CN111719870A - One-step forming installation method for electromechanical pipeline of super high-rise standard layer - Google Patents

One-step forming installation method for electromechanical pipeline of super high-rise standard layer Download PDF

Info

Publication number
CN111719870A
CN111719870A CN202010641777.1A CN202010641777A CN111719870A CN 111719870 A CN111719870 A CN 111719870A CN 202010641777 A CN202010641777 A CN 202010641777A CN 111719870 A CN111719870 A CN 111719870A
Authority
CN
China
Prior art keywords
installation
platform
site
unit module
supporting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202010641777.1A
Other languages
Chinese (zh)
Other versions
CN111719870B (en
Inventor
李�浩
赵小飞
桂勇刚
吴永江
陈业
杨延超
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Fourth Bureau Installation Engineering Co Ltd
Original Assignee
China Construction Fourth Bureau Installation Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Fourth Bureau Installation Engineering Co Ltd filed Critical China Construction Fourth Bureau Installation Engineering Co Ltd
Priority to CN202010641777.1A priority Critical patent/CN111719870B/en
Publication of CN111719870A publication Critical patent/CN111719870A/en
Application granted granted Critical
Publication of CN111719870B publication Critical patent/CN111719870B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G1/00Scaffolds primarily resting on the ground
    • E04G1/15Scaffolds primarily resting on the ground essentially comprising special means for supporting or forming platforms; Platforms
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G1/00Scaffolds primarily resting on the ground
    • E04G1/18Scaffolds primarily resting on the ground adjustable in height
    • E04G1/22Scaffolds having a platform on an extensible substructure, e.g. of telescopic type or with lazy-tongs mechanism
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G1/00Scaffolds primarily resting on the ground
    • E04G1/24Scaffolds primarily resting on the ground comprising essentially special base constructions; comprising essentially special ground-engaging parts, e.g. inclined struts, wheels
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G1/00Scaffolds primarily resting on the ground
    • E04G1/15Scaffolds primarily resting on the ground essentially comprising special means for supporting or forming platforms; Platforms
    • E04G2001/157Extensible platforms, e.g. telescopic platforms
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G1/00Scaffolds primarily resting on the ground
    • E04G1/24Scaffolds primarily resting on the ground comprising essentially special base constructions; comprising essentially special ground-engaging parts, e.g. inclined struts, wheels
    • E04G2001/242Scaffolds movable on wheels or tracks

Abstract

The invention relates to a method for mounting electromechanical pipelines of a super high-rise standard layer in one-step molding, which comprises the steps of reviewing drawings, building a BIM model, decomposing prefabricated components, processing the components, mounting on site, testing, debugging and operating, and takes the BIM technology as a core, only simple component assembly is carried out on a construction site, so that the dynamic and electric operation on site is reduced, the welding operation on site is reduced, the high-rise operation on site and the cross operation on site are reduced, the processing components have certain reproducibility by reasonably decomposing and prefabricating the BIM comprehensive scheme, single-professional batch production is realized, the batch production of a single floor and the batch production of the whole standard layer are realized, the processing and mounting efficiency is effectively improved, a supporting and hanging bracket supporting beam is mounted by lifting a fixed linkage lifting platform to a corridor unit module, the mechanical and automatic supporting and hanging bracket mounting is realized, and the mounting efficiency can be further improved, synchronous lifting is realized in the electromechanical installation process, modularization and quick installation are realized, and the construction progress is effectively improved.

Description

One-step forming installation method for electromechanical pipeline of super high-rise standard layer
Technical Field
The invention relates to a one-step forming installation method for an electromechanical pipeline of a super high-rise standard layer, and belongs to the technical field of electromechanical installation of constructional engineering.
Background
The electromechanical installation project is used as an important component of a modern building, has a great influence on the function of the building, how to fully utilize a prefabricated assembly type construction technology to complete the construction task of the electromechanical installation project becomes an important research subject in the development of the current electromechanical installation enterprise, and as a super high-rise building, a standard floor occupies 80 percent of the area, so the installation progress and the quality of the standard floor directly influence the integral image of the building.
Disclosure of Invention
The invention aims to provide a one-step forming installation method of an electromechanical pipeline of a super high-rise standard layer, which realizes mechanical automatic installation of a supporting and hanging frame by installing a supporting and hanging frame supporting beam by lifting a fixed linkage lifting platform to a corridor unit module, is safer and quicker compared with the traditional manual installation mode, can further improve the installation efficiency and quicken the progress of electromechanical installation engineering, takes a BIM technology as a core, combines site construction conditions and processing plant production conditions to manufacture prefabricated processing drawings, completes pipeline blanking, threading, cutting, painting, rust removal and the like in a factory, only carries out simple component assembly on a construction site, reduces site dynamic and electric operation, reduces site welding operation, reduces site high-place operation, cross operation and the like, greatly improves the installation benefit, reasonably decomposes prefabrication by a BIM comprehensive scheme, make its processing component have certain replicatability, realize single professional batch production, the batch production of single floor is even the batch production of whole standard layer, effectively improves processing installation effectiveness, realizes promoting in step in the electromechanical installation process, and the quick installation of modularization effectively improves the construction progress, can effectively solve the problem in the background art.
In order to solve the technical problems, the invention provides the following technical scheme:
a one-step forming installation method for an electromechanical pipeline of a super high-rise standard layer comprises the following steps: a. review of drawings
Firstly, the original design drawing is reviewed, the design intention, the design key points, the clarification of doubt points, the elimination of design defects and the unification idea are further known, the overall BIM deepening concept is elaborately solved by combining the review condition of the original design drawing, the superiority and inferiority of the BIM deepening scheme and the rationality of the decomposition processing of a single specialty are discussed, 100% of the BIM deepening design meets the standard requirement, the requirement of an owner on clearance height and the requirement of later-stage operation and maintenance are met, the field construction condition is met, and the electromechanical installation efficiency is effectively improved;
b. BIM model building
Building a single professional model, building models of all professionals (a building model, a water heating electricity professional model and a support hanger model) according to the situation of the joint examination of drawings, the requirement of an owner, the actual situation of a site, material parameters and the like, integrating parameters of all electromechanical pipelines, valves and the like of a standard layer, including length, nominal diameter, outer diameter, thickness, connection modes and the like, inputting deep design software (revit) for parameterization through directly or re-building a family type and the like, summarizing the single professional model and combining corresponding design construction specifications, the pertinence requirement of the owner, the actual situation of the site, the material parameter situation and the like to carry out BIM comprehensive wiring deep design;
c. disassembly of prefabricated parts
According to the design, construction and acceptance specifications of each specialty, field transportation conditions, actual installation conditions, material parameter conditions and the like, performing single-specialty decomposition and ensuring the installation feasibility and rationality of the decomposed components;
d. component processing
Processing and assembling centralized components of a processing plant according to a component decomposition drawing, and prefabricating and assembling the processing plant according to a support hanger drawing prototype and a construction and installation plan condition;
e. installation in situ
Mounting the prefabricated and assembled support and hanger on an on-site standard layer, prefabricating and mounting the support and pipeline according to a drawing and a BIM comprehensive wiring scheme to finish the pre-mounting of the aisle unit module, and finally finishing the on-site mounting by a method of integrally lifting the aisle unit module;
f. testing, debugging and running
Various pipelines in the pipeline are electrified, ventilated and water-through debugged, and normal use after installation is ensured.
Further, the step e includes:
installing branch pipeline components: before the branch pipeline is prefabricated and installed, the branch pipeline is prefabricated and assembled on the ground at a corresponding position, and a movable scaffold platform is set up according to the on-site branch pipeline laying condition to carry out on-site assembly and branch pipeline installation;
secondly, mounting a hanging bracket: aiming at the tail end point of the DN25 pipeline, a gun is adopted to perform ground fixed point prefabrication, punching and mounting of a supporting and hanging bracket, so that the tail end point mounting procedure is effectively saved;
installing a corridor unit module: the corridor adopts an integral lifting installation method of the whole corridor unit module, accurate paying-off positioning is needed between installation, an assembly platform is erected at a corresponding position on the ground to assemble the unit modules of the whole corridor, the corridor unit module comprises all electromechanical pipelines, connecting pieces, valve pieces, supporting hangers and the like of a single-sided corridor, the assembly platform mainly comprises three fixed linkage lifting platforms with the load of 2000kg, the size of 2000 x 1500mm of a table top and the lifting height of 3500mm, fixed battens, infrared instruments and the like, the lifting platforms are used for synchronous linkage type integral lifting installation after the corridor unit module is assembled, and the supporting hangers are used for efficient supporting hanger fixation after the corridor unit module is lifted to a specified height.
Further, the third step of e includes:
i, assembling electromechanical pipelines, connecting pieces and valve pieces, placing all pipelines at the top of channel steel according to a BIM comprehensive wiring scheme, and moving the channel steel to the top of a unit module supporting platform;
II, connecting all the pipelines according to a BIM comprehensive wiring scheme through flanges, connecting pieces and valve pieces, and fixing the aisle unit module between the movable baffle and the fixed baffle through a screw rod transmission mechanism;
III, adjusting the support and hanger fixing platform to a horizontal position through an adjusting screw, pre-fixing a support cross beam of the support and hanger on the top of the magnetic sleeve through a bolt, and driving the support cross beam of the support and hanger to be right below the support and hanger through a linear motor;
IV, carrying out synchronous linkage type integral lifting on the fixed linkage lifting platform by adopting a synchronous motor and a synchronous oil cylinder, and lifting the aisle unit module to a specified height;
and V, fixing the support cross beam of the support hanger to the bottom of the support hanger by using a driving motor and a hydraulic cylinder to finish lifting installation.
Further, the unit module supporting platform is fixedly connected to the top of the fixed linkage lifting platform, and the supporting and hanging bracket fixing platform is rotatably connected to the left side and the right side of the fixed linkage lifting platform through the adjusting screw rods.
Furthermore, the top of the unit module supporting platform is provided with a sliding groove, the fixed baffle is fixedly connected to the top of the unit module supporting platform, the movable baffle is connected to the top of the unit module supporting platform through the sliding groove, and the output end of the screw rod transmission mechanism is fixedly connected with the movable baffle.
Further, the support and hanger fixing platform is composed of a rotating platform, a hydraulic cylinder, a driving motor and a linear motor, the hydraulic cylinder is connected to the top of the rotating platform in a sliding mode, the driving motor is fixedly connected to the top of the hydraulic cylinder, the linear motor is fixedly connected to the top of the rotating platform, and the output end of the linear motor is fixedly connected with the hydraulic cylinder.
Further, the step c includes:
one-professional decomposition: according to the design, construction and acceptance specifications of each specialty, field transportation conditions, actual installation conditions, material parameter conditions and the like, carrying out single-professional decomposition and ensuring the installation feasibility and rationality of the decomposed components, and compiling corresponding prefabricated components tables for the purposes of improving the prefabrication and processing efficiency, improving the field installation progress, reducing material waste and the like;
disassembling the passage component: the integrated lifting installation method is adopted in the concentrated area of the electromechanical pipeline of the passageway, the concentrated area is mainly divided into four faces of east, west, south and north according to the actual situation of the site, lifting installation is carried out according to one unit module of each face, an assembling platform is erected below the corresponding position according to the paying-off situation of the site by utilizing three fixed linkage lifting platforms with the load of 2000kg, the table-board size of 2000 x 1500mm and the lifting height of 3500mm, the passing module assembly of the whole face is carried out on the platform, and the linkage lifting installation is carried out by adopting a synchronous motor and a synchronous oil cylinder after the assembly is finished.
Further, the step d includes:
machining an electromechanical pipeline component: processing and assembling centralized components of a processing plant according to a component decomposition drawing;
secondly, prefabricating and assembling a hanging bracket: according to a gallows drawing big appearance and the construction installation plan condition, carry out the prefabricated equipment of processing factory, utilize the adjustability, the dismountability and the repeatability of a finished product gallows to improve the efficiency of construction greatly, guarantee construction quality.
Compared with the prior art, the invention has the following beneficial effects:
1. the top of the unit module supporting platform is provided with a screw rod transmission mechanism to drive the movable baffle plate to move, the aisle unit modules are driven to move, under the driving action of the screw rods, the connected aisle unit modules move more uniformly, the connection and installation between pipelines are facilitated, the aisle unit modules are more convenient compared with manual movement and more labor-saving at the same time, the left side and the right side of the fixed linkage lifting platform are provided with the support and hanger fixing platforms, when the fixed linkage lifting platform lifts the aisle unit modules, firstly, bolts are connected onto threaded holes on the support and hanger supporting cross beams in a threaded manner, the support and hanger fixing platforms are adjusted to be in a horizontal state, a magnetic sleeve is adjusted to be right below the support and hanger mounting holes through a linear motor, the bolts at the bottoms of the support and hanger supporting cross beams are placed inside the magnetic sleeves, and when the fixed linkage lifting platform lifts the aisle unit, the supporting and hanging bracket supporting beam can be synchronously lifted to the bottom of the aisle unit module, so that subsequent installation of a supporting and hanging bracket and a supporting and hanging bracket supporting beam is facilitated, after the supporting and hanging bracket supporting beam and the aisle unit module are lifted to the designated height, the supporting and hanging bracket supporting beam is driven to ascend through the hydraulic cylinder to enable bolts on the supporting and hanging bracket supporting beam to be in contact with threaded holes in the bottom of the supporting and hanging bracket, then a driving motor and the hydraulic cylinder are started to fix the supporting and hanging bracket supporting beam at the bottom of the supporting and hanging bracket through the bolts, the supporting and hanging bracket supporting beam can be installed by lifting the aisle unit module through the fixed linkage lifting platform, mechanical automatic supporting and hanging bracket installation is realized, compared with a traditional manual installation mode, the installation efficiency can be further improved, and the;
2. as a super high-rise building, a standard floor occupies 80 percent of the area, so the installation progress and quality of the standard floor directly influence the integral image, the construction is carried out by adopting a standard floor prefabrication assembly type installation method, the influence of a plurality of uncontrollable factors on the installation progress and quality is avoided due to the change of a production mode, the normal installation progress is ensured, the installation quality is greatly improved, the processing components have certain reproducibility by reasonably decomposing and prefabricating a BIM comprehensive scheme, the single-professional batch production is realized, the batch production of a single floor and the batch production of the whole standard floor are effectively improved, the processing and installation efficiency is effectively improved, the electromechanical installation engineering tends to be refined, standardized and batched, the integral benefit of the electromechanical installation engineering of construction is effectively improved, and the prefabricated assembly type installation is successfully carried out aiming at the landmark building, the method has the advantages that the concept of building assembly type installation is effectively boosted, the popularity and the core competitiveness of enterprises are improved, the once forming construction technology of the electromechanical pipeline of the standard layer of the super high-rise building is adopted, the construction node can be effectively controlled, the installation quality is improved, the potential safety hazard is reduced, the environmental pollution is reduced, the material waste is reduced, and the economic benefit and the social benefit are better.
Drawings
The accompanying drawings, which are included to provide a further understanding of the invention and are incorporated in and constitute a part of this specification, illustrate embodiments of the invention and together with the description serve to explain the principles of the invention and not to limit the invention.
Fig. 1 is a schematic flow chart of a one-step forming installation method of an electromechanical pipeline of a super high-rise standard layer.
Fig. 2 is a top view of a fixed linkage lifting platform in a one-step forming installation method of an electromechanical pipeline of a super high-rise standard layer.
Fig. 3 is a mounting schematic diagram of a support and hanger of the one-step forming mounting method of the electromechanical pipeline of the super high-rise standard layer.
Fig. 4 is a front view of a fixed linkage lifting platform in a one-step forming installation method of an electromechanical pipeline of a super high-rise standard layer.
Reference numbers in the figures: 1. a fixed linkage lifting platform; 2. a unit module support platform; 3. a support and hanger fixing platform; 4. fixing a baffle plate; 5. a movable baffle; 6. a screw drive mechanism; 7. a chute; 8. a support and hanger frame; 9. the supporting and hanging frame supports the cross beam; 10. rotating the platform; 11. a hydraulic cylinder; 12. a drive motor; 13. a magnetic sleeve; 14. adjusting the screw rod; 15. a linear motor.
Detailed Description
The present invention will be further described with reference to the following detailed description, wherein the drawings are for illustrative purposes only and are not intended to be limiting, wherein certain elements may be omitted, enlarged or reduced in size, and are not intended to represent the actual dimensions of the product, so as to better illustrate the detailed description of the invention.
Examples
Before the electromechanical mounting is performed, the following should be noted:
according to the field installation condition, the transportation condition, the material size parameter and the prefabrication processing production condition, and in combination with the corresponding construction design specification: the prefabricated parts are decomposed in the design specifications of water supply and drainage of buildings, the design specifications of heating, ventilation and air conditioning of civil buildings, the electrical design specifications of civil buildings, the earthquake-resistant design specifications of electromechanical engineering of buildings and the like.
According to the requirements of a drawing review, an owner, field installation conditions and the like, a BIM technology is adopted to coordinate various specialties, collision inspection, space clear height analysis and comprehensive design of electromechanical pipelines of all specialties are carried out, and the dimensional parameters of the electromechanical pipelines, electromechanical valves, supports and hangers and the like are combined to carry out model parameterization setting and carry out 1: 1, and ensuring that the BIM model reaches LOD500 with high precision and the error is controlled within 2 mm.
The design and construction specifications, the transportation conditions, the production conditions, the material related parameters and the like are comprehensively considered to derive the prefabricated drawing, and the on-site actual measurement and correction are carried out according to the corresponding prefabricated drawing, so that the corresponding prefabricated member drawing can meet the transportation conditions, the installation condition and the safety of the on-site, and the installation efficiency can be effectively improved.
And performing factory prefabrication according to the proofreading and error-free prefabrication drawing, operating according to the process quality requirements of mechanical manufacturing in the machining process, sequentially ensuring the machining quality, transporting according to the transportation requirements of prefabricated products of materials after finishing the machining of the prefabricated pipeline and finishing the assembly of the modules, well marking and protecting the components, and then transporting to a corresponding standard layer on site for assembly construction.
Before field installation, corresponding paying-off is required to be carried out according to a BIM comprehensive model drawing, a datum line is found, all groups need to be carried out according to the datum line in the installation, and the installation accuracy is ensured.
Before the electromechanical module of the whole passageway is lifted and installed, a lifting platform needs to be operated and exercised in advance, and the synchronous uniformity, stability, safety and the like of a plurality of devices in the process are ensured.
As shown in fig. 1-4, a method for one-step forming and installing an electromechanical pipeline of a super high-rise standard layer comprises the following steps: a. review of drawings
Firstly, the original design drawing is reviewed, the design intention, the design key points, the clarification of doubt points, the elimination of design defects and the unification idea are further known, the overall BIM deepening concept is elaborately solved by combining the review condition of the original design drawing, the superiority and inferiority of the BIM deepening scheme and the rationality of the decomposition processing of a single specialty are discussed, 100% of the BIM deepening design meets the standard requirement, the requirement of an owner on clearance height and the requirement of later-stage operation and maintenance are met, the field construction condition is met, and the electromechanical installation efficiency is effectively improved;
b. BIM model building
Building a single professional model, building a building model, a water heating electricity professional model and a support and hanger model according to models of each professional according to the situation of drawing review, owner requirements, field actual conditions, material parameters and the like, integrating parameters of all electromechanical pipelines, valves and the like of a standard layer, including length, nominal diameter, outer diameter, thickness, connection modes and the like, inputting deep design software revit for parameterization through directly or re-building a family type and the like, summarizing the single professional model, and combining corresponding design construction specifications, the pertinence requirements of owners, the field actual conditions, the material parameter conditions and the like to carry out BIM comprehensive wiring deep design;
c. disassembly of prefabricated parts
According to the design, construction and acceptance specifications of each specialty, field transportation conditions, actual installation conditions, material parameter conditions and the like, performing single-specialty decomposition and ensuring the installation feasibility and rationality of the decomposed components;
d. component processing
Processing and assembling centralized components of a processing plant according to a component decomposition drawing, and prefabricating and assembling the processing plant according to a support hanger drawing prototype and a construction and installation plan condition;
e. installation in situ
Mounting the prefabricated and assembled support and hanger on an on-site standard layer, prefabricating and mounting the support and pipeline according to a drawing and a BIM comprehensive wiring scheme to finish the pre-mounting of the aisle unit module, and finally finishing the on-site mounting by a method of integrally lifting the aisle unit module;
f. testing, debugging and running
Various pipelines in the pipeline are electrified, ventilated and water-through debugged, and normal use after installation is ensured.
The method has the advantages that the accuracy of the scheme is improved by the aid of drawing review and building of the BIM model, prefabrication construction is carried out on the premise that the standard layer BIM scheme is determined, a supervision party, a construction party and a design party need to be organized to discuss when comprehensive wiring of the standard layer scheme is carried out in the early stage, and the comprehensive wiring scheme of the BIM model is comprehensively determined by fully combining professional construction specifications, field conditions, later-stage operation, requirements of the first party and the like of water and electricity so as to ensure absolute feasibility of the scheme.
The centralized processing improves the processing standardization, the traditional on-site measurement blanking installation is transferred to the centralized processing production of a processing factory, the centralized and standardized management of production is convenient, the whole process is strictly carried out according to the quality control standard, the processing production is carried out according to the prefabricated processing drawing, the mechanized blanking processing is far more stable and reliable than the technology of on-site constructors, the processing quality of electromechanical pipelines is ensured, the electromechanical on-site assembly type construction is realized, the on-site potential safety hazard and the environmental pollution are reduced, the simple assembly connection is carried out on the assembly type construction installation site, the on-site construction procedures of cutting, polishing, welding, painting and the like are avoided, the on-site potential safety hazard, noise pollution, light pollution and gas pollution are effectively controlled, the on-site operation environment is greatly improved, and the important effect is finally played for the efficiency and quality promotion of the electromechanical.
In this embodiment, the step e includes:
installing branch pipeline components: before the branch pipeline is prefabricated and installed, the branch pipeline is prefabricated and assembled on the ground at a corresponding position, and a movable scaffold platform is set up according to the on-site branch pipeline laying condition to carry out on-site assembly and branch pipeline installation;
secondly, mounting a hanging bracket: aiming at the tail end point of the DN25 pipeline, a gun is adopted to perform ground fixed point prefabrication, punching and mounting of a supporting and hanging bracket, so that the tail end point mounting procedure is effectively saved;
installing a corridor unit module: the corridor adopts an integral lifting installation method of the whole corridor unit module, accurate paying-off positioning is needed between installation, an assembly platform is erected at a corresponding position on the ground to assemble the unit modules of the whole corridor, the corridor unit module comprises all electromechanical pipelines, connecting pieces, valve pieces, supporting hangers and the like of a single-sided corridor, the assembly platform mainly comprises three fixed linkage lifting platforms with the load of 2000kg, the size of a table top of 2000 x 1500mm and the lifting height of 3500mm, fixed battens, infrared instruments and the like, the lifting platforms are used for synchronous linkage type integral lifting installation after the corridor unit module is assembled, and the supporting hangers and the fixing platforms 3 are used for efficient supporting hangers fixation after the corridor unit module is lifted to the specified height.
In the combined installation stage, when the prefabricated pipe section is in butt joint with the air conditioner water vertical pipe, the butt joint of the flanges is not easy to keep consistent, so that the lap joint flange is arranged on the prefabricated pipe section, and the butt joint precision is ensured.
As shown in fig. 2-3, in this embodiment, the third step of step e includes:
i, assembling electromechanical pipelines, connecting pieces and valve pieces, placing all pipelines at the top of channel steel according to a BIM comprehensive wiring scheme, and moving the channel steel to the top of a unit module supporting platform 2;
II, connecting all pipelines according to a BIM comprehensive wiring scheme through flanges, connecting pieces and valve pieces, and fixing the aisle unit module between the movable baffle 5 and the fixed baffle 4 through a screw rod transmission mechanism 6;
III, adjusting the support and hanger fixing platform 3 to a horizontal position through an adjusting screw 14, pre-fixing a support and hanger supporting beam 10 on the top of a magnetic sleeve 13 through a bolt, and driving the support and hanger supporting beam 10 to be right below a support and hanger 8 through a linear motor 15;
IV, carrying out synchronous linkage type integral lifting on the fixed linkage lifting platform 1 by adopting a synchronous motor and a synchronous oil cylinder, and lifting the aisle unit module to a specified height;
and V, fixing the support cross beam 9 of the support hanger to the bottom of the support hanger 8 by using a driving motor 12 and a hydraulic cylinder 11 to finish lifting installation.
In this embodiment, the unit module supporting platform 2 is fixedly connected to the top of the fixed type linkage lifting platform 1, and the supporting and hanging bracket fixing platform 3 is rotatably connected to the left and right sides of the fixed type linkage lifting platform 1 through the adjusting screw 14.
In this embodiment, the top of the unit module supporting platform 2 is provided with a sliding groove 7, the fixed baffle 4 is fixedly connected to the top of the unit module supporting platform 2, the movable baffle 5 is slidably connected to the top of the unit module supporting platform 2 through the sliding groove 7, and the output end of the screw rod transmission mechanism 6 is fixedly connected to the movable baffle 5.
Wherein, screw drive mechanism 6 can set up through the synchronous motor drive, through placing the branch pipeline inside the channel-section steel, utilize screw drive mechanism 6 to press from both sides passageway unit module tightly, later connect the branch pipeline, under the lead screw drive effect, the passageway unit module after connecting removes more uniformly, makes things convenient for the connection installation between the pipeline, compares artifical removal more convenient, uses manpower sparingly simultaneously more.
In this embodiment, the support and hanger fixing platform 3 is composed of a rotating platform 10, a hydraulic cylinder 11, a driving motor 12, and a linear motor 15, the hydraulic cylinder 11 is slidably connected to the top of the rotating platform 10, the driving motor 12 is fixedly connected to the top of the hydraulic cylinder 11, the linear motor 15 is fixedly connected to the top of the rotating platform 10, and an output end of the linear motor 15 is fixedly connected to the hydraulic cylinder 11.
In the invention, the support hanger 8 is arranged in an inverted T shape, the bottom of the support hanger 8 and the support hanger supporting beam 9 are provided with matched threaded holes, the support hanger 8 is firstly installed at the bottom of the ceiling of the standard layer, and the support hanger 8 and the support hanger supporting beam 9 are fixedly connected through the threaded holes by bolts so as to realize the support of the aisle unit module after the lifting is completed.
In the invention, when the supporting and hanging bracket fixing platform 3 is not used, the supporting and hanging bracket fixing platform 3 can be fixed on the left side and the right side of the fixed linkage lifting platform 1 in the vertical direction by adjusting the rotating screw rods 14, so that a larger space is provided, the passageway unit modules can be conveniently installed at the beginning, and the supporting and hanging bracket fixing platform 3 can be adjusted to be in a horizontal state before the fixed linkage lifting platform 1 rises.
The top of the unit module supporting platform 2 is provided with a screw rod transmission mechanism 6 to drive the movable baffle plate to move, the aisle unit modules are driven to move, under the driving action of the screw rods, the connected aisle unit modules move more uniformly, the connection and installation among pipelines are convenient, the aisle unit modules are more convenient compared with manual movement and more labor-saving at the same time, the left side and the right side of the fixed linkage lifting platform 1 are provided with the support and hanger fixing platforms 3, when the fixed linkage lifting platform 1 lifts the aisle unit modules, firstly, bolts are connected onto threaded holes on the support and hanger supporting cross beams 9 in a threaded manner, the support and hanger fixing platforms 3 are adjusted to be in a horizontal state, the linear motors 15 are used for adjusting the magnetic sleeves 13 to be right below the support and hanger mounting holes, the bolts at the bottoms of the support and hanger supporting cross beams 9 are placed in the magnetic sleeves 13, when the fixed linkage lifting platform 1 lifts the aisle unit modules, can promote a gallows supporting beam 9 to passageway unit module bottom in step, thereby make things convenient for follow-up an gallows 8 and an installation of gallows supporting beam 9, after a gallows supporting beam 9 all promoted appointed height with passageway unit module, it makes a bolt on the gallows supporting beam 9 contact with the screw hole of a gallows 8 bottom to rise through a pneumatic cylinder 11 drive gallows supporting beam 9, later start driving motor 12 and pneumatic cylinder 11 and fix a gallows supporting beam 9 in a gallows 8 bottom through the bolt, can install a gallows supporting beam 9 through the promotion to passageway unit module with the help of fixed linkage lift platform 1, realize mechanical automation's a gallows installation, it is safe more swift to compare traditional manual installation mode, can further improve the installation effectiveness, accelerate the progress of electromechanical installation engineering.
In this embodiment, the step c includes:
one-professional decomposition: according to the design, construction and acceptance specifications of each specialty, field transportation conditions, actual installation conditions, material parameter conditions and the like, carrying out single-professional decomposition and ensuring the installation feasibility and rationality of the decomposed components, and compiling corresponding prefabricated components tables for the purposes of improving the prefabrication and processing efficiency, improving the field installation progress, reducing material waste and the like;
disassembling the passage component: the integrated lifting installation method is adopted in the concentrated area of the electromechanical pipeline of the passageway, the concentrated area is mainly divided into four faces of east, west, south and north according to the actual situation of the site, lifting installation is carried out according to one unit module of each face, an assembling platform is erected below the corresponding position according to the paying-off situation of the site by utilizing three fixed linkage lifting platforms with the load of 2000kg, the table-board size of 2000 x 1500mm and the lifting height of 3500mm, the passing module assembly of the whole face is carried out on the platform, and the linkage lifting installation is carried out by adopting a synchronous motor and a synchronous oil cylinder after the assembly is finished.
The reasonable decomposition and prefabrication of the BIM comprehensive scheme enables the machined components to have certain reproducibility, single-professional batch production, batch production of a single floor and even batch production of the whole standard floor are realized, the machining and installing efficiency is effectively improved, the electromechanical installation engineering tends to be refined, standardized and batched, and the overall benefit of the electromechanical installation engineering is effectively improved.
In this embodiment, the step d includes:
machining an electromechanical pipeline component: processing and assembling centralized components of a processing plant according to a component decomposition drawing;
secondly, prefabricating and assembling a hanging bracket: according to a gallows drawing big appearance and the construction installation plan condition, carry out the prefabricated equipment of processing factory, utilize the adjustability, the dismountability and the repeatability of a finished product gallows to improve the efficiency of construction greatly, guarantee construction quality.
Because the processing, the assembly, the welding, the flaw detection, the heat treatment and the like of the pipeline are all completed by adopting mechanical equipment in a prefabricated factory, the processing quality of the pipeline is improved, the pipeline is only orderly installed on site according to a component drawing, the mess caused by the pipeline manufacturing is avoided, the cross operation surfaces of various specialties are reduced, the technical requirements of installation workers are lowered, the installation quality is greatly improved, all the operations of pipeline processing, welding and the like are all completed in the prefabricated factory, the site is only simply assembled according to a diagram, the factors of high-altitude operation, cross operation, fire operation, pipeline transportation, large personnel investment and the like on site are reduced, the safe production on site is effectively ensured, the feasible scheme is determined in advance by utilizing the BIM technology, the prefabricated diagram manufacturing is carried out according to the scheme, the traditional site processing installation is transferred to a processing factory for centralized processing production, the influence of field installation environment conditions, weather conditions, cross operation conditions, professional field control conditions and the like is avoided, the prefabricated member is processed and produced in advance, and the prefabricated member is produced in batch according to the pipeline installation repeatability of the standard layer, so that the project installation progress can be greatly improved.
Through the deepening design to the standard layer BIM scheme earlier stage, reduced the design defect, increased the feasibility of scheme, "measure the body and draw materials" according to BIM integrated wiring scheme, carry out hierarchical optimization of material segmentation to combine corresponding material supplier's condition, reduced the waste of material, adopt the processing production of prefabricated component of processing factory, avoided the time consuming and labouring phenomenon that causes because of reasons such as weather, on-the-spot installation condition and process design error, material saving reduces cost.
The processing, the assembly, the welding, the flaw detection, the heat treatment and the like of the pipeline are all completed by adopting mechanical equipment in a prefabricated factory, so the processing quality of the pipeline is improved, the pipeline is only orderly installed according to a component drawing on site, the mess caused by the pipeline manufacturing is avoided, the cross operation surfaces of various specialties are reduced, the technical requirements of installation workers are reduced, the installation quality is greatly improved, all the operations of pipeline processing, welding and the like are completely completed in the prefabricated factory, the site is only simply assembled according to a diagram, the factors of high-altitude operation, cross operation, fire operation, pipeline transportation, large personnel investment and the like on site are reduced, and the safe production on site is effectively ensured.
By adopting the technical scheme: as a super high-rise building, a standard floor occupies 80 percent of the area, so the installation progress and quality of the standard floor directly influence the integral image, the construction is carried out by adopting a standard floor prefabrication assembly type installation method, the influence of a plurality of uncontrollable factors on the installation progress and quality is avoided due to the change of a production mode, the normal installation progress is ensured, the installation quality is greatly improved, the processing components have certain reproducibility by reasonably decomposing and prefabricating a BIM comprehensive scheme, the single-professional batch production is realized, the batch production of a single floor and the batch production of the whole standard floor are effectively improved, the processing and installation efficiency is effectively improved, the electromechanical installation engineering tends to be refined, standardized and batched, the integral benefit of the electromechanical installation engineering of construction is effectively improved, and the prefabricated assembly type installation is successfully carried out aiming at the landmark building, the building assembly type installation concept is effectively boosted, and the popularity and the core competitiveness of enterprises are improved.
By adopting the once-forming construction technology of the electromechanical pipelines of the standard layer of the super high-rise building, the construction nodes are effectively controlled, the installation quality is improved, the potential safety hazard is reduced, the environmental pollution is reduced, the material waste is reduced, and the consistent good comment of owners and supervisors is obtained.
The super high-rise standard layer electromechanical pipeline one-step forming installation method disclosed by the invention is used for installing in a project of a financial center of Guiyang and a project of a hot spring tourist city of Guiyang city in Guiyang of Guizhou province by adopting a super high-rise building standard layer electromechanical full-professional pipeline one-step forming construction technology, BIM is adopted to guide field construction in the whole project construction process, the problem of one difficult point is solved, the quality and the appearance of an electromechanical device are improved, high recognition of an owner is obtained, the popularity and the core competitiveness of an enterprise are improved, construction nodes are effectively controlled, the installation quality is improved, potential safety hazards are reduced, the environmental pollution is reduced, the material waste is reduced, and the consistent and good evaluation of the owner and a prisoner is obtained.
While there have been shown and described what are at present considered the preferred embodiments of the invention, the fundamental principles and essential features of the invention and advantages thereof, it will be understood by those skilled in the art that the invention is not limited by the embodiments described above, which are included to illustrate the principles of the invention, but that various changes and modifications may be made therein without departing from the spirit and scope of the invention as defined by the appended claims and their equivalents.

Claims (8)

1. A one-step forming installation method for an electromechanical pipeline of a super high-rise standard layer is characterized by comprising the following steps:
a. review of drawings
Firstly, the original design drawing is reviewed, the design intention, the design key points, the clarification of doubt points, the elimination of design defects and the unification idea are further known, the overall BIM deepening concept is elaborately solved by combining the review condition of the original design drawing, the superiority and inferiority of the BIM deepening scheme and the rationality of the decomposition processing of a single specialty are discussed, 100% of the BIM deepening design meets the standard requirement, the requirement of an owner on clearance height and the requirement of later-stage operation and maintenance are met, the field construction condition is met, and the electromechanical installation efficiency is effectively improved;
b. BIM model building
Building a single professional model, building models of all professionals (a building model, a water heating electricity professional model and a support hanger model) according to the situation of the joint examination of drawings, the requirement of an owner, the actual situation of a site, material parameters and the like, integrating parameters of all electromechanical pipelines, valves and the like of a standard layer, including length, nominal diameter, outer diameter, thickness, connection modes and the like, inputting deep design software (revit) for parameterization through directly or re-building a family type and the like, summarizing the single professional model and combining corresponding design construction specifications, the pertinence requirement of the owner, the actual situation of the site, the material parameter situation and the like to carry out BIM comprehensive wiring deep design;
c. disassembly of prefabricated parts
According to the design, construction and acceptance specifications of each specialty, field transportation conditions, actual installation conditions, material parameter conditions and the like, performing single-specialty decomposition and ensuring the installation feasibility and rationality of the decomposed components;
d. component processing
Processing and assembling centralized components of a processing plant according to a component decomposition drawing, and prefabricating and assembling the processing plant according to a support hanger drawing prototype and a construction and installation plan condition;
e. installation in situ
Mounting the prefabricated and assembled support and hanger on an on-site standard layer, prefabricating and mounting the support and pipeline according to a drawing and a BIM comprehensive wiring scheme to finish the pre-mounting of the aisle unit module, and finally finishing the on-site mounting by a method of integrally lifting the aisle unit module;
f. testing, debugging and running
Various pipelines in the pipeline are electrified, ventilated and water-through debugged, and normal use after installation is ensured.
2. The method for installing the super high-rise standard layer electromechanical pipeline in one forming mode according to claim 1, wherein the step e comprises the following steps:
installing branch pipeline components: before the branch pipeline is prefabricated and installed, the branch pipeline is prefabricated and assembled on the ground at a corresponding position, and a movable scaffold platform is set up according to the on-site branch pipeline laying condition to carry out on-site assembly and branch pipeline installation;
secondly, mounting a hanging bracket: aiming at the tail end point of the DN25 pipeline, a gun is adopted to perform ground fixed point prefabrication, punching and mounting of a supporting and hanging bracket, so that the tail end point mounting procedure is effectively saved;
installing a corridor unit module: the corridor adopts an integral lifting installation method of the whole corridor unit module, accurate paying-off positioning is needed between installation, an assembly platform is erected at a corresponding position on the ground to assemble the unit modules of the whole corridor, the corridor unit module comprises all electromechanical pipelines, connecting pieces, valve pieces, supporting hangers and the like of a single-sided corridor, the assembly platform mainly comprises three fixed linkage lifting platforms, fixed battens, infrared meters and the like, the three loads are 2000kg, the sizes of the platforms are 2000 x 1500mm, the lifting height is 3500mm, the lifting platforms are used for synchronous linkage type integral lifting installation after the corridor unit module is assembled, and the supporting hangers are fixed efficiently by the supporting hangers fixing platform (3) after the corridor unit module is lifted to the designated height.
3. The method for one-step forming and installing the electromechanical pipeline of the super high-rise standard layer according to claim 2, wherein the step e comprises the following steps:
i, assembling electromechanical pipelines, connecting pieces and valve pieces, placing all pipelines at the top of channel steel according to a BIM comprehensive wiring scheme, and moving the channel steel to the top of a unit module supporting platform (2);
II, connecting all pipelines according to a BIM comprehensive wiring scheme through flanges, connecting pieces and valve pieces, and fixing the aisle unit module between the movable baffle (5) and the fixed baffle (4) through a screw rod transmission mechanism (6);
III, adjusting the support and hanger fixing platform (3) to a horizontal position through an adjusting screw (14), pre-fixing a support and hanger supporting beam (10) on the top of the magnetic sleeve (13) through a bolt, and driving the support and hanger supporting beam (10) to be right below the support and hanger (8) through a linear motor (15);
IV, synchronous linkage type integral lifting is carried out on the fixed linkage lifting platform (1) by adopting a synchronous motor and a synchronous oil cylinder, and the aisle unit module is lifted to a specified height;
and V, fixing a supporting and hanging frame supporting beam (9) at the bottom of a supporting and hanging frame (8) by using a driving motor (12) and a hydraulic cylinder (11) to finish lifting and mounting.
4. The method for installing the electromechanical pipeline of the super high-rise standard layer in one step as claimed in claim 3, wherein the unit module supporting platform (2) is fixedly connected to the top of the fixed type linkage lifting platform (1), and the supporting and hanging bracket fixing platform (3) is rotatably connected to the left side and the right side of the fixed type linkage lifting platform (1) through adjusting screws (14).
5. The method for mounting the super high-rise standard layer electromechanical pipeline in one-step forming manner according to claim 2, wherein a sliding groove (7) is formed in the top of the unit module supporting platform (2), the fixed baffle (4) is fixedly connected to the top of the unit module supporting platform (2), the movable baffle (5) is slidably connected to the top of the unit module supporting platform (2) through the sliding groove (7), and the output end of the screw rod transmission mechanism (6) is fixedly connected with the movable baffle (5).
6. The method for mounting the electromechanical pipeline of the ultra-high-rise standard layer in one step as claimed in claim 2, wherein the support and hanger fixing platform (3) is composed of a rotating platform (10), a hydraulic cylinder (11), a driving motor (12) and a linear motor (15), the hydraulic cylinder (11) is slidably connected to the top of the rotating platform (10), the driving motor (12) is fixedly connected to the top of the hydraulic cylinder (11), the linear motor (15) is fixedly connected to the top of the rotating platform (10), and the output end of the linear motor (15) is fixedly connected to the hydraulic cylinder (11).
7. The method for installing the super high-rise standard layer electromechanical pipeline in one forming mode according to claim 1, wherein the step c comprises the following steps:
one-professional decomposition: according to the design, construction and acceptance specifications of each specialty, field transportation conditions, actual installation conditions, material parameter conditions and the like, carrying out single-professional decomposition and ensuring the installation feasibility and rationality of the decomposed components, and compiling corresponding prefabricated components tables for the purposes of improving the prefabrication and processing efficiency, improving the field installation progress, reducing material waste and the like;
disassembling the passage component: the integrated lifting installation method is adopted in the concentrated area of the electromechanical pipeline of the passageway, the concentrated area is mainly divided into four faces of east, west, south and north according to the actual situation of the site, lifting installation is carried out according to one unit module of each face, an assembling platform is erected below the corresponding position according to the paying-off situation of the site by utilizing three fixed linkage lifting platforms with the load of 2000kg, the table-board size of 2000 x 1500mm and the lifting height of 3500mm, the passing module assembly of the whole face is carried out on the platform, and the linkage lifting installation is carried out by adopting a synchronous motor and a synchronous oil cylinder after the assembly is finished.
8. The method for installing the super high-rise standard layer electromechanical pipeline in one forming mode according to claim 1, wherein the step d comprises the following steps:
machining an electromechanical pipeline component: processing and assembling centralized components of a processing plant according to a component decomposition drawing;
secondly, prefabricating and assembling a hanging bracket: according to a gallows drawing big appearance and the construction installation plan condition, carry out the prefabricated equipment of processing factory, utilize the adjustability, the dismountability and the repeatability of a finished product gallows to improve the efficiency of construction greatly, guarantee construction quality.
CN202010641777.1A 2020-07-06 2020-07-06 One-step forming installation method for electromechanical pipeline of super high-rise standard layer Expired - Fee Related CN111719870B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010641777.1A CN111719870B (en) 2020-07-06 2020-07-06 One-step forming installation method for electromechanical pipeline of super high-rise standard layer

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010641777.1A CN111719870B (en) 2020-07-06 2020-07-06 One-step forming installation method for electromechanical pipeline of super high-rise standard layer

Publications (2)

Publication Number Publication Date
CN111719870A true CN111719870A (en) 2020-09-29
CN111719870B CN111719870B (en) 2021-08-31

Family

ID=72572146

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010641777.1A Expired - Fee Related CN111719870B (en) 2020-07-06 2020-07-06 One-step forming installation method for electromechanical pipeline of super high-rise standard layer

Country Status (1)

Country Link
CN (1) CN111719870B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113802824A (en) * 2021-10-13 2021-12-17 广东一新长城建筑集团有限公司 Lifting device for prefabricated building and construction method applied to lifting device
CN113914591A (en) * 2021-10-27 2022-01-11 易建网科技有限公司 Modularization intelligent movement scaffold frame

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2014010662A (en) * 2012-06-29 2014-01-20 Toshiba Elevator Co Ltd Bim system, server device, terminal device, method, and program
CN106677534A (en) * 2016-11-16 2017-05-17 上海建工集团股份有限公司 Assembly integral building electromechanical engineering installation system and method
CN107542161A (en) * 2017-08-23 2018-01-05 中建八局第建设有限公司 BIDA engineering of integrating technical systems
CN109408903A (en) * 2018-09-29 2019-03-01 鼎宸建设管理有限公司 Assembled architecture design method based on BIM technology
CN109514188A (en) * 2018-10-23 2019-03-26 筑梦高科建筑有限公司 Electromechanical pipeline and equipment batch production prefabricating and constructing based on BIM
KR102056320B1 (en) * 2019-05-30 2019-12-16 (주)더퍼스트아이씨티 Smart Plant Multidimensional Space 3D Piping Design Collaboration System

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2014010662A (en) * 2012-06-29 2014-01-20 Toshiba Elevator Co Ltd Bim system, server device, terminal device, method, and program
CN106677534A (en) * 2016-11-16 2017-05-17 上海建工集团股份有限公司 Assembly integral building electromechanical engineering installation system and method
CN107542161A (en) * 2017-08-23 2018-01-05 中建八局第建设有限公司 BIDA engineering of integrating technical systems
CN109408903A (en) * 2018-09-29 2019-03-01 鼎宸建设管理有限公司 Assembled architecture design method based on BIM technology
CN109514188A (en) * 2018-10-23 2019-03-26 筑梦高科建筑有限公司 Electromechanical pipeline and equipment batch production prefabricating and constructing based on BIM
KR102056320B1 (en) * 2019-05-30 2019-12-16 (주)더퍼스트아이씨티 Smart Plant Multidimensional Space 3D Piping Design Collaboration System

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113802824A (en) * 2021-10-13 2021-12-17 广东一新长城建筑集团有限公司 Lifting device for prefabricated building and construction method applied to lifting device
CN113914591A (en) * 2021-10-27 2022-01-11 易建网科技有限公司 Modularization intelligent movement scaffold frame

Also Published As

Publication number Publication date
CN111719870B (en) 2021-08-31

Similar Documents

Publication Publication Date Title
CN110952811A (en) Assembly type machine room deepening design process based on BIM and construction method thereof
CN111719870B (en) One-step forming installation method for electromechanical pipeline of super high-rise standard layer
CN106989211B (en) Assembled architecture pipeline hanger system installation method based on BIM
CN111306363A (en) Assembly type fire pump room hoisting construction method and construction structure based on BIM technology
CN109766649A (en) A kind of Air Conditioning Facilities prefabrication of tube section installation method
CN110566720A (en) construction method of arc corridor pipeline
CN109079437B (en) Construction method of multilayer flap seal head of large-scale marine liquefied gas storage tank
CN115758553B (en) Modularized assembly type machine room implementation method based on BIM technology
CN101451397A (en) Steel structure modularization construction process
CN103498523A (en) Floor system
CN111104709A (en) BIM-based large-scale refrigeration machine room digital assembly method and system
CN112832557A (en) Assembly type construction method of subway station cold water machine room based on BIM
CN112613100A (en) Integrated pipeline integral assembly method based on BIM technology
CN104763157A (en) Large stadium pipe truss and spiral duct modularization installation method and combination structure
CN113565332A (en) Roof steel structure and air pipe synchronous sliding construction method
CN112464424A (en) Air duct system prefabricating method based on BIM
CN111745608B (en) Track type mounting device and method for integrated group of refrigerating room pipeline equipment
CN102733614B (en) A kind of construction method of room module of nuclear power plant
CN101752017B (en) Modularization construction method for nuclear power station nuclear island
CN101736925B (en) Modular construction method for nuclear island of nuclear power station
CN112052501A (en) Prefabricated construction method for modular factory of laboratory electromechanical system
CN112926114B (en) Electromechanical and steel structure integrated construction method
CN110850816A (en) Galvanized sheet angle iron flange tuber pipe product production management system based on BIM
CN108194702B (en) Method for installing pipeline in narrow pipe hoistway
CN114576843A (en) Assembly type welding pipeline alignment device and assembly type welding pipeline construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20210831