CN111424664A - Construction method for removing pile head of pre-fractured bored pile - Google Patents

Construction method for removing pile head of pre-fractured bored pile Download PDF

Info

Publication number
CN111424664A
CN111424664A CN202010306341.7A CN202010306341A CN111424664A CN 111424664 A CN111424664 A CN 111424664A CN 202010306341 A CN202010306341 A CN 202010306341A CN 111424664 A CN111424664 A CN 111424664A
Authority
CN
China
Prior art keywords
expansion box
pile head
pile
expansion
annular
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010306341.7A
Other languages
Chinese (zh)
Inventor
陈岩
董光
吕涛
李振兵
王振东
杨胜楠
李恒旭
安宝石
赵一山
高峦
高鑫
李成
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway No 9 Group Co Ltd
Seventh Engineering Co Ltd of China Railway No 9 Group Co Ltd
Original Assignee
China Railway No 9 Group Co Ltd
Seventh Engineering Co Ltd of China Railway No 9 Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway No 9 Group Co Ltd, Seventh Engineering Co Ltd of China Railway No 9 Group Co Ltd filed Critical China Railway No 9 Group Co Ltd
Priority to CN202010306341.7A priority Critical patent/CN111424664A/en
Publication of CN111424664A publication Critical patent/CN111424664A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D9/00Removing sheet piles bulkheads, piles, mould-pipes or other moulds or parts thereof

Abstract

The invention relates to a construction method for removing a pile head of a pre-fractured bored pile, which comprises the following steps of: 1) the outer side of the reinforcement cage is annularly and fixedly connected with an annular expansion box; 2) the concrete pouring is completed to reach a final setting state; 3) the annular expansion box expands, the volume of the annular expansion box is increased, and the upper surface and the lower surface of the expansion box generate contact pressure; 4) the pile head and the pile body are broken under the expansion action of the expansion box. Annular expansion box is installed to pile head position steel reinforcement cage outside hoop in the pile foundation construction, and the expansion of expansion box makes the pile head fracture, reaches abolish pile head purpose, convenient operation, and the time limit for a project is short, reduces the risk index.

Description

Construction method for removing pile head of pre-fractured bored pile
Technical Field
The invention relates to a construction method, in particular to a construction method for removing pile heads of pre-fractured bored piles.
Background
In bridge construction, a pile foundation form is the most common structural form at present, and a construction method commonly adopted in pile head breaking construction is a manual pneumatic pick chiseling method at present. Cutting the pile top of the pile foundation, chiseling the concrete of the reinforcing steel bar protection layer along the cutting line by using an air pick, stripping all reinforcing steel bars at the position of the pile head, drilling holes around the pile head by using an electric drill, and expanding the pile head by using an expanding device such as an expanding drill or a splitting machine to insert into the holes to break the pile head by using a crane to lift the pile head, wherein the analysis shows that the existing construction method mainly has the following defects:
1) the cost is high: pile head chiseling needs the manual work to use the hoop cutting machine to cut in pile head position round, and the manual work uses the pneumatic pick to chisel the protective layer concrete, punches in pile head department with drilling equipment, uses expansion equipment to expand absolutely with the pile head, and during the construction, need drop into manual work, small-size machines are more, and the cost is higher.
2) The construction period is long: after the pile head is excavated, the whole construction process is time-consuming and labor-consuming due to the full manual chiseling in the construction link, the whole pile head needs one person for construction for 1-2 days, and the construction period is seriously influenced if the number of the pile heads on site is large and the number of air compression equipment is insufficient.
3) The quality is low: because the pile head adopts the manual chiseling mode, the end face of the pile head is easy to be irregular in the construction process.
4) The safety risk is high: the traditional construction method needs more manpower and small-sized machines, and equipment such as an air compressor, an air pick, a hoop cutting machine, a hydraulic expansion drill rod, a splitting machine and the like has certain risks in the use process.
Disclosure of Invention
The invention aims to solve the technical problem of providing a construction method for removing the pile head of a pre-fractured bored pile.
In order to solve the above problems, the specific technical scheme of the invention is as follows: a construction method for removing pile heads of pre-fractured bored piles comprises the pile heads, wherein reinforcement cages are arranged on the pile head parts, and the steps are as follows: 1) the outer side of the reinforcement cage is annularly and fixedly connected with an annular expansion box; 2) completing initial strength setting of concrete pouring; 3) the annular expansion box expands, the volume of the annular expansion box is increased, and the upper surface and the lower surface of the expansion box generate contact pressure; 4) the pile head and the pile body are broken under the expansion action of the expansion box.
The outer circumference of each steel bar of the steel bar cage of the pile head part is sleeved with a pvc pipe. The pvc pipe prevents the steel bar from being bonded with the concrete.
When the annular expansion box is a slow expansion type expansion box, a water-swelling adhesive tape is placed in the slow expansion type expansion box, and the annular expansion box expands to 2-3 times of the original volume within 72 hours after meeting water.
The annular expansion box is a timing expansion box, a static explosive and a water-full plastic pipe are arranged in the timing expansion box, a resistance wire is fixed on the pipe wall, and the electric wire of the resistance wire is connected to the pile head. After the concrete reaches a final setting state, an expansion reaction is triggered before pile detection, the resistance wire is electrified, the plastic pipe is heated and melted, water in the plastic pipe is in contact with an expansion agent to react, the volume is rapidly increased, and huge contact pressure is generated by expansion, so that a pile head and a pile body are pulled to break.
The invention has the following beneficial effects: 1. the cost is saved; 2. the construction speed is improved, and the construction period is saved; 3. the construction quality is improved, and the end face of the pile head is smooth; 4. and the construction safety factor is improved.
Drawings
Fig. 1 is a schematic diagram of a pile foundation structure.
Fig. 2 is a schematic diagram of a pile foundation structure provided with an expansion box.
Fig. 3 is a structural schematic diagram of the annular expansion box.
Fig. 4 is a schematic diagram of the internal structure of the annular expansion box.
Fig. 5 is a resistance connection circuit diagram.
Detailed Description
As shown in fig. 1 to 5, a construction method for removing a pile head of a pre-fractured bored pile includes a pile head 1, a reinforcement cage is arranged at the part of the pile head 1, and the steps are as follows: 1) the outer side of the reinforcement cage is annularly and fixedly connected with an annular expansion box 2; 2) completing initial strength setting of concrete pouring; 3) the annular expansion box 2 expands, the volume is increased, and the upper surface and the lower surface of the expansion box generate contact pressure; 4) the pile head 1 and the pile body are broken under the expansion action of the expansion box.
The outer circumference of each steel bar of the steel bar cage of the part of the pile head 1 is sleeved with a pvc pipe 3.
When the annular expansion box 2 is a slow expansion type expansion box, a water-swelling adhesive tape is placed in the slow expansion type expansion box, the water-swelling adhesive tape expands to 2-3 times of the original volume within 72 hours after meeting water, and the water-swelling adhesive tape expands within 72 hours after concrete pouring is completed to generate huge surface contact pressure, so that the pile body and the pile head 1 are broken in a tensile manner, and the purpose of breaking the pile head 1 is achieved.
When the annular expansion box 2 is a timing expansion box, a static explosive and a water-full plastic pipe 2-1 are arranged in the timing expansion box, a resistance wire 2-2 is fixed on the pipe wall, an electric wire of the resistance wire 2-2 is connected to the pile head 1, when concrete reaches a final setting state, an expansion reaction is triggered before pile detection, the resistance wire 2-2 is electrified, the plastic pipe 2-1 is heated and melted, water in the pipe is in contact with the static explosive to react, the volume is rapidly increased, and huge contact pressure is generated by expansion, so that the pile head 1 and the pile body are pulled to break.
What has been described above is merely a preferred embodiment of the invention. It should be noted that variations and modifications can be made by those skilled in the art without departing from the principle of the present invention, and they should also be considered as falling within the scope of the present invention.

Claims (4)

1. The utility model provides a pre-fracture drilling pile head gets rid of construction method, includes the pile head, and pile head part is equipped with the steel reinforcement cage, its characterized in that following step: 1) the outer side of the reinforcement cage is annularly and fixedly connected with an annular expansion box; 2) completing initial strength setting of concrete pouring; 3) the annular expansion box expands, the volume of the annular expansion box is increased, and the upper surface and the lower surface of the expansion box generate contact pressure; 4) the pile head and the pile body are broken under the expansion action of the expansion box.
2. The pile head removing construction method of the pre-fractured bored pile according to claim 1, comprising: the outer circumference of each steel bar of the steel bar cage of the pile head part is sleeved with a pvc pipe.
3. The pile head removing construction method of the pre-fractured bored pile according to claim 1, comprising: the annular expansion box is a slow expansion type expansion box, a water-swelling adhesive tape is placed in the slow expansion type expansion box, and the annular expansion box expands to 2-3 times of the original volume within 72 hours after meeting water.
4. The pile head removing construction method of the pre-fractured bored pile according to claim 1, comprising: the annular expansion box is a timing expansion box, a static explosive and a plastic pipe filled with water are arranged inside the timing expansion box, an electric heating resistance wire is fixed on the wall of the plastic pipe, an electric wire of the electric heating resistance wire is connected to the pile head, the resistance wire is electrified during a triggering reaction, the plastic pipe is heated and melted, water in the pipe reacts with the expansion agent, the volume is rapidly increased, and the expansion agent is expanded until the pile head is broken.
CN202010306341.7A 2020-04-17 2020-04-17 Construction method for removing pile head of pre-fractured bored pile Pending CN111424664A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010306341.7A CN111424664A (en) 2020-04-17 2020-04-17 Construction method for removing pile head of pre-fractured bored pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010306341.7A CN111424664A (en) 2020-04-17 2020-04-17 Construction method for removing pile head of pre-fractured bored pile

Publications (1)

Publication Number Publication Date
CN111424664A true CN111424664A (en) 2020-07-17

Family

ID=71551920

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010306341.7A Pending CN111424664A (en) 2020-04-17 2020-04-17 Construction method for removing pile head of pre-fractured bored pile

Country Status (1)

Country Link
CN (1) CN111424664A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2800444C1 (en) * 2023-03-05 2023-07-21 Акционерное общество "Производственное объединение "Возрождение" (АО "ПО "Возрождение") Method for dismantling bored pile heads

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS56131712A (en) * 1980-03-17 1981-10-15 Kensuke Asakura Removing method of defective concrete at upper part of pile when driving pile in site
CN104404950A (en) * 2014-11-20 2015-03-11 李京财 Construction method for steel bar isolated dust-free oriented self-breaking pile head
CN204356777U (en) * 2015-04-08 2015-05-27 李京财 A kind of directional expansion pipe for dustless directional fracture foundation pile pile crown
CN206110122U (en) * 2016-10-11 2017-04-19 中铁三局集团有限公司 Bridge drilled pile convenient to get rid of pile head
CN108999188A (en) * 2018-08-30 2018-12-14 中建五局土木工程有限公司 Crushing device, restructuring bankrupt and the application of cast-in-situ bored pile pile crown
CN109457690A (en) * 2018-12-18 2019-03-12 北京市市政四建设工程有限责任公司 A kind of application static(al) abolishes pile crown system and its restructuring bankrupt
CN110847157A (en) * 2019-12-20 2020-02-28 中铁四局集团第二工程有限公司 Self-triggering partition device for pile head of concrete poured pile
CN111005378A (en) * 2019-11-30 2020-04-14 浙江交工国际工程有限公司 Construction method for breaking pile head of cast-in-situ bored pile through static spalling

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS56131712A (en) * 1980-03-17 1981-10-15 Kensuke Asakura Removing method of defective concrete at upper part of pile when driving pile in site
CN104404950A (en) * 2014-11-20 2015-03-11 李京财 Construction method for steel bar isolated dust-free oriented self-breaking pile head
CN204356777U (en) * 2015-04-08 2015-05-27 李京财 A kind of directional expansion pipe for dustless directional fracture foundation pile pile crown
CN206110122U (en) * 2016-10-11 2017-04-19 中铁三局集团有限公司 Bridge drilled pile convenient to get rid of pile head
CN108999188A (en) * 2018-08-30 2018-12-14 中建五局土木工程有限公司 Crushing device, restructuring bankrupt and the application of cast-in-situ bored pile pile crown
CN109457690A (en) * 2018-12-18 2019-03-12 北京市市政四建设工程有限责任公司 A kind of application static(al) abolishes pile crown system and its restructuring bankrupt
CN111005378A (en) * 2019-11-30 2020-04-14 浙江交工国际工程有限公司 Construction method for breaking pile head of cast-in-situ bored pile through static spalling
CN110847157A (en) * 2019-12-20 2020-02-28 中铁四局集团第二工程有限公司 Self-triggering partition device for pile head of concrete poured pile

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2800444C1 (en) * 2023-03-05 2023-07-21 Акционерное общество "Производственное объединение "Возрождение" (АО "ПО "Возрождение") Method for dismantling bored pile heads

Similar Documents

Publication Publication Date Title
CN104727306A (en) Cast-in place pile pouring and pile head cutting-off method
CN105649083B (en) The clear stake device of the disposable rotary-cutting type of full-sleeve and its clear piling method
CN111005378A (en) Construction method for breaking pile head of cast-in-situ bored pile through static spalling
CN104404950B (en) A kind of reinforcing bar is isolated dustless orientation and is autotomyed the construction method of pile crown
CN106996107A (en) A kind of filling pile head abolishes device and its construction method
CN106968251A (en) A kind of concrete filling pile head abolishes device and its construction method
CN103321242B (en) Subsection steel-bar-distribution prestressed concrete continuous wall and construction method thereof
CN111424664A (en) Construction method for removing pile head of pre-fractured bored pile
CN213328999U (en) Bored concrete pile structure of position preliminary isolation processing and protection owner muscle is cut to pile foundation ring
CN109853564A (en) A kind of construction method and dedicated inner tamping tube hammer of compaction pile
CN207260148U (en) Service sleeve pile crown integrally abolishes device
CN107401388B (en) Drilling machine stuck drill processing device and method
CN117051831A (en) Pile head breaking method for cast-in-place pile
CN109024572A (en) A kind of rotary digging pile construction method
CN206110122U (en) Bridge drilled pile convenient to get rid of pile head
CN109853534B (en) Construction method of stiffening core pedestal pile
CN109403326B (en) Method for taking out reinforcement cage based on serious hole collapse of drilled pile
GB2413350A (en) Hydraulic Pile Cap Removal
CN110158613B (en) Shaped steel fender pile
JPH03107017A (en) Pile head treatment method for cast-in-place concrete pile
CN219175234U (en) Pile head breaking device for filling pile
CN101392531A (en) Construction method for cutting and breaking reinforced concrete pile, column or ground beam
CN210031806U (en) Broken stake pre-buried device of high efficiency
CN112729035A (en) Integral static blasting device for relatively complete rock stratum and construction method thereof
CN212427098U (en) Preset fracture system of concrete pile head that breaks

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20200717

RJ01 Rejection of invention patent application after publication