CN110215779A - Green construction environmental monitoring system - Google Patents

Green construction environmental monitoring system Download PDF

Info

Publication number
CN110215779A
CN110215779A CN201910465700.0A CN201910465700A CN110215779A CN 110215779 A CN110215779 A CN 110215779A CN 201910465700 A CN201910465700 A CN 201910465700A CN 110215779 A CN110215779 A CN 110215779A
Authority
CN
China
Prior art keywords
detection signal
control platform
centralized control
environmental monitoring
signal
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910465700.0A
Other languages
Chinese (zh)
Inventor
王铁
马小平
朱国华
汤秦凉
陆聪
施雪成
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Hongxiang Construction Group Ltd By Share Ltd
Original Assignee
Zhejiang Hongxiang Construction Group Ltd By Share Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang Hongxiang Construction Group Ltd By Share Ltd filed Critical Zhejiang Hongxiang Construction Group Ltd By Share Ltd
Priority to CN201910465700.0A priority Critical patent/CN110215779A/en
Publication of CN110215779A publication Critical patent/CN110215779A/en
Pending legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B01PHYSICAL OR CHEMICAL PROCESSES OR APPARATUS IN GENERAL
    • B01DSEPARATION
    • B01D47/00Separating dispersed particles from gases, air or vapours by liquid as separating agent
    • B01D47/06Spray cleaning
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01DMEASURING NOT SPECIALLY ADAPTED FOR A SPECIFIC VARIABLE; ARRANGEMENTS FOR MEASURING TWO OR MORE VARIABLES NOT COVERED IN A SINGLE OTHER SUBCLASS; TARIFF METERING APPARATUS; MEASURING OR TESTING NOT OTHERWISE PROVIDED FOR
    • G01D21/00Measuring or testing not otherwise provided for
    • G01D21/02Measuring two or more variables by means not covered by a single other subclass

Landscapes

  • Chemical & Material Sciences (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Catching Or Destruction (AREA)

Abstract

The invention discloses a kind of green construction environmental monitoring systems, its key points of the technical solution are that: several fog gun machines and safety cap is arranged in a kind of green construction environmental monitoring system, each region, and green construction environmental monitoring system includes, particulate matter sensors, for exporting concentration detection signal;Sensor noise detects signal for output noise;Zone controller, for by concentration detection signal and noise measuring signal acquisition and being sent to centralized control platform;Centralized control platform is built-in with particle concentration predetermined value and noise predetermined value, for receiving simultaneously analytical concentration detection signal and noise measuring signal, and sends control instruction, to control the opening and closing of fog gun machine;Centralized control platform was built-in with for the first predetermined time, and when more than the first predetermined time, concentration detection signal is also higher than particle concentration predetermined value, then centralized control platform issues standby signal.Green construction environmental monitoring system of the invention to carry out the daily life that environmental monitoring ensures periphery health automatically.

Description

Green construction environmental monitoring system
Technical field
The present invention relates to the technical fields of building monitoring, more particularly, to a kind of green construction environmental monitoring system.
Background technique
With the fast development of all types of processes of industrialization, environmental problem is got worse, and the public is to living in a health Natural environment have tight demand;Thus environmental monitoring becomes more and more important.Brought by current building engineering construction Environmental pollution can not despise, there are many building engineering construction includes: for example, the engineering construction of urban public infrastructure, Industrial building engineering construction, city commercial and residential construction engineering construction etc..
Since extensive management, construction worker lack the reasons such as environmental consciousness in building construction process at present, cause During construction operation at this stage, affect to urban environment;Produced pollution source master in work progress To include in city commercial and residential construction construction process, in certain a road section work progress of urban traffic road with And generated dust pollution, noise pollution and pernicious gas pollution etc. in City Buried Pipeline work progress, and harmful gas Risk caused by body: cause caused by the Combustible Gas Leak in pernicious gas in the damage and maintenance of urban pipeline Explosion danger on fire, these pollutions can all cause serious influence and harm to environment;Therefore, green construction is to realize that the modern times build The important link of industry energy-saving and emission-reduction is built, and becomes the inevitable requirement in building course.
As a result, it is often necessary to be monitored to construction site environment etc., to ensure the daily life of nearby residents health.
Summary of the invention
In view of the deficiencies of the prior art, the present invention intends to provide a kind of green construction environmental monitoring system, With automatic continuous carry out environmental monitoring, the daily life of nearby residents health is ensured.
Foregoing invention purpose of the invention has the technical scheme that
A kind of green construction environmental monitoring system, construction site are divided into multiple regions, and several fog gun machines are arranged in each region With with the matched safety cap of construction personnel, the green construction environmental monitoring system includes,
Particulate matter sensors are installed on safety cap, for detecting the particle concentration of site operation environment, and export concentration inspection Survey signal;
Sensor noise is installed on the noise monitor point in each region, and for detecting construction noise, and output noise detects signal;
Zone controller is connected to particulate matter sensors and sensor noise, for believing concentration detection signal and noise measuring It number acquires and is sent to centralized control platform;
Centralized control platform, connect with zone controller, particle concentration predetermined value and noise predetermined value is built-in with, for receiving And analytical concentration detects signal and noise measuring signal, and sends control instruction, to control the opening and closing of fog gun machine;
Centralized control platform was built-in with for the first predetermined time, when more than the first predetermined time, concentration detection signal also higher than Grain object concentration predetermined value, then centralized control platform issues standby signal.
By using above-mentioned technical proposal, in a construction site, with the progress of construction operation, dust pollution and Noise pollution is undoubtedly most significant, and country is also all to have its limit value, and each construction site is just needed for the two The two is reduced in limit value hereinafter, guarantee same and to construction personnel's health, avoids long-term work in particle In object concentration over-standard, the serious environment of noise pollution;Entire construction site is marked off into multiple regions as needed first, each The fog gun machine and configuration corresponding safety cap that several are used to depositing dust are set in region;Particulate matter sensors and noise are sensed Device is mounted on safety cap, detects construction environment locating for construction personnel on the spot, more accurate and meet actual demand, by concentration It detects signal and noise measuring signal and centralized control platform is sent to by zone controller region, then centralized control platform receives And analytical concentration detects signal, when particle concentration is exceeded, sends control instruction, zone controller controls the starting of fog gun machine, Depositing dust processing is carried out to the region in time, and after more than the first predetermined time, it is dense that concentration detection signal is also higher than particulate matter Predetermined value is spent, then centralized control platform issues standby signal and at the first time reaches construction environment to carry out other depositing dust schemes Good standard;When noise is exceeded, centralized control platform issues early warning, to carry out sound insulation or noise reduction process to the region, with It avoids having an impact periphery living environment, to be always ensured that the green and healthy of construction environment.
The present invention is further arranged to: the zone controller is also connected with the wind transducer being set in each region, For detecting current wind direction, and wind direction detection signal is exported, the centralized control platform detects signal according to wind direction and shows Current wind direction.
By using above-mentioned technical proposal, in the case where there is wind, fog gun machine will should be sprayed with the wind, can be only achieved most Big effect;Gone out in construction site by wind transducer real-time monitoring/region in wind direction so that when carrying out depositing dust, Fog gun machine can be sprayed in the case where with the wind, to reach the maximization of dust-laying effect.
The present invention is further arranged to: the zone controller is connected with the GPS module being installed on safety cap, for sending out The positioning signal of each construction personnel is sent, the centralized control platform includes GIS map module, for receiving positioning signal, and Show construction personnel's location information.
By using above-mentioned technical proposal, because each region is each equipped with respective safety cap, and pacify in safety cap GPS module is filled, to carry out the positioning of local environment to construction personnel, so that the particulate matter sensors on the safety cap detect When the concentration detection signal of local environment is greater than particle concentration predetermined value, which can be accurately positioned by GPS module The location of member, and depositing dust processing is carried out to the regional location.
The present invention is further arranged to: the centralized control platform is connected with communication module, and the communication module signal connects It is connected to first movement terminal, when more than the first predetermined time, concentration detection signal is also higher than particle concentration predetermined value, then collects Middle control platform sends prompt information to first movement terminal by communication module, and prompt information includes construction personnel position letter Breath, current wind direction information.
By using above-mentioned technical proposal, when particle concentration is exceeded, control instruction is sent, zone controller controls mist The starting of big gun machine, carries out depositing dust processing to the region in time, but when more than the first predetermined time after, concentration detection signal is also higher than When grain object concentration predetermined value, then centralized control platform is sent out by communication module to first movement terminal entrained by Regional Champion Prompt information is sent, prompt information includes construction personnel's location information, current wind direction information, carries out other with notification area responsible person Construction environment is reached good standard at the first time by depositing dust scheme, more information-based, intelligent without issuing a separate notice again.
The present invention is further arranged to: the communication module is also connected with the second mobile terminal, and in centralized control platform It was equipped with for the second predetermined time, when more than the second predetermined time, concentration detection signal is also higher than particle concentration predetermined value, then collects Middle control platform sends timeout treatment information to the second mobile terminal by communication module.
By using above-mentioned technical proposal, when particle concentration is exceeded, control instruction is sent, zone controller controls mist The starting of big gun machine carries out depositing dust processing to the region in time, but when more than the second predetermined time, (it is pre- that the second predetermined time was greater than first Fix time) after, when concentration detection signal is also higher than particle concentration predetermined value, then centralized control platform is by communication module to total Second mobile terminal entrained by responsible person send timeout treatment signal, timely feedback the situation to person in overall, avoid because The carelessness of some of the staff or the seriousness of situation and cause duration particle concentration exceeded, to guarantee the good of construction environment.
The present invention is further arranged to: the zone controller is connected with the temperature sensor for being installed on each region, is used for The real time temperature in each region is detected, and issues temperature detection signal, the centralized control platform receives and analyzes temperature detection letter Number, and control instruction is sent, to control the opening and closing of fog gun machine.
By using above-mentioned technical proposal, summer high-temperature weather annoyings always construction personnel, continues in the high temperature environment Operation, it is easy to lead to heatstroke, therefore when temperature detection signal detection Current Temperatures are excessively high, by control fog gun machine it is spraying into Row cooling, fog gun machine can also be cooled down while playing the role of depositing dust by water mist, to guarantee construction personnel's life Health.
The present invention is further arranged to: the zone controller is connected with display, and the zone controller is according to concentration It detects signal, noise measuring signal, wind direction detection signal and temperature detection signal control display and shows current region particulate matter Concentration, noise level, wind direction and temperature information.
By using above-mentioned technical proposal, installation is used to show current region particle concentration, noise in each region The display of size, wind direction and temperature information enables and recognizes current construction environment in region construction personnel, with Make counter-measure, than such as whether than with a mask, to ensure itself health.
The present invention is further arranged to: the fog gun machine includes pedestal, U-bracket and is rotationally connected on U-bracket For the spraying gun barrel of atomizing de-dusting, turntable is rotatably connected on the pedestal, the turntable is connected by setting shaft There is direct driving motor, the U-bracket is fixed on turntable upper surface.
By using above-mentioned technical proposal, turntable is driven to be rotated by the transmission of direct driving motor, to drive U Spraying gun barrel on shape bracket carries out 360 degree rotation, can carry out atomizing de-dusting to all directions.
The present invention is further arranged to: rotary encoder is provided in the shaft of the turntable, for detecting shaft Angular displacement, and angle displacement detects signal, the centralized control platform is controlled according to the positioning signal of GPS module to region Device sends control instruction, drives turntable rotation predetermined angular displacement to control direct driving motor.
By using above-mentioned technical proposal, the positioning signal and wind direction that are issued according to GPS module when centralized control platform Sensor issue wind direction detect signal, so that it is determined that in the region fog gun machine spray direction, thus direct driving motor driving rotation Turntable turns to the spray direction, and determines angular displacement by rotary encoder, to guarantee the correctness of spray direction.
In conclusion advantageous effects of the invention are as follows:
1. when particle concentration is exceeded, send control instruction, zone controller controls the starting of fog gun machine, in time to the region into The processing of row depositing dust, and after more than the first predetermined time, concentration detection signal is also higher than particle concentration predetermined value, to carry out Other depositing dust schemes, reach good standard for construction environment at the first time;
2. Current Temperatures are excessively high, cooled down by spraying by controlling fog gun machine, fog gun machine is gone back while playing the role of depositing dust It can be cooled down by water mist, to guarantee construction personnel's life and health;
3. fog gun machine drives turntable to be rotated by the transmission of direct driving motor, to drive the spraying big gun on U-bracket Cylinder carries out 360 degree rotation, can carry out atomizing de-dusting to all directions;
4. the spray direction of fog gun machine in the region is determined by GPS module, so that direct driving motor driving turntable turns to this Spray direction, and angular displacement is determined by rotary encoder, to guarantee the correctness of spray direction.
Detailed description of the invention
Fig. 1 is system block diagram of the invention;
Fig. 2 is the overall structure diagram of fog gun machine.
In figure, 1, fog gun machine;101, pedestal;102, U-bracket;103, spraying gun barrel;104, turntable;105, straight to drive electricity Machine;106, rotary encoder;2, particulate matter sensors;3, sensor noise;4, zone controller;5, centralized control platform;6, GPS module;7, GIS map module;8, wind transducer;9, communication module;10, first movement terminal;11, second is mobile whole End;12, display;13, temperature sensor.
Specific embodiment
Below in conjunction with attached drawing, invention is further described in detail.
It referring to Fig.1, is a kind of green construction environmental monitoring system disclosed by the invention, construction site is divided into multiple areas Domain, each region be arranged several fog gun machines 1 and with the matched safety cap of construction personnel, green construction environmental monitoring system packet It includes, particulate matter sensors 2 are installed on safety cap, for detecting the particle concentration of site operation environment, and export concentration inspection Survey signal;Sensor noise 3 is installed on the noise monitor point in each region, for detecting construction noise, and output noise detection letter Number;Zone controller 4 is connected to particulate matter sensors 2 and sensor noise 3, is used for concentration detection signal and noise measuring Signal acquisition is simultaneously sent to centralized control platform 5;Centralized control platform 5 connect with zone controller 4, it is dense to be built-in with particulate matter Predetermined value and noise predetermined value are spent, for receiving simultaneously analytical concentration detection signal and noise measuring signal, and sends control instruction, To control the opening and closing of fog gun machine;Centralized control platform 5 was built-in with for the first predetermined time, when more than the first predetermined time, concentration inspection It surveys signal and is also higher than particle concentration predetermined value, then centralized control platform 5 issues standby signal.
In a construction site, with the progress of construction operation, dust pollution and noise pollution are undoubtedly most significantly , and country be also all for the two have its limit value, and each construction site just need by the two reduce limit value with Under, same is also the guarantee to construction personnel's health, avoids long-term work particle concentration is exceeded, noise pollution is tight In the environment of weight;First entire construction site is marked off into multiple regions as needed, several are arranged in each region and is used to The fog gun machine 1 and the corresponding safety cap of configuration of depositing dust;Particulate matter sensors 2 and sensor noise 3 are mounted on safety cap, Construction environment locating for construction personnel is detected on the spot, it is more accurate and meet actual demand, concentration detection signal and noise are examined It surveys signal and centralized control platform 5 is sent to by 4 region of zone controller, then centralized control platform 5 receives and analytical concentration is examined Signal is surveyed, when particle concentration is exceeded, sends control instruction, zone controller 4 controls fog gun machine 1 and starts, in time to the area Domain carries out depositing dust processing, and after more than the first predetermined time, concentration detection signal is also higher than particle concentration predetermined value, then Centralized control platform 5 issues standby signal and construction environment is reached good mark at the first time to carry out other depositing dust schemes It is quasi-;When noise is exceeded, centralized control platform 5 issues early warning, to carry out sound insulation or noise reduction process to the region, to avoid to week Side living environment has an impact, to be always ensured that the green and healthy of construction environment.
For the maximization for reaching dust-laying effect, referring to Fig.1, zone controller 4 is connected with the wind direction being set in each region Sensor 8 for detecting current wind direction, and exports wind direction detection signal, and centralized control platform 5 detects signal according to wind direction and shows Current wind direction is shown.In the case where there is wind, fog gun machine 1 will should be sprayed with the wind, can be only achieved maximum efficiency;Pass through wind direction 8 real-time monitoring of sensor goes out in construction site/region in wind direction so that fog gun machine 1 can be existed when carrying out depositing dust It is sprayed in the case where with the wind, to reach the maximization of dust-laying effect.
In addition, referring to Fig.1, zone controller 4 is also connected with the GPS module 6 being installed on safety cap, each for sending The positioning signal of construction personnel, centralized control platform 5 include GIS map module 7, for receiving positioning signal, and show construction Personnel location information.Because each region is each equipped with respective safety cap, and GPS module 6 is installed, in safety cap with to applying Worker person carries out the positioning of local environment, so that when the particulate matter sensors 2 on the safety cap detect the concentration of local environment When detecting signal greater than particle concentration predetermined value, the location of the construction personnel can be accurately positioned by GPS module 6, And depositing dust processing is carried out to the regional location.
To realize intelligentized control method, referring to Fig.1, centralized control platform 5 is connected with communication module 9, and 9 signal of communication module connects It is connected to first movement terminal 10, when more than the first predetermined time, concentration detection signal is also higher than particle concentration predetermined value, then Centralized control platform 5 sends prompt information to first movement terminal 10 by communication module 9, and prompt information includes construction personnel position Confidence breath, current wind direction information.When particle concentration is exceeded, control instruction is sent, zone controller 4 controls fog gun machine 1 and opens It is dynamic, depositing dust processing is carried out to the region in time, but after more than the first predetermined time, it is dense that concentration detection signal is also higher than particulate matter When spending predetermined value, then centralized control platform 5 is sent by communication module 9 to first movement terminal 10 entrained by Regional Champion Prompt information, prompt information include construction personnel's location information, current wind direction information, carry out other drops with notification area responsible person Construction environment is reached good standard at the first time by dirt scheme, more information-based, intelligent without issuing a separate notice again.
Meanwhile referring to Fig.1, communication module 9 is also connected with the second mobile terminal 11, and centralized control platform 5 is built-in with Two predetermined times, when more than the second predetermined time, concentration detection signal is also higher than particle concentration predetermined value, then centralized control Platform 5 sends timeout treatment information to the second mobile terminal 11 by communication module 9.When particle concentration is exceeded, control is sent System instruction, zone controller 4 control fog gun machine 1 and start, and carry out depositing dust processing to the region in time, but when more than the second pre- timing Between after (the second predetermined time be greater than the first predetermined time), when concentration detection signal is also higher than particle concentration predetermined value, then collect Middle control platform 5 sends timeout treatment signal to the second mobile terminal 11 entrained by person in overall by communication module 9, to total Responsible person timely feedbacks the situation, avoids causing duration particulate matter dense due to the seriousness because of the carelessness of some of the staff or situation Spend it is exceeded, to guarantee the good of construction environment.
To avoid that Heat stroke phenomenon occurs, referring to Fig.1, zone controller 4 is connected with the temperature biography for being installed on each region Sensor 13 for detecting the real time temperature in each region, and issues temperature detection signal, and centralized control platform 5 receives and analyzes temperature Degree detection signal, and control instruction is sent, to control the opening and closing of fog gun machine.Summer high-temperature weather annoyings always construction personnel, holds Continuous operation in the high temperature environment, it is easy to lead to heatstroke, therefore when temperature detection signal detection Current Temperatures are excessively high, pass through control Fog gun machine 1 processed cools down by spraying, and fog gun machine 1 can also be cooled down while playing the role of depositing dust by water mist, thus Guarantee construction personnel's life and health.
To check site environment situation convenient for construction personnel and administrative staff, referring to Fig.1, zone controller 4 is connected with aobvious Show device 12, zone controller 4 is according to concentration detection signal, noise measuring signal, wind direction detection signal and temperature detection signal control Display 12 processed shows current region particle concentration, noise level, wind direction and temperature information.It installs and uses in each region The display 12 of current region particle concentration, noise level, wind direction and temperature information is shown, so that constructing in the region Personnel can recognize current construction environment, to make counter-measure, than such as whether than with a mask, to ensure the strong of itself Health.
In the present embodiment, referring to Fig. 2, fog gun machine 1 is including pedestal 101, U-bracket 102 and is rotationally connected with U-shaped branch It is used for the spraying gun barrel 103 of atomizing de-dusting on frame 102, turntable 104 is rotatably connected on pedestal 101, turntable 104 is by setting It sets shaft and is connected with direct driving motor 105, U-bracket 102 is fixed on 104 upper surface of turntable.Pass through the transmission of direct driving motor 105 Turntable 104 is driven to be rotated, so that the spraying gun barrel 103 on U-bracket 102 be driven to carry out 360 degree rotation, with can Atomizing de-dusting is carried out to all directions.
Meanwhile referring to Fig.1, Fig. 2, rotary encoder 106 is provided in the shaft of turntable 104, for detecting shaft Angular displacement, and angle displacement detects signal, and centralized control platform 5 is controlled according to the positioning signal of GPS module 6 to region Device 4 sends control instruction, drives turntable 104 to rotate predetermined angular displacement to control direct driving motor 105.When centralized control platform 5 The wind direction that the positioning signal and wind transducer 8 issued according to GPS module 6 issues detects signal, so that it is determined that in the region The spray direction of fog gun machine 1 so that direct driving motor 105 drives turntable 104 to turn to the spray direction, and passes through rotary coding Device 106 determines angular displacement, to guarantee the correctness of spray direction.
The embodiment of present embodiment is presently preferred embodiments of the present invention, not limits protection model of the invention according to this It encloses, therefore: the equivalence changes that all structures under this invention, shape, principle are done should all be covered by within protection scope of the present invention.

Claims (9)

1. a kind of green construction environmental monitoring system, it is characterised in that: construction site is divided into multiple regions, each region setting Several fog gun machines (1) and with the matched safety cap of construction personnel, the green construction environmental monitoring system includes,
Particulate matter sensors (2), are installed on safety cap, for detecting the particle concentration of site operation environment, and export dense Degree detection signal;
Sensor noise (3) is installed on the noise monitor point in each region, for detecting construction noise, and output noise detection letter Number;
Zone controller (4) is connected to particulate matter sensors (2) and sensor noise (3), for by concentration detection signal with make an uproar Sound detection signal acquisition is simultaneously sent to centralized control platform (5);
Centralized control platform (5) is connect with zone controller (4), is built-in with particle concentration predetermined value and noise predetermined value, is used Signal and noise measuring signal are detected in receiving simultaneously analytical concentration, and sends control instruction, to control the opening and closing of fog gun machine;
Centralized control platform (5) was built-in with for the first predetermined time, and when more than the first predetermined time, concentration detection signal is also higher than Particle concentration predetermined value, then centralized control platform (5) issues standby signal.
2. green construction environmental monitoring system according to claim 1, it is characterised in that: the zone controller (4) is also It is connected with the wind transducer (8) being set in each region, for detecting current wind direction, and exports wind direction detection signal, institute It states centralized control platform (5) and current wind direction is shown according to wind direction detection signal.
3. green construction environmental monitoring system according to claim 2, it is characterised in that: the zone controller (4) is even It is connected to the GPS module (6) being installed on safety cap, for sending the positioning signal of each construction personnel, the centralized control is flat Platform (5) includes GIS map module (7), for receiving positioning signal, and shows construction personnel's location information.
4. green construction environmental monitoring system according to claim 3, it is characterised in that: the centralized control platform (5) It is connected with communication module (9), communication module (9) signal is connected with first movement terminal (10), when more than the first pre- timing Between when, concentration detection signal is also higher than particle concentration predetermined value, then centralized control platform (5) is by communication module (9) to the One mobile terminal (10) sends prompt information, and prompt information includes construction personnel's location information, current wind direction information.
5. green construction environmental monitoring system according to claim 4, it is characterised in that: the communication module (9) also connects It is connected to the second mobile terminal (11), and centralized control platform (5) was built-in with for the second predetermined time, when more than the second predetermined time When, concentration detection signal is also higher than particle concentration predetermined value, then centralized control platform (5) passes through communication module (9) to second Mobile terminal (11) sends timeout treatment information.
6. green construction environmental monitoring system according to claim 2, it is characterised in that: the zone controller (4) is even It is connected to the temperature sensor (13) for being installed on each region, for detecting the real time temperature in each region, and issues temperature detection signal, The centralized control platform (5) receives and analyzes temperature detection signal, and sends control instruction, to control the opening and closing of fog gun machine.
7. green construction environmental monitoring system according to claim 6, it is characterised in that: the zone controller (4) is even Be connected to display (12), the zone controller (4) according to concentration detection signal, noise measuring signal, wind direction detection signal and Temperature detection signal controls display (12) and shows current region particle concentration, noise level, wind direction and temperature information.
8. green construction environmental monitoring system according to claim 3, it is characterised in that: the fog gun machine (1) includes bottom Seat (101), U-bracket (102) and be rotationally connected on U-bracket (102) be used for atomizing de-dusting spraying gun barrel (103), It is rotatably connected to turntable (104) on the pedestal (101), the turntable (104) is connected with straight drive electricity by the way that shaft is arranged Machine (105), the U-bracket (102) are fixed on turntable (104) upper surface.
9. green construction environmental monitoring system according to claim 8, it is characterised in that: the turntable (104) turns Rotary encoder (106) are provided on axis, for detecting the angular displacement of shaft, and angle displacement detects signal, the concentration Control platform (5) sends control instruction to zone controller (4) according to the positioning signal of GPS module (6), to control straight drive electricity Machine (105) drives turntable (104) to rotate predetermined angular displacement.
CN201910465700.0A 2019-05-30 2019-05-30 Green construction environmental monitoring system Pending CN110215779A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910465700.0A CN110215779A (en) 2019-05-30 2019-05-30 Green construction environmental monitoring system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910465700.0A CN110215779A (en) 2019-05-30 2019-05-30 Green construction environmental monitoring system

Publications (1)

Publication Number Publication Date
CN110215779A true CN110215779A (en) 2019-09-10

Family

ID=67818724

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910465700.0A Pending CN110215779A (en) 2019-05-30 2019-05-30 Green construction environmental monitoring system

Country Status (1)

Country Link
CN (1) CN110215779A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111521738A (en) * 2020-05-06 2020-08-11 北方工业大学 Construction environment monitoring and early warning method based on BIM and sensor technology
CN112070941A (en) * 2020-07-17 2020-12-11 上海有间建筑科技有限公司 Wisdom building site is environment supervisory systems for construction
CN113932847A (en) * 2021-09-22 2022-01-14 单连杰 Building engineering construction environment monitoring system
CN115437433A (en) * 2022-09-26 2022-12-06 中国五冶集团有限公司 Remote control system for field fog gun machine controlled by environmental factors
CN116777160A (en) * 2023-06-21 2023-09-19 苏州傲之途智慧科技有限公司 Environment intelligent supervision system and method for urban construction site

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103246256A (en) * 2013-04-10 2013-08-14 合肥工业大学 Field production safety monitoring system for building construction and application method thereof
CN205549910U (en) * 2016-02-23 2016-09-07 福建省雾精灵环境科技有限公司 Barrier dust shaker is kept away to intelligence
CN106383463A (en) * 2016-09-06 2017-02-08 华中科技大学 Construction environmental monitoring system and method based on safety helmet
CN107544326A (en) * 2017-08-30 2018-01-05 深圳市易联智道科技有限公司 Ensure the multifunction monitoring system of construction site security
CN206881968U (en) * 2017-05-25 2018-01-16 湖北恒信国通信息产业有限公司 A kind of building site environmental monitoring and spray integrated apparatus
CN109137809A (en) * 2018-09-03 2019-01-04 武汉梦之蓝科技有限公司 A kind of electronic fog gun vehicle

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103246256A (en) * 2013-04-10 2013-08-14 合肥工业大学 Field production safety monitoring system for building construction and application method thereof
CN205549910U (en) * 2016-02-23 2016-09-07 福建省雾精灵环境科技有限公司 Barrier dust shaker is kept away to intelligence
CN106383463A (en) * 2016-09-06 2017-02-08 华中科技大学 Construction environmental monitoring system and method based on safety helmet
CN206881968U (en) * 2017-05-25 2018-01-16 湖北恒信国通信息产业有限公司 A kind of building site environmental monitoring and spray integrated apparatus
CN107544326A (en) * 2017-08-30 2018-01-05 深圳市易联智道科技有限公司 Ensure the multifunction monitoring system of construction site security
CN109137809A (en) * 2018-09-03 2019-01-04 武汉梦之蓝科技有限公司 A kind of electronic fog gun vehicle

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111521738A (en) * 2020-05-06 2020-08-11 北方工业大学 Construction environment monitoring and early warning method based on BIM and sensor technology
CN112070941A (en) * 2020-07-17 2020-12-11 上海有间建筑科技有限公司 Wisdom building site is environment supervisory systems for construction
CN113932847A (en) * 2021-09-22 2022-01-14 单连杰 Building engineering construction environment monitoring system
CN115437433A (en) * 2022-09-26 2022-12-06 中国五冶集团有限公司 Remote control system for field fog gun machine controlled by environmental factors
CN116777160A (en) * 2023-06-21 2023-09-19 苏州傲之途智慧科技有限公司 Environment intelligent supervision system and method for urban construction site

Similar Documents

Publication Publication Date Title
CN110215779A (en) Green construction environmental monitoring system
CN208606809U (en) A kind of green construction environment protection and monitoring system
CN210233046U (en) Rail mounted utility tunnel patrols and examines robot and system
CN208044404U (en) A kind of natural gas crusing robot
CN109754562A (en) A kind of municipal administration synthesis pipe gallery alarm system
CN106922162B (en) Method, wind field, controller and the method for controlling cabin yaw system of verificating sensor
CN202393703U (en) Device for gas leakage monitoring by means of three-dimensional cradle head scanning and laser telemetering
CN108506172B (en) Online detection system for health state of wind power generation blade
CN107671831B (en) A kind of power station subregion intelligent inspection system and method
CN103010885B (en) Long-range positioning and monitoring system for engineering elevator
CN206795819U (en) Rail mounted electric inspection process robot
CN208444335U (en) A kind of cruising inspection system
CN105351754A (en) Urban underground comprehensive pipe gallery intelligent monitoring system
CN107765145A (en) A kind of shelf depreciation automatic detection device, system and method
CN112327729A (en) Underground cable monitoring system
CN111721969A (en) Tower drum health state monitoring method based on fixed detection and movable detection
KR102196719B1 (en) System for measuring and forecasting of fine dust
CN107239072A (en) A kind of outdoor automatic tour inspection system
CN111521738A (en) Construction environment monitoring and early warning method based on BIM and sensor technology
CN109781174A (en) A kind of municipal administration synthesis pipe gallery detection system
CN205582222U (en) Long -range failure alarm system supplies water
CN109231012A (en) Power station portal formula lifting group of planes collision protection intelligence control system
CN113672009A (en) Intelligent dehumidification robot system and method for power distribution station room
CN206363539U (en) Traffic signal light fault early warning system
CN206562235U (en) A kind of lift car speed of service and station acquisition device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20190910