CN112070941A - Wisdom building site is environment supervisory systems for construction - Google Patents

Wisdom building site is environment supervisory systems for construction Download PDF

Info

Publication number
CN112070941A
CN112070941A CN202010693896.1A CN202010693896A CN112070941A CN 112070941 A CN112070941 A CN 112070941A CN 202010693896 A CN202010693896 A CN 202010693896A CN 112070941 A CN112070941 A CN 112070941A
Authority
CN
China
Prior art keywords
sensor
construction
module
personnel
construction site
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010693896.1A
Other languages
Chinese (zh)
Inventor
沈忠平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Youjian Construction Technology Co ltd
Original Assignee
Shanghai Youjian Construction Technology Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Youjian Construction Technology Co ltd filed Critical Shanghai Youjian Construction Technology Co ltd
Priority to CN202010693896.1A priority Critical patent/CN112070941A/en
Publication of CN112070941A publication Critical patent/CN112070941A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • GPHYSICS
    • G07CHECKING-DEVICES
    • G07CTIME OR ATTENDANCE REGISTERS; REGISTERING OR INDICATING THE WORKING OF MACHINES; GENERATING RANDOM NUMBERS; VOTING OR LOTTERY APPARATUS; ARRANGEMENTS, SYSTEMS OR APPARATUS FOR CHECKING NOT PROVIDED FOR ELSEWHERE
    • G07C9/00Individual registration on entry or exit
    • G07C9/20Individual registration on entry or exit involving the use of a pass
    • G07C9/22Individual registration on entry or exit involving the use of a pass in combination with an identity check of the pass holder
    • G07C9/25Individual registration on entry or exit involving the use of a pass in combination with an identity check of the pass holder using biometric data, e.g. fingerprints, iris scans or voice recognition
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01DMEASURING NOT SPECIALLY ADAPTED FOR A SPECIFIC VARIABLE; ARRANGEMENTS FOR MEASURING TWO OR MORE VARIABLES NOT COVERED IN A SINGLE OTHER SUBCLASS; TARIFF METERING APPARATUS; MEASURING OR TESTING NOT OTHERWISE PROVIDED FOR
    • G01D21/00Measuring or testing not otherwise provided for
    • G01D21/02Measuring two or more variables by means not covered by a single other subclass
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06311Scheduling, planning or task assignment for a person or group
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0639Performance analysis of employees; Performance analysis of enterprise or organisation operations
    • G06Q10/06393Score-carding, benchmarking or key performance indicator [KPI] analysis
    • GPHYSICS
    • G08SIGNALLING
    • G08BSIGNALLING OR CALLING SYSTEMS; ORDER TELEGRAPHS; ALARM SYSTEMS
    • G08B7/00Signalling systems according to more than one of groups G08B3/00 - G08B6/00; Personal calling systems according to more than one of groups G08B3/00 - G08B6/00
    • G08B7/06Signalling systems according to more than one of groups G08B3/00 - G08B6/00; Personal calling systems according to more than one of groups G08B3/00 - G08B6/00 using electric transmission, e.g. involving audible and visible signalling through the use of sound and light sources

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • General Physics & Mathematics (AREA)
  • Physics & Mathematics (AREA)
  • Economics (AREA)
  • Strategic Management (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Educational Administration (AREA)
  • Development Economics (AREA)
  • Marketing (AREA)
  • Game Theory and Decision Science (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Tourism & Hospitality (AREA)
  • General Business, Economics & Management (AREA)
  • Theoretical Computer Science (AREA)
  • Human Computer Interaction (AREA)
  • Alarm Systems (AREA)

Abstract

The invention discloses an environment supervision system for construction of an intelligent construction site, which is provided with an environment monitoring module, wherein the environment monitoring module comprises a plurality of data acquisition devices, the data acquisition devices are internally provided with a PM2.5 sensor, a PM10 sensor, a sulfur dioxide sensor, a nitrogen dioxide sensor, a carbon monoxide sensor, a noise monitor, a temperature sensor, a humidity sensor, an air pressure sensor, a wind direction sensor, a wind speed sensor and a dust raising monitor, the data acquisition devices are arranged at each construction site of a construction site, so that the environment supervision system can be used for independently supervising a plurality of construction sites, and can be used for tracing real-name system responsibility to personnel in charge of the construction site environment and alarming according to dangerous situations monitored by the environment monitoring module by arranging a region division module, a personnel examination module, a processing module, an alarm module and a display module, and the environment monitoring information, the area division information and the personnel assessment information are displayed in real time through the display module.

Description

Wisdom building site is environment supervisory systems for construction
Technical Field
The invention belongs to the technical field of environment monitoring, and particularly relates to an intelligent environment supervision system for construction of a construction site.
Background
The building industry is one of the important material production departments and the pillar industry of national economy in China, and plays an important role in improving living conditions, perfecting infrastructure, promoting economic growth and the like. Meanwhile, the construction industry is also a high-risk industry with multiple safety accidents, how to strengthen the safety management of construction sites, reduce the accident occurrence frequency, stop various illegal operations and illegal constructions, and improve the quality of construction factories is an important research subject in front of all levels of government departments, people in the industry and broad students, and therefore, an environment supervision system for intelligent construction site construction is urgently needed.
Along with the large-scale construction site, the scattered degree increases, and often a plurality of job sites need to be supervised on the construction site, however, most of the existing environment supervision systems for construction are integrally supervised, and can not be used for independently supervising a plurality of job sites, and the existing environment supervision systems for construction can not be used for real-name system responsibility tracing of personnel responsible for the construction site environment.
Disclosure of Invention
The invention aims to provide an intelligent construction site construction environment supervision system, which aims to solve the problems that most of the existing construction environment supervision systems are integrally supervised, can not be used for independently supervising a plurality of construction sites, and can not be used for carrying out real-name system responsibility tracing on personnel in charge of construction site environments.
In order to achieve the purpose, the invention provides the following technical scheme: the utility model provides an environmental supervision system is used in construction of wisdom building site, wherein: the system comprises a processing module, wherein the processing module is connected with an environment monitoring module, an area dividing module, a personnel assessment module, an alarm module and a display module;
the environment monitoring module comprises a plurality of data acquisition devices, wherein a PM2.5 sensor, a PM10 sensor, a sulfur dioxide sensor, a nitrogen dioxide sensor, a carbon monoxide sensor, a noise monitor, a temperature sensor, a humidity sensor, an air pressure sensor, a wind direction sensor, a wind speed sensor and a dust raising monitor are arranged in each data acquisition device;
the region division module comprises a personnel information real-name registration unit and a personnel responsible region division unit;
the personnel assessment module comprises a violation operation reporting unit and a safety score management unit;
the alarm module comprises a buzzer and a signal lamp;
the display module comprises a display screen and a mobile terminal.
Preferably, the PM2.5 sensor, the PM10 sensor, the sulfur dioxide sensor, the nitrogen dioxide sensor, the carbon monoxide sensor, the noise monitor, the temperature sensor, the humidity sensor, the air pressure sensor, the wind direction sensor, the wind speed sensor and the dust emission monitor can set respective alarm thresholds.
Preferably, the staff information real-name registration unit may perform real-name system information registration by swiping an identification card and swiping a face of a constructor.
Preferably, the person responsible area dividing unit may divide a specific construction area and designate a specific constructor to take responsible supervision of the environment of the area.
Preferably, the violation operation reporting unit can enable on-site constructors to report violation operations through randomly shooting and submitting violation and unsafe operations or contents with potential safety hazards in the actual construction process.
Preferably, the safety score management unit may manage the safety score of the constructor by judging the environmental condition of the area in which a specific person is responsible and reporting or being reported the violation operation.
Preferably, the signal lamp includes a green lamp and a red lamp.
Preferably, the mobile terminal comprises a mobile phone and a tablet.
The invention has the technical effects and advantages that:
firstly, the method comprises the following steps: the environment monitoring system is provided with the environment monitoring module, the environment monitoring module comprises a plurality of data acquisition devices, the data acquisition devices are internally provided with a PM2.5 sensor, a PM10 sensor, a sulfur dioxide sensor, a nitrogen dioxide sensor, a carbon monoxide sensor, a noise monitor, a temperature sensor, a humidity sensor, an air pressure sensor, a wind direction sensor, a wind speed sensor and a dust raising monitor, and the data acquisition devices are arranged on each construction site of a construction site, so that the environment monitoring system can be used for independently monitoring a plurality of construction sites.
Secondly, the method comprises the following steps: by arranging the area division module, the personnel assessment module, the processing module, the alarm module and the display module, the real-name system responsibility tracing can be carried out on personnel in charge of the construction site environment, the alarm is carried out aiming at the dangerous case monitored by the environment monitoring module, and the environment monitoring information, the area division information and the personnel assessment information are displayed in real time through the display module.
Thirdly, the method comprises the following steps: the invention has wide applicability and good market prospect.
Drawings
FIG. 1 is a block diagram of the system architecture of the present invention;
fig. 2 is a block diagram of an environmental data acquisition apparatus of the present invention.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to fig. 1-2 in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
The present invention provides an intelligent site construction environment supervision system as shown in fig. 1-2, wherein: the system comprises a processing module, wherein the processing module is connected with an environment monitoring module, an area dividing module, a personnel assessment module, an alarm module and a display module;
the environment monitoring module comprises a plurality of data acquisition devices, wherein a PM2.5 sensor, a PM10 sensor, a sulfur dioxide sensor, a nitrogen dioxide sensor, a carbon monoxide sensor, a noise monitor, a temperature sensor, a humidity sensor, an air pressure sensor, a wind direction sensor, a wind speed sensor and a dust raising monitor are arranged in each data acquisition device;
the region division module comprises a personnel information real-name registration unit and a personnel responsible region division unit;
the personnel assessment module comprises a violation operation reporting unit and a safety score management unit;
the alarm module comprises a buzzer and a signal lamp;
the display module comprises a display screen and a mobile terminal.
Specifically, the PM2.5 sensor, the PM10 sensor, the sulfur dioxide sensor, the nitrogen dioxide sensor, the carbon monoxide sensor, the noise monitor, the temperature sensor, the humidity sensor, the air pressure sensor, the wind direction sensor, the wind speed sensor and the dust emission monitor can be set with respective alarm thresholds.
Specifically, the personnel information real-name registration unit may perform identification card swiping and face swiping on the constructor to perform real-name system information registration.
Specifically, the personnel responsible area dividing unit may divide a specific construction area and designate a specific constructor to supervise the environment of the area.
Specifically, the violation operation reporting unit can enable on-site constructors to report violation operations through randomly shooting and submitting violation and unsafe operations or contents with potential safety hazards in the actual construction process.
Specifically, the safety score management unit may manage the safety score of the constructor by judging the environmental condition of the area in which the specific person is responsible and reporting the violation operation or being reported.
Specifically, the signal lamp comprises a green lamp and a red lamp.
Specifically, the mobile terminal comprises a mobile phone and a tablet.
The working principle of the invention is as follows:
the environment monitoring system is provided with an environment monitoring module, the environment monitoring module comprises a plurality of data acquisition devices, PM2.5 sensors, PM10 sensors, sulfur dioxide sensors, nitrogen dioxide sensors, carbon monoxide sensors, noise monitors, temperature sensors, humidity sensors, air pressure sensors, wind direction sensors, wind speed sensors and dust raising monitors are arranged in the data acquisition devices, and the data acquisition devices are arranged on each construction site of a construction site, so that the environment monitoring system can be used for independently monitoring a plurality of construction sites.
The invention is provided with an area dividing module, a personnel assessment module, a processing module, an alarm module and a display module, wherein the area dividing module comprises a personnel information real-name registration unit and a personnel responsible area dividing unit, the personnel assessment module comprises a violation operation reporting unit and a safety score management unit, the alarm module comprises a buzzer and a signal lamp, the display module comprises a display screen and a mobile terminal, the personnel information real-name registration unit can register real-name information of personnel entering a construction site, the personnel responsible area dividing unit can define a specific construction area and designate a specific constructor to be responsible for monitoring the environment of the area, the violation operation reporting unit can enable on-site constructors to report violation and unsafe operations or contents with potential safety hazards to report the violation operations through random shooting in the actual construction process, the safety score management unit can manage safety scores of constructors through judgment of environmental conditions of areas in charge of specific personnel and reporting of illegal operations or reported, wherein the signal lamps comprise green lamps and red lamps, and the mobile terminal comprises a mobile phone and a flat panel. When the data acquisition devices in the environment monitoring module monitor data outside the respective set safety threshold values, the processing module controls the alarm module to enable the buzzer in the alarm module to give an alarm, the signal lamp displays a red light, when the data acquisition devices in the environment monitoring module monitor data within the respective set safety threshold values, the signal lamp displays a green light, and the data monitored by the data acquisition devices in the environment monitoring module are displayed in real time through the display module. The information in the personnel assessment module and the information in the area division module are displayed in real time through the display module. According to the method, real-name system responsibility tracing can be performed on personnel in charge of the construction site environment, alarm is performed on dangerous situations monitored by the environment monitoring module, and environment monitoring information, area division information and personnel assessment information are displayed in real time through the display module.
In summary, the following steps: the invention solves the problems that most of the existing construction environment supervision systems are integrally supervised, can not carry out independent supervision on a plurality of construction sites, and can not carry out real-name system responsibility tracing on personnel responsible for construction site environments. In the description of the present invention, it is to be understood that the terms "bottom", "front", "side", "outer", "central", "inner", "upper", "lower", "one end", "vertical", "lower", "outer", "circumferential", "end", "lower", "horizontal", and the like, indicate orientations and positional relationships based on the orientations and positional relationships shown in fig. 1-2, and are used merely for convenience in describing the present invention and for simplicity in description, and do not indicate or imply that the device or element being referred to must have a particular orientation, be constructed and operated in a particular orientation, and therefore, should not be considered as limiting the present invention.
The terms "first," "second," "third," and the like are used solely to distinguish one from another and are not to be construed as indicating or implying relative importance.
The terms "parallel", "perpendicular", etc. do not require that the components be absolutely parallel or perpendicular, but may be slightly inclined. For example, "parallel" merely means that the directions are more parallel relative to "perpendicular," and does not mean that the structures are necessarily perfectly parallel, but may be slightly tilted.
The terms "horizontal", "vertical", "overhang" and the like do not imply that the components are required to be absolutely horizontal or overhang, but may be slightly inclined. For example, "horizontal" merely means that the direction is more horizontal than "vertical" and does not mean that the structure must be perfectly horizontal, but may be slightly inclined.
Furthermore, the terms "substantially", and the like are intended to indicate that the relative terms are not necessarily strictly required, but may have some deviation. For example: "substantially equal" does not mean absolute equality, but it is difficult to achieve absolute equality in actual production and operation, and some deviation generally exists. Thus, in addition to absolute equality, "substantially equal" also includes the above-described case where there is some deviation. In this case, unless otherwise specified, terms such as "substantially", and the like are used in a similar manner to those described above.
In the present invention, unless otherwise explicitly specified or limited, the terms "embedded", "disposed", "connected", "fixed", "distributed", and the like are to be understood in a broad sense, and for example, may be fixedly connected, detachably connected, or integrated; can be mechanically or electrically connected; they may be directly connected or indirectly connected through intervening media, or they may be connected internally or in any other suitable relationship, unless expressly stated otherwise. The specific meanings of the above terms in the present invention can be understood by those skilled in the art according to specific situations.
Finally, it should be noted that: although the present invention has been described in detail with reference to the foregoing embodiments, it will be apparent to those skilled in the art that modifications may be made to the embodiments or portions thereof without departing from the spirit and scope of the invention.

Claims (8)

1. The utility model provides an environmental supervision system is used in construction of wisdom building site which characterized in that: the system comprises a processing module, wherein the processing module is connected with an environment monitoring module, an area dividing module, a personnel assessment module, an alarm module and a display module;
the environment monitoring module comprises a plurality of data acquisition devices, wherein a PM2.5 sensor, a PM10 sensor, a sulfur dioxide sensor, a nitrogen dioxide sensor, a carbon monoxide sensor, a noise monitor, a temperature sensor, a humidity sensor, an air pressure sensor, a wind direction sensor, a wind speed sensor and a dust raising monitor are arranged in each data acquisition device;
the region division module comprises a personnel information real-name registration unit and a personnel responsible region division unit;
the personnel assessment module comprises a violation operation reporting unit and a safety score management unit;
the alarm module comprises a buzzer and a signal lamp;
the display module comprises a display screen and a mobile terminal.
2. The intelligent environment supervision system for construction of construction site as claimed in claim 1, wherein: the PM2.5 sensor, the PM10 sensor, the sulfur dioxide sensor, the nitrogen dioxide sensor, the carbon monoxide sensor, the noise monitor, the temperature sensor, the humidity sensor, the air pressure sensor, the wind direction sensor, the wind speed sensor and the raise dust monitor can be set with respective alarm thresholds.
3. The intelligent environment supervision system for construction of construction site as claimed in claim 1, wherein: the personnel information real-name registration unit can perform identity card swiping and face swiping on constructors to perform real-name system information registration.
4. The intelligent environment supervision system for construction of construction site as claimed in claim 1, wherein: the personnel responsible area dividing unit can divide a specific construction area and designate a specific constructor to supervise the environment of the area.
5. The intelligent environment supervision system for construction of construction site as claimed in claim 1, wherein: the violation operation reporting unit can enable on-site constructors to report violation operations, unsafe operations or contents with potential safety hazards by taking photos at will during actual construction.
6. The intelligent environment supervision system for construction of construction site as claimed in claim 1, wherein: the safety score management unit can manage the safety score of the constructor by judging the environmental condition of the area in which a specific person is responsible and reporting the illegal operation or reporting the illegal operation.
7. The intelligent environment supervision system for construction of construction site as claimed in claim 1, wherein: the signal lamp comprises a green light and a red light.
8. The intelligent environment supervision system for construction of construction site as claimed in claim 1, wherein: the mobile terminal comprises a mobile phone and a tablet.
CN202010693896.1A 2020-07-17 2020-07-17 Wisdom building site is environment supervisory systems for construction Pending CN112070941A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010693896.1A CN112070941A (en) 2020-07-17 2020-07-17 Wisdom building site is environment supervisory systems for construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010693896.1A CN112070941A (en) 2020-07-17 2020-07-17 Wisdom building site is environment supervisory systems for construction

Publications (1)

Publication Number Publication Date
CN112070941A true CN112070941A (en) 2020-12-11

Family

ID=73656596

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010693896.1A Pending CN112070941A (en) 2020-07-17 2020-07-17 Wisdom building site is environment supervisory systems for construction

Country Status (1)

Country Link
CN (1) CN112070941A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112668860A (en) * 2020-12-23 2021-04-16 中哲国际工程设计有限公司 Building construction management system and method based on neural network
CN113155190A (en) * 2021-04-16 2021-07-23 浙江农林大学 Foundation pit construction area environment monitoring device and method
CN113885414A (en) * 2021-09-10 2022-01-04 中建三局集团有限公司 Wisdom building site environmental monitoring system
CN116777160A (en) * 2023-06-21 2023-09-19 苏州傲之途智慧科技有限公司 Environment intelligent supervision system and method for urban construction site

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106447195A (en) * 2016-09-28 2017-02-22 国网浙江省电力公司湖州供电公司 Safety bearing capacity analysis method based on employee integral and outsourcing team evaluation
CN107665419A (en) * 2017-08-24 2018-02-06 北京融通智慧科技有限公司 The labor service real-name management system of national grid wisdom building site control platform
CN107730428A (en) * 2017-10-17 2018-02-23 贾俊力 Job site intelligent monitoring administration system and its control method
CN109214779A (en) * 2018-09-06 2019-01-15 厦门路桥信息股份有限公司 Construction site information managing and control system
CN110215779A (en) * 2019-05-30 2019-09-10 浙江鸿翔建设集团股份有限公司 Green construction environmental monitoring system
CN110620906A (en) * 2019-09-12 2019-12-27 国网上海市电力公司 Electric power construction safety management system based on thing networking
CN110956394A (en) * 2019-11-29 2020-04-03 广东建采网科技有限公司 Building labor worker credit assessment method and system

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106447195A (en) * 2016-09-28 2017-02-22 国网浙江省电力公司湖州供电公司 Safety bearing capacity analysis method based on employee integral and outsourcing team evaluation
CN107665419A (en) * 2017-08-24 2018-02-06 北京融通智慧科技有限公司 The labor service real-name management system of national grid wisdom building site control platform
CN107730428A (en) * 2017-10-17 2018-02-23 贾俊力 Job site intelligent monitoring administration system and its control method
CN109214779A (en) * 2018-09-06 2019-01-15 厦门路桥信息股份有限公司 Construction site information managing and control system
CN110215779A (en) * 2019-05-30 2019-09-10 浙江鸿翔建设集团股份有限公司 Green construction environmental monitoring system
CN110620906A (en) * 2019-09-12 2019-12-27 国网上海市电力公司 Electric power construction safety management system based on thing networking
CN110956394A (en) * 2019-11-29 2020-04-03 广东建采网科技有限公司 Building labor worker credit assessment method and system

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112668860A (en) * 2020-12-23 2021-04-16 中哲国际工程设计有限公司 Building construction management system and method based on neural network
CN113155190A (en) * 2021-04-16 2021-07-23 浙江农林大学 Foundation pit construction area environment monitoring device and method
CN113885414A (en) * 2021-09-10 2022-01-04 中建三局集团有限公司 Wisdom building site environmental monitoring system
CN116777160A (en) * 2023-06-21 2023-09-19 苏州傲之途智慧科技有限公司 Environment intelligent supervision system and method for urban construction site

Similar Documents

Publication Publication Date Title
CN112070941A (en) Wisdom building site is environment supervisory systems for construction
CN112954071A (en) Intelligent construction site management system
CN110620906A (en) Electric power construction safety management system based on thing networking
CN209231777U (en) Wisdom building site management system
CN108205694B (en) Construction site operation personnel positioning system based on chromatographic beacon
CN113960953A (en) Intelligent construction site application system based on Internet of things technology and use method thereof
CN207078937U (en) Safe construction early warning system applied to tower crane
CN214799539U (en) Intelligent construction site management system
CN206088803U (en) Outer broken alarm device is prevented to power transmission line
CN112050851A (en) Wisdom building site environmental monitoring system
CN114386741A (en) Building site construction safety monitoring system based on risk identification
CN202352037U (en) Safety alarm system based on technology of Internet of things
CN110031043B (en) Civil engineering building structure real-time intelligent monitoring system
CN115240362A (en) Monitoring alarm system and method of intelligent construction site management and control platform
CN113885414A (en) Wisdom building site environmental monitoring system
CN112488595A (en) Wisdom building site system
CN113479801A (en) All-round intelligent security monitored control system of mobile crane
CN206502527U (en) Tower crane construction safety monitoring system
CN116911756A (en) Intelligent building site special equipment monitoring system
CN205193534U (en) Intelligence roofing management system
CN215642349U (en) Wisdom mine industry thing networking operating system
CN216105739U (en) Quick detachable tower crane lifting rope collision device that can have enough to meet need
CN219738275U (en) SF (sulfur hexafluoride) 6 Gas alarm monitoring system
CN112073605A (en) Wisdom city building site thing networking device monitoring device
CN215181563U (en) Production site safety management system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20201211