CN112529337A - Reserve library optimization method and system based on power material demand management - Google Patents
Reserve library optimization method and system based on power material demand management Download PDFInfo
- Publication number
- CN112529337A CN112529337A CN202011582523.3A CN202011582523A CN112529337A CN 112529337 A CN112529337 A CN 112529337A CN 202011582523 A CN202011582523 A CN 202011582523A CN 112529337 A CN112529337 A CN 112529337A
- Authority
- CN
- China
- Prior art keywords
- material demand
- plan
- demand plan
- reserve
- library
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 239000000463 material Substances 0.000 title claims abstract description 203
- 238000000034 method Methods 0.000 title claims abstract description 24
- 238000005457 optimization Methods 0.000 title claims abstract description 21
- 238000007726 management method Methods 0.000 claims abstract description 30
- 238000012545 processing Methods 0.000 claims abstract description 8
- 238000012790 confirmation Methods 0.000 claims abstract description 7
- 238000006243 chemical reaction Methods 0.000 claims description 6
- 230000008676 import Effects 0.000 claims description 6
- 238000010276 construction Methods 0.000 description 4
- 238000012552 review Methods 0.000 description 3
- 230000008901 benefit Effects 0.000 description 2
- 230000007547 defect Effects 0.000 description 2
- 230000007246 mechanism Effects 0.000 description 2
- 238000009430 construction management Methods 0.000 description 1
- 238000013461 design Methods 0.000 description 1
- 238000011161 development Methods 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 230000006872 improvement Effects 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 230000003287 optical effect Effects 0.000 description 1
- 239000002994 raw material Substances 0.000 description 1
Images
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/04—Forecasting or optimisation specially adapted for administrative or management purposes, e.g. linear programming or "cutting stock problem"
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/06—Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
- G06Q10/063—Operations research, analysis or management
- G06Q10/0631—Resource planning, allocation, distributing or scheduling for enterprises or organisations
- G06Q10/06315—Needs-based resource requirements planning or analysis
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/10—Office automation; Time management
- G06Q10/103—Workflow collaboration or project management
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Systems or methods specially adapted for specific business sectors, e.g. utilities or tourism
- G06Q50/06—Electricity, gas or water supply
Abstract
The invention discloses a reserve bank optimization method and system based on power material demand management, which comprises the following steps: transmitting the project processing parameters to a material demand prediction model, and outputting a material advance storage demand plan; inputting the material advance storage demand plan and the material demand storage plan stored in the project storage library into a material demand plan storage library; converting the confirmed material demand plan in the material demand plan reserve library into a formal material demand plan of the ERP system, and realizing the linkage of the material demand plan reserve library and the material demand plan compilation of the ERP system; the stock optimization method links the material demand planning stock and the material demand planning of the ERP system, realizes the centralized confirmation of the material demands in the material demand planning stock, improves the effective updating of the material demands and is convenient for the arrangement of subsequent purchasing work.
Description
Technical Field
The invention relates to the technical field of county material demand management, in particular to a method and a system for optimizing a reserve bank based on power material demand management.
Background
In order to improve management benefits and efficiency, the innovation of 'putting management service' is comprehensively promoted in the field of materials, and the optimization construction of a modern intelligent supply chain is promoted based on the improvement. In the field of materials, the planning and management of the demand of electric power materials always occupies an important position and is closely related to future development and construction and daily operation. However, the demand planning of the power material supply is strong, the total amount is large, the raw material resources are short, and the uncertainty of emergency demand exists, so that the demand planning management has extremely high requirements. Meanwhile, in the service layer: the material demand plan storage management is not available before the procurement batch plan is submitted, the material specialty cannot grasp the material demand in advance, the procurement plan compilation work is repeated frequently, and the examination efficiency and the subsequent procurement work arrangement are also influenced by scattered examination; at a system level: the reserve library is planned according to the material demand, and the full-information coverage is not realized.
Disclosure of Invention
Based on the technical problems in the background art, the invention provides a reserve bank optimization method and system based on power material demand management, which are used for compiling and linking a material demand plan reserve bank and a material demand plan of an ERP system, so that the material demand in the material demand plan reserve bank is centrally confirmed, the effective updating of the material demand is improved, and the subsequent purchasing work arrangement is facilitated.
The invention provides a reserve bank optimization method based on power material demand management, which comprises the following steps:
transmitting the project processing parameters to a material demand prediction model, and outputting a material advance storage demand plan;
inputting the material advance storage demand plan and the material demand storage plan stored in the project storage library into a material demand plan storage library;
and converting the confirmed material demand plan in the material demand plan reserve library into a formal material demand plan of the ERP system, so as to realize the linkage of the material demand plan reserve library and the material demand plan compilation of the ERP system.
Further, a material demand planning reserve library is constructed, and the method comprises the following steps: for the project which is already clear, the annual material advance storage demand plan is converted into a material demand plan and is brought into a material demand plan storage library, and the purchasing demand which is already clear but does not reach the batch submission time point is updated and maintained in the storage library in advance.
Further, the step of converting the confirmed material demand plan in the material demand plan reserve library into a formal material demand plan of the ERP system includes:
according to the project information and the batch requirements, the material demands in the material demand plan reserve library are selected, converted into the formal material demand plan of the ERP system, and the material demand plan reserve library is linked with the material demand plan compilation of the ERP system, so that the material demands in the material demand plan reserve library are confirmed in a centralized mode.
A reserve bank optimization system based on power material demand management comprises a material advance reserve demand plan output module, a material import module and a material confirmation conversion module;
the material advance reserve demand plan output module is used for transmitting project processing parameters to the material demand prediction model and outputting a material advance reserve demand plan;
the material import module is used for inputting the material advance storage demand plan and the material demand storage plan stored in the project storage library into the material demand plan storage library;
the material confirmation and conversion module is used for converting the confirmed material demand plan in the material demand plan reserve library into a formal material demand plan of the ERP system, and the material demand plan reserve library is linked with the material demand plan compilation of the ERP system.
A computer readable storage medium having stored thereon a number of get taxonomy procedures for being invoked by a processor and performing the method of repository optimization of claim 1.
The reserve bank optimization method and the reserve bank optimization system based on the power material demand management have the advantages that: the reserve bank optimization method and system based on power material demand management, which are provided by the structure, establish a demand plan reserve bank management mechanism, provide an information channel for material plan managers to pre-estimate material demand scale in advance, realize staged centralized review, and directly convert the demand detail selection into a formal material demand plan of an ERP system to realize the optimization of a reserve bank; the method overcomes the defect that no material demand plan stock management is required before the plan submission of the procurement batch in the conventional ERP system.
Drawings
FIG. 1 is a schematic structural view of the present invention;
Detailed Description
The present invention is described in detail below with reference to specific embodiments, and in the following description, numerous specific details are set forth in order to provide a thorough understanding of the present invention. This invention may, however, be embodied in many different forms and should not be construed as limited to the embodiments set forth herein, but rather should be construed as broadly as the present invention is capable of modification in various respects, all without departing from the spirit and scope of the present invention.
The method for optimizing the reserve library in the embodiment depends on an ERP system and an auxiliary decision system, is associated with a foreground service scene for constructing material demands and intelligently predicting annual demands in the system, and is used for structuring forecast information of the material demands, including demanded materials, material types, demanded dates, demanded quantities, amounts, units, projects and the like, and forecast external material demands, including data of the demanded materials, the material types, the demanded dates, the demanded quantities, the amounts, the units, the projects and the like. Meanwhile, data standardization processing is carried out on material demand prediction information, prediction external material demands and material demand plans including required materials, material types, required dates, required quantity, money, units, projects and the like. The data source system comprises a capital construction management and control system and an ERP system, service implementation is based on the ERP system, deployment is carried out in a two-level deployment mode, and a decision-making assisting system needs to be provided with a data interface.
As shown in fig. 1, the method for optimizing a reserve bank based on demand management of electric power supplies according to the present invention includes:
s1: transmitting the project processing parameters to a material demand prediction model, and outputting a material advance storage demand plan;
the project progress parameters comprise a project reserve plan, a project investment plan, a project milestone plan, historical material requirements and a project progress; and the material demand prediction model compares and screens the parameters of the project to obtain a material advance storage demand plan of the current project.
S2: inputting the material advance storage demand plan and the material demand storage plan stored in the project storage library into a material demand plan storage library;
wherein, the construction of the material demand plan reserve library comprises the steps of; for the project which is already clear, the annual material advance storage demand plan is converted into a material demand plan and is brought into a material demand plan storage library, and the purchasing demand which is already clear but does not reach the batch submission time point is updated and maintained in the storage library in advance.
Therefore, the material demand reserve plan for the project is reserved in the material demand plan reserve library after the construction is completed, the material demand reserve plan can be understood as an accurate prediction plan before the project is started, and the accurate prediction plan is stored in the material demand plan reserve library.
The material demand plan reserve library is mainly implemented through an ERP system. In specific implementation, an ECP2.0 and ERP typical design are combined, a material demand plan reserve library management module is constructed in an ERP system, and the annual material advance reserve demand plan in the decision-making system is assisted to be converted into information of a material demand plan reserve library in the ERP through an interface.
S3: and converting the confirmed material demand plan in the material demand plan reserve library into a formal material demand plan of the ERP system, so as to realize the linkage of the material demand plan reserve library and the material demand plan compilation of the ERP system.
According to the project information and the batch requirements, the material demands in the material demand plan reserve library are selected, converted into the formal material demand plan of the ERP system, and linked with the material demand plan schedule compilation of the ERP system, so that the demand plan reporting work is simplified, the material demands in the material demand plan reserve library are confirmed in a centralized manner, and the material demand review efficiency is improved.
Through steps S10 to S30, an entrance for inputting a material demand and reserve plan in advance is provided by establishing a demand plan and reserve management mechanism and system functions, meanwhile, an annual material advance reserve demand plan with definite projects is directly converted into a material demand plan and is brought into a material demand plan reserve library, an information channel is provided for material plan managers to estimate the material demand scale in advance, and staged centralized review is realized; a purchasing planning and arranging mode is innovated, the quality and the effect of material planning reporting and reviewing management are improved, the active service capability of a material management department is enhanced, and the defect that no material demand planning stock library management is needed before purchasing batch planning reporting in the conventional ERP system is overcome. Meanwhile, the material demand plan reserve library mainly provides support for a material demand department and a plan management department to carry out demand plan management work, after the material demand plan reserve library is established, the material demand department can update and maintain a material demand reserve plan stored in a project reserve library, the plan management department can carry out centralized examination in the material demand plan reserve library, and the requirement detail is selected and directly converted into a formal material demand plan of an ERP system, so that optimization of the reserve library is realized.
A reserve bank optimization system based on power material demand management comprises a material advance reserve demand plan output module, a material import module and a material confirmation conversion module;
the material advance reserve demand plan output module is used for transmitting project processing parameters to the material demand prediction model and outputting a material advance reserve demand plan;
the material import module is used for inputting the material advance storage demand plan and the material demand storage plan stored in the project storage library into the material demand plan storage library;
the material confirmation and conversion module is used for converting the confirmed material demand plan in the material demand plan reserve library into a formal material demand plan of the ERP system, and the material demand plan reserve library is linked with the material demand plan compilation of the ERP system.
A computer readable storage medium having stored thereon a number of get taxonomy procedures for being invoked by a processor and performing the method of vault optimization described above.
Those of ordinary skill in the art will understand that: all or part of the steps for implementing the method embodiments may be implemented by hardware related to program instructions, and the program may be stored in a computer readable storage medium, and when executed, the program performs the steps including the method embodiments; and the aforementioned storage medium includes: various media that can store program codes, such as ROM, RAM, magnetic or optical disks.
The above description is only for the preferred embodiment of the present invention, but the scope of the present invention is not limited thereto, and any person skilled in the art should be considered to be within the technical scope of the present invention, and the technical solutions and the inventive concepts thereof according to the present invention should be equivalent or changed within the scope of the present invention.
Claims (5)
1. A reserve bank optimization method based on power material demand management is characterized by comprising the following steps:
transmitting the project processing parameters to a material demand prediction model, and outputting a material advance storage demand plan;
inputting the material advance storage demand plan and the material demand storage plan stored in the project storage library into a material demand plan storage library;
and converting the confirmed material demand plan in the material demand plan reserve library into a formal material demand plan of the ERP system, so as to realize the linkage of the material demand plan reserve library and the material demand plan compilation of the ERP system.
2. The reserve bank optimization method based on power material demand management according to claim 1, wherein constructing a material demand planning reserve bank comprises: for the project which is already clear, the annual material advance storage demand plan is converted into a material demand plan and is brought into a material demand plan storage library, and the purchasing demand which is already clear but does not reach the batch submission time point is updated and maintained in the storage library in advance.
3. The reserve bank optimization method based on power material demand management according to claim 1, wherein the step of converting the material demand plan in the confirmed material demand plan reserve bank into a formal material demand plan of the ERP system comprises:
according to the project information and the batch requirements, the material demands in the material demand plan reserve library are selected, converted into the formal material demand plan of the ERP system, and the material demand plan reserve library is linked with the material demand plan compilation of the ERP system, so that the material demands in the material demand plan reserve library are confirmed in a centralized mode.
4. A reserve bank optimization system based on power material demand management is characterized by comprising a material advance reserve demand plan output module, a material import module and a material confirmation conversion module;
the material advance reserve demand plan output module is used for transmitting project processing parameters to the material demand prediction model and outputting a material advance reserve demand plan;
the material import module is used for inputting the material advance storage demand plan and the material demand storage plan stored in the project storage library into the material demand plan storage library;
the material confirmation and conversion module is used for converting the confirmed material demand plan in the material demand plan reserve library into a formal material demand plan of the ERP system, and the material demand plan reserve library is linked with the material demand plan compilation of the ERP system.
5. A computer readable storage medium having stored thereon a plurality of get taxonomy procedures for being invoked by a processor and performing the method of repository optimization according to claim 1.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202011582523.3A CN112529337A (en) | 2020-12-28 | 2020-12-28 | Reserve library optimization method and system based on power material demand management |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202011582523.3A CN112529337A (en) | 2020-12-28 | 2020-12-28 | Reserve library optimization method and system based on power material demand management |
Publications (1)
Publication Number | Publication Date |
---|---|
CN112529337A true CN112529337A (en) | 2021-03-19 |
Family
ID=74976865
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202011582523.3A Pending CN112529337A (en) | 2020-12-28 | 2020-12-28 | Reserve library optimization method and system based on power material demand management |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN112529337A (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113408830A (en) * | 2021-08-19 | 2021-09-17 | 国网浙江省电力有限公司金华供电公司 | Precise multidimensional material linkage utilization method and device based on ZigBee |
CN113592351A (en) * | 2021-08-12 | 2021-11-02 | 山西益通电网保护自动化有限责任公司 | Material demand plan implementation method and device |
CN114529118A (en) * | 2021-07-28 | 2022-05-24 | 广东电网有限责任公司佛山供电局 | Material management monitoring method and system |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105447624A (en) * | 2015-11-12 | 2016-03-30 | 云南电网有限责任公司物流服务中心 | Typical configuration model and system for auditing material requirement plan of power project |
CN108133307A (en) * | 2017-12-01 | 2018-06-08 | 国家电网公司 | Goods and materials plan review method, system and terminal device |
CN110942204A (en) * | 2019-12-04 | 2020-03-31 | 国网安徽省电力有限公司合肥供电公司 | New power grid capital construction project annual planning model construction method and system |
CN111553643A (en) * | 2020-05-18 | 2020-08-18 | 国网河北省电力有限公司物资分公司 | Material purchasing plan and supply chain management system |
-
2020
- 2020-12-28 CN CN202011582523.3A patent/CN112529337A/en active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105447624A (en) * | 2015-11-12 | 2016-03-30 | 云南电网有限责任公司物流服务中心 | Typical configuration model and system for auditing material requirement plan of power project |
CN108133307A (en) * | 2017-12-01 | 2018-06-08 | 国家电网公司 | Goods and materials plan review method, system and terminal device |
CN110942204A (en) * | 2019-12-04 | 2020-03-31 | 国网安徽省电力有限公司合肥供电公司 | New power grid capital construction project annual planning model construction method and system |
CN111553643A (en) * | 2020-05-18 | 2020-08-18 | 国网河北省电力有限公司物资分公司 | Material purchasing plan and supply chain management system |
Non-Patent Citations (2)
Title |
---|
夏子朋: "供电企业物资管理提质增效的实践与思考", 《中国电业》, no. 10, 10 October 2020 (2020-10-10), pages 84 - 85 * |
宋孜等: "智慧申报 需求计划更智能", 《华北电业》, no. 08, 25 August 2020 (2020-08-25), pages 28 - 29 * |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114529118A (en) * | 2021-07-28 | 2022-05-24 | 广东电网有限责任公司佛山供电局 | Material management monitoring method and system |
CN113592351A (en) * | 2021-08-12 | 2021-11-02 | 山西益通电网保护自动化有限责任公司 | Material demand plan implementation method and device |
CN113408830A (en) * | 2021-08-19 | 2021-09-17 | 国网浙江省电力有限公司金华供电公司 | Precise multidimensional material linkage utilization method and device based on ZigBee |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN112529337A (en) | Reserve library optimization method and system based on power material demand management | |
Donti et al. | Task-based end-to-end model learning in stochastic optimization | |
US20220027817A1 (en) | Deep reinforcement learning for production scheduling | |
US20180018614A1 (en) | Method and apparatus for optimizing constraint-based data | |
JP3332032B2 (en) | Generator operation planning device, generator operation planning method, and storage medium storing generator operation planning program | |
Chaleshtarti et al. | A hybrid genetic and Lagrangian relaxation algorithm for resource-constrained project scheduling under nonrenewable resources | |
Wang et al. | Synchronizing production scheduling with resources allocation for precast components in a multi-agent system environment | |
Rostami et al. | Resource pool location for periodic services in decentralized multi-project scheduling problems | |
Ekel et al. | Decision making in a fuzzy environment and its application to multicriteria power engineering problems | |
CN106325232A (en) | Mold manufacture automatic production control system and method | |
Trentesaux et al. | Product-driven control: concept, literature review and future trends | |
JP6917288B2 (en) | Maintenance plan generation system | |
Maalouf et al. | Production management for mass customization and smart cellular manufacturing system: NSGAII and SMPSO for factory-level planning | |
Ullah et al. | Towards comprehensive release planning for software product lines | |
Owusu et al. | On optimising resource planning in BT plc with FOS | |
Khokhlovsky et al. | MODERNISATION OF A CONTROL CABINET PRODUCTION PROCESS USING MULTICRITERIA OPTIMIZATION LOGIC AND AUGMENTED REALITY. | |
Di Nucci et al. | Making nuclear waste problems governable: Conflicts, participation and acceptability | |
Joe et al. | Developing a strategy for full nuclear plant modernization | |
Ridgway | Analysis of decision centres and information flow in project management | |
KR102242446B1 (en) | A power management device and a power system capable of automatic modification of constraint code during operation of the power system | |
Bo et al. | Modeling and Optimizing Pumped Storage in a Multi-stage Large Scale Electricity Market under Portfolio Evolution | |
Wei et al. | Intelligent manufacturing: bridging the gap between the Internet of Things and machinery to achieve optimized operations | |
US11315201B2 (en) | Intelligent bill of materials advisor | |
Rzevski et al. | Customization of Multi-Agent Systems for Adaptive Resource Management with the Use of Domain Ontologies | |
Elfaham et al. | Recipe Based Skill Matching |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20210319 |
|
RJ01 | Rejection of invention patent application after publication |