CN110952811A - Assembly type machine room deepening design process based on BIM and construction method thereof - Google Patents

Assembly type machine room deepening design process based on BIM and construction method thereof Download PDF

Info

Publication number
CN110952811A
CN110952811A CN201911015277.0A CN201911015277A CN110952811A CN 110952811 A CN110952811 A CN 110952811A CN 201911015277 A CN201911015277 A CN 201911015277A CN 110952811 A CN110952811 A CN 110952811A
Authority
CN
China
Prior art keywords
design
deepening
construction
pipeline
bim
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201911015277.0A
Other languages
Chinese (zh)
Inventor
吴建军
黄舍荣
巨鹏
杨培娜
陈宗飞
雷波
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhongtian Northwest Construction Invest Group Co ltd
Zhongtian Construction Group Co Ltd
Original Assignee
Zhongtian Northwest Construction Invest Group Co ltd
Zhongtian Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhongtian Northwest Construction Invest Group Co ltd, Zhongtian Construction Group Co Ltd filed Critical Zhongtian Northwest Construction Invest Group Co ltd
Priority to CN201911015277.0A priority Critical patent/CN110952811A/en
Publication of CN110952811A publication Critical patent/CN110952811A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H5/00Buildings or groups of buildings for industrial or agricultural purposes
    • E04H5/02Buildings or groups of buildings for industrial purposes, e.g. for power-plants or factories

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention relates to a deepening design process of an assembled machine room based on BIM and a construction method thereof, which divide all the electromechanical construction work into three parts of deepening design, prefabrication and assembly. Determining the brand and specification of products in the machine room according to the design drawing, extracting cloud storage data, realizing three-dimensional modeling of a precise construction drawing, comprehensively arranging an optimized path, and outputting a construction part processing decomposition drawing and other professional matching drawings; and the prefabricating processing factory realizes the processing of the components according to the component processing drawing, pastes the identification, protects the finished product to be transported to the site, and completes the assembling construction process of the pump set of the machine room and the matched pipe valve. Through the advanced deep design, the pre-buried location and the factory prefabrication processing, the modularization assembly is realized, and the purpose of one-time survival is achieved. The invention has the advantages of modular splitting, factory high-precision prefabrication, improvement of construction precision and quality, reduction of a large amount of welding work on site, improvement of site installation precision and realization of the requirement of green construction.

Description

Assembly type machine room deepening design process based on BIM and construction method thereof
Technical Field
The invention belongs to the field of electromechanical construction, and particularly relates to an assembled machine room deepened design flow based on BIM and a construction method thereof.
Background
Along with the process of urbanization in China, the building electromechanical installation industry is rapidly developed. The problems of resource waste, environmental pollution, construction safety and low efficiency are increasingly prominent. Therefore, safe, efficient, energy-saving, environment-friendly and civilized construction is an urgent need for the healthy development of the industry. Under the guidance, the development direction of "BIM-based electromechanical industrialization" gradually becomes a necessary choice and trend for sustainable development of the electromechanical installation industry.
With the vigorous development of building mechanics and electronics, the requirement of the building owner on the building products is only limited to the construction quality, the structure is stable, and the appearance quality of the construction is increasingly becoming a key item for the building owner to investigate. The construction of electromechanical installations plays a particularly important role therein.
In order to meet the aim, the progress of electromechanical factory processing and flow line construction is also promoted increasingly. The assembly type pipeline of the machine room is a new direction for research of the current construction unit, and the construction market is a service company which successively develops a whole chain for machine room design, disassembly, drawing, prefabrication, transportation and assembly construction. In the aspect of a software platform, part of software can realize efficient and orderly interaction of BIM data and field information by scanning two-dimensional codes, and track and understand the description of the field installation position from a factory to a field, so that information acquisition, acquisition and tracing are more convenient and faster.
The problems of poor construction quality, serious errors and waste and the like exist in the traditional electromechanical engineering due to the problems of unclear drawing design, strong independence of each specialty and the like. The invention provides improvement aiming at the defects of low efficiency of pipeline installation, slow dragging project progress, large error and the like of a machine room pump station in the prior art.
Disclosure of Invention
The invention aims to solve the problems and provides a BIM-based deep design process of an assembled machine room and a construction method thereof.
In order to achieve the purpose, the invention provides the following technical scheme:
a deepened design flow of an assembly machine room based on BIM and a construction method thereof comprise the following steps:
s1 deepening design
1) Deepening requirement confirmation:
filling in a deepened design application form by a project department to confirm the deepened design requirement of the project and signing a deepened design service agreement;
2) deepening point confirmation:
design institute deepens design person in charge, and the same department of project confirms deepens node range according to 'deepens design bill', and the department of project perfects a deepens design information confirmation table;
3) deepening information confirmation:
the identification project deepened design relates to information such as size, material, construction method and the like of a finished product material, and written confirmation is carried out according to a confirmation form;
s2 BIM preliminary modeling:
1) establishing a family library: according to the relevant information collection condition, perfecting the project family library, and extracting product data parameters from the cloud warehouse database;
2) building and structural modeling: building a civil model according to the building and structure diagram;
3) clear height analysis: comprehensively analyzing a pipeline elevation system according to the first square elevation requirement and the garage structure form;
4) electromechanical installation preliminary modeling: according to the construction drawing, an electromechanical installation model is preliminarily established, the plane arrangement is arranged according to the original drawing, and the pipelines of each system are arranged in different elevations and layers, so that the subsequent deepening adjustment is facilitated;
s3: BIM deepening modeling: searching for 'mistake', 'leakage', 'collision' and 'deficiency' in the drawing through the BIM model, and performing node deepening and arrangement optimization on the construction drawing;
1) establishing a family library: perfecting the project family library according to the relevant information collection condition;
2) building and structural modeling: building a civil model according to the building and structure diagram;
3) clear height analysis: comprehensively analyzing a pipeline elevation system according to the first square elevation requirement and the garage structure form;
4) electromechanical installation preliminary modeling: according to the construction drawing, an electromechanical installation model is preliminarily established, the plane arrangement is arranged according to the original drawing, and the pipelines of each system are arranged in different elevations and layers, so that the subsequent deepening adjustment is facilitated;
s3, BIM deepening modeling:
1) deepening an electromechanical mounting plane: deepening the plane layout of the comprehensive pipeline according to a deepening design principle;
2) deepening the elevation of the collision inspection: after the plane arrangement is finished, carrying out pipeline collision inspection to deepen a pipeline elevation system;
3) standard nodes: according to the requirements of a deepened design achievement diagram, standard nodes of all parts are perfected;
and S4, design file auditing and confirmation:
the method is checked by a design institute, reviewed by an engineering department, and confirmed mainly aiming at deepening integrity, reliability, rationality and applicability, and issued after signing; internal checking, namely exchanging the deepened design result drawing with a project to confirm by a design first party;
s5, deepening design bottom crossing:
the deepening design responsible person organizes the pre-construction deepening design drawing intersection of the project according to the deepening design result drawing;
s6, field rechecking and adjusting:
after the on-site main body is constructed, carrying out on-site rechecking on the installation embedded content and the structure deviation condition, and adjusting the deepened content under the condition of common identification with the project;
s7: formally deepening the drawing:
forming a formal design file;
s8: prefabricating and processing complex positions of pipelines: the construction is simpler and more convenient, shortens the time limit for a project.
And (3) preparing materials and debugging machines before prefabrication, and performing technical interaction on operating personnel. Processing the materials one by one according to a material specification list in a component part processing diagram, splicing into groups, pasting coding marks, and performing semi-finished product protection work; the prefabricated content comprises pipeline turning and tee bend turning positions, the fixed-length pipeline is processed by a field processing factory, the shaped electromechanical module is processed by the electromechanical processing factory, and the supports on the construction field are shared; the support is directly designed through a deepened design flow, processing is carried out according to a deepened design drawing, and construction can be directly adopted during construction. And performing field lofting according to the flat vertical cut chart paper output by the BIM, and determining installation control lines and line snapping marks of a pump set, a pipeline set, an accessory equipment set and the like.
And (4) transporting the semi-finished structural parts to the site according to the structural part processing drawings and lists, and landing the pump structural parts through vertical transport tools such as truck cranes and the like for acceptance inspection. After being qualified, the materials are horizontally conveyed into a machine room. If the roof of the machine room is provided with a hoisting reserved hole before construction, the roof can be hoisted into the machine room through vertical transportation equipment and then is subjected to acceptance inspection, horizontal transportation and the like.
The software adopted for BIM deepening modeling in the S3 is the Inventor software.
A BIM-based construction method for an assembled machine room comprises the following steps:
s1: and (3) installing a pump set:
1) the pump set is horizontally transported to the position near the installation position of the machine room, and the pump set is pushed to the installation position by a ground tank;
2) after the pump group is pulled to the installation position, the adjustment before taking place is carried out, and the connection control points of the front and back, the left and right and the upper and lower dimensions are ensured to be consistent with the model;
3) a jack is used for assisting the pump set to be in place, the ground tank is taken out, and the position of the pump set is fixed; the synchronous control of the descending process of the screw jack is noticed, so that the positioning deviation or deformation which cannot be absorbed by the whole pump set is avoided;
s2: and (3) installing a pipeline set:
1) after the main equipment and the pump set are in place, the main equipment and the pump set are sequentially installed according to the number sequence in the component part processing exploded view;
2) the pipeline groups are connected through adjustable flanges, pre-assembly is carried out firstly, and after all the pipeline groups and the accessory equipment groups are installed, deviation is adjusted;
3) after adjusting the deviation, finally fixing the connection part of the component parts;
s3: washing and pressure test acceptance: and after the pipeline of the whole machine room is installed, the whole machine room is washed according to a special construction scheme of the project pump room. The washing flow rate is generally not less than 3.0m/s, a drainage measure system is required to be solved before washing, a washing medium adopts clean tap water, continuous washing is required to be ensured, the color of the discharged washing water is visually observed according to a washing result, and the transparency is basically consistent with that of the water at an inlet, namely the product is qualified.
If the pressure of the water supply pump room pipeline is tested, in the pressure test, the pressure gauge is installed at the lowest point of the whole pipeline system as far as possible. The test pressure is in accordance with the design requirement, and when the design is not indicated, the test pressure of the water supply pipeline systems made of various materials is 1.5 times of the working pressure, but is not less than 0.6 MPa; observing the metal and composite pipe water supply pipeline system under test pressure for 10min, wherein the pressure drop is not more than 0.02MPa, and then, the pressure drop is reduced to working pressure for inspection, and the water supply pipeline system is not allowed to leak; the pressure of the plastic pipe water supply system is stabilized for 1 hour under the test pressure, the pressure drop is not more than 0.05MPa, then the pressure is stabilized for 2 hours under the state of 1.15 times of the working pressure, the pressure drop is not more than 0.03MPa, and meanwhile, the leakage at each joint is checked.
The assembly work is accomplished by project department installation team earlier stage, treats the later stage project and popularizes the back, according to project progress demand, carries out the assembly type production construction service to a plurality of projects simultaneously.
The method is suitable for the construction of pump sets and matched pipe valves in various water supply pump rooms, fire pump rooms, lifting pump stations, refrigerating machine rooms and boiler rooms, and has the characteristics of short construction period, high work efficiency, good economy, high safety, energy conservation, environmental protection and the like.
Compared with the prior art, the invention has the beneficial effects that:
1. and extracting cloud storage data to realize 1:1 copying of the product. Product brands meeting design requirements are selected, product real data are extracted by relying on a cloud warehouse database, 1:1 three-dimensional modeling is carried out, and comprehensive arrangement accuracy and accuracy are improved.
2. The factory prefabrication processing is adopted, the quality is guaranteed, and the loss is reduced. All parts of the equipment can be prefabricated in advance in a machining workshop of a prefabrication factory, workers with high selection technical level undertake the work of cutting, welding and the like, are not influenced by factors such as climate, environment and the like, can be produced in batches in advance according to the concrete progress requirements of the engineering, effectively improve the cutting precision and the welding quality of the pipeline, and obviously improve the quality of semi-finished products.
3. The site assembly construction is adopted, the safety is ensured, and the work efficiency is improved. All the installed pipes can be prefabricated in advance only by providing deep processing drawings, and the construction is performed in parallel with civil engineering construction; meanwhile, the installation precision is improved through factory machining, rework is avoided, the construction efficiency is improved to the maximum extent, and the construction period is shortened. The high-altitude cutting and welding operation does not exist in the field, the danger that objects falling from the high altitude fall down to people is reduced, the safety factor of the field fire prevention is improved, and the safety construction degree is greatly improved.
4. Is green and environment-friendly. Each prefabricated part is processed and produced in a prefabricating factory in advance, prefabricated components are transported to a construction site to be assembled, the construction site is low in energy consumption and free of pollutant emission, the environment-friendly effect is obvious, and the environment-friendly construction requirement is met.
The problems of poor construction quality, serious errors and waste and the like exist in the traditional electromechanical engineering due to the problems of unclear drawing design, strong independence of each specialty and the like. The mechanical and electrical industrialization is promoted based on the BIM, the BIM is utilized to carry out comprehensive arrangement of pipelines, modularization splitting and factory high-precision prefabrication. The method has strong demonstration and guidance significance for improving the construction precision and quality and the organization of constructors. According to the invention, during assembly, a plurality of projects are simultaneously subjected to assembly type production construction service according to project schedule requirements, so that the construction quality standard is unified, and the labor loss of electromechanical construction teams and groups at the project department due to discontinuous working surfaces is avoided. As each installation module of the pump room is split and prefabricated in advance, the installation efficiency is greatly improved and the construction time is saved only by directly assembling the installation modules according to the functional modules on the construction site.
Drawings
In order to more clearly illustrate the technical solution of the embodiment of the present invention, the drawings needed to be used in the description of the embodiment will be briefly introduced below, and it is obvious that the drawings in the following description are only for more clearly illustrating the embodiment of the present invention or the technical solution in the prior art, and for those skilled in the art, other drawings can be obtained according to the drawings without any creative effort.
FIG. 1 is a block diagram of the construction process of the present invention.
Detailed Description
In order to make the technical solutions of the present invention better understood and implemented by those skilled in the art, the present invention is further described with reference to the following specific examples, which are provided for illustration only and are not intended to limit the present invention.
The assembly work is completed by installing teams and groups by the project department in the early stage, and after the projects are popularized in the later stage, the assembly type production construction service is simultaneously carried out on a plurality of projects according to the project progress requirements.
The invention relates to 'BIM-based electromechanical industrialization' which is basically characterized in that all electromechanical construction work is divided into three parts of 'deepened design', 'prefabrication' and 'assembly'. The three parts work independently, and the flow intersection is less.
According to the operation mode of a company, the early stage of 'deep design' can be borne by a northwest branch institute of a design institute, the project training and popularization are carried out in the early stage, and after the development and maturity, the project can be borne by a project department of business or technicians.
The 'prefabrication' can be carried out by a directly-affiliated material company or industrialization, the main prefabrication contents are complex positions such as turning, three-way bending and the like of the pipeline, the fixed-length pipeline is automatically digested by a field processing plant, and the electromechanical processing plant is used for producing a shaped electromechanical module of a project.
The assembly work is completed by the installation team of the project department in the early stage, after the project is popularized in the later stage, the material company or the industrialization can cultivate the professional installation team of the material company or the industrialization, and the assembly type production construction service is carried out on a plurality of projects according to the project schedule requirements. Not only unifies the construction quality standard, but also avoids the work loss of the electromechanical construction team of the project department caused by the discontinuity of the working surface.
Firstly, deepening targets:
construction and installation are fully considered, energy conservation and environmental protection are achieved, operation and maintenance factors are operated, a humanized and unit type assembled high-precision machine room model is designed by using the BIM technology, an industrial-grade assembly drawing is provided, and the aims of industrial processing, informatization distribution and modularized installation are fulfilled.
Secondly, the deepening design point of the invention:
1. pipeline split node survives at one time
2. Pipeline machining size node
3. Pipeline regulating pipe section joint
Thirdly, key points and protection points of the invention:
1. the process management in the electromechanical module factory prefabrication processing, the precision of the accessory in millimeter level in the module processing can meet the field assembly requirement, and the key technology of controlling the machining precision of the prefabricated module is realized.
2. In the process of splitting, processing and transporting the model, the prefabricated module has inevitable errors, and the assembly construction process or the splitting scheme of the survival rate of the module is improved on the premise of the existence of the size errors of the prefabricated module.
3. The electromechanical module component splitting key technology, the component node and the connection processing technology.
4. The key technology of transporting, installing and hoisting the special-shaped electromechanical module on site.
The assembly process in the actual construction of the invention is the content of the prior art, and the creativity of the invention is mainly embodied in the advanced design, modeling and factory processing prefabrication.
Fourthly, comparing before and after deepening design:
Figure BDA0002245494290000071
fifth, deepening the achievements
For 4 pump house types: the deep design is implemented to living pump house, fire pump house, heat exchange station, refrigerator station, 29 deepening points, realizes the accurate pre-buried of 5 types of parts, and the accurate location of 7 types of nodes, the one-time survival of 11 types of nodes. The specific deepening design part (node) and deepening points are as follows:
1. accurate positioning:
1) accurate positioning of air pipe, bridge and pipeline plane
2) Accurate positioning of air pipe, bridge and pipeline elevation
3) Accurate positioning of equipment and foundation
4) Accurate positioning of drainage ditch
5) Accurate positioning of main pipeline pipe support
6) Accurate positioning of bridge expansion joint
7) Accurate positioning of pipeline identification
2. Accurate pre-embedding:
1) accurate pre-embedding of support steel plate
2. Accurate pre-buried of power and automatic control linkage
3) Accurate pre-burying of unit, water pump and water tank ground connection
4) Accurate pre-embedding of hole and sleeve
5) Accurate pre-embedding of footing bolt
3. Class of primary survival
1) Pipeline bracket joint becomes alive at one time
2) Pipeline split node survives at one time
3) One-time survival of air pipe support joint
4) One-time survival of joint of air pipe fitting
5) Bridge frame special-shaped part joint one-time survival
6) Bridge crane support joint one-time survival
7) One-time survival of water pump installation comprehensive node
8) One-time survival of node of self-spraying alarm device
9) One-time activation of pressure reducing valve group node
10) One-time survival of rubber and plastic heat preservation method node
11) Spraying system end device node one-time survival
4. And others:
1) drainage ditch structure making node
2) Water tank expansion joint
3) Pipeline bracket processing node
4) Pipeline machining size node
5) Pipeline regulating pipe section joint
6) Bridge frame plane size node
Identifying and determining 10 types of standard component bill of materials:
1. list of industrial chain professional delivery standard parts:
1) PC types: a seepage and drainage ditch PC and a shallow drainage ditch PC;
2) materials class: the system comprises an air pipe angle steel flange, an air pipe hanger cross arm, a bridge support cross arm, a pipeline through outer wall rigid sleeve and a pipeline system identifier;
2. and (3) field centralized processing of a standard part list:
section steel support, prefabricated pipeline and prefabricated air pipe
Sixthly, benefit analysis of the construction method
1. Benefits of construction period
Taking the example that the system comprises 3 water chilling units and 8 circulating pump units, and the total number of various pipelines is about 960 meters, the construction period of the key line of the assembly construction of the assembly refrigeration machine room is only 3 days, which is 1/10 of the traditional construction period.
2. Economic benefits
The pump group and the auxiliary equipment pipe valve group are assembled on site, and the cost can be saved by 3.41 ten thousand yuan. See tables 1 and 2.
TABLE 1 comparison of offset costs of fabricated construction and traditional construction materials
Figure BDA0002245494290000091
TABLE 2 Manual comparison of traditional construction and fabricated construction
Figure BDA0002245494290000092
3. Social benefits
The BIM-based assembly type machine room construction method reduces noise and raised dust pollution of a construction site, improves civilized and green construction level of the construction site, and is energy-saving and environment-friendly.
Seventh, example
Example 1:
the project name is as follows: research center building of Siman test research institute
A construction unit: zhongtian construction group Co Ltd
Overview of the engineering:
(1) the structure type is as follows: frame shear wall
(2) Area of building (m)2):21700
(3) Engineering cost (ten thousand yuan): 3900
(4) The date of start-up is 2017, 6 months and 13 days; completion date: 4 and 7 months in 2018
(5) Engineering site: three routes of science sources of Fengdong New region of Xixi province of Shaanxi province
(6) The name of the construction method is as follows: BIM-based assembly type machine room construction method
(7) Explanation of the application part and the application effect of the construction method: a research center building of the Western's Ann test research institute is located in three paths of science sources of New Fengdong in New Fengdong province in Xixi province of Shaanxi province, has a frame shear wall structure and has a total building area of 21700 square meters. 1 layer underground, 6 layers above the ground and 30.9m in building height. In order to meet the temperature control requirements of large-area and multiple devices, a refrigerating machine room is arranged on the north side of the underground layer of the building. The machine room occupies 273.16 square meters, 3 water chilling units are selected as cold sources, 6-13 ℃ air conditioner chilled water is provided, and the temperature difference of supply return water is 7 ℃. Each loop return water main pipe is provided with a manual regulating valve with good regulating performance, and the hydraulic balance of the loop is regulated. The air-conditioning chilled water and cooling water systems are respectively provided with 4 circulating pump sets which are used as one pump and a backup pump.
1) Screening out a pump set model;
2) processing and decomposing structural parts;
3) prefabricating a processing decomposition section of the pipeline group;
4) installing and constructing a pump set and an auxiliary pipe valve;
5) and (5) installing and constructing a water cooler connector pipeline set.
The method adopts an assembly machine room construction method based on BIM, realizes modularized assembly through early-stage deep design, pre-buried positioning and factory prefabrication processing, and achieves the purpose of one-time survival. And a large amount of welding work on site is reduced, the site installation precision is improved, the requirement of green construction is met, consistent affirmation and high evaluation of owners, supervision and quality supervision units are obtained, and a good social image is established.
Example 2:
the project name is as follows: birch forest reunion 1 standard segment engineering
A construction unit: zhongtian construction group Co Ltd
Overview of the engineering:
(1) the structure type is as follows: frame shear wall
(2) Area of building (m)2):60,649m2
(3) Engineering cost (ten thousand yuan): 20,460 ten thousand yuan
(4) The start date is 2017, 6 months and 28 days; completion date: 12 and 16 months in 2019
(5) Engineering site: in the suburb of Xian city, the eight branches of Fengcheng city and one branch of Minjing are crossed to the north by 200 m
(6) The name of the construction method is as follows: BIM-based assembly type machine room construction method
(7) Explanation of the application part and the application effect of the construction method: the economic benefit situation analysis shows through developing and applying the construction method and the traditional method: the method adopts an assembly type pump room (station) construction method based on BIM in the birch reunion 1 standard section engineering project:
1) screening out a pump set model;
2) processing and decomposing structural parts;
3) prefabricating a processing decomposition section of the pipeline group;
4) installing and constructing a pump set and an auxiliary pipe valve;
5) and (5) installing and constructing a water cooler connector pipeline set.
The modular assembly is realized through advanced design, pre-buried positioning and factory prefabrication processing in the early stage, the purpose of one-time survival is achieved, a large amount of welding work on site is avoided, a large amount of personnel and construction period investment are saved, about 862 meters of all kinds of pipelines are taken as an example, the construction period is saved by 85% through measurement and calculation, the pipeline material is saved by 12.3%, the personnel configuration is saved by 25%, the total cost is saved by 2.46 ten thousand yuan, and the economic benefit is obvious.
The method adopts an assembly machine room construction method based on BIM, realizes modularized assembly through early-stage deep design, pre-buried positioning and factory prefabrication processing, and achieves the purpose of one-time survival. And a large amount of welding work on site is reduced, the site installation precision is improved, the requirement of green construction is met, consistent affirmation and high evaluation of owners, supervision and quality supervision units are obtained, and a good social image is established.
Through the exploration and application of the two projects, the practicability and the economical efficiency of the construction method are verified, good economic and social benefits are obtained, and the construction method has a very wide application prospect in electromechanical engineering construction.
The invention is based on the promotion of BIM electromechanical industrialization, and has the advantages of comprehensive arrangement of pipelines, modularized splitting and industrialized high-precision prefabrication by utilizing BIM. The method has strong demonstration and guidance significance for improving the construction precision and quality and the organization of constructors. According to the invention, during assembly, a plurality of projects are simultaneously subjected to assembly type production construction service according to project schedule requirements, so that the construction quality standard is unified, and the labor loss of electromechanical construction teams and groups at the project department due to discontinuous working surfaces is avoided. As each installation module of the pump room is split and prefabricated in advance, the installation efficiency is greatly improved and the construction time is saved only by directly assembling the installation modules according to the functional modules on the construction site.
The details of the present invention not described in detail are prior art.
The above description is only for the purpose of illustrating the preferred embodiments of the present invention and is not to be construed as limiting the invention, and any modifications, equivalents, improvements and the like that fall within the spirit and principle of the present invention are intended to be included therein.

Claims (4)

1. The deep design process of the assembled machine room based on the BIM is characterized by comprising the following steps of:
s1, deepening design:
1) deepening requirement confirmation:
filling a deepened design application form to confirm the deepened design requirements of the project and signing a deepened design service agreement;
2) deepening point confirmation:
confirming the range of the deepened nodes according to a deepened design bill and perfecting a deepened design information confirmation table;
3) deepening information confirmation:
identifying the information of the size, the material and the construction method of the finished product material in the deepened design of the project, and confirming the information in writing;
s2 BIM preliminary modeling:
1) establishing a family library: according to the relevant information collection condition, perfecting the project family library, and extracting product data parameters from the cloud warehouse database;
2) building and structural modeling: building a civil model according to the building and structure diagram;
3) clear height analysis: comprehensively analyzing a pipeline elevation system according to the first square elevation requirement and the garage structure form;
4) electromechanical installation preliminary modeling: according to the construction drawing, an electromechanical installation model is preliminarily established, the plane arrangement is arranged according to the original drawing, and the pipelines of each system are arranged in different elevations and layers, so that the subsequent deepening adjustment is facilitated;
s3: BIM deepening modeling: searching for 'mistake', 'leakage', 'collision' and 'deficiency' in the drawing through the BIM model, and performing node deepening and arrangement optimization on the construction drawing;
1) deepening an electromechanical mounting plane: deepening the plane layout of the comprehensive pipeline according to a deepening design principle;
2) deepening the elevation of the collision inspection: after the plane arrangement is finished, carrying out pipeline collision inspection to deepen a pipeline elevation system;
3) standard nodes: according to the requirements of a deepened design achievement diagram, standard nodes of all parts are perfected;
and S4, design file auditing and confirmation:
checking, reviewing and signing and then issuing; internal checking, namely exchanging the deepened design result drawing with a project to confirm by a design first party;
s5, deepening design bottom crossing:
performing optimization and deepening design drawing intersection before construction according to the deepening design result drawing;
s6, field rechecking and adjusting:
after the on-site main body is constructed, carrying out on-site rechecking on the installation embedded content and the structure deviation condition, and adjusting the deepened content under the condition of common identification with the project;
s7: formally deepening the drawing:
forming a formal design file;
s8: prefabricating and processing complex positions of pipelines:
the prefabricated content comprises pipeline turning positions and tee bend turning positions, the fixed-length pipeline is processed by a field processing factory, the shaped electromechanical module is processed by the electromechanical processing factory, the support is shared by the construction field, and the support is processed according to a deepened design drawing.
2. The BIM-based assembly machine room deepening design flow according to claim 1, wherein software adopted for BIM deepening modeling in the S3 is Inventor software.
3. A BIM-based construction method for an assembled machine room is characterized by comprising the following steps:
s1: and (3) installing a pump set:
1) the pump set is horizontally transported to the position near the installation position of the machine room, and the pump set is pushed to the installation position by a ground tank;
2) after the pump group is pulled to the installation position, the adjustment before taking place is carried out, and the connection control points of the front and back, the left and right and the upper and lower dimensions are ensured to be consistent with the model;
3) a jack is used for assisting the pump set to be in place, the ground tank is taken out, and the position of the pump set is fixed; the synchronous control of the descending process of the screw jack is noticed, so that the deviation or deformation of positioning is avoided;
s2: and (3) installing a pipeline set:
1) after the main equipment and the pump set are in place, the main equipment and the pump set are sequentially installed according to the number sequence in the component part processing exploded view;
2) the pipeline groups are connected through adjustable flanges, pre-assembly is carried out firstly, and after all the pipeline groups and the accessory equipment groups are installed, deviation is adjusted;
3) after adjusting the deviation, finally fixing the connection part of the component parts;
s3: washing and pressure test acceptance: and after the pipeline of the whole machine room is installed, the whole machine room is washed according to a special construction scheme of the project pump room.
4. The BIM-based prefabricated room construction method of claim 3, wherein the flushing flow rate in S3 is generally not less than 3.0 m/S.
CN201911015277.0A 2019-10-24 2019-10-24 Assembly type machine room deepening design process based on BIM and construction method thereof Pending CN110952811A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201911015277.0A CN110952811A (en) 2019-10-24 2019-10-24 Assembly type machine room deepening design process based on BIM and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201911015277.0A CN110952811A (en) 2019-10-24 2019-10-24 Assembly type machine room deepening design process based on BIM and construction method thereof

Publications (1)

Publication Number Publication Date
CN110952811A true CN110952811A (en) 2020-04-03

Family

ID=69975759

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201911015277.0A Pending CN110952811A (en) 2019-10-24 2019-10-24 Assembly type machine room deepening design process based on BIM and construction method thereof

Country Status (1)

Country Link
CN (1) CN110952811A (en)

Cited By (22)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111540455A (en) * 2020-04-30 2020-08-14 中建三局智能技术有限公司 Quick debugging method and system for disease control hospital epidemic prevention engineering intelligent system
CN112031487A (en) * 2020-06-24 2020-12-04 中铁建工集团有限公司 DMBP (distributed binary BP) assembly type machine room construction method based on BIM (building information modeling) technology
CN112112418A (en) * 2020-09-29 2020-12-22 中国建筑一局(集团)有限公司 Construction method of high-rise building aluminum formwork climbing frame combined system
CN112252784A (en) * 2020-10-26 2021-01-22 北京市第三建筑工程有限公司 Assembly construction method for refrigerating room
CN112446073A (en) * 2020-11-10 2021-03-05 上海宝冶集团有限公司 Rapid construction method for air conditioner room of automobile factory building based on BIM deepened design
CN112464494A (en) * 2020-12-14 2021-03-09 北京城建集团有限责任公司 Construction system is built to wisdom
CN112651067A (en) * 2020-11-16 2021-04-13 中国建筑一局(集团)有限公司 Prefabricated machine room assembly construction method and system based on BIM
CN112922404A (en) * 2021-01-27 2021-06-08 中建五局第三建设有限公司 Building method of modular assembly type machine room
CN112966317A (en) * 2021-03-22 2021-06-15 上海原构设计咨询有限公司 Deepened design method and process flow for prefabricated machine room
CN112982474A (en) * 2021-02-25 2021-06-18 中建八局第四建设有限公司 Method for prefabricating and effectively fixing equipment foundation
CN113027172A (en) * 2021-02-05 2021-06-25 广西建工集团第五建筑工程有限责任公司 Modularized division type building method for building containers quickly
CN113076588A (en) * 2021-04-29 2021-07-06 上海原构设计咨询有限公司 BIM technology-based power transformation and distribution station deepened design process and technology
CN113205251A (en) * 2021-04-29 2021-08-03 上海原构建筑工程有限公司 Comprehensive deepening design flow and process for core tube motor electric well pipeline of super high-rise building
CN113239546A (en) * 2021-05-17 2021-08-10 中建八局第四建设有限公司 Assembly type machine room construction method based on DDCI system
CN113293998A (en) * 2021-06-03 2021-08-24 中建三局集团有限公司 Discrete type prefabrication distributed construction method for high-density refrigeration machine room
CN113653367A (en) * 2021-01-19 2021-11-16 重庆华瑞铝业有限公司 Method for quickly building light steel villa
CN113722788A (en) * 2021-07-15 2021-11-30 广东二十冶建设有限公司 BIM-based modular machine room transportation and installation determination method and system
CN113719662A (en) * 2021-09-09 2021-11-30 中建八局第一建设有限公司 Sectional integral lifting installation construction method for large-scale dense pipeline system
CN114682956A (en) * 2022-04-19 2022-07-01 中天建设集团有限公司 Multifunctional sleeve welding combination table and construction method thereof
CN115758554A (en) * 2022-12-28 2023-03-07 中建七局建筑装饰工程有限公司 ALC (autoclaved lightweight concrete) slab lean construction method based on BIM (building information modeling) technology
CN116167146A (en) * 2023-04-25 2023-05-26 中铁八局集团电务工程有限公司 Modularized installation method for urban rail transit cold water machine room
CN117195445A (en) * 2023-08-02 2023-12-08 中建八局第四建设有限公司 Modularized assembly construction method for clustered air conditioner room

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001188812A (en) * 1999-12-28 2001-07-10 Asahi Kasei Corp Industrialized custom-built house design method and system
EP2113616A1 (en) * 2007-02-15 2009-11-04 Shanghai Precision Houses Manufacturing Co., Ltd. A cpad system for prefab frame building with full-function and a method thereof
CN106193176A (en) * 2016-06-29 2016-12-07 江苏宜安建设有限公司 A kind of hydromechanical installer engineering construction method
CN108564343A (en) * 2018-04-11 2018-09-21 中国冶集团有限公司 A kind of pipe prefabrication construction method using BIM technology
CN109543233A (en) * 2018-10-26 2019-03-29 中交第航务工程局有限公司 A kind of electromechanical pipeline assembly construction method based on BIM technology
CN109614719A (en) * 2018-12-14 2019-04-12 中建二局第建筑工程有限公司 A kind of refrigerating plant room assembly construction method based on BIM technology
CN109766649A (en) * 2019-01-17 2019-05-17 中建三局安装工程有限公司 A kind of Air Conditioning Facilities prefabrication of tube section installation method

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001188812A (en) * 1999-12-28 2001-07-10 Asahi Kasei Corp Industrialized custom-built house design method and system
EP2113616A1 (en) * 2007-02-15 2009-11-04 Shanghai Precision Houses Manufacturing Co., Ltd. A cpad system for prefab frame building with full-function and a method thereof
CN106193176A (en) * 2016-06-29 2016-12-07 江苏宜安建设有限公司 A kind of hydromechanical installer engineering construction method
CN108564343A (en) * 2018-04-11 2018-09-21 中国冶集团有限公司 A kind of pipe prefabrication construction method using BIM technology
CN109543233A (en) * 2018-10-26 2019-03-29 中交第航务工程局有限公司 A kind of electromechanical pipeline assembly construction method based on BIM technology
CN109614719A (en) * 2018-12-14 2019-04-12 中建二局第建筑工程有限公司 A kind of refrigerating plant room assembly construction method based on BIM technology
CN109766649A (en) * 2019-01-17 2019-05-17 中建三局安装工程有限公司 A kind of Air Conditioning Facilities prefabrication of tube section installation method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
高喜玲等: "《安装工程施工组织与管理》", 30 November 2010, 徐州:中国矿业大学出版社 *

Cited By (27)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111540455A (en) * 2020-04-30 2020-08-14 中建三局智能技术有限公司 Quick debugging method and system for disease control hospital epidemic prevention engineering intelligent system
CN112031487A (en) * 2020-06-24 2020-12-04 中铁建工集团有限公司 DMBP (distributed binary BP) assembly type machine room construction method based on BIM (building information modeling) technology
CN112112418A (en) * 2020-09-29 2020-12-22 中国建筑一局(集团)有限公司 Construction method of high-rise building aluminum formwork climbing frame combined system
CN112112418B (en) * 2020-09-29 2022-03-29 中国建筑一局(集团)有限公司 Construction method of high-rise building aluminum formwork climbing frame combined system
CN112252784A (en) * 2020-10-26 2021-01-22 北京市第三建筑工程有限公司 Assembly construction method for refrigerating room
CN112446073A (en) * 2020-11-10 2021-03-05 上海宝冶集团有限公司 Rapid construction method for air conditioner room of automobile factory building based on BIM deepened design
CN112651067A (en) * 2020-11-16 2021-04-13 中国建筑一局(集团)有限公司 Prefabricated machine room assembly construction method and system based on BIM
CN112464494A (en) * 2020-12-14 2021-03-09 北京城建集团有限责任公司 Construction system is built to wisdom
CN113653367A (en) * 2021-01-19 2021-11-16 重庆华瑞铝业有限公司 Method for quickly building light steel villa
CN112922404A (en) * 2021-01-27 2021-06-08 中建五局第三建设有限公司 Building method of modular assembly type machine room
CN113027172A (en) * 2021-02-05 2021-06-25 广西建工集团第五建筑工程有限责任公司 Modularized division type building method for building containers quickly
CN112982474A (en) * 2021-02-25 2021-06-18 中建八局第四建设有限公司 Method for prefabricating and effectively fixing equipment foundation
CN112966317A (en) * 2021-03-22 2021-06-15 上海原构设计咨询有限公司 Deepened design method and process flow for prefabricated machine room
CN112966317B (en) * 2021-03-22 2023-07-28 上海原构设计咨询有限公司 Deep design method and process flow of prefabricated assembly machine room
CN113076588A (en) * 2021-04-29 2021-07-06 上海原构设计咨询有限公司 BIM technology-based power transformation and distribution station deepened design process and technology
CN113205251A (en) * 2021-04-29 2021-08-03 上海原构建筑工程有限公司 Comprehensive deepening design flow and process for core tube motor electric well pipeline of super high-rise building
CN113076588B (en) * 2021-04-29 2023-07-21 上海原构设计咨询有限公司 BIM technology-based deep design flow and technology for transformer and distribution station
CN113239546A (en) * 2021-05-17 2021-08-10 中建八局第四建设有限公司 Assembly type machine room construction method based on DDCI system
CN113239546B (en) * 2021-05-17 2022-08-02 中建八局第四建设有限公司 Assembly type machine room construction method based on DDCI system
CN113293998A (en) * 2021-06-03 2021-08-24 中建三局集团有限公司 Discrete type prefabrication distributed construction method for high-density refrigeration machine room
CN113722788A (en) * 2021-07-15 2021-11-30 广东二十冶建设有限公司 BIM-based modular machine room transportation and installation determination method and system
CN113722788B (en) * 2021-07-15 2023-09-29 广东二十冶建设有限公司 Determination method and system for transportation and installation of modularized machine room based on BIM
CN113719662A (en) * 2021-09-09 2021-11-30 中建八局第一建设有限公司 Sectional integral lifting installation construction method for large-scale dense pipeline system
CN114682956A (en) * 2022-04-19 2022-07-01 中天建设集团有限公司 Multifunctional sleeve welding combination table and construction method thereof
CN115758554A (en) * 2022-12-28 2023-03-07 中建七局建筑装饰工程有限公司 ALC (autoclaved lightweight concrete) slab lean construction method based on BIM (building information modeling) technology
CN116167146A (en) * 2023-04-25 2023-05-26 中铁八局集团电务工程有限公司 Modularized installation method for urban rail transit cold water machine room
CN117195445A (en) * 2023-08-02 2023-12-08 中建八局第四建设有限公司 Modularized assembly construction method for clustered air conditioner room

Similar Documents

Publication Publication Date Title
CN110952811A (en) Assembly type machine room deepening design process based on BIM and construction method thereof
CN107895091B (en) Module intelligent cold and hot station installation system and BIM model prefabrication construction method thereof
CN204478334U (en) modular integrated refrigeration station
CN110440054B (en) Subway station refrigerating machine room pipeline assembling construction method
CN112651067A (en) Prefabricated machine room assembly construction method and system based on BIM
CN112832557A (en) Assembly type construction method of subway station cold water machine room based on BIM
CN111306363A (en) Assembly type fire pump room hoisting construction method and construction structure based on BIM technology
CN105888317A (en) Central refrigeration machine room modular prefabrication and assembled construction method
CN115758553B (en) Modularized assembly type machine room implementation method based on BIM technology
CN110765515A (en) BIM-based pipe heald optimization method
CN112765701B (en) Integrated construction method for design and construction of farmer new village
CN110440429A (en) Subway arch top ventilation shaft assembling constructing method
CN114139997A (en) Integrated electromechanical installation construction process based on BIM and DPMA management
CN113293998A (en) Discrete type prefabrication distributed construction method for high-density refrigeration machine room
CN100570757C (en) The modular construction method that is used for nuclear island of nuclear power station
CN111395744A (en) Construction method of aluminum template in horizontal flowing section process of villa
CN101752017B (en) Modularization construction method for nuclear power station nuclear island
CN101736925B (en) Modular construction method for nuclear island of nuclear power station
CN115114697A (en) Pipe fitting prefabricating and assembling technological process
CN116956403A (en) BIM-based river water source energy station pipeline assembly type construction process
CN111719870A (en) One-step forming installation method for electromechanical pipeline of super high-rise standard layer
CN111931316A (en) Modular assembly type machine room equipment and pipeline construction method
CN103473398B (en) The analogue system of a kind of integrated refrigeration station and emulation method
CN112966317B (en) Deep design method and process flow of prefabricated assembly machine room
Xie et al. Smart building materials of BIM and RFID in lifecycle management of steel structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20200403