range of the small construction platform boundary.
7. The method of claim 5,
the operation of building a medium construction platform (4) on the slope body (100) comprises: inserting a plurality of medium-sized fixed piles (3) into the slope body (100) according to the medium-sized construction platform boundary corresponding to the medium-sized construction platform (4), wherein the diameter of each medium-sized fixed pile (3) is 100-120 cm, and critical stable slope rock-soil mass (9) penetrating through the slope body (100) is inserted into the stable slope rock-soil mass (10) of the slope body (100); and forming the medium construction platform (4) within the boundaries of the medium construction platform, and/or
-operation of building said large construction platform (6), comprising: inserting a plurality of large fixing piles (5) into the slope body (100) according to the boundary of the large construction platform corresponding to the large construction platform (6), wherein the diameter of each large fixing pile (5) is 180-250 cm, and the critical stable slope rock-soil mass (9) penetrating through the slope body (100) is inserted into the stable slope rock-soil mass (10) of the slope body (100); and forming the large construction platform (6) within the boundaries of the large construction platform.
8. A method of performing a construction project on a slope (100), comprising:
method according to any one of claims 1 to 8, building a construction platform (6) for constructing the construction project; and
and carrying out the construction project on the construction platform (6).
9. The method according to claim 8, characterized in that the operations of the construction project are carried out on the construction platform (6) comprising:
and performing tunnel boring construction or bridge construction on the construction platform (6).
10. A multi-stage construction platform built on a slope body (100) is characterized by comprising at least one stage of auxiliary construction platform (2, 4); and a construction platform (6) for carrying out construction works on the slope body (100), wherein
The at least one stage of auxiliary construction platform (2, 4) is built along the slope body (100) from the bottom to top from the slope toe of the slope body (100); and
the construction platform (6) is built on the last-stage auxiliary construction platform (4).
CN202011633616.4A 2020-12-31 2020-12-31 Multistage construction platform for critical stable slope and construction method thereof Pending CN112854251A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202011633616.4A CN112854251A (en) 2020-12-31 2020-12-31 Multistage construction platform for critical stable slope and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202011633616.4A CN112854251A (en) 2020-12-31 2020-12-31 Multistage construction platform for critical stable slope and construction method thereof

Publications (1)

Publication Number Publication Date
CN112854251A true CN112854251A (en) 2021-05-28

Family

ID=76000040

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202011633616.4A Pending CN112854251A (en) 2020-12-31 2020-12-31 Multistage construction platform for critical stable slope and construction method thereof

Country Status (1)

Country Link
CN (1) CN112854251A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114991194A (en) * 2022-06-16 2022-09-02 上海建工四建集团有限公司 Pile foundation construction method for multistage slope cutting

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000104257A (en) * 1998-09-28 2000-04-11 Taisei Corp Installation method for hoisting equipment in constructing structure on slope
CN103437370A (en) * 2013-07-31 2013-12-11 广州市设计院 Method and supporting structure for slip resisting and soil retaining of abrupt slope
CN106149625A (en) * 2016-08-23 2016-11-23 上海市水利工程设计研究院有限公司 A kind of ecological self-purification type landscape revetment reconstruction structure and construction method thereof
CN107142949A (en) * 2017-06-07 2017-09-08 深圳市工勘岩土集团有限公司 The foundation pit supporting construction of soft layer
CN207760804U (en) * 2017-12-11 2018-08-24 上海市水利工程设计研究院有限公司 A kind of Multi-functional economy dike structure
CN110832964A (en) * 2019-09-20 2020-02-25 日昌升建筑新材料设计研究院有限公司 Building aggregate mine in-situ soil improvement and greening method
CN111271074A (en) * 2020-04-06 2020-06-12 中交路桥建设有限公司 Tunnel slag tapping transfer station positioned on steep slope and transfer method

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000104257A (en) * 1998-09-28 2000-04-11 Taisei Corp Installation method for hoisting equipment in constructing structure on slope
CN103437370A (en) * 2013-07-31 2013-12-11 广州市设计院 Method and supporting structure for slip resisting and soil retaining of abrupt slope
CN106149625A (en) * 2016-08-23 2016-11-23 上海市水利工程设计研究院有限公司 A kind of ecological self-purification type landscape revetment reconstruction structure and construction method thereof
CN107142949A (en) * 2017-06-07 2017-09-08 深圳市工勘岩土集团有限公司 The foundation pit supporting construction of soft layer
CN207760804U (en) * 2017-12-11 2018-08-24 上海市水利工程设计研究院有限公司 A kind of Multi-functional economy dike structure
CN110832964A (en) * 2019-09-20 2020-02-25 日昌升建筑新材料设计研究院有限公司 Building aggregate mine in-situ soil improvement and greening method
CN111271074A (en) * 2020-04-06 2020-06-12 中交路桥建设有限公司 Tunnel slag tapping transfer station positioned on steep slope and transfer method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114991194A (en) * 2022-06-16 2022-09-02 上海建工四建集团有限公司 Pile foundation construction method for multistage slope cutting

Similar Documents

Publication Publication Date Title
CN100564700C (en) The job practices of lattice type steel column tower crane pedestal
CN106640091B (en) A kind of shallow tunnel section construction method
CN102704957A (en) Shed-frame method for shallowly burying large-sized underground structure construction
CN110017144A (en) A kind of three step construction method of loess tunnel considering bottom stab ilization processing
CN111851509A (en) Temporary channel construction method based on deep foundation pit inner support structure
CN209836779U (en) Light bridge abutment of reinforced concrete
CN102505704A (en) Large open caisson construction method in soft geological shaft
CN111851597B (en) Penetration protection structure of pipe jacking close-distance downward-penetrating pipe gallery and construction method
CN108867723A (en) The method of frame structure building rectification and underground increasing layer
CN112854251A (en) Multistage construction platform for critical stable slope and construction method thereof
CN209836778U (en) Light bridge abutment
CN111894023A (en) Construction method of steep-slope bridge foundation
CN105887913A (en) Design method for steel structure platform and trestle structure for shallow water area pole and tower foundation construction
CN106884431A (en) One kind building pit foundation construction safety supporting construction
CN213038380U (en) Earthwork temporary passage system based on foundation pit inner supporting structure
CN210002410U (en) ring frame support enclosure system capable of being used as retaining wall
CN105986578A (en) Ejecting pipe construction method of roadside tubular underground garage
CN209941689U (en) Reinforcing device
CN107023021A (en) A kind of design and construction method of flexible compound Diaphragm Wall Support Structure
CN104005414A (en) Method for constructing large-diameter reinforced concrete cast-in-place pile supporting stand column
CN111576479A (en) Retaining structure of filling slope and construction method
CN214695666U (en) Cantilever antiskid anchoring system for large landslide
CN105239573A (en) Rock anchoring construction method for implanted pipe of structural steel trestle
CN212175363U (en) Frame-type anti-skidding structure with road system
CN214883731U (en) Light gallery structure for protecting rock-soil mixed slope road

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20210528

RJ01 Rejection of invention patent application after publication