CN110850816A - Galvanized sheet angle iron flange tuber pipe product production management system based on BIM - Google Patents

Galvanized sheet angle iron flange tuber pipe product production management system based on BIM Download PDF

Info

Publication number
CN110850816A
CN110850816A CN201910943459.8A CN201910943459A CN110850816A CN 110850816 A CN110850816 A CN 110850816A CN 201910943459 A CN201910943459 A CN 201910943459A CN 110850816 A CN110850816 A CN 110850816A
Authority
CN
China
Prior art keywords
pipe
angle iron
air
flange
air pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910943459.8A
Other languages
Chinese (zh)
Inventor
刘桂平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tianjin Ott Electromechanical Equipment Co Ltd
Original Assignee
Tianjin Ott Electromechanical Equipment Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tianjin Ott Electromechanical Equipment Co Ltd filed Critical Tianjin Ott Electromechanical Equipment Co Ltd
Priority to CN201910943459.8A priority Critical patent/CN110850816A/en
Publication of CN110850816A publication Critical patent/CN110850816A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • GPHYSICS
    • G05CONTROLLING; REGULATING
    • G05BCONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS
    • G05B19/00Programme-control systems
    • G05B19/02Programme-control systems electric
    • G05B19/418Total factory control, i.e. centrally controlling a plurality of machines, e.g. direct or distributed numerical control [DNC], flexible manufacturing systems [FMS], integrated manufacturing systems [IMS], computer integrated manufacturing [CIM]
    • G05B19/41875Total factory control, i.e. centrally controlling a plurality of machines, e.g. direct or distributed numerical control [DNC], flexible manufacturing systems [FMS], integrated manufacturing systems [IMS], computer integrated manufacturing [CIM] characterised by quality surveillance of production
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B23MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
    • B23PMETAL-WORKING NOT OTHERWISE PROVIDED FOR; COMBINED OPERATIONS; UNIVERSAL MACHINE TOOLS
    • B23P15/00Making specific metal objects by operations not covered by a single other subclass or a group in this subclass
    • GPHYSICS
    • G05CONTROLLING; REGULATING
    • G05BCONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS
    • G05B2219/00Program-control systems
    • G05B2219/30Nc systems
    • G05B2219/32Operator till task planning
    • G05B2219/32368Quality control
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/02Total factory control, e.g. smart factories, flexible manufacturing systems [FMS] or integrated manufacturing systems [IMS]

Abstract

The invention relates to a production management system of galvanized sheet angle iron flange air pipes based on BIM, wherein the galvanized sheet angle iron flange air pipes are connected with each other through angle iron flanges at two edges during installation. The invention has the beneficial effects that: the air duct production process is automated and intelligentized; firstly, a sketch with composite requirements is formulated according to field requirements, and then sketch data is led into a BIM system to realize the manufacturing processes of accurate blanking, bending and fixing of the air pipe through the data control of production line machinery; in addition, the manufacturing process of the air pipe can be simulated in advance, so that the manufacturing process is optimized to the maximum extent, and the possibility of misoperation is reduced.

Description

Galvanized sheet angle iron flange tuber pipe product production management system based on BIM
Technical Field
The invention belongs to the field of air pipe preparation, and particularly relates to a production management system for a galvanized sheet angle iron flange air pipe product based on BIM.
Background
The air pipe is a pipeline system for air conveying and distribution, and is generally formed by assembling a plurality of sections of air pipe monomers, and because the air pipe is generally longer, the firmness of the air pipe is a key factor for determining the service life of the air pipe in the assembling process. In addition, in order to realize reasonable and transmission routes in different environments, various special structure styles can exist in each air pipe unit, so that the special structure is manufactured and requires mature experience and manufacturing process, and errors are easy to occur, so that the special-shaped pipe body becomes a weak link of the whole air pipe.
Disclosure of Invention
In order to solve the technical problem, the invention provides a production management system for galvanized sheet angle iron flange air pipe products based on BIM.
The technical scheme adopted by the invention is as follows: the production method of the galvanized sheet angle iron flange air pipe comprises the following specific steps:
firstly, manufacturing a draft of an air duct;
preparing a single straight pipe air pipe body according to an air pipe sketch, preparing a connected thin-wall flange edge, and connecting and reinforcing the angle iron flange and the connected thin-wall flange edge to prepare a single straight pipe air pipe to be installed;
thirdly, preparing a single special-shaped pipe air pipe body according to an air pipe sketch, preparing a connected thin-wall flange edge, and connecting the angle iron flange and the connected thin-wall flange edge to prepare a single special-shaped pipe air pipe to be installed;
and fourthly, assembling and fixing one or more single straight pipe air pipes and one or more single special-shaped pipe air pipes to form the galvanized plate angle iron flange air pipe.
And in the second step, the preparation method of the monomer straight pipe air pipe comprises the following steps:
a1, cutting corners and shearing plates of the galvanized plates according to draft information of the air ducts;
step A2, the cut galvanized sheet is engaged and assembled to form a single straight pipe air duct body;
a3, bending the edge of the single straight pipe wind pipe body to form a connected thin-wall flange edge;
step A4, sleeving the flanges made of angle iron into the single straight pipe air duct body, respectively attaching the two flange sleeves to the connected thin-wall flange edges at the two ends, and fixing the flanges and the connected thin-wall flange edges by rivets to form the single straight pipe air duct.
The preparation method of the single special-shaped pipe air pipe in the third step comprises the following steps:
step B1, cutting a semi-finished product from the galvanized sheet according to the draft information of the air duct;
step B2, the cut galvanized sheet is engaged and assembled to form a single special-shaped pipe body;
b3, bending the edge of the single special-shaped pipe wind pipe body to form a connected thin-wall flange edge;
and step B4, sleeving the flanges made of angle iron into the single special-shaped pipe air duct body, respectively attaching the two flange sleeves to the connected thin-wall flange edges at the two ends, and fixing the flanges and the connected thin-wall flange edges by rivets to form the single special-shaped pipe air duct.
Preferably, when the size of the large side of the air pipe is larger than 630mm, the method further comprises a reinforcing step;
when the size of the large side of the air duct is 630-1000mm, a step A0 is arranged before the step A1,
step A0, reinforcing the galvanized sheet by ribbing;
when the large side size of the air duct is larger than 1000mm, the step A4 is carried out after the step A3,
step A4, adopting any method of angle steel, flat steel, steel pipes, Z-shaped grooves and harness cord screws to reinforce the inside and outside of the pipe;
when the section of the air pipe is larger than 1250mm multiplied by 630mm, the four corners in the air pipe are reinforced by inclined supports at 90 ℃;
preferably, the angle steel, flat steel, steel pipe or ribbing is less than the flange structure height.
A galvanized plate angle iron flange air pipe product production management system based on BIM is characterized in that an air pipe sketch is manufactured through an Autodesk review in a galvanized plate angle iron flange air pipe production method, and the production process of the galvanized plate angle iron flange air pipe is controlled through Autodesk noise.
The specific process is as follows:
step S1, constructing a primary BIM model through Autodesk Revit according to the preparation requirement of the angle iron flange air pipe;
step S2, checking and adjusting the primary BIM model, and confirming the secondary BIM model;
step S3, preparing a prefabricated product, carrying out secondary model adjustment according to product formation, and determining a final BIM model;
and step S4, importing the product information standard into an Autodesk Fabric control system, and generating a prefabricated product library in the BIM through the interaction module product information standard.
The product prefabricating and processing steps are as follows:
step S5, generating a prefabricated product according to the final BIM model information;
step S6, length optimization is carried out on the prefabricated product, and the consistency of the product specification form of the enterprise and the BIM model is realized;
step S7, the optimized model information is converted into processing machine data;
and step S8, transmitting the data to the matched production equipment to cut and blank the galvanized sheet.
Preferably, the prefabricated product is encoded in step S5, and the encoded information corresponds to the formed pipe fittings one by one.
The invention has the advantages and positive effects that:
1, the air duct production process is automated and intelligentized; firstly, a sketch with composite requirements is formulated according to field requirements, and then sketch data is led into a BIM system to realize the manufacturing processes of accurate blanking, bending and fixing of the air pipe through the data control of production line machinery; in addition, the manufacturing process of the air pipe can be simulated in advance, so that the manufacturing process is optimized to the maximum extent, and the possibility of misoperation is reduced;
2, the production line has high degree of mechanization and automation, greatly improves the manufacturing efficiency and the manufacturing precision of the air pipe, and reduces the construction cost; the air pipe is automatically ribbed, the strength is high, the appearance is attractive and tidy, and a zinc layer is not damaged; the production and installation are quick, the labor intensity is reduced, the labor efficiency is improved, the requirements of modern engineering are met, and the competitive advantage of installation units is improved.
Drawings
FIG. 1 is a schematic view of the present invention for reinforcement of a rib; 1. pressing ribs;
FIG. 2 is a schematic view of the reinforcement of the angle iron of the present invention; 2. angle steel;
FIG. 3 is a schematic view of the reinforcement of the frame of the present invention; 3. reinforcing the frame;
FIG. 4 is a schematic view of the angle iron flange connection of the present invention; 41. flange sleeve, 42, rivet, 43, bolt, 44, nut.
Detailed Description
An embodiment of the present invention will be described below with reference to the drawings.
The production method of the galvanized sheet angle iron flange air pipe comprises the following steps:
firstly, manufacturing an air duct sketch according to manufacturing requirements, drawing a processing sketch according to a system served by an air duct according to a construction drawing and actual field conditions (air duct elevation, trend and other professional coordination conditions), numbering according to the system, and carrying out datamation on the manufacturing process of the air duct through corresponding data;
step two, preparing a single straight pipe air pipe body according to an air pipe sketch, processing a flange edge by using a bending machine, wherein the flange edge is 8mm in size, preparing a connected thin-wall flange edge, and connecting and reinforcing the angle iron flange and the connected thin-wall flange edge to prepare the single straight pipe air pipe to be installed
Thirdly, preparing a single special-shaped pipe air pipe body according to an air pipe sketch, preparing a connected thin-wall flange edge, and connecting an angle iron flange and the connected thin-wall flange edge to prepare a single special-shaped pipe air pipe to be installed;
and step four, fixedly connecting the two angle iron flanges in contact through bolts, and assembling and fixing one or more monomer straight pipe air pipes and one or more monomer special-shaped pipe air pipes to form the galvanized plate angle iron flange air pipe.
Selecting a galvanized sheet with a smooth surface and without serious scratch and corrosion of a cold-rolled sheet, and preventing angle steel from being seriously rusted and deformed; the preparation method of the single straight pipe air pipe comprises the following steps:
a1, cutting corners and shearing plates of the galvanized plates according to draft information of the air ducts, and numbering according to the draft information;
step A2, the cut galvanized sheet is engaged and assembled to form a closed tubular structure, and a main body part of the single air duct is constructed;
a3, bending the edge of the single straight pipe wind pipe body to form a connected thin-wall flange edge;
step A4, putting the flange sleeves 41 made of angle iron into the single straight pipe air duct body, respectively attaching the two flange sleeves to the connected thin-wall flange edges at the two ends, fixing the flanges and the connected thin-wall flange edges by using rivets 42 to form the single straight pipe air duct, and when connecting, fixedly connecting the two angle iron flanges with nuts 44 through bolts 43 as shown in figure 4.
When the method is adopted for preparing the single air duct, when the large side of the air duct is larger than 630mm, the air duct needs to be reinforced in order to increase the stability of the air duct, when the large side of the air duct is 630-1000mm, step A0 is arranged before step A1, the galvanized sheet is ribbed, as shown in figure 1, the arrangement is regular, the intervals are uniform, the sheet surface is not deformed obviously, and then the ribbed or galvanized sheet with Z-shaped grooves is cut; when the size of the large side of the air pipe is larger than 1000mm, after the step A3, the step A4 is carried out, the outer side of the manufactured single air pipe is reinforced, angle steel 2, flat steel, steel pipes or Z-shaped grooves are adopted for reinforcement, as shown in figure 2, or a reinforcing frame 3 is prepared, as shown in figure 3, the reinforcing frame is fixedly sleeved on the outer side of the single air pipe to realize the reinforcing effect, or a harness cord screw is additionally arranged for reinforcing the air pipe, wherein the height of the angle steel, the flat steel, the steel pipes or the press bars is smaller than the height of the flange structure, the angle steel, the flat steel, the steel pipes or the press bars are arranged in order, the intervals are uniform and symmetrical and are not larger; when the section of the air duct is larger than 1250mm multiplied by 630mm, in order to keep the adjacent wall surfaces vertical to each other, the four corners in the air duct are reinforced by adopting 90-degree inclined supports. In addition, the internal reinforcement can be carried out by adopting a harness cord screw. When the length of the medium-pressure and high-pressure system air pipe is more than 1250mm, a reinforcing frame is adopted for reinforcing, and a reinforcing or reinforcing measure for preventing the expansion crack of a single seaming seam of the high-pressure system air pipe is also required.
Similar to the preparation process of the single air duct, the preparation method of the single special-shaped air duct comprises the following steps:
step B1, cutting a semi-finished product from the galvanized sheet according to the draft of the air duct, and numbering according to the draft information;
step B2, performing seaming assembly on the semi-finished galvanized plate to form a closed tubular structure, and constructing a main body part of the single air duct;
b3, bending the edge of the single special-shaped pipe wind pipe body to form a connected thin-wall flange edge;
and step B4, sleeving the flanges made of angle iron into the single special-shaped pipe air duct body, respectively attaching the two flange sleeves to the connected thin-wall flange edges at the two ends, and fixing the flanges and the connected thin-wall flange edges by rivets to form the single special-shaped pipe air duct.
Because the air duct production line and the construction site cannot be in the same place, the air duct production line and the construction site are processed into semi-finished products according to drawn sketches in a workshop, numbered according to a system, and assembled according to the serial numbers on the site.
In order to guarantee the transmission effect of the air pipe, the air pipe is required to be sealed, the flange angle position and the joint of the branch pipe and the main pipe are sealed, and the bolt joint is sealed. Sealing the low-pressure air pipe to a position 40-50 mm inside the pipe at the folding position of the air pipe joint part; the high-pressure air pipe is also sealed at the longitudinal bite of the air pipe and the composite part of the air pipe. The flange seal is preferably mounted adjacent the outer side of the flange or intermediate the flanges. When the flange sealing strips are overlapped on the flange end faces, the overlapping is about 30-40 mm. The joint of the angle iron flange needs to be sealed and leak-proof by glass cement, the joint seaming needs to be sealed and leak-proof by glass cement at the position 80mm downward from the flange angle, and the sealant is arranged on the positive pressure side of the air pipe.
A galvanized plate angle iron flange air pipe product production management system based on BIM is characterized in that an air pipe sketch is manufactured through Autodesk Revit in a galvanized plate angle iron flange air pipe production method, a single straight pipe air pipe and a single special-shaped air pipe are manufactured on the basis of the sketch, prefabricated manufacturing information is led into an Autodesk noise control system, and the galvanized plate angle iron flange air pipe production process is controlled through Autodesk noise. The process is as follows:
step S1, constructing a primary BIM model through Autodesk Revit according to the preparation requirement of the angle iron flange air pipe;
step S2, checking and adjusting the primary BIM model, and confirming the secondary BIM model;
step S3, preparing a prefabricated product, carrying out secondary model adjustment according to product formation, and determining a final BIM model;
and step S4, importing the product information standard into an Autodesk Fabric control system, and generating a prefabricated product library in the BIM through the interaction module product information standard.
The product prefabricating and processing steps are as follows:
step S5, generating a prefabricated product according to the final BIM model information, and coding the produced prefabricated product, wherein the coding information corresponds to the formed pipe fittings one by one;
step S6, length optimization is carried out on the prefabricated product, and the consistency of the product specification form of the enterprise and the BIM model is realized;
step S7, the optimized model information is converted into processing machine data;
and step S8, transmitting the data to the matched production equipment to cut and blank the galvanized sheet.
The practical operation profile comprises the following steps: data collection, data sorting and analysis, difficult and complicated question answering, building of a BIM model, collision check of an integral model, submission of a collision report, design consultation, adjustment scheme issuing, adjustment of the BIM model, collision check of the integral model, confirmation of the BIM model, manufacturing of a prefabricated product, secondary adjustment of the model according to product formation, secondary confirmation of the BIM model, prefabricated processing of the product, issuing of data such as a product installation drawing and the like, and field construction and installation.
Wherein the product prefabricating and processing process is as follows:
1 prefabrication and preparation work: the application software Autodesk fibre manufacturing CAMduct can provide the user with tools for manufacturing HVAC ducts through innovative interfaces and comprehensive parameterized component libraries. Meanwhile, operation input sites can be added, so that the whole production process is accelerated. The Autodesk fabric CAMduct software sets air duct product parameters according to characteristics of air duct production equipment, and sets the air duct product parameters respectively according to the plate, the air duct form and the connection mode.
2, prefabricating and processing steps: performing product prefabrication treatment by using a BIM model;
loading a prefabricated part in the BIM, selecting a set sample plate, adding a corresponding air pipe system type, and loading a prefabricated service; selecting a pipeline system to be prefabricated, generating a prefabricated product, and selecting the type of the pipeline system; optimizing the length of the prefabricated product to realize the consistency of the product specification form of the enterprise and the BIM model; converting each optimized part into a product; transferring the processed model into processing machine data; processing the data through prefabricated processing machine software; typesetting the prefabricated product, adjusting the typesetting of the prefabricated product, and inputting the prefabricated product into a machine for cutting according to a drawing; in order to facilitate later transportation and installation, the prefabricated product needs to be coded; and the known drawings for transportation and installation are provided, and the completeness and integrity of transportation are ensured. The installation process has guidance basis, and the construction task can be completed quickly and conveniently.
Example (b):
the galvanized sheet angle iron flange air pipe can be used for industrial factory buildings, civil buildings, commercial buildings and rail transit, and is mainly used for ventilation systems with large air pressure, equipment air exhaust and smoke exhaust systems. For example, in industrial plants for equipment exhaust, fume extraction systems; in commercial buildings or civil buildings, for roof fans, exhaust systems; the air exhaust system is used for a new air exhaust system in rail transit. The angle iron flange air duct has smooth inner wall, small resistance, small ventilation loss, reduced energy consumption, saved operating cost, good air tightness and tightness, high pressure-bearing and compressive strength, and good fireproof performance, and is also the reason for wide application of the angle iron flange air duct in engineering. A production management method of a galvanized sheet angle iron flange air pipe product based on BIM comprises the following specific steps:
step 1, constructing a primary BIM model through Autodesk Revit according to the preparation requirement of an angle iron flange air pipe;
step 2, checking and adjusting the primary BIM model, and confirming the secondary BIM model;
step 3, preparing a prefabricated product, carrying out secondary model adjustment according to product formation, and determining a final BIM model;
step 4, importing the product information standard into an Autodesk failure control system, and generating a prefabricated product library in a BIM (building information modeling) through the product information standard of an interaction module;
step 5, generating a prefabricated product according to the final BIM model information, and coding the produced prefabricated product, wherein the coding information corresponds to the formed pipe fittings one by one;
step 6, optimizing the length of the prefabricated product to realize the consistency of the product specification form of the enterprise and the BIM model;
step 7, converting the optimized model information into processing machine data;
step 8, transmitting the data to matched production equipment;
step 9, cutting and blanking the galvanized sheet to respectively form a single straight tube air tube plate and a single special-shaped tube air tube plate;
step 10, seaming and assembling the cut single straight pipe air duct plate and the single special-shaped pipe air duct plate galvanized plate, and bending and flanging the edges to form a flange structure to form a single straight pipe air duct or a single special-shaped pipe straight pipe air duct;
step 11, reinforcing a reinforcing frame of the galvanized plate, and fixing the reinforcing frame of the angle iron with the height not higher than that of an angle iron flange in the middle of the outer wall of the single air pipe;
and 12, fixing the flange angle and the turned edge, and assembling and fixing one or more single straight pipe air pipes and one or more single special-shaped pipe air pipes to form the galvanized plate angle iron flange air pipe.
By adopting the method, various processes are completed through a full-automatic assembly line, the production efficiency is high, the size is accurate, and the forming quality is good. The air leakage rate is obviously reduced, the energy is saved, the running cost of the main engine is reduced, and the long-term stability can be kept. The BIM-based production mode has the advantages that the production automation degree is high, the labor intensity is reduced, the labor efficiency is improved, the labor cost is reduced, and the requirements of modern engineering are met; and the installation and operation are simple, convenient and quick, the construction period can be shortened, the progress of engineering construction can be accelerated, and the noise pollution generated by manufacturing the air pipes on the construction site is reduced, so that the civilized construction is facilitated.
While one embodiment of the present invention has been described in detail, the description is only a preferred embodiment of the present invention and should not be taken as limiting the scope of the invention. All equivalent changes and modifications made within the scope of the present invention shall fall within the scope of the present invention.

Claims (8)

1. The production method of the galvanized sheet angle iron flange air pipe is characterized by comprising the following steps of: the preparation method comprises the following steps:
firstly, manufacturing a draft of an air duct;
preparing a single straight pipe air pipe body according to an air pipe sketch, preparing a connected thin-wall flange edge, and connecting and reinforcing the angle iron flange and the connected thin-wall flange edge to prepare a single straight pipe air pipe to be installed;
thirdly, preparing a single special-shaped pipe air pipe body according to an air pipe sketch, preparing a connected thin-wall flange edge, and connecting the angle iron flange and the connected thin-wall flange edge to prepare a single special-shaped pipe air pipe to be installed;
and fourthly, assembling and fixing one or more single straight pipe air pipes and one or more single special-shaped pipe air pipes to form the galvanized plate angle iron flange air pipe.
2. The method for producing a galvanized sheet angle iron flange air pipe according to claim 1, characterized in that: the preparation method of the monomer straight pipe air duct in the step two is as follows:
a1, cutting corners and shearing plates of the galvanized plates according to draft information of the air ducts;
step A2, the cut galvanized sheet is engaged and assembled to form a single straight pipe air duct body;
a3, bending the edge of the single straight pipe wind pipe body to form a connected thin-wall flange edge;
step A4, sleeving the flanges made of angle iron into the single straight pipe air duct body, respectively attaching the two flange sleeves to the connected thin-wall flange edges at the two ends, and fixing the flanges and the connected thin-wall flange edges by rivets to form the single straight pipe air duct.
3. The method for producing a galvanized sheet angle iron flange air pipe according to claim 1, characterized in that: the preparation method of the single special-shaped pipe air pipe in the third step comprises the following steps:
step B1, cutting a semi-finished product from the galvanized sheet according to the draft information of the air duct;
step B2, the cut galvanized sheet is engaged and assembled to form a single special-shaped pipe body;
b3, bending the edge of the single special-shaped pipe wind pipe body to form a connected thin-wall flange edge;
and step B4, sleeving the flanges made of angle iron into the single special-shaped pipe air duct body, respectively attaching the two flange sleeves to the connected thin-wall flange edges at the two ends, and fixing the flanges and the connected thin-wall flange edges by rivets to form the single special-shaped pipe air duct.
4. The method for producing a galvanized sheet angle iron flange air pipe according to claim 1, characterized in that: when the size of the large side of the air pipe is larger than 630mm, the method also comprises a reinforcing step;
when the size of the large side of the air duct is 630-1000mm, a step A0 is arranged before the step A1,
step A0, reinforcing the galvanized sheet by ribbing;
when the large side size of the air duct is larger than 1000mm, the step A4 is carried out after the step A3,
step A4, adopting any method of angle steel, flat steel, steel pipes, Z-shaped grooves and harness cord screws to reinforce the inside and outside of the pipe; when the section of the air pipe is larger than 1250mm multiplied by 630mm, the four corners in the air pipe are reinforced by inclined supports at 90 ℃;
preferably, the angle steel, flat steel, steel pipe or ribbing is less than the flange structure height.
5. Galvanized sheet angle bar flange tuber pipe product production management system based on BIM, its characterized in that: the method of manufacturing angle iron-flanged galvanized air pipe as claimed in any one of claims 1 to 4, wherein the angle iron-flanged air pipe manufacturing process is controlled by Autodesk simulation by making a draft for the air pipe by Autodesk review.
6. The BIM-based galvanized sheet angle iron flange air pipe product production management system of claim 5, wherein: the specific process is as follows:
step S1, constructing a primary BIM model through Autodesk Revit according to the preparation requirement of the galvanized sheet angle iron flange air pipe;
step S2, checking and adjusting the primary BIM model, and confirming the secondary BIM model;
step S3, preparing a prefabricated product, carrying out secondary model adjustment according to product formation, and determining a final BIM model;
and step S4, importing the product information standard into an Autodesk Fabric control system, and generating a prefabricated product library in the BIM through the interaction module product information standard.
7. The BIM-based galvanized sheet angle iron flange air pipe product production management system of claim 6, wherein: the product prefabricating and processing steps are as follows:
step S5, generating a prefabricated product according to the final BIM model information;
step S6, length optimization is carried out on the prefabricated product, and the consistency of the product specification form of the enterprise and the BIM model is realized;
step S7, the optimized model information is converted into processing machine data;
and step S8, transmitting the data to the matched production equipment to cut and blank the galvanized sheet.
8. The BIM-based galvanized sheet angle iron flange air pipe product production management system of claim 7, wherein:
and in the step S5, the produced prefabricated product is coded, and the coded information corresponds to the formed pipe fittings one by one.
CN201910943459.8A 2019-09-30 2019-09-30 Galvanized sheet angle iron flange tuber pipe product production management system based on BIM Pending CN110850816A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910943459.8A CN110850816A (en) 2019-09-30 2019-09-30 Galvanized sheet angle iron flange tuber pipe product production management system based on BIM

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910943459.8A CN110850816A (en) 2019-09-30 2019-09-30 Galvanized sheet angle iron flange tuber pipe product production management system based on BIM

Publications (1)

Publication Number Publication Date
CN110850816A true CN110850816A (en) 2020-02-28

Family

ID=69596184

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910943459.8A Pending CN110850816A (en) 2019-09-30 2019-09-30 Galvanized sheet angle iron flange tuber pipe product production management system based on BIM

Country Status (1)

Country Link
CN (1) CN110850816A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111853375A (en) * 2020-05-25 2020-10-30 重庆龙润建筑安装工程有限公司 Ponding device is prevented to outdoor tuber pipe
CN113084463A (en) * 2021-04-20 2021-07-09 中国直升机设计研究所 Method for machining outer sleeve of infrared stealth device of helicopter

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105058055A (en) * 2015-08-21 2015-11-18 中铁建大桥工程局集团第五工程有限公司 Manufacturing and installation method for built-in flange and air hose for building construction
CN108515087A (en) * 2018-03-28 2018-09-11 中建七局安装工程有限公司 A kind of air hose automatic production line and production method
US20180356117A1 (en) * 2017-06-12 2018-12-13 Fran Lanciaux HVAC Duct System, Method and Machine
CN110008606A (en) * 2019-04-10 2019-07-12 浙江中信设备安装有限公司 One kind being based on BIM air hose automatic processing method
CN110253303A (en) * 2019-05-21 2019-09-20 中外建安装有限公司 The processing of plate flange blast pipe and its mounting process altogether

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105058055A (en) * 2015-08-21 2015-11-18 中铁建大桥工程局集团第五工程有限公司 Manufacturing and installation method for built-in flange and air hose for building construction
US20180356117A1 (en) * 2017-06-12 2018-12-13 Fran Lanciaux HVAC Duct System, Method and Machine
CN108515087A (en) * 2018-03-28 2018-09-11 中建七局安装工程有限公司 A kind of air hose automatic production line and production method
CN110008606A (en) * 2019-04-10 2019-07-12 浙江中信设备安装有限公司 One kind being based on BIM air hose automatic processing method
CN110253303A (en) * 2019-05-21 2019-09-20 中外建安装有限公司 The processing of plate flange blast pipe and its mounting process altogether

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111853375A (en) * 2020-05-25 2020-10-30 重庆龙润建筑安装工程有限公司 Ponding device is prevented to outdoor tuber pipe
CN111853375B (en) * 2020-05-25 2023-12-29 重庆龙润建筑安装工程有限公司 Ponding device is prevented to outdoor tuber pipe
CN113084463A (en) * 2021-04-20 2021-07-09 中国直升机设计研究所 Method for machining outer sleeve of infrared stealth device of helicopter

Similar Documents

Publication Publication Date Title
CN110850816A (en) Galvanized sheet angle iron flange tuber pipe product production management system based on BIM
CN110440429B (en) Subway arched roof ventilating pipeline assembling construction method
CN105058055B (en) Built-in flange blast pipe fabrication and installation engineering method for construction
CN115758553B (en) Modularized assembly type machine room implementation method based on BIM technology
CN112613100A (en) Integrated pipeline integral assembly method based on BIM technology
CN110814640A (en) Stainless steel welding air pipe product production management system based on BIM
CN112832557A (en) Assembly type construction method of subway station cold water machine room based on BIM
CN110968932A (en) Metal air duct product production management system based on BIM
CN110834181A (en) Galvanized sheet is board flange tuber pipe product production management system altogether based on BIM
CN110399666B (en) Method for designing parameterization scheme of tubular air preheater based on NX software
CN110848477A (en) BIM-based production management system for internal heat-preservation silencing air pipe products
CN102426620A (en) High-pressure and ultrahigh-pressure hydraulic pipeline 3D (Three-Dimensional) preassembly and plant prefabrication construction method
CN111382471A (en) BIM-based composite air duct product production management system
CN110802309A (en) Carbon steel welding air pipe product production management system based on BIM
CN111719870B (en) One-step forming installation method for electromechanical pipeline of super high-rise standard layer
CN110825038A (en) Purification system tuber pipe product production management system based on BIM
CN110860579A (en) Galvanized sheet spiral air duct product production management system based on BIM
CN1316327A (en) Method for in-situ repairing used pipeline by inserting high-density polyethylene pipe
CN112303349A (en) Large-section assembled air pipe for stadium roof and installation method
CN106825337A (en) A kind of processing technology for the production of precast stair steel reinforcement cage
CN115618455A (en) Modularized and assembled digital construction method for multi-pump unit
CN111382492A (en) Air duct product production management system based on BIM
CN111365543B (en) Round-top square tube and processing method thereof
CN103437273B (en) Method for machining bottom box used for assembly-type steel box composite beam
CN114576843A (en) Assembly type welding pipeline alignment device and assembly type welding pipeline construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20200228