CN111691601A - Overlapped column with corner vertical holes in centralized arrangement and directly connected with stressed longitudinal bars and construction process - Google Patents

Overlapped column with corner vertical holes in centralized arrangement and directly connected with stressed longitudinal bars and construction process Download PDF

Info

Publication number
CN111691601A
CN111691601A CN202010584141.8A CN202010584141A CN111691601A CN 111691601 A CN111691601 A CN 111691601A CN 202010584141 A CN202010584141 A CN 202010584141A CN 111691601 A CN111691601 A CN 111691601A
Authority
CN
China
Prior art keywords
column
prefabricated
longitudinal
stirrups
vertical hole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010584141.8A
Other languages
Chinese (zh)
Inventor
郁银泉
韩文龙
肖明
王赞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Institute of Building Standard Design and Research Co Ltd
Original Assignee
China Institute of Building Standard Design and Research Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Institute of Building Standard Design and Research Co Ltd filed Critical China Institute of Building Standard Design and Research Co Ltd
Priority to CN202010584141.8A priority Critical patent/CN111691601A/en
Publication of CN111691601A publication Critical patent/CN111691601A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C3/00Structural elongated elements designed for load-supporting
    • E04C3/30Columns; Pillars; Struts
    • E04C3/34Columns; Pillars; Struts of concrete other stone-like material, with or without permanent form elements, with or without internal or external reinforcement, e.g. metal coverings
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/62Insulation or other protection; Elements or use of specified material therefor
    • E04B1/92Protection against other undesired influences or dangers
    • E04B1/98Protection against other undesired influences or dangers against vibrations or shocks; against mechanical destruction, e.g. by air-raids
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C5/00Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
    • E04C5/16Auxiliary parts for reinforcements, e.g. connectors, spacers, stirrups
    • E04C5/162Connectors or means for connecting parts for reinforcements
    • E04C5/163Connectors or means for connecting parts for reinforcements the reinforcements running in one single direction
    • E04C5/165Coaxial connection by means of sleeves
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H9/00Buildings, groups of buildings or shelters adapted to withstand or provide protection against abnormal external influences, e.g. war-like action, earthquake or extreme climate
    • E04H9/02Buildings, groups of buildings or shelters adapted to withstand or provide protection against abnormal external influences, e.g. war-like action, earthquake or extreme climate withstanding earthquake or sinking of ground
    • E04H9/025Structures with concrete columns

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Business, Economics & Management (AREA)
  • Emergency Management (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Reinforcement Elements For Buildings (AREA)

Abstract

角部竖孔集中配置直接连接受力纵筋的叠合柱及施工工艺,预埋定型管道在预制柱四个角部形成贯通竖孔,预制柱内仅配置构造纵筋、辅助纵筋、箍筋及拉筋,无钢筋伸出预制柱;施工现场在预制柱角部竖孔内集中配置柱受力纵筋,上下层柱受力纵筋在预制柱根部采用机械连接接头直接连接;浇筑竖孔内后浇混凝土后,预制柱与后浇部分形成叠合柱参与结构受力。定型管道采用薄壁钢板卷折制作。柱截面较大时在预制柱截面中部设置贯通浇筑孔,保证底部水平接缝后浇混凝土浇筑密实。上述构造预制柱生产阶段模具不开孔,预制柱内不配置受力纵筋,模具、钢筋笼标准化程度高;受力纵筋直接连接,连接可靠、成本低;现场无常规灌浆施工,施工速度快、质量易于保证。

Figure 202010584141

The vertical holes at the corners are centrally configured with superimposed columns and construction techniques that directly connect the stressed longitudinal bars. The pre-buried shaped pipes form through vertical holes at the four corners of the prefabricated columns. Only the structural longitudinal bars, auxiliary longitudinal bars and hoop are arranged in the prefabricated columns. Bars and tie bars, no reinforcement sticks out of the prefabricated column; the longitudinal reinforcement of the column is centrally arranged in the vertical hole at the corner of the prefabricated column at the construction site, and the longitudinal reinforcement of the upper and lower columns is directly connected by mechanical connection joints at the root of the prefabricated column; After the concrete is post-cast in the hole, the precast column and post-cast part form a superimposed column to participate in the structural stress. Shaped pipes are made by rolling thin-walled steel plates. When the column section is large, a through pouring hole is set in the middle of the prefabricated column section to ensure that the bottom horizontal joint is poured and the concrete is poured densely. In the production stage of the above-mentioned prefabricated columns, the molds do not have holes, and the prefabricated columns are not equipped with longitudinal reinforcement. The standardization of the mold and the reinforcement cage is high; the longitudinal reinforcement is directly connected, the connection is reliable, and the cost is low. Fast, quality is easy to guarantee.

Figure 202010584141

Description

角部竖孔集中配置直接连接受力纵筋的叠合柱及施工工艺Stacked Columns Directly Connected with Stressed Longitudinal Reinforcing Bars and Construction Technology

技术领域technical field

本发明属于建筑技术领域,涉及预制柱,特别涉及一种角部竖孔集中配置直接连接受力纵筋的叠合柱及施工工艺。The invention belongs to the technical field of construction, relates to a prefabricated column, and particularly relates to a superimposed column with vertical holes at the corners being centrally arranged to directly connect the longitudinal reinforcement under force and a construction process.

背景技术Background technique

目前装配式混凝土框架结构在我国装配式混凝土公共建筑中广泛应用,其中预制柱纵筋多采用套筒灌浆连接,预制柱为实心构件、自重大,运输、吊装要求高;预制柱需伸出纵筋,生产阶段模具需开孔,预制柱钢筋笼标准化程度低,生产效率较低;纵筋采用套筒灌浆连接,存在钢筋对位困难、接头灌浆质量管控难度大及冬季施工可行性差等问题,引发了一系列社会关注。At present, prefabricated concrete frame structures are widely used in prefabricated concrete public buildings in my country. The longitudinal bars of prefabricated columns are mostly connected by sleeve grouting. In the production stage, the mold needs to be opened, the standardization of the prefabricated column reinforcement cage is low, and the production efficiency is low; aroused a series of social concerns.

针对以上问题,国内外发展了以纵筋搭接连接为基础的空心柱技术,缓解了预制柱纵筋采用套筒灌浆连接带来的加工、安装难度,但一般来说,柱纵筋直径往往大于20mm,采用搭接连接时存在搭接长度较长、钢筋用量较大的问题,且大直径钢筋搭接连接传力的可靠性尚未得到充分的试验验证。搭接连接会导致地震作用下柱塑性铰上移,削弱柱的弹塑性变形能力,同时易形成短柱效应。此外,现有空心柱多采用抽芯或多次预制加工形成内部中空,生产工艺复杂、工序多,无法在我国大量既有平模生产线上生产,推广受到制约。In response to the above problems, the hollow column technology based on the lap connection of longitudinal bars has been developed at home and abroad, which relieves the processing and installation difficulties caused by the use of sleeve grouting connection for the longitudinal bars of prefabricated columns. If it is larger than 20mm, there are problems of long lap length and large amount of steel bars when using lap joints, and the reliability of the force transmission of large-diameter steel bar lap joints has not been fully verified by tests. The lap joint will cause the plastic hinge of the column to move up under the action of earthquake, weaken the elastic-plastic deformation ability of the column, and easily form the short column effect. In addition, the existing hollow columns mostly use core pulling or multiple prefabrication processes to form an internal hollow, the production process is complex, and there are many procedures, which cannot be produced on a large number of existing flat die production lines in my country, and the promotion is restricted.

发明内容SUMMARY OF THE INVENTION

为了克服上述现有技术的缺点,本发明的目的在于提供一种角部竖孔集中配置直接连接受力纵筋的叠合柱及施工工艺,采用定型管道经一次混凝土浇筑在预制柱角部形成贯通竖孔,无需专用成孔设备,可在既有平模生产线上生产,预制生产环节少、生产效率高。柱受力纵筋穿设于预制柱角部竖孔内并采用机械连接接头直接连接,传力可靠,可避免纵筋搭接连接引起的柱塑性铰上移、弹塑性变形能力降低及短柱破坏效应,可保证叠合柱达到等同现浇的抗震性能。此外,预制柱无钢筋伸出,生产阶段可实现模具标准化、通用化,有助于预制柱成本控制及运输过程中的成品保护In order to overcome the above-mentioned shortcomings of the prior art, the purpose of the present invention is to provide a superimposed column and a construction process in which the vertical holes at the corners are centrally arranged to directly connect the stressed longitudinal bars, and the formed pipes are formed at the corners of the prefabricated columns by one-time concrete pouring. Through the vertical hole, there is no need for special hole-forming equipment, and it can be produced on the existing flat die production line, with few prefabricated production links and high production efficiency. The longitudinal reinforcement of the column is penetrated in the vertical hole at the corner of the prefabricated column and is directly connected by mechanical connection joints. The force transmission is reliable, which can avoid the upward movement of the column plastic hinge, the reduction of the elastic-plastic deformation capacity and the short column caused by the overlapping connection of the longitudinal reinforcement. The damage effect can ensure that the composite column achieves the same seismic performance as cast-in-place. In addition, the prefabricated column has no steel bar protruding, and the standardization and generalization of the mold can be realized in the production stage, which is helpful for the cost control of the prefabricated column and the protection of the finished product during transportation.

为了实现上述目的,本发明采用的技术方案是:In order to achieve the above object, the technical scheme adopted in the present invention is:

角部竖孔集中配置直接连接受力纵筋的叠合柱,包括预制柱1,在预制柱1的每个角部分别布置一个竖孔11,施工现场在每个竖孔11内集中布置受力纵筋21,为叠合柱提供抗弯能力,并在预制柱1内配置箍筋,对预制柱混凝土及后浇混凝土24形成箍筋约束作用,为叠合柱提供弹塑性变形能力,其中受力纵筋21和箍筋分离配置,后浇混凝土24浇筑于竖孔11内,浇筑后预制柱1与后浇混凝土24及受力纵筋21形成叠合柱整体,参与结构受力。The vertical holes at the corners are centrally arranged with superimposed columns directly connected to the longitudinal reinforcement under stress, including the prefabricated column 1. A vertical hole 11 is arranged at each corner of the prefabricated column 1, and the construction site is centrally arranged in each vertical hole 11. The longitudinal reinforcement 21 provides bending resistance for the superimposed column, and stirrups are arranged in the prefabricated column 1 to form a stirrup restraint effect on the precast column concrete and the post-cast concrete 24, and provide elastic-plastic deformation capacity for the superimposed column, wherein The stressed longitudinal bars 21 and the stirrups are arranged separately, the post-cast concrete 24 is poured in the vertical holes 11, and the post-cast precast column 1, the post-cast concrete 24 and the stressed longitudinal bars 21 form a superimposed column as a whole, participating in the structural stress.

所述预制柱1横截面为矩形,在其四个角部预埋定型管道12浇筑预制柱1混凝土后形成贯通的竖孔11所述定型管道12采用薄壁钢板卷折制作,内壁可设置凸起形成粗糙面,也可采用钢板自然成型面,横截面形状为六边形、切角矩形、圆角矩形或圆形,相应的竖孔11横截面形状为六边形、切角矩形、圆角矩形或圆形,定型管道12边沿距离预制柱1四边的最大尺寸均不小于120mm。The cross-section of the prefabricated column 1 is rectangular, and the prefabricated column 1 is pre-buried at its four corners to form a vertical hole 11 after the prefabricated column 1 is poured with concrete. The shape of the cross section is hexagon, chamfered rectangle, rounded rectangle or circle, and the corresponding vertical hole 11 has a cross section shape of hexagon, chamfered rectangle, circle The corners are rectangular or round, and the maximum dimension of the edge of the shaping pipe 12 from the four sides of the prefabricated column 1 is not less than 120mm.

在预制柱1内配置构造纵筋131或辅助纵筋132,与箍筋形成预制柱钢筋笼13,构造纵筋131或辅助纵筋132的直径均为构造要求,不随叠合柱受力情况改变,构造纵筋131或辅助纵筋132不伸出预制柱1的底面、顶面,不参与受力计算。The structural longitudinal reinforcement 131 or the auxiliary longitudinal reinforcement 132 is arranged in the prefabricated column 1, and the prefabricated column reinforcement cage 13 is formed with the stirrups. The diameter of the structural longitudinal reinforcement 131 or the auxiliary longitudinal reinforcement 132 is a structural requirement and does not change with the stress of the superimposed column. , the structural longitudinal bars 131 or the auxiliary longitudinal bars 132 do not protrude from the bottom surface and top surface of the prefabricated column 1, and do not participate in the force calculation.

所述构造纵筋131布设于预制柱1箍筋角部或相交位置,构造纵筋131直径介于8~12mm,根数及位置根据箍筋形式确定,与箍筋绑扎或焊接固定;所述竖孔11内侧的箍筋沿水平方向的肢距a不大于400mm时,不在预制柱1各边中部设置辅助纵筋132;所述竖孔11内侧的箍筋沿水平方向的肢距a大于400mm时,在预制柱1各边中部设置辅助纵筋132以控制箍筋肢距,辅助纵筋132直径介于10~14mm。The structural longitudinal bars 131 are arranged at the corners or intersections of the stirrups of the prefabricated column 1. The diameter of the structural longitudinal bars 131 is between 8 and 12 mm. When the distance a of the stirrups inside the vertical hole 11 along the horizontal direction is not greater than 400mm, the auxiliary longitudinal bars 132 are not arranged in the middle of each side of the prefabricated column 1; the distance a of the stirrups inside the vertical hole 11 along the horizontal direction is greater than 400mm At the time, auxiliary longitudinal bars 132 are arranged in the middle of each side of the prefabricated column 1 to control the distance between the legs of the stirrups, and the diameter of the auxiliary longitudinal bars 132 is between 10 and 14 mm.

所述箍筋采用由大箍筋133、小箍筋134及拉筋135形成的复合箍筋,或采用焊接箍筋网136,其中大箍筋133、小箍筋134采用焊接封闭箍,小箍筋134在每一层有多个,分别对相邻的竖孔11形成约束,大箍筋133对所有竖孔11形成约束。The stirrups are composite stirrups formed by large stirrups 133, small stirrups 134 and tie bars 135, or a welded stirrup net 136, wherein the large stirrups 133 and the small stirrups 134 are welded closed stirrups, and the small stirrups are welded. There are a plurality of ribs 134 on each layer, which constrain the adjacent vertical holes 11 respectively, and the large stirrups 133 constrain all the vertical holes 11 .

当预制柱1边长大于700mm时,在预制柱1截面中部预埋定型管道或波纹管形成贯通预制柱1高度方向的浇筑孔16,保证底部水平接缝4后浇混凝土24浇筑密实;浇筑孔16横截面距离预制柱1四边的最大尺寸均不小于90mm;施工现场浇筑孔16内不布设纵筋。When the length of the side of the prefabricated column 1 is greater than 700mm, the prefabricated pipes or corrugated pipes are embedded in the middle of the section of the prefabricated column 1 to form a pouring hole 16 penetrating the height direction of the prefabricated column 1 to ensure that the bottom horizontal joint 4 is poured with concrete 24. 16. The maximum dimension of the cross section from the four sides of the prefabricated column 1 is not less than 90mm; no longitudinal reinforcement is arranged in the pouring hole 16 at the construction site.

每个竖孔11内布设的受力纵筋21不多于四根,受力纵筋21参与受力计算,直径不小于16mm且不大于32mm,配筋面积满足叠合柱受弯承载力验算要求,且需满足现行规范对柱受力纵筋的最小配筋率要求;上下层受力纵筋21采用钢筋接头23连接,钢筋接头23为机械连接接头,布置在同一高度,或沿高度错开一定距离。There are no more than four stressed longitudinal bars 21 arranged in each vertical hole 11, and the stressed longitudinal bars 21 are involved in the stress calculation. and the minimum reinforcement ratio requirements of the current code for the longitudinal reinforcement of the column; the longitudinal reinforcement 21 of the upper and lower layers is connected by the reinforcement joint 23, and the reinforcement joint 23 is a mechanical connection joint, arranged at the same height, or staggered along the height a certain distance.

在预制柱1底部设置凸起14保证底部水平接缝4与预制柱1底面附近后浇混凝土24的密实性,提高底部水平接缝4的抗剪能力,凸起14突出预制柱1的高度不小于30mm,四周设置斜面。Protrusions 14 are arranged at the bottom of the prefabricated column 1 to ensure the compactness of the bottom horizontal joint 4 and the post-cast concrete 24 near the bottom surface of the prefabricated column 1, and to improve the shear resistance of the bottom horizontal joint 4. The height of the projection 14 protruding from the prefabricated column 1 is not Less than 30mm, bevels are set around.

本发明还提供了所述角部竖孔集中配置直接连接受力纵筋的叠合柱的施工工艺,在预制柱1的每个角部分别加工一个贯通的竖孔11,在施工现场,将受力纵筋21集中布置在每个竖孔11内,为叠合柱提供抗弯能力,并在预制柱1内配置箍筋,对预制柱混凝土及后浇混凝土24形成箍筋约束作用,为叠合柱提供弹塑性变形能力,其中受力纵筋21和箍筋分离配置,在竖孔11内浇筑后浇混凝土24,浇筑后预制柱1与后浇混凝土24及受力纵筋21形成叠合柱整体,参与结构受力。The present invention also provides a construction process in which the vertical holes at the corners are centrally arranged with the superimposed columns directly connected to the stressed longitudinal bars. A through vertical hole 11 is respectively machined at each corner of the prefabricated column 1. On the construction site, the The stressed longitudinal reinforcement 21 is concentrated in each vertical hole 11 to provide bending resistance for the stacked column, and stirrups are arranged in the prefabricated column 1 to form a stirrup restraint effect on the prefabricated column concrete and the post-cast concrete 24. The superimposed column provides elastic-plastic deformation ability, wherein the longitudinal reinforcement 21 and the stirrup are arranged separately, and the concrete 24 is poured after pouring in the vertical hole 11. Combined with the column as a whole, it participates in the stress of the structure.

所述预制柱1在受力纵筋21与楼板3伸出的下层柱受力纵筋22连接后吊装,预制柱1底部水平接缝4高度不小于60mm,钢筋接头23布设在竖孔11内,通过调平螺栓25控制底部水平接缝4的高度及预制柱1的安装精度,调平螺栓25拧入预埋于预制柱1底部的预埋内螺纹套筒15;或在预制柱1吊装完成后,在竖孔11内穿设受力纵筋21与楼板3伸出的下层柱受力纵筋22连接,预制柱1底部水平接缝4高度不小于200mm,钢筋接头23布设在底部水平接缝4内,通过柱腿26控制底部水平接缝4的高度。The prefabricated column 1 is hoisted after the longitudinal reinforcement 21 is connected with the longitudinal reinforcement 22 of the lower column extending from the floor 3. The height of the horizontal joint 4 at the bottom of the prefabricated column 1 is not less than 60mm, and the steel joint 23 is arranged in the vertical hole 11. , the height of the bottom horizontal joint 4 and the installation accuracy of the prefabricated column 1 are controlled by the leveling bolt 25. The leveling bolt 25 is screwed into the pre-embedded internal thread sleeve 15 embedded in the bottom of the prefabricated column 1; or the prefabricated column 1 is hoisted. After completion, the longitudinal reinforcement 21 is inserted in the vertical hole 11 to connect with the longitudinal reinforcement 22 of the lower column extending from the floor 3. The height of the horizontal joint 4 at the bottom of the prefabricated column 1 is not less than 200mm, and the steel joint 23 is arranged at the bottom level. Inside the seam 4, the height of the bottom horizontal seam 4 is controlled by the legs 26.

具体地,先连接后吊装时,将底部水平接缝4内大箍筋133摆放于下层柱受力纵筋22根部,将受力纵筋21与楼板3伸出的下层柱受力纵筋22逐一采用钢筋接头23连接,然后吊装预制柱1,调节调平螺栓25校准预制柱1安装精度,接着将底部水平接缝4内大箍筋133向上移动至设计位置并与下层柱受力纵筋22绑扎定位;之后支设底部水平接缝4,通过竖孔11完成底部水平接缝4及竖孔4内后浇混凝土24的浇筑;最后养护拆模,完成预制柱1与下层结构的连接。Specifically, when first connecting and then hoisting, place the large stirrups 133 in the bottom horizontal joint 4 at the root of the lower column stress longitudinal bars 22, and place the stress longitudinal bars 21 and the lower column stress longitudinal bars extending from the floor 3. 22 Connect the steel bar joints 23 one by one, then hoist the prefabricated column 1, adjust the leveling bolts 25 to calibrate the installation accuracy of the prefabricated column 1, and then move the large stirrups 133 in the bottom horizontal joint 4 upward to the design position and bear longitudinal force with the lower column. The rib 22 is bound and positioned; the bottom horizontal joint 4 is then supported, and the bottom horizontal joint 4 and the post-poured concrete 24 in the vertical hole 4 are completed through the vertical hole 11; finally, the curing formwork is removed to complete the connection between the prefabricated column 1 and the lower structure .

先吊装后连接时,将底部水平接缝4内大箍筋133摆放于下层柱受力纵筋22根部;然后放置柱腿26,吊装预制柱1,调节预制柱1安装精度;接着在竖孔11内从上往下穿设受力纵筋21,并在底部水平接缝4内完成钢筋接头23的连接施工,再将底部水平接缝4内大箍筋133向上移动至设计位置并与受力纵筋21、下层柱受力纵筋22绑扎定位,之后支设底部水平接缝4,通过竖孔11完成底部水平接缝4及竖孔11内后浇混凝土24的浇筑;最后养护拆模,完成预制柱1与下层结构的连接。When first hoisting and then connecting, place the large stirrups 133 in the bottom horizontal joint 4 at the root of the lower column stressed longitudinal bars 22; then place the column legs 26, hoist the prefabricated column 1, and adjust the installation accuracy of the prefabricated column 1; The stressed longitudinal bars 21 are pierced from top to bottom in the holes 11, and the connection construction of the steel bar joints 23 is completed in the bottom horizontal joint 4, and then the large stirrups 133 in the bottom horizontal joint 4 are moved upwards to the design position and are connected with each other. The stressed longitudinal reinforcement 21 and the lower column stressed longitudinal reinforcement 22 are bound and positioned, and then the bottom horizontal joint 4 is supported, and the bottom horizontal joint 4 and the post-cast concrete 24 in the vertical hole 11 are completed through the vertical hole 11; The mold is completed to complete the connection between the prefabricated column 1 and the lower structure.

与现有技术相比,本发明的有益效果是:Compared with the prior art, the beneficial effects of the present invention are:

(1)本发明预制柱受力纵筋无需采用套筒灌浆连接接头连接,避免了现有套筒灌浆连接预制柱钢筋对位困难、接头灌浆质量管控难度大及冬季施工可行性差等问题。(1) The longitudinal reinforcement of the prefabricated column of the present invention does not need to be connected by the sleeve grouting connection joint, which avoids the problems of the existing sleeve grouting connection of the prefabricated column steel bar alignment difficulty, the difficulty of joint grouting quality control, and the poor feasibility of winter construction.

(2)本发明柱受力纵筋集中布设在预制柱角部竖孔内,且采用钢筋机械连接接头,纵筋受力效率高,无钢筋对位问题,现场安装效率高,接头成本低。(2) The longitudinal reinforcement of the column under force of the present invention is concentratedly arranged in the vertical hole at the corner of the prefabricated column, and the mechanical connection joint of the reinforcement is adopted, the longitudinal reinforcement has high stress efficiency, no reinforcement alignment problem, high on-site installation efficiency, and low joint cost.

(3)相较纵筋搭接连接的空心柱,本发明柱受力纵筋采用钢筋机械连接接头直接连接,传力可靠,可避免纵筋搭接连接引起的柱塑性铰上移、弹塑性变形能力降低及短柱破坏效应,可保证叠合柱达到等同现浇的抗震性能。(3) Compared with the hollow column connected by the lap joint of the longitudinal reinforcement, the longitudinal reinforcement of the column in the present invention is directly connected by the mechanical connection joint of the reinforcement bar, and the force transmission is reliable, which can avoid the upward movement of the column plastic hinge and the elastic plastic caused by the overlapping connection of the longitudinal reinforcement. Deformation capacity reduction and short column failure effect can ensure that the composite column achieves the same seismic performance as cast-in-place.

(4)本发明预制柱采用定型管道一次浇筑形成竖孔,无需专用成孔设备,可采用既有平模生产线平模生产,预制柱一次成型,预制生产环节少、生产效率高。(4) The prefabricated column of the present invention is casted in one time to form a vertical hole, without special hole-forming equipment, and can be produced by a flat die of an existing flat die production line.

(5)本发明所采用的定型管道形状简单,便于加工,且成本较低,有利于预制柱的成本控制。(5) The shape of the shaping pipe used in the present invention is simple, easy to process, and has a low cost, which is beneficial to the cost control of the prefabricated column.

(6)本发明预制柱钢筋笼无受力纵筋,构造纵筋和辅助纵筋的直径便于统一,可实现预制柱钢筋笼的标准化、通用化,便于预制构件厂生产组织。(6) The prefabricated column reinforcement cage of the present invention has no longitudinal reinforcement under stress, the diameters of the structural longitudinal reinforcement and the auxiliary longitudinal reinforcement are easy to unify, the standardization and generalization of the prefabricated column reinforcement cage can be realized, and the production organization of the prefabricated component factory is convenient.

(7)本发明预制柱无钢筋伸出,生产阶段模具无需开孔,可采用标准化模具降低成本,有利于运输、吊装过程中预制柱的成品保护。(7) The prefabricated column of the present invention does not have steel bars protruding, and the mold does not need to open holes in the production stage, and standardized molds can be used to reduce costs, which is beneficial to the finished product protection of the prefabricated column during transportation and hoisting.

附图说明Description of drawings

图1为本发明预制柱的三维示意图,预制柱内预埋横截面为六边形的定型管道形成竖孔。Fig. 1 is a three-dimensional schematic diagram of a prefabricated column of the present invention. A vertical hole is formed by pre-embedding a hexagonal shaped pipe in the prefabricated column.

图2为图1中A-A截面示意图。FIG. 2 is a schematic view of the section A-A in FIG. 1 .

图3为图1中采用的六边形定型管道的三维示意图。FIG. 3 is a three-dimensional schematic diagram of the hexagonal shaped pipe used in FIG. 1 .

图4为图1中预制柱钢筋笼的示意图。FIG. 4 is a schematic diagram of the prefabricated column reinforcement cage in FIG. 1 .

图5为先连接柱受力纵筋、再安装预制柱时的预制柱与下层结构连接的三维示意图。FIG. 5 is a three-dimensional schematic diagram of the connection between the prefabricated column and the lower structure when the longitudinal reinforcement of the column is connected first, and then the prefabricated column is installed.

图6为图5中B-B截面示意图。FIG. 6 is a schematic cross-sectional view of B-B in FIG. 5 .

图7为图5中底部水平接缝连接构造示意图。FIG. 7 is a schematic diagram of the bottom horizontal seam connection structure in FIG. 5 .

图8为图5中底部水平接缝局部构造三维示意图。FIG. 8 is a three-dimensional schematic diagram of the partial structure of the bottom horizontal seam in FIG. 5 .

图9为图5中预制柱底部构造三维示意图。FIG. 9 is a three-dimensional schematic diagram of the bottom structure of the prefabricated column in FIG. 5 .

图10为先安装预制柱、再连接柱受力纵筋时的预制柱与下层结构连接的三维示意图。FIG. 10 is a three-dimensional schematic diagram of the connection between the prefabricated column and the lower structure when the prefabricated column is installed first, and then the longitudinal reinforcement of the column is connected.

图11为图10中底部水平接缝连接构造示意图。FIG. 11 is a schematic diagram of the connection structure of the bottom horizontal seam in FIG. 10 .

图12为预制柱竖孔横截面为切角矩形的叠合柱构造示意图。Fig. 12 is a schematic diagram of the structure of a superimposed column with a vertical hole of a prefabricated column having a rectangular cross-section.

图13为图12中预制柱采用的横截面为切角矩形的定型管道示意图。Fig. 13 is a schematic diagram of a shaped pipe whose cross section is a chamfered rectangle used in the prefabricated column in Fig. 12 .

图14为预制柱竖孔横截面为圆角矩形的叠合柱构造示意图。Fig. 14 is a schematic diagram of the structure of a superimposed column with a vertical hole of a prefabricated column having a rounded rectangular cross-section.

图15为图14中预制柱采用的横截面为圆角矩形的定型管道示意图。FIG. 15 is a schematic diagram of a shaped pipe with a rounded rectangular cross-section used in the prefabricated column in FIG. 14 .

图16为采用焊接箍筋网的预制柱截面构造示意图。Fig. 16 is a schematic diagram of the cross-sectional structure of a prefabricated column using a welded stirrup mesh.

图17为图16中预制柱钢筋笼的示意图。FIG. 17 is a schematic diagram of the prefabricated column reinforcement cage in FIG. 16 .

图18为横截面中部设置贯通浇筑孔的预制柱的三维示意图。FIG. 18 is a three-dimensional schematic diagram of a prefabricated column with a through-casting hole provided in the middle of the cross section.

图19为图18中预制柱形成的叠合柱的截面构造示意图。FIG. 19 is a schematic cross-sectional structural diagram of the superimposed column formed by the prefabricated column in FIG. 18 .

图20为预制柱截面较小、不设置辅助纵筋的截面示意图。Figure 20 is a schematic cross-sectional view of a prefabricated column with a small cross-section and no auxiliary longitudinal reinforcement.

图21为预制柱竖孔横截面为切角矩形、每个竖孔内配置四根受力纵筋的叠合柱构造示意图。Figure 21 is a schematic diagram of the structure of a superimposed column in which the vertical hole of the prefabricated column is a rectangle with cut corners in cross section, and four longitudinal ribs are arranged in each vertical hole.

图22为预制柱竖孔横截面为圆角矩形、每个竖孔内配置四根受力纵筋的叠合柱构造示意图。Figure 22 is a schematic diagram of the structure of a superimposed column in which the vertical hole of the prefabricated column is a rounded rectangle in cross section, and four longitudinal ribs are arranged in each vertical hole.

图中:1-预制柱;11-竖孔;12-定型管道;13-预制柱钢筋笼;131-构造纵筋;132-辅助纵筋;133-大箍筋;134-小箍筋;135-拉筋;136-焊接箍筋网;14-凸起;15-预埋内螺纹套筒;16-浇筑孔;21-受力纵筋;22-下层柱受力纵筋;23-钢筋接头;24-后浇混凝土;25-调平螺栓;26-柱腿;3-楼板;4-底部水平接缝。In the figure: 1- prefabricated column; 11- vertical hole; 12- shaped pipe; 13- prefabricated column reinforcement cage; 131- structural longitudinal reinforcement; 132- auxiliary longitudinal reinforcement; 133- large stirrup; 134- small stirrup; 135 - Tension bar; 136 - Welded stirrup mesh; 14 - Protrusion; 15 - Embedded internal thread sleeve; 16 - Pouring hole; 21 - Stressed longitudinal reinforcement; 22 - Stressed longitudinal reinforcement of lower column; ; 24- post-cast concrete; 25- leveling bolts; 26- column legs; 3- floors; 4- bottom horizontal joints.

具体实施方式Detailed ways

下面结合附图和实施例详细说明本发明的实施方式。The embodiments of the present invention will be described in detail below with reference to the accompanying drawings and examples.

如图1~图22所示,本发明角部竖孔集中配置直接连接受力纵筋的叠合柱及施工工艺,叠合柱包括预制柱1、后浇混凝土24及布设于竖孔11内的受力纵筋21。其中受力纵筋21为叠合柱提供抗弯能力,箍筋通过约束作用改善混凝土受压性能进而保证叠合柱的弹塑性变形能力,本发明基于叠合柱内不同功能的钢筋分离配置的思想,对预制柱及连接构造做出优化、改进,将受力纵筋21及箍筋分离配置。As shown in FIGS. 1 to 22 , the vertical holes at the corners of the present invention are centrally configured with stacked columns and construction techniques that directly connect the stressed longitudinal bars. The stressed longitudinal bars 21. Among them, the longitudinal reinforcement 21 provides bending resistance for the superimposed column, and the stirrup improves the compressive performance of the concrete through the restraint effect to ensure the elastic-plastic deformation ability of the superimposed column. The idea is to optimize and improve the prefabricated column and connection structure, and separate and configure the longitudinal reinforcement 21 and the stirrup.

具体地,在预制柱1各个角部预留贯通竖孔11,施工现场将受力纵筋21集中布置于预制柱1的角部竖孔11内,为叠合柱提供抗弯能力;将箍筋全部配置于预制柱1内,对预制柱混凝土及后浇混凝土24形成箍筋约束作用,保证叠合柱的弹塑性变形能力;浇筑竖孔11内后浇混凝土24后,预制柱1与后浇混凝土24及布设于竖孔11内的受力纵筋21形成叠合柱整体参与结构受力。Specifically, through vertical holes 11 are reserved at each corner of the prefabricated column 1, and the stressed longitudinal bars 21 are centrally arranged in the corner vertical holes 11 of the prefabricated column 1 on the construction site to provide bending resistance for the superimposed column; The ribs are all arranged in the prefabricated column 1, forming a stirrup restraint effect on the prefabricated column concrete and the post-cast concrete 24 to ensure the elastic-plastic deformation capacity of the superimposed column; The poured concrete 24 and the stressed longitudinal bars 21 arranged in the vertical holes 11 form a superimposed column to participate in the stress of the structure as a whole.

上下层竖孔11内受力纵筋21采用钢筋接头23连接,钢筋接头23为机械连接接头,优先采用直螺纹接头,接头可布置在同一高度,也可沿高度错开一定距离避免在同一连接区段100%连接,以降低对接头性能的要求。受力纵筋21参与受力计算,配筋总面积满足叠合柱受弯承载力验算要求,且需满足现行规范对柱受力纵筋的最小配筋率要求。每个竖孔11内受力纵筋21的总根数不超过四根,受力纵筋21的直径不小于16mm且不应大于32mm,每个竖孔11内受力纵筋21的根数应根据配筋总面积、直径综合确定,在优选地控制受力纵筋21的直径介于20~28mm的前提下,尽可能减少每个竖孔11内受力纵筋21的根数,减少钢筋接头23的数量,同时便于竖孔11内后浇混凝土24的浇筑及振捣,提高现场施工效率、降低成本。The longitudinal reinforcement bars 21 in the vertical holes 11 on the upper and lower layers are connected by steel bar joints 23. The steel bar joints 23 are mechanical connection joints, and straight threaded joints are preferred. The joints can be arranged at the same height or staggered along the height to avoid being in the same connection area. Segments are 100% connected to reduce demands on joint performance. The stressed longitudinal reinforcement 21 participates in the stress calculation, and the total reinforcement area meets the requirements for checking the flexural bearing capacity of the superimposed column, and also needs to meet the minimum reinforcement ratio requirements of the current code for the longitudinal reinforcement of the column under stress. The total number of stressed longitudinal bars 21 in each vertical hole 11 shall not exceed four, the diameter of the stressed longitudinal bars 21 shall not be less than 16 mm and shall not be greater than 32 mm, and the number of stressed longitudinal bars 21 in each vertical hole 11 shall be It should be comprehensively determined according to the total area and diameter of the reinforcement. Under the premise that the diameter of the longitudinal reinforcement 21 under stress is preferably controlled to be between 20 and 28 mm, the number of longitudinal reinforcement reinforcement 21 in each vertical hole 11 should be reduced as much as possible. The number of steel bar joints 23 facilitates the pouring and vibrating of the post-cast concrete 24 in the vertical hole 11, thereby improving the site construction efficiency and reducing the cost.

本发明的一种结构中,预制柱1横截面为矩形,仅在预制柱1四个角部预留贯通的竖孔11用以布设受力纵筋21,避免施工现场受力纵筋21干扰预制梁安装,同时在保证受力纵筋21布设的前提下减少竖孔11数量、控制预制柱1成本。在预制柱1内配置构造纵筋131或辅助纵筋132与箍筋形成预制柱钢筋笼13,构造纵筋131或辅助纵筋132不伸出预制柱底面、顶面,不参与受力计算。In one structure of the present invention, the cross-section of the prefabricated column 1 is rectangular, and only through vertical holes 11 are reserved at the four corners of the prefabricated column 1 for arranging the force-bearing longitudinal bars 21 to avoid the interference of the force-bearing longitudinal bars 21 on the construction site. Prefabricated beams are installed, and at the same time, the number of vertical holes 11 is reduced and the cost of prefabricated columns 1 is controlled on the premise of ensuring the layout of stressed longitudinal bars 21 . The structural longitudinal reinforcement 131 or the auxiliary longitudinal reinforcement 132 and the stirrups are arranged in the prefabricated column 1 to form the prefabricated column reinforcement cage 13 .

竖孔11采用预埋定型管道12在浇筑预制柱1混凝土后一次成型,定型管道12采用薄壁钢板卷折制作,内壁可设置凸起形成粗糙面,也可采用钢板自然成型面,横截面形状为六边形、切角矩形、圆角矩形或圆形,相应的竖孔11横截面形状为六边形、切角矩形、圆角矩形或圆形,定型管道12平行于预制柱1四边的最大尺寸均不小于120mm。The vertical hole 11 is formed by pre-buried shaped pipe 12 after pouring the concrete of the prefabricated column 1. The shaped pipe 12 is made by rolling thin-walled steel plate. The inner wall can be set with protrusions to form a rough surface, or the natural forming surface of the steel plate can be used. The cross-sectional shape It is hexagon, chamfered rectangle, rounded rectangle or circle, and the corresponding vertical hole 11 has a cross-sectional shape of hexagon, chamfered rectangle, rounded rectangle or circle. The maximum size is not less than 120mm.

本发明的一种结构中,构造纵筋131布设在预制柱1箍筋角部或相交位置,与箍筋形成预制柱钢筋笼13,构造纵筋131直径介于8~12mm,根数及位置根据箍筋形式确定,与箍筋绑扎或焊接固定。In one structure of the present invention, the structural longitudinal bars 131 are arranged at the corners or intersections of the stirrups of the prefabricated column 1 to form a prefabricated column reinforcement cage 13 with the stirrups. Determined according to the form of stirrups, tied with stirrups or fixed by welding.

本发明中,预制柱箍筋可采用大箍筋133、小箍筋134及拉筋135组成的复合箍筋,也可直接采用焊接箍筋网136,其中大箍筋133、小箍筋134优先采用焊接封闭箍。小箍筋134可设置四个,分部对相邻的竖孔11形成围合,加强对集中配置于竖孔11内的受力纵筋21的约束作用。In the present invention, the prefabricated column stirrups can be composite stirrups composed of large stirrups 133, small stirrups 134 and tie bars 135, or directly welded stirrup nets 136, of which the large stirrups 133 and the small stirrups 134 are preferred Welded closure hoop. Four small stirrups 134 can be provided, and the subsections form an enclosure for the adjacent vertical holes 11 to strengthen the restraint effect on the stressed longitudinal bars 21 centrally arranged in the vertical holes 11 .

本发明中,预制柱1角部竖孔11内侧的箍筋沿水平方向的肢距a不大于400mm时,可不在预制柱1各边中部设置辅助纵筋132;预制柱1角部竖孔11内侧的箍筋沿水平方向的肢距a大于400mm时,在预制柱1各边中部设置辅助纵筋132以控制箍筋肢距,辅助纵筋132直径介于10~14mm。In the present invention, when the leg distance a of the stirrups inside the vertical holes 11 at the corners of the prefabricated column 1 is not greater than 400 mm in the horizontal direction, the auxiliary longitudinal bars 132 may not be provided in the middle of each side of the prefabricated column 1; the vertical holes 11 at the corners of the prefabricated column 1 When the leg distance a of the inner stirrups along the horizontal direction is greater than 400mm, auxiliary longitudinal bars 132 are arranged in the middle of each side of the prefabricated column 1 to control the leg distance of the stirrups. The diameter of the auxiliary longitudinal bars 132 is between 10 and 14 mm.

本发明中,预制柱1在受力纵筋21与楼板3伸出的下层柱受力纵筋22连接后吊装,此时预制柱1底部水平接缝4高度不小于60mm,钢筋接头23布设在竖孔11内,通过调平螺栓25控制底部水平接缝4的高度及预制柱1的安装精度,调平螺栓25拧入预埋于预制柱1底部的预埋内螺纹套筒15;或在预制柱1吊装完成后,在竖孔11内穿设受力纵筋21与楼板3伸出的下层柱受力纵筋22连接,此时预制柱1底部水平接缝4高度不小于200mm,钢筋接头23布设在底部水平接缝4内,通过柱腿26控制底部水平接缝4的高度。In the present invention, the prefabricated column 1 is hoisted after the longitudinal reinforcement 21 is connected to the longitudinal reinforcement 22 of the lower column extending from the floor 3. At this time, the height of the horizontal joint 4 at the bottom of the prefabricated column 1 is not less than 60mm, and the reinforcement joint 23 is arranged in In the vertical hole 11, the height of the bottom horizontal joint 4 and the installation accuracy of the prefabricated column 1 are controlled by the leveling bolt 25. After the prefabricated column 1 is hoisted, the longitudinal reinforcement 21 is inserted in the vertical hole 11 to connect with the longitudinal reinforcement 22 of the lower column extending from the floor 3. At this time, the height of the horizontal joint 4 at the bottom of the prefabricated column 1 is not less than 200mm. The joint 23 is arranged in the bottom horizontal seam 4, and the height of the bottom horizontal seam 4 is controlled by the column legs 26.

本发明的一种结构中,预制柱1底部设置凸起14保证底部水平接缝4与预制柱1底面附近后浇混凝土24的密实性、提高底部水平接缝4的抗剪能力,凸起14突出预制柱1的高度不小于30mm,四周设置斜面。In one structure of the present invention, protrusions 14 are arranged at the bottom of the prefabricated column 1 to ensure the compactness of the bottom horizontal joint 4 and the post-cast concrete 24 near the bottom surface of the prefabricated column 1, and to improve the shear resistance of the bottom horizontal joint 4. The protrusions 14 The height of the protruding prefabricated column 1 is not less than 30mm, and slopes are arranged around it.

本发明预制柱1边长大于700mm时,可在预制柱1截面中部预埋定型管道或波纹管形成一个或多个浇筑孔16,浇筑孔16贯通预制柱1高度方向,保证底部水平接缝后浇混凝土24浇筑密实;浇筑孔16横截面为圆形或其他形状,边缘距离预制柱1四边的最大尺寸均不小于90mm;施工现场浇筑孔16内不布设纵筋。When the side length of the prefabricated column 1 of the present invention is greater than 700 mm, one or more casting holes 16 can be pre-buried in the middle of the cross-section of the prefabricated column 1 to form one or more pouring holes 16. The pouring concrete 24 is poured densely; the cross-section of the pouring hole 16 is circular or other shapes, and the maximum dimension of the edge from the four sides of the prefabricated column 1 is not less than 90mm; no longitudinal reinforcement is arranged in the pouring hole 16 at the construction site.

图1~图9所示为本发明优选实施例一。如图1~图3所示,预制柱1仅在四个角部预埋图3所示的横截面为六边形的定型管道12形成贯通的竖孔11。定型管道12边沿距离预制柱1四边的最大尺寸均不小于120mm,采用薄壁钢板卷折制作,内壁可设置凸起形成粗糙面。1 to 9 show a preferred embodiment 1 of the present invention. As shown in FIGS. 1 to 3 , only four corners of the prefabricated column 1 are pre-embedded in the hexagonal shaped pipes 12 shown in FIG. 3 to form through vertical holes 11 . The maximum dimension of the edge of the shaping pipe 12 from the four sides of the prefabricated column 1 is not less than 120mm, and is made of thin-walled steel plate, and the inner wall can be provided with protrusions to form a rough surface.

如图4所示,预制柱箍筋采用大箍筋133、小箍筋134及拉筋135组成的复合箍筋,其中大箍筋133、小箍筋134为焊接封闭箍,小箍筋134有四个,每个小箍筋134对相邻的两个竖孔11形成围合,加强对集中配置于竖孔11内的受力纵筋21的约束作用。如图2、图4所示,在大箍筋133四个角部与定型管道12之间各布设一根直径介于8~12mm的构造纵筋131;竖孔11内侧的小箍筋134沿水平方向的肢距a大于400mm,在预制柱1四边中部各设置一根直径介于10~14mm的辅助纵筋132以控制箍筋肢距,在位于平行两边的辅助纵筋132之间布设拉筋135;构造纵筋131、辅助纵筋132与大箍筋133、小箍筋134及拉筋135绑扎或焊接固定,形成图4所示的预制柱钢筋笼13。构造纵筋131、辅助纵筋132的直径均为构造要求,不随叠合柱受力情况改变,因此可实现同一截面尺寸预制柱1的预制柱钢筋笼13的标准化、通用化,便于工业化生产。构造纵筋131或辅助纵筋132不伸出预制柱1底面、顶面,不参与受力计算。As shown in Figure 4, the prefabricated column stirrups are composite stirrups composed of large stirrups 133, small stirrups 134 and tie bars 135, wherein the large stirrups 133 and the small stirrups 134 are welded closed stirrups, and the small stirrups 134 have Four, each small stirrup 134 forms an enclosure for two adjacent vertical holes 11 , and strengthens the restraint effect on the stressed longitudinal ribs 21 centrally arranged in the vertical holes 11 . As shown in FIG. 2 and FIG. 4 , between the four corners of the large stirrup 133 and the shaping pipe 12, a structural longitudinal bar 131 with a diameter of 8 to 12 mm is arranged; the small stirrups 134 inside the vertical hole 11 are along the The distance between the limbs a in the horizontal direction is greater than 400mm. In the middle of the four sides of the prefabricated column 1, an auxiliary longitudinal bar 132 with a diameter of 10 to 14 mm is arranged to control the distance between the legs of the stirrup. Ribs 135 ; structural longitudinal ribs 131 , auxiliary longitudinal ribs 132 , large stirrups 133 , small stirrups 134 and ties 135 are bound or welded to form the prefabricated column reinforcement cage 13 shown in FIG. 4 . The diameters of the structural longitudinal bars 131 and the auxiliary longitudinal bars 132 are all structural requirements and do not change with the stress of the superimposed column. Therefore, the standardization and generalization of the prefabricated column reinforcement cage 13 of the prefabricated column 1 with the same cross-sectional size can be realized, which is convenient for industrial production. The structural longitudinal bars 131 or the auxiliary longitudinal bars 132 do not protrude from the bottom and top surfaces of the prefabricated column 1 and do not participate in the force calculation.

图5、图7、图8提供了预制柱1与下层结构连接的示意图,预制柱1在受力纵筋21与楼板3伸出的下层柱受力纵筋22连接后吊装。如图5~图8所示,施工现场将受力纵筋21集中布置于预制柱1的角部竖孔11内,受力纵筋21与下层柱受力纵筋22采用钢筋接头23直接连接,钢筋接头23为机械连接接头,优先采用直螺纹接头,钢筋接头23在竖孔11内错开一定距离以便于钢筋接头23的连接施工。受力纵筋21参与受力计算,配筋总面积满足叠合柱受弯承载力验算要求,且需满足现行规范对柱受力纵筋的最小配筋率要求。每个竖孔11内受力纵筋21的总根数不超过四根,受力纵筋21的直径不小于16mm且不应大于32mm,图5~图8中每个竖孔11内配置三根受力纵筋21。Figures 5, 7 and 8 provide schematic diagrams of the connection between the prefabricated column 1 and the lower structure. As shown in Figures 5 to 8, the stressed longitudinal bars 21 are centrally arranged in the corner vertical holes 11 of the prefabricated column 1 on the construction site. The steel bar joints 23 are mechanical connection joints, preferably straight threaded joints. The stressed longitudinal reinforcement 21 participates in the stress calculation, and the total reinforcement area meets the requirements for checking the flexural bearing capacity of the superimposed column, and also needs to meet the minimum reinforcement ratio requirements of the current code for the longitudinal reinforcement of the column under stress. The total number of stressed longitudinal ribs 21 in each vertical hole 11 is not more than four, and the diameter of the stressed longitudinal ribs 21 is not less than 16mm and should not be greater than 32mm. In FIGS. 5 to 8 , three are arranged in each vertical hole 11 Stressed longitudinal bars 21.

如图5、图7及图8所示,预制柱1底部设置高度不小于60mm的底部水平接缝4,底部水平接缝4内布设一道大箍筋133,浇筑竖孔11内后浇混凝土24的同时完成底部水平接缝4内后浇混凝土24的浇筑。采用调平螺栓25控制底部水平接缝4的高度及预制柱1的安装精度,调平螺栓25拧入图9中所示的预埋于预制柱1底部的预埋内螺纹套筒15。As shown in Figure 5, Figure 7 and Figure 8, the bottom of the prefabricated column 1 is provided with a bottom horizontal joint 4 with a height of not less than 60mm, a large stirrup 133 is arranged in the bottom horizontal joint 4, and concrete 24 is poured in the vertical hole 11 after pouring. At the same time, the pouring of the post-cast concrete 24 in the bottom horizontal joint 4 is completed. The height of the bottom horizontal joint 4 and the installation accuracy of the prefabricated column 1 are controlled by leveling bolts 25 , which are screwed into the pre-embedded internal thread sleeve 15 shown in FIG. 9 and embedded in the bottom of the prefabricated column 1 .

如图9所示,预制柱1底部设置凸起14保证底部水平接缝4与预制柱1底面附近后浇混凝土24的密实性,同时凸起14与底部水平接缝4内后浇混凝土24形成抗剪键,提高底部水平接缝4的抗剪能力。凸起14突出预制柱1的高度不小于30mm,四周设置斜面,以避免底部水平接缝4内后浇混凝土24浇筑过程中上部形成气泡。As shown in FIG. 9 , the protrusions 14 are provided at the bottom of the prefabricated column 1 to ensure the compactness of the bottom horizontal joint 4 and the post-cast concrete 24 near the bottom surface of the precast column 1, and the post-cast concrete 24 is formed in the protrusion 14 and the bottom horizontal joint 4 at the same time. Shear key to improve the shear resistance of the bottom horizontal seam 4. The height of the protrusion 14 protruding from the prefabricated column 1 is not less than 30mm, and slopes are arranged around it to avoid the formation of air bubbles in the upper part of the post-cast concrete 24 in the bottom horizontal joint 4 during the pouring process.

优选实施例一的现场施工工艺如下:步骤一,将底部水平接缝4内大箍筋133摆放于下层柱受力纵筋22根部,将受力纵筋21与楼板3伸出的下层柱受力纵筋22逐一采用钢筋接头23连接;步骤二,吊装预制柱1,需注意控制受力纵筋21的位置,防止其干扰预制柱下落;步骤三,通过调平螺栓25控制底部水平接缝4的高度,调整预制柱1的垂直度;步骤四,将底部水平接缝4内大箍筋133向上移动至设计位置并与下层柱受力纵筋22绑扎定位;步骤五,支设底部水平接缝4,通过竖孔11完成底部水平接缝4及竖孔11内后浇混凝土24的浇筑;步骤六,养护拆模,完成预制柱1与下层结构的连接,预制柱1与后浇混凝土24及布设于竖孔11内的受力纵筋21形成叠合柱整体参与结构受力。The on-site construction process of the preferred embodiment 1 is as follows: Step 1, place the large stirrups 133 in the bottom horizontal joint 4 at the root of the longitudinal reinforcement 22 of the lower column, and place the longitudinal reinforcement 21 and the lower column extending from the floor 3 The stressed longitudinal bars 22 are connected by steel joints 23 one by one; in step 2, the prefabricated column 1 is hoisted, and attention should be paid to control the position of the stressed longitudinal bars 21 to prevent it from interfering with the falling of the prefabricated column; Adjust the verticality of the prefabricated column 1 according to the height of the seam 4; step 4, move the large stirrup 133 in the bottom horizontal seam 4 to the design position and bind it with the longitudinal reinforcement 22 of the lower column; step 5, support the bottom The horizontal joint 4, through the vertical hole 11, completes the bottom horizontal joint 4 and the pouring of the post-cast concrete 24 in the vertical hole 11; Step 6, curing and removing the formwork, completing the connection between the prefabricated column 1 and the lower structure, and the prefabricated column 1 and the post-casting The concrete 24 and the stressed longitudinal bars 21 arranged in the vertical holes 11 form a superimposed column and participate in the stress of the structure as a whole.

当不便采用优选实施例一的现场施工安装工艺时,此时可按图10、图11所示,在预制柱1吊装完成后,在竖孔11内穿设受力纵筋21与楼板3伸出的下层柱受力纵筋22连接,此时预制柱1底部水平接缝4高度不小于200mm,底部水平接缝4内布设两道大箍筋133。钢筋接头23布设在底部水平接缝4内且布置在同一高度,通过柱腿26控制底部水平接缝4的高度。When it is inconvenient to use the on-site construction and installation process of the preferred embodiment 1, at this time, as shown in Figure 10 and Figure 11, after the prefabricated column 1 is hoisted, the longitudinal reinforcement 21 and the floor slab 3 are drilled in the vertical hole 11. The lower column is connected by the longitudinal reinforcement 22. At this time, the height of the bottom horizontal joint 4 of the prefabricated column 1 is not less than 200mm, and two large stirrups 133 are arranged in the bottom horizontal joint 4. The steel bar joints 23 are arranged in the bottom horizontal joint 4 at the same height, and the height of the bottom horizontal joint 4 is controlled by the column legs 26 .

图10、图11所示叠合柱的现场施工工艺如下:步骤一,将底部水平接缝4内大箍筋133摆放于下层柱受力纵筋22根部;步骤二,放置柱腿26,吊装预制柱1,采用柱腿26控制底部水平接缝4的高度,调整预制柱1的垂直度;步骤三,在竖孔11内从上往下穿设受力纵筋21,并在底部水平接缝4内完成钢筋接头23的连接施工;步骤四,将底部水平接缝4内大箍筋133向上移动至设计位置并与受力纵筋21、下层柱受力纵筋22绑扎定位;步骤五,支设底部水平接缝4,通过竖孔11完成底部水平接缝4及竖孔11内后浇混凝土24的浇筑;步骤六,养护拆模,完成预制柱1与下层结构的连接,预制柱1与后浇混凝土24及布设于竖孔11内的受力纵筋21形成叠合柱整体参与结构受力。The on-site construction process of the superimposed column shown in Figure 10 and Figure 11 is as follows: step 1, place the large stirrups 133 in the bottom horizontal joint 4 at the root of the longitudinal reinforcement 22 of the lower column; step 2, place the column legs 26, Hoist the prefabricated column 1, use the column legs 26 to control the height of the bottom horizontal seam 4, and adjust the verticality of the prefabricated column 1; Step 3, in the vertical hole 11 from top to bottom, wear longitudinal reinforcement 21, and horizontally at the bottom The connection construction of the steel bar joint 23 is completed in the joint 4; step 4, the large stirrup 133 in the bottom horizontal joint 4 is moved upward to the design position and is bound and positioned with the longitudinal reinforcement 21 and the longitudinal reinforcement 22 of the lower column; step Fifth, the bottom horizontal joint 4 is supported, and the bottom horizontal joint 4 and the post-cast concrete 24 in the vertical hole 11 are completed through the vertical hole 11; Step 6, the maintenance and removal of the formwork are completed, and the connection between the prefabricated column 1 and the lower structure is completed. The column 1, the post-cast concrete 24 and the force-bearing longitudinal bars 21 arranged in the vertical hole 11 form a superimposed column and participate in the force bearing of the structure as a whole.

图12、图13为图6所示叠合柱的竖孔11改进型一,在预制柱1四个角部预埋横截面形状为切角矩形的定型管道12形成竖孔11,定型管道12仅在大箍筋133对应的角部切角以避让大箍筋133。定型管道12平行于预制柱1四边的最大尺寸均不小于120mm,采用薄壁钢板卷折制作,内壁可设置凸起形成粗糙面。预制柱1的构造钢筋131布置与优选实施例一相同。Fig. 12 and Fig. 13 are the modified version 1 of the vertical hole 11 of the superimposed column shown in Fig. 6. The four corners of the prefabricated column 1 are pre-embedded in the four corners of the prefabricated column 1. The shape of the cross-sectional shape is a rectangular shape. The vertical hole 11 is formed. Only the corners corresponding to the large stirrups 133 are cut to avoid the large stirrups 133 . The maximum dimension of the shaped pipe 12 parallel to the four sides of the prefabricated column 1 is not less than 120mm, and is made of thin-walled steel plate, and the inner wall can be provided with protrusions to form a rough surface. The arrangement of the structural reinforcement bars 131 of the prefabricated column 1 is the same as that of the first preferred embodiment.

图14、图15为图6所示叠合柱的竖孔11改进型二,在预制柱1四个角部预埋横截面形状为圆角矩形的定型管道12形成竖孔11,定型管道12四个角部均为圆角。定型管道12平行于预制柱1四边的最大尺寸均不小于120mm,采用薄壁钢板卷折制作,内壁可设置凸起形成粗糙面。预制柱1的构造钢筋131布设在小箍筋134与大箍筋133相交位置,共布置8根构造钢筋131。Figures 14 and 15 show the second modification of the vertical hole 11 of the superimposed column shown in Figure 6. The four corners of the prefabricated column 1 are pre-embedded in the four corners of the prefabricated column 1. The shape of the cross-sectional shape is a rounded rectangle to form the vertical hole 11, and the shaped pipe 12 All four corners are rounded. The maximum dimension of the shaped pipe 12 parallel to the four sides of the prefabricated column 1 is not less than 120mm, and is made of thin-walled steel plate, and the inner wall can be provided with protrusions to form a rough surface. The structural steel bars 131 of the prefabricated column 1 are arranged at the intersection of the small stirrups 134 and the large stirrups 133 , and a total of eight structural steel bars 131 are arranged.

图16、图17为图1~图4所示预制柱的箍筋改进型,采用焊接箍筋网136代替图1~图4中大箍筋133、小箍筋134及拉筋135组成的复合箍筋作为预制柱1的箍筋,其优势在于箍筋布置简单、钢筋用量小。Figures 16 and 17 are the improved stirrups of the prefabricated columns shown in Figures 1 to 4. The welded stirrup mesh 136 is used to replace the composite composite composed of the large stirrups 133, the small stirrups 134 and the tie bars 135 in Figures 1 to 4. As the stirrups of the prefabricated column 1, the stirrups have the advantages of simple arrangement of stirrups and small amount of steel bars.

图18、图19提供了本发明应用于大截面叠合柱的构造示意,预制柱1边长大于700mm时,可在预制柱1截面中部预埋定型管道或波纹管形成一个或多个浇筑孔16,图18、图19设置两个浇筑孔16,浇筑孔16贯通预制柱1高度方向。浇筑孔16横截面为圆形,直径不宜小于90mm,施工现场浇筑孔16内不布设纵筋。现场施工时,同时通过竖孔11和浇筑孔16向底部水平接缝4内浇筑后浇混凝土24,以保证底部水平接缝4内后浇混凝土24浇筑密实。Figures 18 and 19 provide a schematic diagram of the structure of the present invention applied to a large-section superimposed column. When the side length of the prefabricated column 1 is greater than 700mm, one or more pouring holes can be formed by pre-embedding a shaped pipe or corrugated pipe in the middle of the section of the prefabricated column 1 16, Figures 18 and 19 are provided with two pouring holes 16, the pouring holes 16 pass through the height direction of the prefabricated column 1. The cross section of the pouring hole 16 is circular, and the diameter should not be less than 90mm, and no longitudinal reinforcement is arranged in the pouring hole 16 at the construction site. During on-site construction, the post-cast concrete 24 is poured into the bottom horizontal joint 4 through the vertical hole 11 and the pouring hole 16 at the same time, so as to ensure that the post-cast concrete 24 in the bottom horizontal joint 4 is densely poured.

图20提供了本发明应用于小截面叠合柱的构造示意,竖孔11内侧的小箍筋134沿水平方向的肢距a不大于400mm,预制柱1四边中部不设置辅助纵筋132,预制柱1内仅在四个角部设置一根构造纵筋131与大箍筋133、小箍筋134形成预制柱钢筋笼13,无需设置拉筋135。Figure 20 provides a schematic diagram of the structure of the present invention applied to a small-section superimposed column. The distance a between the small stirrups 134 inside the vertical hole 11 along the horizontal direction is not greater than 400mm, and the middle of the four sides of the prefabricated column 1 is not provided with auxiliary longitudinal bars 132. In the column 1, only one structural longitudinal reinforcement 131 is provided at the four corners, the large stirrups 133 and the small stirrups 134 form the prefabricated column reinforcement cage 13, and no tie bars 135 are required.

图21、图22提供了预制柱1每个竖孔11内布设四根受力纵筋21的叠合柱构造示意,此时定型管道12横截面形状宜分别选用图21、图22中的切角矩形或圆角矩形,不宜采用图2中的六边形。Figures 21 and 22 provide a schematic diagram of the superimposed column structure in which four longitudinal reinforcement bars 21 are arranged in each vertical hole 11 of the prefabricated column 1. At this time, the cross-sectional shape of the shaping pipe 12 should be selected from the cutouts in Figures 21 and 22, respectively. The corner rectangle or rounded rectangle should not be the hexagon in Figure 2.

以上,仅为本发明较佳的具体实施方式,但本发明的保护范围并不局限于此,任何熟悉本技术领域的技术人员在本发明揭露的技术范围内,可轻易想到的变化和替换,都应涵盖在本发明的保护范围之内。因此,本发明的保护范围应该以权力要求的保护范围为准。The above are only preferred specific embodiments of the present invention, but the protection scope of the present invention is not limited thereto. Any person skilled in the art can easily think of changes and substitutions within the technical scope disclosed by the present invention, All should be included within the protection scope of the present invention. Therefore, the protection scope of the present invention should be subject to the protection scope of the claims.

Claims (10)

1. The superposed column is characterized in that each corner of the prefabricated column (1) is provided with a vertical hole (11), the stressed longitudinal bars (21) are arranged in each vertical hole (11) in a centralized manner in a construction site, bending resistance is provided for the superposed column, stirrups are arranged in the prefabricated column (1), stirrups are formed in prefabricated column concrete and post-cast concrete (24) under the constraint action of the stirrups, and elastic-plastic deformation capability is provided for the superposed column, the stressed longitudinal bars (21) and the stirrups are separately arranged, the post-cast concrete (24) is poured in the vertical holes (11), and the poured prefabricated column (1), the post-cast concrete (24) and the stressed longitudinal bars (21) form the integral superposed column and participate in structural stress.
2. The corner vertical hole centralized configuration stress longitudinal bar's of claim 1 superimposed column, characterized by that, the cross section of the said precast column (1) is rectangle, form the through vertical hole (11) after its four corners pre-buried shaping pipeline (12) pour precast column (1) concrete; the shaping pipeline (12) is made of a thin-wall steel plate through rolling and folding, the inner wall of the shaping pipeline is provided with a protrusion to form a rough surface, or a steel plate natural forming surface is adopted, the cross section of the shaping pipeline is hexagonal, corner cutting rectangular, round corner rectangular or circular, the cross section of the corresponding vertical hole (11) is hexagonal, corner cutting rectangular, round corner rectangular or circular, and the maximum size of the edge of the shaping pipeline (12) to the four sides of the prefabricated column (1) is not less than 120 mm.
3. The corner vertical hole centralized arrangement stress-bearing column according to claim 1 or 2 is characterized in that a construction longitudinal rib (131) or an auxiliary longitudinal rib (132) is arranged in the prefabricated column (1) to form a prefabricated column reinforcement cage (13) together with a stirrup, the diameters of the construction longitudinal rib (131) or the auxiliary longitudinal rib (132) are both construction requirements and are not changed along with the stress condition of the prefabricated column, and the construction longitudinal rib (131) or the auxiliary longitudinal rib (132) does not extend out of the bottom surface and the top surface of the prefabricated column (1) and does not participate in stress calculation;
the structural longitudinal ribs (131) are arranged at the corners or the intersection positions of the stirrups of the prefabricated column (1), the diameter of each structural longitudinal rib (131) is 8-12 mm, the number and the positions of the structural longitudinal ribs are determined according to the stirrups, and the structural longitudinal ribs are bound with the stirrups or welded and fixed; when the limb distance a of the stirrup on the inner side of the vertical hole (11) along the horizontal direction is not more than 400mm, auxiliary longitudinal ribs (132) are not arranged at the middle of each side of the prefabricated column (1); when the limb distance a of the stirrup on the inner side of the vertical hole (11) in the horizontal direction is larger than 400mm, the auxiliary longitudinal rib (132) is arranged in the middle of each edge of the prefabricated column (1) to control the limb distance of the stirrup, and the diameter of the auxiliary longitudinal rib (132) is 10-14 mm.
4. The corner vertical hole centralized configuration is a superposed column directly connected with stressed longitudinal bars according to claim 1, wherein the stirrups adopt composite stirrups formed by large stirrups (133), small stirrups (134) and tie bars (135) or adopt welded stirrup networks (136), wherein the large stirrups (133) and the small stirrups (134) adopt welded closed hoops, the small stirrups (134) are arranged in each layer and respectively form constraint on adjacent vertical holes (11), and the large stirrups (133) form constraint on all the vertical holes (11).
5. The corner vertical hole centralized configuration direct connection atress longitudinal reinforcement's superimposed column according to claim 1 or 4, characterized in that, when prefabricated post (1) length of side is greater than 700mm, pre-buried design pipeline or bellows in prefabricated post (1) cross-section middle part form run through prefabricated post (1) high direction pouring hole (16), guarantee bottom horizontal joint (4) post-cast concrete (24) pour closely; the maximum size of the cross section of the pouring hole (16) away from the four sides of the prefabricated column (1) is not less than 90 mm; longitudinal bars are not distributed in the construction site pouring holes (16).
6. The corner vertical hole centralized configuration stress longitudinal bar laminated column according to claim 1, characterized in that, the stress longitudinal bar (21) laid in each vertical hole (11) is not more than four, the stress longitudinal bar (21) participates in stress calculation, the diameter is not less than 16mm and not more than 32mm, the reinforcement area meets the laminated column bending bearing capacity check calculation requirement, and the minimum reinforcement ratio requirement of the current standard to the column stress longitudinal bar is required to be met; the upper and lower stressed longitudinal bars (21) are connected by steel bar joints (23), and the steel bar joints (23) are mechanical connection joints and are arranged at the same height or staggered by a certain distance along the height.
7. The corner vertical hole centralized configuration is with the superimposed column of direct connection atress longitudinal reinforcement according to claim 1, characterized by, set up arch (14) in prefabricated post (1) bottom and guarantee bottom horizontal joint (4) and the near prefabricated post (1) bottom post-cast concrete's (24) compactness, improve bottom horizontal joint (4) shear resistance, the height that arch (14) extrudes prefabricated post (1) is not less than 30mm, set up the inclined plane all around.
8. The construction process of the composite column with the corner vertical holes intensively configured with the stressed longitudinal bars directly connected is characterized in that each corner of the prefabricated column (1) is respectively provided with a through vertical hole (11), the stressed longitudinal bars (21) are intensively arranged in each vertical hole (11) at a construction site to provide bending resistance for the composite column, the prefabricated column (1) is provided with the stirrups to form a stirrup restraining effect on prefabricated column concrete and post-cast concrete (24) and provide elastic-plastic deformation capability for the composite column, wherein the stressed longitudinal bars (21) and the stirrups are separately configured, the post-cast concrete (24) is cast in the vertical holes (11), and the cast prefabricated column (1), the post-cast concrete (24) and the stressed longitudinal bars (21) form the integral composite column to participate in structural stress.
9. The construction process according to claim 8, wherein the precast column (1) is hoisted after the stressed longitudinal bar (21) is connected with the lower-layer column stressed longitudinal bar (22) extending out of the floor slab (3), the height of the horizontal joint (4) at the bottom of the precast column (1) is not less than 60mm, the steel bar joint (23) is arranged in the vertical hole (11), the height of the horizontal joint (4) at the bottom and the installation precision of the precast column (1) are controlled through the leveling bolt (25), and the leveling bolt (25) is screwed into the embedded internal thread sleeve (15) embedded at the bottom of the precast column (1); or after the hoisting of prefabricated post (1) is accomplished, wear to establish the atress in vertical hole (11) and indulge muscle (22) and be connected with lower floor's post atress that floor (3) stretch out, prefabricated post (1) bottom horizontal joint (4) height is not less than 200mm, lays twice big stirrup (133) in bottom horizontal joint (4), and bar joint (23) are laid in bottom horizontal joint (4), through the height of post leg (26) control bottom horizontal joint (4).
10. The construction process according to claim 9, wherein when the prefabricated column is connected and hoisted, the large stirrups (133) in the horizontal bottom joints (4) are placed at the roots of the stressed longitudinal reinforcements (22) of the lower column, the stressed longitudinal reinforcements (21) and the stressed longitudinal reinforcements (22) of the lower column extending out of the floor slab (3) are connected one by one through the reinforcement joints (23), then the prefabricated column (1) is hoisted, the installation precision of the prefabricated column (1) is calibrated by adjusting the leveling bolts (25), and then the large stirrups (133) in the horizontal bottom joints (4) are moved upwards to the designed position and are bound and positioned with the stressed longitudinal reinforcements (22) of the lower column; then, a bottom horizontal joint (4) is erected, and the bottom horizontal joint (4) and the post-cast concrete (24) in the vertical hole (4) are poured through the vertical hole (11); finally, maintaining and removing the mold to complete the connection between the prefabricated column (1) and the lower-layer structure;
when hoisting and connecting, the large stirrup (133) in the horizontal seam (4) at the bottom is placed at the root of the stressed longitudinal rib (22) of the lower-layer column; then placing the column legs (26), hoisting the prefabricated column (1), and adjusting the installation precision of the prefabricated column (1); then, a stressed longitudinal bar (21) penetrates through the vertical hole (11) from top to bottom, connection construction of a steel bar joint (23) is completed in the bottom horizontal joint (4), then a large stirrup (133) in the bottom horizontal joint (4) is moved upwards to a designed position and is bound and positioned with the stressed longitudinal bar (21) and the lower-layer column stressed longitudinal bar (22), then the bottom horizontal joint (4) is erected, and pouring of post-cast concrete (24) in the bottom horizontal joint (4) and the vertical hole (11) is completed through the vertical hole (11); and finally, maintaining and removing the mold to complete the connection of the prefabricated column (1) and the lower-layer structure.
CN202010584141.8A 2020-06-23 2020-06-23 Overlapped column with corner vertical holes in centralized arrangement and directly connected with stressed longitudinal bars and construction process Pending CN111691601A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010584141.8A CN111691601A (en) 2020-06-23 2020-06-23 Overlapped column with corner vertical holes in centralized arrangement and directly connected with stressed longitudinal bars and construction process

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010584141.8A CN111691601A (en) 2020-06-23 2020-06-23 Overlapped column with corner vertical holes in centralized arrangement and directly connected with stressed longitudinal bars and construction process

Publications (1)

Publication Number Publication Date
CN111691601A true CN111691601A (en) 2020-09-22

Family

ID=72482921

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010584141.8A Pending CN111691601A (en) 2020-06-23 2020-06-23 Overlapped column with corner vertical holes in centralized arrangement and directly connected with stressed longitudinal bars and construction process

Country Status (1)

Country Link
CN (1) CN111691601A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113789861A (en) * 2021-09-24 2021-12-14 华侨大学 Fabricated connecting joint of corrugated plate-ECC column and concrete beam and construction method thereof
CN114182883A (en) * 2021-12-23 2022-03-15 华神建设集团有限公司 Large-section square tube concrete column and construction method
CN117646491A (en) * 2023-12-11 2024-03-05 苏州建设(集团)规划建筑设计院有限责任公司 Beam column joint and construction method thereof

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07252884A (en) * 1994-03-11 1995-10-03 Kajima Corp Construction method of frame with precast members
CN103122677A (en) * 2012-12-04 2013-05-29 北京工业大学 Corner-reinforced steel bone-steel tube concrete composite column and manufacturing method thereof
CN208996313U (en) * 2018-09-07 2019-06-18 三一筑工科技有限公司 Prefabricated superposed column, reinforced column and assembled architecture body
CN110725475A (en) * 2019-11-20 2020-01-24 中国建筑标准设计研究院有限公司 Prefabricated column with built-in high-corrugated pipe, frame structure of prefabricated column and construction method of prefabricated column
CN210459769U (en) * 2019-06-26 2020-05-05 三一筑工科技有限公司 Prefabricated hollow column and assembled concrete column
CN212562184U (en) * 2020-06-23 2021-02-19 中国建筑标准设计研究院有限公司 Overlapped column with corner vertical holes in centralized arrangement and directly connected with stressed longitudinal bars

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07252884A (en) * 1994-03-11 1995-10-03 Kajima Corp Construction method of frame with precast members
CN103122677A (en) * 2012-12-04 2013-05-29 北京工业大学 Corner-reinforced steel bone-steel tube concrete composite column and manufacturing method thereof
CN208996313U (en) * 2018-09-07 2019-06-18 三一筑工科技有限公司 Prefabricated superposed column, reinforced column and assembled architecture body
CN210459769U (en) * 2019-06-26 2020-05-05 三一筑工科技有限公司 Prefabricated hollow column and assembled concrete column
CN110725475A (en) * 2019-11-20 2020-01-24 中国建筑标准设计研究院有限公司 Prefabricated column with built-in high-corrugated pipe, frame structure of prefabricated column and construction method of prefabricated column
CN212562184U (en) * 2020-06-23 2021-02-19 中国建筑标准设计研究院有限公司 Overlapped column with corner vertical holes in centralized arrangement and directly connected with stressed longitudinal bars

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113789861A (en) * 2021-09-24 2021-12-14 华侨大学 Fabricated connecting joint of corrugated plate-ECC column and concrete beam and construction method thereof
CN113789861B (en) * 2021-09-24 2023-02-07 华侨大学 Assembly type connecting joint of corrugated plate-ECC column and concrete beam and construction method thereof
CN114182883A (en) * 2021-12-23 2022-03-15 华神建设集团有限公司 Large-section square tube concrete column and construction method
CN117646491A (en) * 2023-12-11 2024-03-05 苏州建设(集团)规划建筑设计院有限责任公司 Beam column joint and construction method thereof

Similar Documents

Publication Publication Date Title
CN110056092B (en) Bolted plug-in upper and lower prefabricated shear walls and composite panels connection structure and construction method
CN105804241A (en) Single-layer prefabricated assembly type reinforced concrete beam-column joint
CN105839846A (en) Prefabricated reinforced concrete composite beam
CN104594500B (en) Integrated slab column formwork structure system and construction method
CN106968381B (en) Prefabricated precast shear wall and composite panel joints connected by combined grouting sleeves
CN109252727B (en) Shock insulation layer rubber support, column, beam and plate system integrated assembly node and method
CN103850363B (en) Prefabricated through hole assembly type reinforced concrete shear wall and construction method of prefabricated through hole assembly type reinforced concrete shear wall
CN111691601A (en) Overlapped column with corner vertical holes in centralized arrangement and directly connected with stressed longitudinal bars and construction process
CN108775083A (en) The assembly concrete frame structure and construction method connected outside precast beam plastic hinge region
CN107476470A (en) Steel pipe built in assembled and GFRP pipe regeneration concrete compound shear walls and its construction method
CN113502948B (en) Reinforced Concrete Shear Wall with Sectional Steel Connector and Soft Steel Support and Construction Method
CN212562184U (en) Overlapped column with corner vertical holes in centralized arrangement and directly connected with stressed longitudinal bars
US20150292168A1 (en) Deck
CN103410269A (en) Unbonded prestress cast-in-place reinforced concrete hollow slab construction structure and method
CN105569222A (en) Vertical connection technology for precast assembled large panel shear walls with concealed supports
CN104453013A (en) Prefabricated wall component and fabricated reinforced concrete shear wall
CN209227836U (en) Prefabricated concrete structure wall-column full steel key connection structure
CN110424548A (en) A kind of steel core concrete column-arch without beam connecting node and its construction method
CN207260378U (en) A kind of assembled frame-shear structure curved scissors type combines keyway connection structure
CN212562032U (en) Take entrance to a cave superimposed shear wall to go out muscle connected node structure in side of indulging and violently wall
CN107023078B (en) Assembled cast-in-situ combined type superposed box net beam floor and construction method
CN109281422A (en) Prefabricated concrete structure wall-column all-steel key connection structure and assembly method
CN108104310A (en) Assembled frame-shear structure column splitlevel connection structure and assembling method
CN109898540B (en) Wet joint structure among bridge pier, bearing platform and pile foundation and construction process thereof
CN214656368U (en) A vertical connecting device suitable for steel-concrete composite girder deck and steel girder body

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination